This scope of work document outlines requirements for architectural and engineering design services to renovate an existing pharmacy at the VA Medical Center in Togus, Maine. The project involves renovating approximately 10,075 square feet of inpatient and outpatient pharmacy space to improve workflow and address any code deficiencies. Key requirements include field investigations and user interviews to prepare construction documents; complying with VA design criteria and standards; coordinating with VA, VISN, and independent life safety reviewers; and completing environmental assessments. The design is to be completed over 224 calendar days according to the schedule laid out. Deliverables include basis of design, schematic design, design development, and construction documents submissions. The selected firm will provide design phase and optional construction phase services overseeing the project through construction closeout. Qualification submissions are due by August 29th, 2022 and requests for information by August 18th, 2022.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARCHITECT-ENGINEER DESIGN SCOPE OF WORK
RENOVATE PHARMACY
PROJECT NO: 402-23-793 Renovate Pharmacy
PROJECT NAME: Renovate Pharmacy – Togus, ME
MAGNITUDE OF CONSTRUCTION COST: Between $2,000,000 and $5,000,000.
1. GENERAL INTENT:
The Contractor (herein referred to as “A/E”) shall provide Architect/Engineer (A/E) services to design a construction project at the VA Maine Health Care System (Togus) in accordance with this design scope of work.
2. STATEMENT OF WORK:
A/E Part One Services (also known as Design Phase) for this design project includes site visits, field investigation, studies and user interviews to prepare drawings, specifications and cost estimates for all facets of work and disciplines/trades to facilitate a construction project to renovate the existing Pharmacy to improve workflow and correct any identified code deficiencies.
The project shall include renovation of inpatient and outpatient pharmacy areas, excluding the new sterile compounding rooms renovated in 2022 (approximately 650 sqft). Total space to be renovated is approximately 10,075 GSF. The new design shall be based on the latest version of PG 18-12 Pharmacy Service design guide. The purpose of this design is to ensure the pharmacy is code compliant and to improve workflow, to include incorporating current outpatient pharmacy waiting room into the pharmacy working area, and moving patient pick up to corridor near front of building 200E. The renovation work includes but is not limited to; demolition of existing area, reconfiguration of pharmacy layout to improve workflow, upgrading interior finishes, upgrading facility lighting and power, demo and replace air handler unit 1 and associated duct work , demo air hander 21 and associated duct work currently serving compounding room, demo existing compounding room and reconfigure as part of pharmacy, upgrade facility HVAC distribution (excluding all HVAC upgrades completed during USP 797 Clean Room project), upgrading building management system interfaces, upgrading communication infrastructure, physical security assessment and upgrades, and hazardous material abatement (asbestos, lead, etc.). A/E to explore possibility of adding bathroom outside of outpatient pharmacy in corridor on ground floor of building 200E. This design should include a phasing plan, the pharmacy must remain operational during renovation. Available as-built drawings will be provided for information only. A/E must field verify all existing conditions. The completed design shall contain all required demolition drawings, specifications, phasing plans, etc. This contract will also include hiring of a 3rd party industrial hygienist to monitor any abatement activities done by contractor during construction.
The selected A/E shall prepare all required National Environmental Policy Act (NEPA) analysis and Environmental Assessment reports and documentation for any improvements made as part of this Pharmacy Renovation Project.
A/E Part Two Services of this design project (also known as Construction Period Services) includes responding to construction contractor Requests For Information (RFIs) during the solicitation (solicitation support) and construction phases of the construction project, attendance at pre-bid, post-award and commissioning kick off construction project conferences, review of construction material submittals and shop drawings, approximately 4 site visits per month during construction (both scheduled and emergent) to ensure compliance with the design drawings and specifications, preparation of site visit reports, coordination with project commissioning requirements, review of any construction project modifications for cost and technical acceptability, attendance and participation during the final acceptance inspection, preparation of the punch list and preparation of record drawings of the completed construction project based on the construction contractor’s as-built drawings. A/E will be responsible for on-site inspections during major construction milestones (demo completion, in-wall inspection, punch list, etc). The A/E shall prepare a submittal log to be utilized by the VA during construction period services, maintain RFI log and provide meeting minutes for weekly construction meetings throughout the duration of construction. All Part Two Services are optional line items and will not be exercised at the time of award.
