SOW_Advance_Redout_Road_and_Parking_Area_Pavement_Preservation.pdf

PDF 2 MB Posted

Attached to
Asphalt Seal Coat, Paving, and Striping Projects Federal contract opportunity
Solicitation number
140P5222Q0033
Issued by
Department of the Interior National Park Service Southeast Region

View the file

Other files for this federal contract opportunity

Other files attached to Asphalt Seal Coat, Paving, and Striping Projects, newest first.
File Type Posted
Sol_140P5222Q0033_Amd_0001.pdf PDF
Site_Visit_Sign-In_0001.pdf PDF
B12_Pre-Bid_Inquiry_and_NPS_clarifications_response_0001.xlsx XLSX spreadsheet
BID_BOND_SF_24-16d_0001.pdf PDF
SPECS_FL_DOT_SSFRABC_January-2022-redline-ebook.pdf PDF
DOL_WD_FL20220165_02-25-2022.pdf PDF
SOW_Fort_Barrancas_Entrance_Trail_Pavement_Preservation.pdf PDF
Sol_140P5222Q0033.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gulf Islands National Seashore Gulf Breeze, FL

STATEMENT OF OBJECTIVES:

Pavement Preservation on Advance Redoubt Road and Parking

Area

PMIS #319627 PEPC #40372

DATED: September 2021

NATIONAL PARK SERVICE

STATEMENT OF OBJECTIVES (SOO)

SOO Format

1. Background

2. Objectives

3. Place of performance

4. Period of performance

5. Scope

6. Safety

7. Tasks

8. Delivery

9. Government-Furnished Property (GFP)

10. Security Considerations

11. Special Material Requirements

12. Other Unique Requirements and Considerations

13. Quality Assurance Requirement

14. Project Personnel

15. Invoices and Payments

1. BACKGROUND

Gulf Islands National Seashore (GUIS) is a unit of the National Park Service and is head quartered in Gulf Breeze, FL. High on a bluff overlooking the entrance to Pensacola Bay, Fort Barrancas stands as a monument to the legacy of America’s early homeland defense. Built with 6 million bricks, walls 4 feet thick and 20 feet high, Fort Barrancas was completed in 1844 and remains an example of military engineering and a marvel of human ingenuity. Advanced Redoubt sits just north of Fort Barrancas and was built to protect Fort Barrancas and the Navy Yard from a land attack. Construction began with enslaved labor in 1845 and was not completed until 1870 by free men, making it the last fort of the Third System Forts to be completed. Though redoubts are typically square, Advanced Redoubt was built as a trapezoid in order to defend the front and the rear of the structure.

2. OBJECTIVES:

The work of this contract consists of all labor, equipment, supervision and materials to accomplish a 2” asphalt overlay of approximately 2100 square feet (12.5 mix) over existing pavement with shoulder support where needed for a safe, smooth driving and parking surface and re-striping of existing parking lots to meet ADA/ABAAS requirements at Advanced Redoubt in the Fort Barrancas Area.

3. PLACE OF PERFORMANCE:

Gulf Islands National Seashore, Fort Barrancas Area, 3182 Taylor Road, Pensacola, FL 32508.

4. PERIOD OF PERFORMANCE:

All work specified herein shall commence after the notice to proceed is received from the Contracting Officer, and completed with-in a 2 month (60 day) period.

5. SCOPE:

In accordance with the terms and conditions herein, the prime contractor or his sub-contractors shall perform the work of this contract for the National Park Service (NPS).

The contractor will complete the following items:

1. Contractor will provide all material, equipment, parts and labor required to perform all of the work of this contract:

2. All equipment, material and waste removed or generated by work of this contract shall be properly disposed of offsite by the contractor.

3. Contractor shall verify the quantity of materials needed to complete the task identified in this SOO.

4. Contractor will provide a work site and environment that is safe for employees, for visitors to the

Park, and NPS staff. If needed, the work area will be cordon off and secure.

5. All work will be performed Monday through Friday from 7:00 am until 3:30 pm. No work will be performed on weekends or federal holidays without prior approval.

