SOW B-700 Under Brush North Slope.docx
DOCX document 27 KB Posted
- Attached to
- EADS Brush Removal
- Solicitation number
- W50S8N-21-Q-0007
- Issued by
-
Department of the Army National Guard
View the file
Other files
| File | Type | Posted |
|---|---|---|
| WD 2015-4165 Rev 13.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
B-700 UNDER BRUSH NORTH SLOPE
EASTERN AIR DEFENSE SECTOR
GRIFFISS BUSINESS AND TECHNOLOGY PARK
BUILDING 700
366 OTIS STREET
ROME, NEW YORK 13441-4812
EADS PROJECT
GRCL-21-0002
23 March 2021
Table of contents
1. SCOPE OF WORK
2. AREA OF WORK
3. DESCRIPTION OF WORK
4. PERIOD OF PERFORMANCE
5. MATERIALS
6. GENERAL CONDITIONS
7. GOVERNMENT WORKING HOURS
8. UTILITIES
9. DISPOSAL OF MATERIALS AND CLEANUP
10. SECURITY
11. ESCORTS
12. SITE VISIT
13. POINT OF CONTACT
14. CONTRACT MANPOWER REPORTING
1. SCOPE OF WORK:
The contractor shall provide all personnel, equipment, tools, materials, supervision, transportation, and other items and services necessary to complete the work as described in this Statement of work (SOW). Work location is at the Eastern Air Defense Sector (EADS) 366 Otis Street, Rome, New York 13441-4812 on the Griffiss Business and Technology Park.
2. AREA OF WORK:
Contractor shall work only in the areas designated by the Engineer in Charge. Area of work is located north of B-700.
Contractor to verify all measurements and quantities at site visit.
3. DESCRIPTION OF WORK:
1. Contractor shall cut and remove all under brush, deciduous and coniferous trees that are deceased, all deciduous and coniferous trees 6 inch and minus on the North Slope directly in back of Building 700.
· Deciduous and coniferous Trees branches shall be trimmed from the ground up to a height of 8 ft.
· Cut and remove all under brush.
· All small wood cut shall be chipped.
· All large wood shall be removed from site.
· All stumps shall be cut flush with finish grade of existing soil.
· All chips shall be leveled off over the existing areas of work, not to create piles of wood chip debris
1. Contractor shall restore all lawn areas that are disturbed during this project back to existing condition.
· Top soil, seed and mulch shall be used for restoration of lawn areas.
4. PERIOD OF PERFORMANCE:
Work must be completed in conjunction with the Mission Schedule without interruption of or interference with the function of the military personnel unless prescheduled prior to start of work. All work shall be completed in 30 days from NTP.
5. MATERIALS:
All materials must be submitted on an AF Form 3000 prior to using for approval by Engineer. General contractor shall be on site to accept, unload and sign for all materials delivered to the work site. EADS shall have 5 business days to review and approve all material submittals. Any agents, cleansers, or chemical materials must be submitted prior to using for approval by Engineer in charge with Safety Data Sheet (SDS) sheets for each product used.
6. GENERAL CONDITIONS:
Contractor and all personnel shall comply with the OSHA standards. Contractor shall protect all government property (Personnel, Buildings, Foliage, Grounds) while work is in progress. Contractor shall have a spill protection plan to protect and prevent and contaminating spills. Contractor shall be 100% responsible for any clean-up cost associated with any fuel spills. Contractor shall work with the time line of EADS. Prime General Contractor shall be on site at all times with a site supervisor for all sub-contractors supervision. Low Price with best Technical Plan will be selected as bid winner. Technical plan shall consist of a general time line of project and a written narrative of how you plan on executing the actual work, what parts of the job will you sub contract out and what parts of the project your company will execute.
7. GOVERNMENT WORKING HOURS:
Work hours shall be Monday thru Friday 0700-1530 hours, with the exception of Federal holidays. Due to EADS 24/7 Mission, the contractor may need to work outside these hours to include weekends. Contractor must have prior approval in writing to work outside these guidelines and must coordinate with the Engineer in charge.
8. UTILITIES:
The Government shall provide at no cost to the Contractor reasonable amounts of water and electricity to support the contract. Hook up will be to existing outlets and will be the contractor’s responsibility.
9. DISPOSAL OF MATERIALS AND CLEANUP:
The contractor shall dispose of all containment debris associated with this job off base and provide valid documentation of disposal. Contractor shall clean up after each work period and dispose of all debris at the close of each day.
· Contractor shall verify all site conditions, quantities, measurements, and project requirements before bidding or ordering materials.
· Contractor shall protect and barricade all work areas at all times to protect workers and the public from injury.
· Contractor shall protect all structures, utilities, vegetation, sidewalks and vehicles from damage at all times. Replace all damaged materials with new materials to the satisfaction of the Government, at no additional cost to the Government.
10. SECURITY:
· EADS Security Forces shall monitor the incoming and outgoing of work personnel during the duration of the project. All deliveries shall be coordinated with the Engineer to arrange for their entrance into the compound.
· The contractor shall submit a list of all personnel names, copy of valid driver’s license within one week after award of contract. Any personnel that will work onsite shall be vetted through EADS security. No one will work on site until a background check is completed and personnel cleared. If at any time the contractor submits additional names for clearance, EADS security will require at least 48 hours’ notice to clear individual.
· All Contractor personnel shall have a minimum of one (1) Form of Photo Identification with them at all times.
· OPSEC Training – Contractor will be briefed in Preconstruction conference.
11. ESCORTS:
N/A, A security briefing will be conducted prior to the start of the contract.
12. SITE VISIT:
One (1) site visit will be scheduled with date and time determined when solicitation issued. Contractors will meet at EADS Building 703, 366 Otis St., Griffiss Business and Technology Park, Rome, New York 13441-4805. Call CMSgt Ashley Pace, (315) 233-2130, if you plan to attend site visit.
13. POINT OF CONTACT:
Mr. Daniel Melie, Chief, Engineering Services (315) 334-6142.
14. CONTRACT MANPOWER REPORTING
The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the New York Air National Guard via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/
Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk at help desk at: http://www.ecmra.mill”
File details come from the government source that posted it. Updated .