The above paragraphs constitute a basic outline of the work to be accomplished and in no way comprises all the details for design of this project. The A/E shall initiate detailed inspection of the project site to determine the needs and conditions for the design of this project. Copies of VA Maine Health Care System (Togus VAMC) record drawings will be made available to the highest rated A/E firm;
the A/E will verify the validity of the record drawings prior to the start of design work and conduct site investigations as necessary throughout the design. SOW Attachment 08 – Togus Campus Map will give AE firm a basic understanding of the VA Maine Health Care System (Togus VAMC) campus.
The A/E shall be solely responsible for the management, including all associated labor, equipment, materials, mailing costs, and inspection, to meet the requirements of the design project. The A/E shall further provide meeting minutes for all meetings held under this design project.
The A/E firms’ representatives performing site investigations on the VA Maine Health Care System (Togus VAMC) campus must show documentation, and meet, the following additional requirements before starting site investigations on campus:
1. Negative TB Test, documented within the past calendar year
2. Negative COVID-19 test prior to entry into sensitive areas with immune-compromised patients
(CLC, SCU, Inpatient Wards on 3N & 3S)
3. Annual influenza vaccination is required for all staff performing work at VA Maine Healthcare
System (Togus VAMC)
4. Completion of a full COVID-19 vaccination series (Moderna, Janssen, or Pfizer) at least 2 weeks prior to arrival onsite
5. Contractor badge must be obtained and worn by contractor, or representative, at all times while on campus
6. These requirements are subject to change. Please reach out prior to any visits to ensure all requirements can be met
If at any time an employee of the A/E firm is found in deficiency of these requirements a stop work order will be issued for safety of VA Maine (Togus VAMC) patients and staff. Please refence the below documents
▪ Seasonal influenza with Vaccines (SOW Attachment 6a)
▪ COVID Vaccinations (SOW Attachment 6b)
3. DESIGN WITHIN FUNDING LIMITATIONS:
The design shall be prepared by the A/E to permit the award of a construction contract, using Federal Acquisition Regulation procedures for the construction of the facilities, at a magnitude of construction cost between $2,000,000 and $5,000,000.
4. DESIGN INDEPENDENCE, FURNITURE AND EQUIPMENT: Designs for construction must produce a “complete and usable” facility or improvement when constructed. VA policy (VHA Office of Capital Assets Management, Engineering and Support memo Updated Construction Guidance and Expectations dated Sep 12, 2016) requires the A/E to certify that their design (including all bid alternates/bid deducts) is independent of any future construction project. In addition, the A/E must certify that it has produced a design that does not include furniture and equipment that will be procured separately. Equipment that can be part of the design in the includes those items to meet code requirements for building occupancy, items covered in the VA’s Master Construction Specifications (PG-18-1) Divisions 1 through 10, 13 through 26 or 28 through 48, non-IT equipment items covered by Division 27 and items covered by Division Numbers 12 31 00, 12 32 00, 12 34 00 and 12 36 00.
The A/E shall submit as part of the Final Bid Documents submittal a signed letter on company letterhead stating the design’s independence.
5. DESIGN CRITERIA: The VA Technical Information Library (TIL) available at http://www.cfm.va.gov/til/index.asp is managed by the VA Office of Construction and Facility Management and is the master repository for all VA Numbered Standards for Construction to include design and construction specifications, procedures, standard details, BIM/CAD standards, equipment guides, space planning and design guides. The documents of the TIL shall be the minimum design criteria for all VA projects performed in the construction of new facilities and the modernization, alteration, addition, or improvement of its real property. All design documents shall be developed in accordance with the VA TIL, including (but not limited to) the following listed Department of Veterans Affairs References:
• PG-18-1 Master Construction Specifications
• PG-18-3 Design and Construction Procedures
• PG-18-4 Standard Details and CAD Standards
• PG-18-5 Equipment Guide List
• H-18-8 Seismic Design Handbook
• PG-18-9 Space Planning Criteria, and VA-Space & Equipment Planning System (VA-SEPS)
• PG-18-10 Design Manuals (by discipline)
• PG-18-12 Design Guides (graphical, by function)
• PG-18-13 Topic Specific Standards and Criteria
• PG-18-14 Room Finishes, Door, and Hardware Schedule
Change Summary
• PG-18-15 Minimum Requirements for A/E Submissions http://www.cfm.va.gov/til/index.asp https://www.cfm.va.gov/TIL/spec.asp https://www.cfm.va.gov/TIL/cPro.asp https://www.cfm.va.gov/TIL/sDetail.asp https://www.cfm.va.gov/TIL/equip.asp https://www.cfm.va.gov/TIL/seismic.asp https://www.cfm.va.gov/TIL/planning.asp https://www.cfm.va.gov/til/dManual.asp https://www.cfm.va.gov/til/dGuide.asp https://www.cfm.va.gov/til/topicSpecific.asp https://www.cfm.va.gov/til/room/RoomFinishes.pdf https://www.cfm.va.gov/til/room/RoomFinishesSumm.pdf https://www.cfm.va.gov/til/aeDesSubReq.asp
• PG-18-17 Environmental Guidance
• D-7545 Cultural Resource Management
• H-7545 Cultural Resource Management Procedures
• SOW Attachment 1- VHA Required Division 01 Specification Section List
The following references should also be used to complete the design documents:
• USP 795 Pharmaceutical Compounding—Nonsterile Preparations
• USP 797 Pharmaceutical Compounding—Sterile Preparations
• USP 800 Hazardous Drugs—Handling in Healthcare Settings
Where conflicts exist between VA adopted codes and standards and the documents on the TIL, the A/E shall bring this to the attention of the VA. The resolution of the conflict shall be made by the authority having jurisdiction for VA to ensure consistency department wide.
6. DESIGN COLLABORATION: The A/E during this design project shall collaborate with the VHA Office of Healthcare Environment and Facilities Programs Special Engineering Program (HEFP/SEP) staff, VISN 1 staff, and the Independent Life Safety Review Agent (LS Agent) for the project. Design submittal comments from these contractors, if concurred with by VA, shall be incorporated into the design.
HEPF/SEP and/or VISN deliverables shall be coordinated with the A/E’s design submittals to ensure compliance with all requirements are met. The A/E is required to ensure all elements of the design adhere to the Life Safety Code, including recommendations for temporary construction barriers, prior to the Independent Life Safety review.
7. INDEPENDENT LIFE SAFETY REVIEW: The A/E shall incorporate any comments from the VA 3rd party life safety review.
8. ENVIRONMENTAL PROTECTION: The A/E shall assist the VA with completion of a National Environmental Policy Act (NEPA) assessment as required by the VA Maine Health Care System (Togus VAMC), Augusta, ME. If the NEPA assessment results in potential environmental impacts, the A/E shall be responsible for completing any auxiliary documentation required per PG-18-17 NEPA Interim Guidance for Projects located on the TIL (http://www.cfm.va.gov/til/etc/NEPAGuidance.pdf). Additional requirements may include, but are not limited to, Environmental Assessment, Environmental Impact Statement, and Record of Decision. The NEPA analysis and concluding documentation must be completed by the Final Bid Documents submittal.
9. PHYSICAL SECURITY DESIGN: The A/E must include a certified physical security specialist. The specialists must be involved with the design beginning with the concept phase and the qualifications must be submitted to the COR for review and approval prior to the concept/basis of design phase. The specialists shall meet the specific requirements listed in the Physical Security Design Manual for Mission Critical Facilities located on the TIL (DESIGN MANUALS (PG-18-10) - Office of Construction & Facilities Management (va.gov)). The A/E shall ensure that all aspects of the applicable VA Physical Security Design Manual (either Life-Safety Protected or Mission Critical Facilities; both will be applicable depending on the area the work is taking place) are incorporated into the design and shall prepare a written report acknowledging compliance as required by the VAMC. The A/E must inform the COR of https://www.cfm.va.gov/environmental/index.asp https://www.va.gov/vapubs/viewPublication.asp?Pub_ID=583&FType2 https://www.va.gov/vapubs/viewPublication.asp?Pub_ID=584&FType2 https://www.usp.org/compounding/general-chapter-795 https://www.usp.org/compounding/general-chapter-797 https://www.usp.org/compounding/general-chapter-hazardous-drugs-handling-healthcare http://www.cfm.va.gov/til/etc/NEPAGuidance.pdf https://www.cfm.va.gov/til/dManual.asp#PSR https://www.cfm.va.gov/til/dManual.asp#PSR any physical security items that will be difficult to achieve during the concept/basis of design phase of the design and assist the VA with waiver requests as necessary.
10. TELECOMMUNICATIONS DESIGN: In accordance with “Telecommunications and Special Telecommunications Systems Design Manual,” February 2016 (https://www.cfm.va.gov/til/dManual/dmTelecomm.pdf), paragraph 1.2 (d), Telecommunications design must be performed and stamped by a BICSI Registered Communications Distribution Designer (RCDD) for all projects. The A&A requirements do not apply, and that a Security Accreditation Package is not required:
11. SUBMITTAL REQUIREMENTS: Design submittals shall follow the requirements of Program Guide, PG-18-15, Volume C - A/E Submission Instructions for Minor and NRM Construction Program dated November 2008. This document is included as SOW Attachment 05. Submittal documents shall be prominently marked “For Official Use Only (FOUO)” if they contain qualifying data as defined in VHA Memorandum 2019-11-13 Sensitive Infrastructure Data Classification – For Official Use Only (FOUO).
This memo is included as SOW Attachment 03, as it is hosted on a non-public VHA site (https://vaww.va.gov/vhapublications/ViewPublication.asp?pub_ID=8949).
The A/E shall deliver design submittal documents that follow the iterative phase breakdown for design work in PG-18-15 and as additionally specified below. Specific requirements for each discipline/work product listed under each phase can be found in PG-18-15; it is expected for the phase of design that each of the checked items in the SD/DD/CD columns will be completed for the submittal. The A/E shall attend a review meeting following each design submittal as indicated under the Project Schedule section of this Scope of Work. Each new submittal will incorporate all VA comments from the previous submittal. The Asbestos Abatement & Lead Abatement requirements in PG-18-15 are applicable at VA Maine Health Care System (Togus VAMC), Augusta, ME due to the age of the campus (construction of some existing buildings began in the 1890’s and continued through the present. Buildings dating from all decades are present on the Togus campus).
The following submittals will be required for this project:
▪ Quality Assurance/Quality Control (QA/QC) Plan
▪ Basis of Design (BD) - 10% - In addition to the requirements in PG-18-15, a Basis of Design is required. Basis of Design is a narrative presentation of facts, sufficiently complete, to demonstrate that the project concept is fully understood, and that subsequent design details, and their ultimate presentation in the final drawings and specifications, will be based on sound architectural and engineering decisions. Conceptual drawings of the planned design and the initial cost estimate will additionally be included.
▪ Schematic Design (SD)- 35%
▪ Design Development One (DD) – 65%
▪ Construction Documents (CD)- 95%
▪ Final Bid Documents (Bid) – 100%
12. DRAWING FORMAT:
All drawings shall adhere to VA project software requirements for Computer Aided Design (CAD) available at http://www.cfm.va.gov/til/projReq.asp. Software shall be AutoCAD 2020 or the latest https://www.cfm.va.gov/til/dManual/dmTelecomm.pdf https://vaww.va.gov/vhapublications/ViewPublication.asp?pub_ID=8949 http://www.cfm.va.gov/til/projReq.asp version available to VA Maine Healthcare System (Togus VAMC). Verify latest version available at the project’s design kickoff meeting.
The A/E shall provide various 3D renderings to present to VA throughout the design phase to adequately represent architectural, mechanical/electrical/plumbing (MEP), site conditions and other items in the design to aide with facility visualization and coordination.
VA Maine Healthcare System (Togus VAMC) buildings are extremely congested with existing utilities.
Completed and submitted drawings shall clearly show the exact pathways, with dimensions, of all telecommunications runs under this project. Pathways shall be fully researched during design and graphically depicted in detail to clearly identify the route of each pathway for conduit and cable.
Schematically showing pathways and circuits will not be accepted as part of a complete drawing submission for the telecommunications disciplines.
VA Maine Healthcare System (Togus VAMC) 1 VA Center 03/28/2022 Augusta, ME 04330
13. SUBMITTAL FORMATS: Submittals shall be submitted in electronic format and hard copy formats as listed below. Portable Document Format (.pdf), Microsoft Office Suite formats (.doc, .xls, and .ppt), Microsoft Project (.mpp) and AutoCAD (.dwg) files are acceptable. Submittals shall additionally be compliant with Section 508 of the Rehabilitation Act (29 U.S.C. 794 d); information on the requirements for accessible media can be found at http://www.section508.gov/. The A/E shall be responsible for providing:
Meeting/Conference Minutes Meeting minutes for all formal meetings and conferences held with the VA; including weekly construction meetings. Meeting minutes shall be submitted within seven (7) calendar days of the meeting or conference. All documents shall be in the electronic formats listed above.
Minimum meeting minutes requirements
• Project name, number, meeting host, Meeting Name
• Date, Time, meeting ID, call in number, Duration, and consecutive number of total related meetings
• Participant list (Name, Title, Phone number (office and Mobile), Email, Attended Meeting (yes/no Check box)
• Meeting purpose, Roll call, COVID-19, and Additional Items
• Agenda items (Decisions, action items, and fixes or next steps)
• Next meeting date and time
• Detailed attachment list
Construction Cost Estimates Construction cost estimates shall comply with Manual for Preparation of Cost Estimates & Related Documents for VA Facilities dated February 1, 2019. This document is available on the TIL at http://www.cfm.va.gov/cost/index.asp. All estimates in any of the electronic formats listed above.
Quality Assurance/Quality Control (QA/QC) Plan
▪ All documents in any of the electronic formats listed above.
Basis of Design (BD)
▪ All documents in any of the electronic formats listed above.
▪ Two (2) half-size paper bond sets of drawings – 2 to VA
Schematic Design (SD)
▪ All documents in any of the electronic formats listed above.
▪ Two (2) half-size paper bond sets of drawings – 2 to VA
▪ Two (2) paper bond sets of specifications – 2 to VA
▪ Two (2) paper bond sets of investigation reports, design calculations, space planning data and cost estimate - 2 to VA
Design Development (DD), and Construction Documents (CD)
▪ All documents in any of the electronic formats listed above.
▪ Memo annotating what was not upgraded and corresponding justifications.
http://www.section508.gov/ http://www.cfm.va.gov/cost/index.asp
▪ One (1) full size paper bond sets of drawings - 1 to VA
▪ Two (2) half-size paper bond sets of drawings – 2 to VA
▪ Two (2) paper bond sets of specifications – 2 to VA
▪ Two (2) paper bond sets of investigation reports, design calculations, space planning data, construction schedule, construction statement of work (SOW) and cost estimate - 2 to VA
Final Bid Documents (Bid)
▪ PDF files of drawings, specifications, and any miscellaneous design analysis documents such as submittal log and physical security compliance report.
▪ Certified memo annotating what areas/times were not upgraded and the corresponding justifications.
▪ Certified memo that the A/E design is independent of future projects and includes all equipment required for the project to be activated/full functional.
▪ Word files of specifications.
▪ Revit and AutoCAD files of drawings.
▪ One (1) full size paper bond sets of drawings - 1 to VA
▪ Two (2) half-size paper bond sets of drawings – 2 to VA
▪ Two (2) paper bond sets of specifications – 2 to VA
▪ One (1) paper bond sets of investigation reports, design calculations, space planning data, construction schedule, construction SOW and cost estimate - 1 to VA
Construction Period Services (CPS)
Requests for Information (RFI) Requests for Information shall be submitted within three (3) calendar days of submittal to the A/E.
Submittal Reviews Submittal reviews shall be submitted within seven (7) calendar days of submittal to the A/E.
Site Visit Reports Site visit reports shall be submitted within seven (7) calendar days of the visit. All documents in any of the electronic formats listed above.
Modification/Change Order Requests Modification requests shall be submitted within seven (7) calendar days of submittal to the A/E.
This includes the review of the contractor’s change order/modification proposal for construction change orders, as well as the formulation of an IGCE for the modification, as requested. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.” All documents in any of the electronic formats listed above. Note - If major modification, VA will provide additional time and document format guidance.
Punch List
Punch list shall be submitted within seven (7) calendar days of the final acceptance inspection.
All documents in any of the electronic formats listed above.
Record Drawings Record drawings shall be delivered to the VA within thirty (30) calendar days after VA acceptance of the construction project. Record drawings shall be in AutoCAD (.dwg) format and fully compliant with all VA CAD standards.
14. PROJECT SCHEDULE/PERIOD OF PERFORMANCE: The A/E shall perform Part One Services/Design Phase work according to the schedule shown below. The A/E is also responsible for following specification Section 01 32 16.10 Architectural And Engineering CPM Schedules, which is located in SOW Attachment 05 – Pharmacy Renovation CPM Schedule. If a due date on the timeline below falls on a Holiday or Weekend, the submittal shall be due the following business day. The remaining timeline will not be shifted to accommodate Holidays or Weekends.
Administrative Time 14 calendar days after receipt of Notice of Award
QA/QC Submittal & Basis of Design
(BD) 10% Submittal 21 calendar days after end of Administrative Time
QA/QC and BD 10% Submittal
Review Meeting
7 calendar days after VA receipt of QA/QC & BD 10%
Submittals
35% SD Submittal 28 calendar days after acceptance of QA/QC & BD
10% Submittals
35% SD Review Meeting 21 calendar days after VA receipt of 35% SD Submittal
65% DD Submittal 35 calendar days after VA acceptance of 35% SD
Submittal
65% DD Review Meeting 21 calendar days after VA receipt of 65% DD
Submittal
95% CD Submittal 28 calendar days after VA acceptance of 65% DD
Submittal
95% CD Review Meeting 21 calendar days after VA receipt of 95% CD Submittal
Final Bid Documents Submittal 14 calendar days after VA acceptance of 95% CD
Submittal
Final Bid Documents Acceptance
Meeting 14 calendar days after VA receipt of Final Bid
Documents Submittal
Total Part One Services/Design
Phase Schedule 224 Calendar Days
The 180 days listed in the part one project schedule may fluctuate based on when each submittal, especially the 95% CD submittal, is determined to meet all VA guidelines and acceptance is issued. If any submittal is not accepted due to insufficient design requirements or failing to meet all VA contract, submittal, and content requirements and additional time is deemed necessary, it is the responsibility of the AE firm to cover all costs associated with such delays and required revisions.
Part Two Services/Construction Period Services (optional Line Items) shall be performed for the length of time between the time the option(s) are exercised and acceptance of Construction Completion. The VA has 365 calendar days from final acceptance of the design to exercise the option(s) for Construction Period Services.
15. CONTRACT OVERSIGHT: All contracts for this project shall be awarded by the NCO-1 (local contracting); only a warranted VA Contracting Officer shall have authority to change the terms and conditions of a contract. These changes may involve the contract award amount, contract period of performance, issuance of stop work orders and changes to the statement of work.
NCO-1 shall designate a Contracting Officer’s Representative (COR) to monitor and manage the A/E’s performance under the design project contract. The COR shall be a representative of the VA Maine Healthcare System (Togus VAMC) Facilities Management Service Project Section and have the technical knowledge required to monitor and oversee the project.
A COR from the VA Maine Healthcare System (Togus VAMC) Facilities Management Service Project Section shall also be designated for the construction project contract to monitor and manage the construction contractor’s performance under the construction project contract. This designation under the construction contract shall be considered equivalent to the industry standard of “Owner’s Representative” and does not supersede or eliminate the A/E’s responsibility for Part Two Services/Construction Period Services. The A/E ultimately shall be responsible for any errors and omissions with the design discovered during and after the construction phase.
16. OI&T INFRASTRUCTURE STANDARD FOR TELECOMMUNICATION SPACE:
The current version for this standard is version 3.1, dated July 1, 2021 (https://www.cfm.va.gov/til/dguide/OIT-InfrastrucStdTelecomSpaces.pdf). The design for this project at The VA Maine Healthcare System (Togus VAMC) must meet the Campus Support Center (CSC) requirements of the Infrastructure Standard for Telecommunications Spaces.
The Infrastructure Standard for Telecommunications Spaces (The Standards) serves as the master reference document of criteria for Department of Veterans Affairs (VA) facility Information Technology (IT) support infrastructure. It defines the technical requirements necessary to maintain optimum reliability and efficiency within VA facilities and computing centers. IT Support Infrastructure is defined as all passive telecommunications and information technology equipment and supporting physical space and equipment.
17. VISITOR SECURITY & REPORTING REQUIREMENTS:
https://www.cfm.va.gov/til/dguide/OIT-InfrastrucStdTelecomSpaces.pdf
Visitors to the pharmacy requires a full-time escort. A/E should bring minimum required personnel for field verification. Multiple trips may be necessary.
All contractor personnel will be required to complete a background check by VA Police and receive a badge prior to being permitted to work on campus. This check is mandatory and will be conducted by VA Police based on information provided by the personnel who will be onsite. The selected AE will be provided the background check forms to fill out during the ‘Administrative Time’ portion of the schedule. These forms shall be returned to the COR during this same portion of the schedule.
Upon their first visit to campus, personnel shall check in with the COR at the designated time and location. They will then be escorted to the VA Police to receive their badge. Badges can be issued for up to 1 year if the same personnel will be returning to site during future visits.
Once badges have been obtained, personnel are required to check in with the COR upon arrival and upon departure from campus each day. Badges must be worn in a visible location at all times when contractor personnel are onsite.
18. SOW and ATTACHMENTS:
The following list of documents are attached to this SOW for A/E use and incorporation into the project documents:
▪ VHA Required Div 01 Specification Sections (See SOW Attachment 01)
▪ PG 18-12 Pharmacy Service Design Guide (See SOW Attachment 02)
▪ Sensitive Infrastructure Data Classification FOUO (See SOW Attachment 03)
▪ 01 32 16.01 Pharmacy Renovation CPM Schedule (See SOW Attachment 04)
▪ Program guide, PG-18-15 Volume C – A/E Submission Instructions for Minor and NRM
Construction program dates November 2008 (See SOW Attachment 05)
▪ Seasonal influenza with vaccines (See SOW Attachment 06a)
▪ COVID Vaccinations (See SOW Attachment 06b)
▪ VHA Directive 1061 Prevention of Healthcare Associated Legionella Disease (See SOW Attachment
07)
▪ Campus Map (See SOW Attachment 08)
▪ Outpatient Floor Plan (See SOW Attachment 09)
▪ Inpatient Floor Plan (See SOW Attachment 10)