6. Contractor and employee parking and equipment storage areas will be designated by the Park. No company signs shall be installed on government property. Smoking and eating will be performed in areas designated by the Park. Employees shall wear appropriate clothing at all times.

7. Contractors will notify NPS staff of scheduled site visits to ensure access to secure areas.

8. The Davis-Bacon Act applies for this contract.

6. SAFETY:

All work performed on government property will be accomplished in accordance with OSHA, EPA, Federal, State and local regulations and requirements. Prior to starting work on government property, the contractor will submit to Gulf Islands National Seashore for approval a copy of their company safety plan pertaining to this particular contract. Although not all inclusive, the safety plan must address at a minimum the following areas:

1) Heavy equipment operations (if required)

2) Fall Protection Plan

3) Public/visitor safety (barriers/signage, etc…)

4) Traffic safety plan (if required)

5) Trenching/sloping of soil (if required)

6) Personal protective equipment to be used

7) Hazardous materials (HAZMAT) to be used

a. Copies of Safety Data Sheets (SDS) must be provided to the Park

b. Storage of HAZMAT

8) Emergency response protocols

9) Personnel training requirements

10) OSHA DART rate

a. OSHA 300A Summary for last three years

Contractor shall use “green” products whenever possible and all HAZMAT must be pre-approved for use by the GUIS Collateral Duty Safety Coordinator. The contractor will be responsible for the safety and security of the site to ensure unauthorized personnel (park visitors & employees) do not enter the construction area.

7. TASKS:

COMMUNICATION

A). Contractor shall notify the Contracting Officer’s Representative (COR) between 7:00 and 7:15 am on the morning work will be performed or inform the COR why services cannot be performed that day. The COR is Hank Reynolds, cell phone: 850-281-2165.

B). Work shall be performed during daylight hours between 7:00 am and 5:30 pm Monday through Friday as per the established schedule. Weekend and holiday work will not be permitted, unless due to inclement weather, equipment problems, etc. or with the prior approval by the park COR or Contracting Specialist.

C). Schedule changes MUST be cleared through the COR or Contracting Officer

SPECIFIC REQUIREMENTS

All work must meet U.S. Department of Transportation, Federal Highway Administration, Federal Lands Highway (FP-14) Specifications. Parking lot striping must meet ADA-ABAAS requirements.

Contractor must confirm all measurements.

GERERAL PROVISIONS

This work area is located within the Fort Barrancas Area of Gulf Islands National Seashore at Advanced Redoubt.

• Clean and prep pavement for asphalt overlay

• Cut, remove and repair ~20’ x 20’ depression before overlay

• Mill transition at Taylor Road

• Apply tack coat ~2100 sq ft

• Lay ~2100 sq ft 12.5 mix asphalt

• Provide shoulder support where needed

• Remove and dispose offsite old bumper blocks

• Replace bumper blocks at handicap parking.

• Thermo plastic ABA-ABAAS re-stripe parking lots

Reapply thermo plastic striping to all existing pavement markings. Contractor is responsible for recording all existing pavement markings with sufficient detail (lengths, widths, symbols, and/or letters, etc.) prior to asphalt work/repairs. All pavement markings shall comply with Manual on Uniform Traffic Control Devices (MUTCD) and ADA-ABAAS requirements.

WEATHER

Contractor shall notify the COR by 7:00 am of any intention to cancel work for the day due to weather.

8. DELIVERY:

All deliverables required to complete this project will be delivered by the contractor.

• All labor, materials, tools and equipment to provide a 2” asphalt overlay

• All labor, materials, tools and equipment to re-stripe current parking areas

• All labor, materials, tools and equipment to provide road shoulder support

• All labor, materials, tools and equipment to provide bumper blocks

• All labor, materials, tools and equipment to provide milling of transitions

9. GOVERNMENT-FURNISHED PROPERTY, MATERIAL, EQUIPMENT, OR INFORMATION

(GFP, GFM, GFE, OR GFI):

None.

10. SECURITY:

The information developed under this Statement of Objectives is the property of the U.S.

government and shall be kept in strict confidence. Proprietary or copyrighted material may not be included into the contract information CDs unless otherwise approved in writing by the Contracting Specialist.

11. SPECIAL MATERIAL REQUIREMENTS:

None

12. OTHER UNIQUE REQUIREMENTS:

All closures must be coordinated with the COR or CO at least two weeks before closure begins. All work must be completed in a timely manner as to reduce duration of closures.

Measures shall be put in place to prevent spills of tack and asphalt materials from entering storm drains or other pathways to water. All materials shall be stored away from storm drains or other pathways to water.

Parking lot striping must meet ADA-ABAAS requirements.

All work must meet U.S. Department of Transportation, Federal Highway Administration, Federal Lands Highway (FP-14) Specifications. Parking lot striping must meet ADA-ABAAS requirements.

Chapter 5: Parking Spaces (access-board.gov):

· The term "parking facility" is used Section 208.2 instead of the term "parking lot" so that it is clear that both parking lots and parking structures are required to comply with this section. The number of parking spaces required to be accessible is to be calculated separately for each parking facility; the required number is not to be based on the total number of parking spaces provided in all of the parking facilities provided on the site.

· For every six or fraction of six parking spaces required by 208.2 to comply with 502, at least one shall be a van parking space complying with 502.

· Car parking spaces shall be 96 inches (2440 mm) wide minimum and van parking spaces shall be 132 inches (3350 mm) wide minimum, shall be marked to define the width, and shall have an adjacent access aisle complying with 502.3.

o EXCEPTION: Van parking spaces shall be permitted to be 96 inches (2440 mm) wide minimum where the access aisle is 96 inches (2440 mm) wide minimum.

· Access aisles serving parking spaces shall comply with 502.3. Access aisles shall adjoin an accessible route. Two parking spaces shall be permitted to share a common access aisle.

· Parking spaces complying with 502 that serve a particular building or facility shall be located on the shortest accessible route from parking to an entrance complying with 206.4. Where parking serves more than one accessible entrance, parking spaces complying with 502 shall be dispersed and located on the shortest accessible route to the accessible entrances. In parking facilities that do not serve a particular building or facility, parking spaces complying with 502 shall be located on the shortest accessible route to an accessible pedestrian entrance of the parking facility.

o EXCEPTIONS: 1. All van parking spaces shall be permitted to be grouped on one level within a multi-story parking facility.

· Parking spaces shall be permitted to be located in different parking facilities if substantially equivalent or greater accessibility is provided in terms of distance from an accessible entrance or entrances, parking fee, and user convenience.

· Total number of parking spaces & minimum number of accessible parking spaces:

o 1 to 25 =1 accessible o 26-50 =2 accessible

· Accessible spaces must be identified by signs with the International Symbol of Accessibility (ISA) (§703.7.2.1). Signs identifying van spaces must include the term “van accessible.” This designation is informative and does not restrict use of such spaces to van users only. No other text or content is required by the Standards.

· Signs must be at least 60” high measured to the bottom edge so that they are visible while vehicles are parked in a space. Signs can be on posts, or where feasible, on walls or suspended from ceilings (an 80” minimum headroom clearance is required at signs suspended above circulation paths (§307.4)). ISA designations on the parking surface, even if required by a state or local government, cannot substitute for above-ground signs that remain visible at all times.

· State or local codes and regulations may address other sign characteristics, including size, color, and additional content, such as “reserved” or violation fines, but the ABA Standards do not.

NPS will install and/or replace any signage.

13. QUALITY ASSURANCE REQUIREMENT:

The contractor shall develop and maintain a quality control program to ensure services are performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. As a minimum the contractor shall develop quality control procedures addressing the critical areas identified in this statement of work. The government will periodically evaluate the contractor’s performance in accordance with the statement of work.

Prior to issuance of Notice to Proceed, the Contractor shall be required to submit to the CO/COR the following items (Electronic submission in PDF or MS Office format is acceptable):

• Safety plan (see FAR clause 52.236-13 (f)(1) for details)

• Proof of Insurance (see FAR clause 52.228-5 for details)

• Alternate Payment Protection (See FAR clause 52.228-13 for details)

• Work Plan/Schedule (see FAR clause 52.236-8 and 52.236-15 for details)

14. PROJECT PERSONNEL:

Contracting Officer (CO):

Andre Ward C: 850-232-4630 Email: andre_ward@nps.gov

Contracting Officer Representative (COR):

Hank Reynolds Facility manager C: 850-281-2165 Email: joseph_h_reynolds@nps.gov

Chief of Facility Management (CFM):

Gary Stansberry Chief of Facilities O: 850-934-2610 C: 850-232-3625 Email: gary_stansberry@nps.gov

15. INVOICES AND PAYMENTS:

52.232-1 PAYMENTS (APR 1984)

The Government shall pay the Contractor, upon the submission of proper invoices or vouchers, the prices stipulated in this contract for supplies delivered and accepted or services rendered and accepted, less any deductions provided in this contract. Unless otherwise specified in this contract, payment shall be made on partial deliveries accepted by the Government if—

(a) The amount due on the deliveries warrants it; or

(b) The Contractor requests it and the amount due on the deliveries is at least $1,000 or 50 percent of the total contract price.

(End of clause)

Adjustment for Inadequate Performance

• Well maintained buildings are the National Park Service’s goals. Routine inspection shall be performed to minimize work improperly performed. Such inspections are designed only to assure that the NPS pays only for those services, which have been specified, and adequately completed by the contractor.

• In the event the contractor fails to successfully perform the required work, the National Park Service has the right to withhold partial payment (see FAR clause 52.232-5

(e) Retainage and or 52.246-12 (f) appropriate adjustment in contract price).

mailto:joseph_h_reynolds@nps.gov mailto:gary_stansberry@nps.gov

16. PHOTOS:

ADA-ABAAS requirements:

Total Number of Minimum Number of

Parking SpacesProvided in Parking Facility Required accessible Parking Spaces

1 to 25 1

26 to 50 2

51 to 75 3

76 to 100 4

101 to 150 5

151 to 200 6

201 to 300 7

301 to 400 8

401 to 500 9

501 to 1000 2 percent of total

1001 and over 20, plus 1 for each 100, or fraction thereof, over

The term "parking facility" is used Section 208.2 instead of the term "parking lot" so that it is clear that both parking lots and parking structures are required to comply with this section. The number of parking spaces required to be accessible is to be calculated separately for each parking facility; the required number is not to be based on the total number of parking spaces provided in all of the parking facilities provided on the site.

For every six or fraction of six parking spaces required by 208.2 to comply with 502, at least one shall be a van parking space complying with 502.

Car parking spaces shall be 96 inches (2440 mm) wide minimum and van parking spaces shall be 132 inches (3350 mm) wide minimum, shall be marked to define the width, and shall have an adjacent access aisle complying with 502.3.

EXCEPTION: Van parking spaces shall be permitted to be 96 inches (2440 mm) wide minimum where the access aisle is 96 inches (2440 mm) wide minimum.

Access aisles serving parking spaces shall comply with 502.3. Access aisles shall adjoin an accessible route. Two parking spaces shall be permitted to share a common access aisle.

Parking spaces complying with 502 that serve a particular building or facility shall be located on the shortest accessible route from parking to an entrance complying with 206.4. Where parking serves more than one accessible entrance, parking spaces complying with 502 shall be dispersed and located on the shortest accessible route to the accessible entrances. In parking facilities that do not serve a particular building or facility, parking spaces complying with 502 shall be located on the shortest accessible route to an accessible pedestrian entrance of the parking facility.

EXCEPTIONS: 1. All van parking spaces shall be permitted to be grouped on one level within a multi-story parking facility.

2. Parking spaces shall be permitted to be located in different parking facilities if substantially equivalent or greater accessibility is provided in terms of distance from an accessible entrance or entrances, parking fee, and user convenience.

Statement of OBJECTIVES (SOO)
1. Background
2. Objectives:
3. Place of Performance:
4. Period of Performance:
5. Scope:
6. Safety:
7. Tasks:
8. Delivery:
9. Government-Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, or GFI):
10. Security:
11. Special Material Requirements:
12. Other Unique Requirements:
13. Quality ASSURANCE Requirement:
The contractor shall develop and maintain a quality control program to ensure services are performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent, and ensure non...
14. Project Personnel: