About this file

This document contains a market research questionnaire and related federal contract opportunity notice regarding a project to replace the fire alarm system at the Federal Correctional Institution in Loretto, Pennsylvania. The Bureau of Prisons is seeking a contractor to remove and replace approximately eighteen existing fire alarm panels, one hundred fifty manual pull stations, eight hundred seventy-five smoke detectors, and other related components. The work must be completed within 280 calendar days and will require inspection of existing wiring, providing as-built drawings, and ensuring the new system communicates properly with the main control panel. Interested small businesses meeting the $19 million size standard are requested to respond with their contact and capability information by June 19, 2023. The subsequent solicitation will have an estimated value between $1-5 million and utilize NAICS code 238210 for electrical contractors.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Justice Federal Bureau of Prisons Field Acquisition Office

U.S. Armed Forces Reserve Complex Grand Prairie, Texas 75051

June 7, 2023

MARKET RESEARCH QUESTIONNAIRE

Building and Facilities Section (B&F) FCI Loretto Replace Fire Alarm

The Federal Bureau of Prisons (FBOP) is conducting market research in accordance with Federal Acquisition Regulation, Part 10. The FBOP anticipates a single solicitation will be issued to (Replace Fire Alarm). The FBOP, Federal Correctional Institution Loretto (FCI Loretto) located at 772 Saint Joseph Street in Loretto Pennsylvania, intends to make a single award to a responsible entity that will provide all necessary equipment, labor, materials, and incidentals to complete the Replace Fire Alarm System at FCI Loretto.

This market research questionnaire is for information purposes only. The statement of work will provide detailed information for the requirement. The project has a performance period of 280 calendar days. The described requirement and specifications are subject to change.

A summary of the requirements is as follows: The contractor shall be responsible for removing and replacing approximately eighteen (18) existing fire alarm panels, one hundred fifty (150) manual pull stations, eight hundred seventy-five (875) smoke detectors, twenty (25) duct smoke detectors, two hundred thirty (230) heat detectors, one hundred eight (108) remote test switch/indicator for duct detectors, one hundred (100) horn/strobes, thirty (30) water flow switches, thirty (30) tamper switches, two hundred ten

(210) monitoring modules, twenty five (25) control modules. All newly installed fire alarm panels and related components and systems, upon completion of installation, shall be tested by the contractor to demonstrate system functionality. All equipment specified in this statement must be brand name or an equal product. Should your firm choose to submit an equal product, you must submit all technical specification of the equal product to be analyzed and a technical determination issued with acceptance/non-acceptance. The government retains the right to determine technical acceptance for all submitted equal products. For security and safety purposes, at no time shall more than one fire alarm system be non-operational at a time without the authorization of the Contracting Officer's Representative (COR).

All related components shall be replaced to create a fully functional alarm system in each installation, and as a whole system. All existing fire alarm panel's report error conditions to the main panel in the Control Center. It is the contractor's responsibility to ensure each new alarm panel will continue to communicate with the main panel in the Control Center.

The contractor shall determine the existing wiring can be utilized and meet or exceed per NFPA 70 2023, National Electrical Code, NFPA 72 2022, National Fire Alarm and Signaling Code. The contractor shall also inspect all splices and junctions in the existing system. Should faulty wiring be located contractor will inform in the COR. The contractor to ensure all connections are labeled. It shall be the Contractors responsibility to obtain all measurements and manufactures installation recommendations.

The FBOP will occupy the site during the entire construction period. Contractor shall perform the work to not interfere with the FBOP's operations as minimal as possible. After major construction activities have been completed, the contractor shall provide a set of AutoCAD as-built drawings to the Contracting Officer's Representative (COR). Drawings will be in DWG format.

Please answer the following questions:

1. Can your firm complete the Replace Fire Alarm project at the institution specified above?

Yes No

2. If you answered “No” in Question 1 above, what construction requirements can your firm provide?

3. The North American Industrial Classification System (NAICS) code for Electrical Contractors and Other Wiring Installation Contractors is 238210, which sets the small business standard at $19.0 million.

