SOW and SPECS Sheet.pdf
PDF 287 KB Posted
- Attached to
- Replace Diesel Fuel System Components for Dry Tort Federal contract opportunity
- Solicitation number
- 140P5420R0030
About this file
This document is a Statement of Work and Specifications sheet for replacing diesel fuel system components for Dry Tortugas National Park. The National Park Service seeks a contractor to inspect, repair, replace, and install various components of the diesel fuel system located on an offshore island in Dry Tortugas National Park, including underground storage tanks, pumps, controls, electrical circuits, conduits, wiring, distribution piping, safety equipment, and overflow protection devices. The work includes replacing fiberglass piping and junction boxes, installing new flexible fuel lines and conduit, replacing generator room fuel hoses and controls circuits, installing tank monitoring equipment, and upgrading electrical components to bring the fuel system into compliance. The performance period for the work is 75 days from notice to proceed at the job site location in Dry Tortugas National Park, Florida.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers_0002.pdf | ||
| Sol_140P5420R0030_Amd_0002.pdf | ||
| Sol_140P5420R0030_Amd_0001.pdf | ||
| Sol_140P5420R0030_0001.pdf | ||
| Wage Rate Determination.pdf | ||
| Attachment 004- Sol 140P5420R0030 Past Performance Questionnaire.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Replace Diesel Fuel System Components
1. Introduction:
The National Park Service, Interior Region 2, South Contracting Office, Homestead, Florida, 33034, seeks responsive bids for inspections, repairs, alterations, and replacement of various components to a diesel fuel system including underground storage tanks, controls, wiring and conduits, distribution, and safety equipment noted here and in the Specification.
2. Background
The diesel fuel system is located on an offshore island of Dry Tortugas National Park, approximately 68 miles W of Key West, Florida, 33040. Job site is in the sub-tropics of the southeastern Gulf of Mexico, reached by seaplane or vessel only. Weather is hot and humid year-round. Terrain is flat, 3 feet above sea level, and mostly sand with southern turf grasses and unimproved pathways. The marine environment is damaging to most metals and reduces normal life spans of electrical and mechanical equipment. There are no services within the national park. All equipment, materials, and supplies to perform the work and food, required medical pharmaceuticals, and other provisions to live comfortably must be procured and transported from Key West, Florida, which is the nearest local community on the mainland.
This solicitation seeks a qualified contractor to make improvements to three 6,000-gallon underground storage tanks, associated pumps, electrical circuits, and controls, switches, and an above ground but under water (depending on tides) delivery system. Safety components are new to the system bringing site into compliance for underground storage tanks within the State of Florida. Parts and equipment replacements restart life span capabilities by renewing equipment damaged by age, use, and the environment.
Work is on historic landscape. An archaeologist will be present on the job site monitoring ground disturbances and trenching.
3. Required Services
Contractor shall be properly licensed by jurisdictional authorities to perform the work within the State of Florida.
Contractor shall provide work plans / engineered drawings and seek approvals / permits for any / all work regulated by the State of Florida DEP (through Monroe County DHS) prior to commencing work. Contractor shall arrange appropriate jurisdictional inspections when work is completed in addition to final inspection with the Contracting Officer or his representative.
Contractor shall perform proper pressure and tank tightness tests and arrange site visit inspection by agencies having jurisdiction.
Contractor shall have intimate knowledge of the National Electrical Code
Contractor shall have knowledge preparing and installing conduit runs and wiring in close proximity to fuel systems and conform to code requirements in place to prevent in-line explosions caused by gases, vapors, or flame.
Contractor shall have a demonstrated history and knowledge, skill, and ability to do the work.
A designated job site supervisor shall be on site at all times.
An Accident / Safety Plan appropriate to the job site shall be submitted for approval prior to beginning work.
Contractor shall have the means to transport equipment, supplies, labor and provisions to the offshore job site.
Contractor work shall be timely, uninterrupted, and once started not be interrupted by work at other job sites.
Contractor shall provide temporary measures to ensure safety of the workplace to employees and visitors on the island 24 hrs / day.
Contractor shall provide work plan / schedule prior to start of work.
4. Major Components
System includes:
a. --three (3) 6000 gallon fiberglass underground storage tanks
b. --transfer pumps
c. --controls, electrical circuits / conduits, wiring, remote E-stop switches
d. --double walled fiberglass and marina grade flex piping delivery system
e. --overflow and leak detector systems
5. Performance Requirements
Acceptable Quality Level of 100% is reached by:
installing, repairing, testing the provided and approved equipment within required timeframe by following guidance on the Statement of Work and Specification.
System shall be ready to run at designed and intended fashion at completion of project. A favorable inspection upon completion of work leads to government acceptance.
6. Period and Place of Performance
Performance shall conclude within 75 days after the Notice to Proceed is issued for job site location Dry Tortugas National Park, Garden Key.
7. Government Furnished Property
a. No tools, equipment, supplies, materials provided.
b. Government furnished housing provided at jobsite if needed at a daily rate of $45 per person per night. Includes fully furnished kitchen, bathroom with shower and toilet, electricity, HVAC, up to 4 beds in a bunkroom setting, potable water, refrigerator / freezer, potable plumbing, satellite tv, propane stove.
8. Reports
a. Pre- and post- work inspection and approval paperwork from agencies having jurisdiction
b. Component operating and parts manuals
c. Submittal cut sheets
d. Warranty provisions.
e. Provide a Piping Disclosure Assessment Report to state and local governments.
f. All formal reports to inspection agencies shall be signed and sealed by a
Professional Engineer.
9. Safety Component
The Contractor shall:
a. Provide a safe and healthful workplace for all employees while on NPS site.
b. Provide a level of public safety commensurate with exposure at NPS worksite.
c. Comply in rectifying all unsafe or unhealthful conditions called to their attention by the contracting officer.
d. Allow for informal and formal, announced and unannounced, safety inspections by the Contracting Officer’s Technical Representative COTR and the appropriate safety officer at the worksite.
e. Submit an acceptable documented safety plan before beginning work.
f. Utilize the “buddy system” for all working in water with one worker always able to contact job site supervisor if assistance needed
g. Provide familiarization of the equipment to the government. This review of operational capability includes explanation of safety features and a demonstration on operating the equipment known as live operation training
h. Provide lock out tag out equipment when necessary
LOGISTICS AND OTHER INFORMATION
Job site is 68 miles off mainland Florida in Dry Tortugas.
On-Site work hours: Work shall be generally performed during working hours of 7:00 am to 7:00 pm. Requests for any work outside those hours must be submitted for approval at least 24 hours in advance.
Commercial Modes of Passenger Travel: The following schedules may be affected by weather conditions and are subject to change:
Yankee Freedom Ferry: Approximately 2-1/2 hours of travel time (one-way). Ferry departs at 8:00 AM from Key West daily and departs at 3:00 PM from Dry Tortugas.
Round trip adult fare at contractor rate is $99 each way or $165 round trip if travel on same day. Contact information: 800-634-0939 or 305-294-7009.
Key West Seaplane Adventures: Approximately 45 minutes of travel time. Departing from Key West International airport morning and afternoon. Service may not be daily.
Costs are as follows: $288 per person for round trip or $288 per way if different days of travel. Contact company for weight of transportable items and other restrictions. Contact information: 305-293-9300.
Accommodations: Accommodations will be made available to the contractor for up to 4 people within Fort Jefferson. The accommodations consist of a 4-bed bunkroom, kitchen/dining room, bathroom and showers. The quarters contain pots and pans, dishes, utensils, microwave, coffeepots, refrigerators, standing freezer, air conditioning, gas range
/ oven. Potable water is available at taps. Linens provided The nightly rate per person is $45.00.
Provisions: Contractor and contractor's personnel shall provide their own food, medications, condiments, drinks and toiletries for the length of their stay. No stores or services at the job site.
Job site is an offshore island. No personal or commercial services (other than mode of travel explained above) available within the park or the Dry Tortugas area.
Specifications
Replace Diesel Fuel System Components
Replace Aboveground Diesel Fuel Line
Work replaces existing double wall fiberglass fuel line with new flex piping. New line marries into existing and similar specified flex piping previously installed late 2016 along a seawall. Work replaces 1 existing aluminum junction boxes (transition sump) that contains transition from flex to pipe deteriorating due to environment and inspection (and replacement if necessary) of transitioning hardware located within. Work requires installation of fiberglass Unistrut into masonry surface for holding flex pipe in position.
Work requires new 2nd junction box to position and provide 90 degree turn in piping to form end of run. Work requires new 3rd junction box for end of flex run connection to 2” galvanized pipe leading into hose reel. Work includes inspection of 1 existing aluminum junction box and pipe transitioning hardware, repair as necessary. Test for tightness and function. Purge existing fuel line and return purged fuel to USTs. Remove from job site and responsibly dispose of old fiberglass piping.
Methods to prevent and contain fuel spills and contain silt in the water column must be presented and approved by the COR and CO prior to commencement of work. Water level can range from approximately 2 to 4 feet depending on type of tide.
--junction boxes (transition sumps), 3, aluminum, approx. 12” X 12” X 10” or what is necessary to contain components, hinged lid, dogears, lockable, 316 stainless steel hardware, watertight capability
--fiberglass Unistrut, color brown, 1.5” X1.5”, 4” clamps, 316 stainless steel hardware, 220 linear feet run, 8 foot spacing, strut length 16”
--OPW Flexworks flexible fuel piping, C 20 A, 2” primary, 4” chase, chase color earthtone if possible, tertiary fittings and junction connects supplied / recommended by manufacturer, 225 foot linear run between junction boxes, continue 90 foot run from junction box to connection into (provided) 2” galvanized pipe at hose reel, marry flex to galvanized pipe in 3rd junction box to complete line
Replace Hose on Hose Reel – Generator Room
Replace Generator Room day tank fuel hose mounted to hose reel. Re-attach existing dispenser nozzle. Hose remains in possession of government.
--diesel fuel hose, Goodyear Redwing or equivalent, 1”, 2BD, 30 feet, end fittings for hose reel and nozzle dispenser connections --test for tightness
Replace Generator Room E-Stop and Controls Circuit
Work replaces existing remote E-Stop, same or close to location; replaces electrical circuit from E-Stop to seawall mounted junction box box(es), run is parallel and close to fuel piping, mounted with flex fuel line strut clamps, make connections at junction boxes, run is 90 feet from E-Stop to 1st junction box, 220 feet between junction boxes; wiring and conduit sized to load and distance, provide 2 spare wires in conduit, mark wiring at openings; replace 2 in-line conduit junction boxes along seawall, mounting location to be field determined.
Work inspects and tests existing circuit continuous from Main Controls Box to junction box replacement mentioned above. Inspect continuity and function, repair as required.
Test for tightness, fit, and function.
--E-Stop, 2 button stop / start, same or similar in function --junction boxes (3), approx. 6 X 6 X 4 with gasket, sch80 pvc, 316 ss mounting hardware, suitable for wet location, cover plate screw attached --conduit and fittings, sch80 pvc, sized to load, distance, and number of wires --all low voltage wire type to be Welden
Inspect / Test Dock House E–Stop and Controls Circuit
Work inspects and tests remote, dock house, diesel delivery system E-Stop for continuity and function, repair if needed as required.
Install Overflow Protection Devices – UST 1, 2, 3
Work installs new overfill protection devices inside 3 diesel underground storage tanks.
Trench and install new conduit and wiring separate and to each of 3 tanks from Main Controls Box. Install high level sensor floats inside each of 3 tanks thru unused 4-inch entry pipe. Install Pneumercator (or equivalent) hub and auxiliary long range warning light next to / outside of Main Controls Box. Install auxiliary long range warning light so as to be seen from dock house. Provide connections to protection device and control component. Test for tightness and functionality. All mounting hardware 316 ss. Train government operator on system use.
--Pneumercator LC1000 A high level alarm system w/ Nema III enclosure, alarm light, enunciator, or equivalent --Pneumercator LS600 level transmitter, level setting programmed to 90%, or equivalent --additional auxiliary strobe alarm light to be seen for up to 300 feet distance, --3 high level sensor floats compatible with other components --conduit, appropriately sized Sch80 pvc conduit fitted in between 10 foot sections EMT conduit (steel, electrogalvanized) leading from inside tank manway and from Mai Controls Box, transition fittings, EMT conduit sealing fittings with Chico sealing compound or equivalent
--junction boxes (if required), suitable for wet locations --wiring, appropriately sized, low voltage Belden wire --appropriately sized manway entry boots and fittings
Replace Electrical Circuits – UST Pumps 1, 2, 3
Work replaces existing conduit and wiring from Main Controls Box to each of 3 transfer pumps in manways on top of UST 1, 2, and 3. Distances are 30, 45, and 55 feet respectfully. Includes connections into pump controls box inside the Main Controls Box and to each of pumps in manways. Work does not include removing old conduit / wiring beyond 2 feet from pumps and Main Control Box.
--conduit, entire length, EMT (steel, electrogalvanized) appropriately sized for load and wire configuration, EMT conduit sealing fittings with Chico sealing compound or equivalent --wiring, appropriately sized for load and length, THWN, 220vac
Test and Certify Leak Detector – UST 3 Pump
Perform leak detection test on UST 3 pump leak detector, repair / replace if test failure, test again. When functioning properly, provide certification to government.
Replace Tank Controls Box
Work replaces existing tank control / selector box whose function is to provide pump on
– off and tank selection capability from manual switch at box and emergency stop capability from 2 remote E-Stop locations. Replaces relays, switches, controls inside box. Replacement enclosure to be mounted in same or close position as existing.
--316 ss cabinet, dog eared, hinged cover, approx 12 X 12 X 4, suitable for wet location, containing necessary switchgear to function properly
Replace Tank Controls Box - Feeder Circuit Boxes
Work replaces two (2) junction boxes acting as feeder boxes under the Tank Controls Box. The J-boxes accumulate and bundle wiring to the Tank Controls Box above. Wiring to these boxes comes from house 120/240vac to power the controls and is a collection point to feed wiring from remote E-Stops into the Tank Control Box. Once new boxes are installed, work organizes and marks wiring to provide operator with understanding of origins and destinations.
--PVC, 12 X 12 X 4 with gasket, suitable for wet locations, cover plate screw attached, 316 ss attaching hardware
File details come from the government source that posted it. Updated .