B12_Pre-Bid_Inquiry_and_NPS_clarifications_response_0001.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Asphalt Seal Coat, Paving, and Striping Projects Federal contract opportunity
- Solicitation number
- 140P5222Q0033
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site_Visit_Sign-In_0001.pdf | ||
| BID_BOND_SF_24-16d_0001.pdf | ||
| Sol_140P5222Q0033_Amd_0001.pdf | ||
| SPECS_FL_DOT_SSFRABC_January-2022-redline-ebook.pdf | ||
| DOL_WD_FL20220165_02-25-2022.pdf | ||
| SOW_Fort_Barrancas_Entrance_Trail_Pavement_Preservation.pdf | ||
| Sol_140P5222Q0033.pdf | ||
| SOW_Advance_Redout_Road_and_Parking_Area_Pavement_Preservation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question No. | Date Received | REFERENCE | QUESTION | GOVERNMENT RESPONSE | Posted on Amend No. | |||
| Page | Section | Para. | ||||||
| 1 | 3.24.22 | SF 1442 | 13 | (b) | Is a bid bond required? | YES, SF 24 Bid Bond Form is attach; penal sum 20% of the bid price. ADD Section L clause 52.228-1 | 1 | |
| 2 | 3.24.22 | FAR | 52.228-15 and 52.228-13 | (b) and (c) | Is a performance & payment bond required if bid is under 150K | ADD clause at 52.228-15 Performance and Payment | ||
| Bonds-Construction that requires performance and payment bonds if the resultant contract is expected to exceed $150,000. However if the resultant contract does not exceed $150,000 a Performance bond is not required per 40 USC §3131. Bonds of contractors of public buildings or works. In which case 40 USC § 3132 Alternatives to payment bonds provided by Federal Acquisition Regulation clause at 52.228-13 require alternatives to payment bonds as payment protections for suppliers of labor and materials under contracts referred to in section 3131(a) of this title that are more than $35,000 and not more than $150,000. | 1 | |||||||
| 3 | 3.24.22 | 3 | 6 | Is a full time Superintendent QCM/Site Safety officer required onsite? | NO requirement to do so, but Prime must comply with clause at 52.246-1 Contractor Inspection Requirements to ensure work accomplished meets the standards of quality established under the contract, since NPS cannot direct Subs and has privity of contract with Prime contractor only. DELETE clause at 52.236-6 Superintendence by the Contractor | 1 | ||
| 4 | 3.24.22 | FAR | 36.501 and 19.507 | (a) and (b); (e)(1) | What percentage of work is the Prime Contractor required to self perform under this contract? | NO minumum required. As neither clause 52.236-1, Performance of Work by the Contractor nor clause 52.219-14 Limitations on Subcontracting apply to contracts below SAT $250,000 | 1 | |
| 5 | 3.24.22 | Please confirm that thermal striping will be 6" for the yellow lane divider line | YES | 1 | ||||
| 6 | 3.24.22 | Please confirm that thermal striping will be 4" for the white lines | YES | 1 | ||||
| 7 | 3.24.22 | Please confirm that the handicap and bus lane lettering is to be painted - No thermal | YES | 1 | ||||
| 8 | 3.24.22 | Current handicap spaces do not appear to meet ADA requirements. Is it acceptable to enlarge and shift spaces as necessary? | YES | 1 | ||||
| 9 | 3.24.22 | SOW: Is the QC manager required to be onsite at all times to oversee all work onsite? | NO, but Prime contractor must ensure QC; see NPS response in row 6 above | 1 | ||||
| 10 | 3.24.22 | Is it acceptable to remove one parking space to accommodate the larger handicap parling spaces as necessary. | YES | 1 | ||||
| 11 | 3.24.22 | Will the NPS trim the overgrowth back and remove debris currenlty on the edges of the parking lots to be paved or is the contractor responsible | YES | 1 | ||||
| 12 | 3.24.22 | Will the NPS trim the low hanging branches where paving is to be milled and replaced or is the contractor responsible? | YES, NPS will do so but only to the extent permitted by regulatory compliance | 1 | ||||
| 13 | 3.24.22 | Do the new wheel stops need to be painted? | NO | 1 | ||||
| 14 | 3.24.22 | 4 | 7 | Should the contractor replace all four wheel stops or just the two at the Fort parking lot? | NO, remove and replace only two at Advance Redoubt with new (like in kind) per SOW | 1 | ||
| 15 | 3.24.22 | 4 | 7 | Should the contractor replace the wheel stops with concrete or HDPE? What color? | Concrete-no paint required | 1 | ||
| 16 | 3.24.22 | Does the NPS want the contractor to infill or repair the edge of the pavment entering the visitor center/ trail entrance where there is an erosion issue and wheel drop hazard? | NO, PM/COR direction at Site Visit indicated edge repair at Fort Barrancas egress side not required | 1 | ||||
| 17 | 3.24.22 | 7 | 12 | last | Do the handicapped signs and mounting poles require replacement? | NO, not part of contract. If necessary, NPS will provide its own material and labor to replace vertical handicapped signs and mounting posts | 1 | |
| 18 | 3.24.22 | Is it acceptable to pave over the existing concrete curb transitions at the fort parking lot to allow for proper run off? | YES | 1 |
SOLICITATION NO. 140P5222Q0033
PROJECT TITLE/LOCATION: Sealcoat, Paving & Striping
| Pre-Bid/Proposal Inquiry Form (Template) |
| &"-,Italic"&KFF0000 |
&"-,Bold Italic"NOTE: Extract Information from Government Preaward Inquiry Form to prepare this form.
March 2022