This sources sought notice is seeking capability statements from businesses interested in performing Lock Wall Modifications at Lock & Dam 25 on the Mississippi River. The project consists of installing new floating mooring bitts and line hooks at three locations and filling in an unused miter gate recess. Work will be performed using marine construction equipment in localized cofferdams and includes concrete demolition and reconstruction, installation of reinforcing steel and concrete, fabrication and installation of miscellaneous metals and lock wall appurtenances, and electrical work. Interested businesses must be System for Award Management registered and email capability statements by March 21, 2022 to the point of contact. Statements should provide business information, examples of relevant past work as a prime contractor bonded for up to $5 million, and experience with marine cranes, lock and dam rehabilitation, major concrete structure work, and electrical utility work. The contract is anticipated to be firm-fixed-price for $1-5 million with a period of performance of 365 days.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sources Sought Notice W912P922Z0010

LOCK & DAM 25 LOCK WALL MODIFICATIONS

PHASE 1 OF NAVIGATION ECOSYSTEM RESTORATION PROGRAM

This announcement is for information and planning purposes only and is not to be construed as a commitment by the Government, implied or otherwise, to issue a solicitation or make a contract award. NO AWARD will be made from this Sources Sought Notice. This is NOT a request for proposal, quote, or invitation for bid. The sole purpose of this notice is to identify potential System for Award Management (SAM) Database registered businesses that are interested and capable of performing this work. USACE is not responsible for any costs incurred by interested parties in responding to this Sources Sought.

POINT OF CONTACT: Whitney Dee, Contract Specialist - whitney.r.dee@usace.army.mill

PROJECT INFORMATION

The U.S. Army Corps of Engineers (USACE), St. Louis District, is seeking businesses that are interested in and capable of performing Lock Wall Modifications at Lock & Dam 25 located on the Mississippi River near Winfield, Missouri, approximately 61.5 river miles upstream from St.

Louis and 241.5 miles above the mouth of the Ohio River. The project consists of a main lock, an incomplete auxiliary lock, a dam containing fourteen tainter gates, and three roller gates. The main lock is 600 ft by 110 ft with a set of miter gates at the upstream and downstream ends. The contract is anticipated to be a Firm-Fixed-Price Construction contract using Subjective Best Value Trade-off evaluation methods. The anticipated period of performance for this project is 365 days.

NAICS CODE: 237990 Other Heavy and Civil Engineering Construction

SIZE STANDARD: $39.5M

CONTRACT ESTIMATED RANGE: Between $1,000,000 and $5,000,000

PROJECT DESCRIPTION

The work will consist of furnishing all labor, equipment, operators, supervision, supplies and materials, and incidentals necessary to perform the Lock and Dam 25 Lock Wall Modifications that is Phase 1 of the Navigation Ecosystem Restoration Program (NESP) Lock and Dam 25 Project. These modifications include installation of new Floating Mooring Bitts (FMB) and Line Hooks at three (3) locations and filling in the existing miter gate recess along the river side of the intermediate wall. The work is anticipated to be accomplished with traditional river marine construction equipment, such as floating plant and barge mounted crane. Contractor staging will be from the river side of the intermediate wall as the lock will be continuously open to river traffic in the main lock during the construction period. This construction work will be performed mailto:whitney.r.dee@usace.army.mill in localized cofferdams so the work can occur in-the-dry prior to completion of the new 1200-ft lock chamber when the chamber can be unwatered.

The structural work on the project includes, but is not limited to the following:

- Installation of contractor furnished cofferdam to perform the work in-the-dry, use of marine divers to install cofferdam. Removal of existing riprap scour protection to facilitate installation of the cofferdam and reinstallation of scour protection following completion of work.

- Concrete removal via diamond wire saw or other conventional methods, installation of reinforcing steel, formwork, miscellaneous metal and appurtenances for FMB recesses and Line Hooks, and placement of new concrete.

- Concrete removal and existing concrete surface preparation via conventional methods within the unused miter gate recess and miter gate machinery pits, installation of reinforcing steel and dowels and placement of reinforced concrete to fill in the miter gate recess.

- Fabrication of miscellaneous metals and other lock wall appurtenances for FMB recesses and Line Hooks, and installation of the floating mooring bitts within the newly constructed recesses.

The mechanical work on the project includes, but is not limited to the following:

- Fabrication of new floating mooring bitts (FMB) including the ultra-high molecular weight (UHMW) sliding blocks.

- Testing and adjusting new FMB to provide proper flotation height.

The electrical work includes, but is not limited to the following:

- Temporary power for high mast lighting (HML) and navigation light circuits prior to structural demolition for new floating mooring bitt (FMB)

- New conduit and wiring for HML and navigation light circuits in vicinity of new FMB

- Construction of new electrical duct bank between existing manholes

- New feeder to include embedded conduit and cable for relocated boat davit on the river wall

CAPABILITY STATEMENT SUBMITTAL

All interested, responsive and responsible System of Award Management (SAM) Database registered businesses are encouraged to participate in this Sources Sought by emailing the required information below to the point of contact. If your company is not SAM-registered, please do so at www.sam.gov.

Responses are to be sent via email to Whitney Dee no later than 10:00 a.m. CST, 21 March 2022.

http://www.sam.gov/

Interested businesses shall include the following information in their response to this Sources Sought announcement:

1. Please provide business information in the following format:

a. Business Name:

b. Point of Contact: (Name/Phone/Email)

c. Address:

d. Business Size and Category (Large/Small/8(A)):

e. CAGE and/or DUNS Code:

f. Indication of the intent to be a prime contractor or subcontractor

g. Documentation supporting company’s capability to bond projects up to $5,000,000 for a single project as a Prime Contractor.

2. Please provide examples of work that your company has performed as the Prime Contractor in the areas listed below. Include the total contract dollar value and amount bonded by submitting firm as the Prime Contractor. Detail what work was self-performed and what percentage of work was subcontracted. No more than three (3) projects should be provided to demonstrate competency and experience in the required areas of work. Describe past work experience showing all or more than one of the areas listed that were performed under one contract. Projects must have been bonded by submitting firm as the Prime Contractor to be considered.

Areas of work involving characteristics that are similar to the types of work described herein:

• Marine crane applications and experience

• Lock and Dam Rehabilitation work on or around river/marine environment.

• Concrete demolition and reconstruction of major concrete structures

• Utility work involving ability to locate embedded piping, raceway/circuits, experience with installation of electrical duct banks and implementing electrical safety procedures including lock-out/tag-out.