Based on this standard, what is your business size, small or large?

Small Large

4. What level of subcontracting, if any, would your firm utilized to provide the listed requirement?

5. Are you eligible for participation in one of the following small business programs? If so, please indicate the program.

“8(a)” Program Women-Owned Small Business concern Economically Disadvantaged Women-Owned Small Business concern HUBZone Small Business concern Veteran-Owned Small Business concern Service-Disabled Veteran-Owned Small Business concern

6. The Performance Period estimated for this project is 280 calendar days for the base period. Does this time frame appear to be suitable for your firm to complete the requirement?

Yes No

If not, what time frame in calendar days would it take your firm to complete?

Calendar Days

7. How many calendar days does your firm need to prepare a bid/proposal resulting from this solicitation?

45 days 60 days

8. After reviewing the above proposed work, are there any industry recommendations you’d suggest other that what we’ve provide in our description?

9. If you were to complete this work, where do you estimate your pricing range?

Between $100,000 and $250,000.

Between $250,000 and $500,000.

Between $500,000 and $1,000,000.

Between $1,000,000 and $5,000,000.

Between $5,000,000 and $10,000,000.

More than $10,000,000.

10. If awarded a contract, how many calendar days after the award could you begin construction?

Please note that all individuals working on site at the institutions must undergo a security clearance investigation. This investigation may take 60 calendar days or longer to complete.

Calendar days after Contract Award

11. Please furnish the following information in reference to your firm:

Name:

Address:

Point of Contact:

Telephone Number:

E-mail Address:

UEI:

Please e-mail your responses to knjohnson@bop.gov include any additional question you may have.

Responses must be received no later than June 19, 2023.

A few notes regarding all FBOP requirements:

1. The resulting solicitation will be distributed solely through the General Services Administration System for Award Management (SAM) website at sam.gov. Hard copies of the solicitation are not available. The website provides download instructions to obtain all documents relating to the solicitation. All future information concerning this acquisition, including the pre-solicitation notices, solicitation, and any subsequent amendments, will be distributed solely through the website. Interested parties are responsible for monitoring the website to ensure they have the most current information about the acquisition.

2. Any contractor interested in obtaining a contract award with the Federal Bureau of Prisons must be registered in the System for Award Management (SAM) at www.sam.gov. In order to qualify for award, your business size metrics information entered in your SAM registration must be less than or equal to the size standard specified above. You must also have the NAICS code stated.

Each bidder's SAM registration will be reviewed by the Government to confirm that your business size meets the small business size standard requirement and the stated NAICS code is listed. All bidders are urged to double check their SAM registration and update as necessary, including the size metrics information and NAICS code.

https://beta.sam.gov/ http://www.sam.gov/

This market research questionnaire is for information purposes only. The statement of work will provide detailed information for the requirement. The project has a performance period of 280 calendar days. The described requirement and specifications a...
A summary of the requirements is as follows: The contractor shall be responsible for removing and replacing approximately eighteen (18) existing fire alarm panels, one hundred fifty (150) manual pull stations, eight hundred seventy-five (875) smoke de...
All related components shall be replaced to create a fully functional alarm system in each installation, and as a whole system. All existing fire alarm panel's report error conditions to the main panel in the Control Center. It is the contractor's res...
The contractor shall determine the existing wiring can be utilized and meet or exceed per NFPA 70 2023, National Electrical Code, NFPA 72 2022, National Fire Alarm and Signaling Code. The contractor shall also inspect all splices and junctions in the ...
The FBOP will occupy the site during the entire construction period. Contractor shall perform the work to not interfere with the FBOP's operations as minimal as possible. After major construction activities have been completed, the contractor shall pr...
A few notes regarding all FBOP requirements: