Text version
WOONSOCKET FLOOD CONTROL PROJECT
JOSEPH ZANCA
121 SOUTH MAIN STREET
WOONSOCKET RI 02895
TEL: 978-318-8419 FAX: 508-347-8732
W13G86102842960001
REQUEST FOR QUOTATIONS
(THIS IS NOT AN ORDER) 1
PAGE OF PAGES
1. REQUEST NO. 2. DATE ISSUED RATING
W912WJ21Q0072 05-Apr-2021 5a. ISSUED BY
8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State, and local taxes)
ITEM NO.
(a)
SUPPLIES/ SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e) (f)
SEE SCHEDULE
AMOUNT
% No. %
NOTE: Additional provisions and representations [ ] are [ ] are not attached.
13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION
16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)
TELEPHONE NO.
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)
PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)
THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE
6. DELIVER BY (Date)
SEE SCHEDULE
AND/OR DMS REG. 1
UNDER BDSA REG. 2
4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE
REQUEST NO.
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
9. DESTINATION (Consignee and address, including ZIP Code)
7. DELIVERY
[ ]X FOB
DESTINATION
[ ] OTHER
(See Schedule)
16-Apr-2021(Date)
PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.
978-318-8256FRED E RILEY
(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:
d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS
W912WJ21Q0072
Section B - Supplies or Services and Prices
INSTRUCTIONS TO OFFERORS
*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE 52.236-27
FOR ADDITIONAL INFORMATION.
*PLEASE DIRECT QUESTIONS TO FRED E. RILEY AT (978) 318-8326 or
FRED.E.RILEY@USACE.ARMY.MIL. ANY INFORMATION RECEIVED AT THE SITE VISIT WHICH
CONFLICTS WITH THIS SOLICITAION SHOULD BE BROUGHT TO THE ATTENTION OF FRED RILEY.
THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE GOVERNING DOCUMENT IN ALL
CASES.
**QUOTES CAN BE E-MAILED TO FRED RILEY AT FRED.E.RILEY@USACE.ARMY.MIL.
NOTE 1: In accordance with FAR Part 28.101-1(c), the Contractor will NOT be required to provide a Bid Guarantee.
NOTE 2: In accordance with FAR Part 28.102-1(b), the Contractor will be required to provide the following payment protections for all construction contracts greater than $150,000.00.
(i) Payment Bond or
(ii) Irrevocable Letter of Credit and
(iii) Performance Bond
NOTE 3: In accordance with FAR Part 28.102-1(c), the Contractor will be required to provide one of the following payment protections for all construction contracts greater than $35,000.00 but not greater than $150,000.00.
(i) Payment bond or
(ii) Irrevocable letter of credit
A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.
**No Payment Protections Required for construction contracts less than $35,000**
NOTE 4:
QUOTATION INSTRUCTIONS:
1. If subcontractor will be used for this work, please provide company names:
2. In accordance with FAR Part 52.204-7(b)(1) Contractors must be registered in the System for Award Management (SAM) database (www.SAM.gov) to submit an offer. (Formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA).) Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website. Please note that Google and Google Chrome are not supported browsers for SAM registration. Mozilla FireFox, Safari, and Internet Explorer are supported browsers.
NOTE: SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks.
In addition, if you are registering a new entity in SAM.gov, you must provide an original, signed notarized letter stating that you are the authorized Entity Administrator. The Entity Administrator must establish a LOGIN.GOV account using the e-mail address that will be associated with the SAM registration. See https://www.gsa.gov/about-us/organization/federal-acquisition-service/office-of-systems-management/integrated-award-environment-iae/sam-update for additional information.
3. Provide business DUNS number: _______________________________ (phone 800-333-0505 for DUNS).
4. Provide business CAGE code: __________________________________
5. Tax Identification Number: ___________________________________
6. Contractors shall provide completed FAR clause 52.204-8 (Annual Representations and Certifications) found in Section K of this solicitation with their quote, if the Contractors have not completed their annual representations and certifications electronically via the SAM website at www.sam.gov. (See Paragraph 2 above).
7. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful offeror will be required to submit this document at the direction of the Technical Point of Contact. The APP must be accepted by the Government Designated Authority prior to the commencement of work.
POTENTIAL QUOTERS ARE NOTIFIED THAT THE BASIS ON WHICH AWARD WILL BE MADE IS
PRICE ALONE.
ALL RESPONSIBLE SOURCES MAY SUBMIT A RESPONSE WHICH, IF TIMELY RECEIVED, MUST
BE CONSIDERED BY THE AGENCY.
INVOICES SHALL BE SENT TO TECHNICAL POINT OF CONTACT.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Woon Trash Rack Replacement
FFP
Contractor shall furnish all labor, materials, supplies, equipment, and transportation necessary to remove the existing trash racks from the Social Pumping Station and Hamlet Pumping Station, and replace with new, stainless steel trash racks in accordance with the Statement of Work.
FOB: Destination
PURCHASE REQUEST NUMBER: W13G86102842960001
PSC CD: Y1QA
NET AMT
Section C - Descriptions and Specifications
STATEMENT OF WORK
WOONSOCKET FLOOD REDUCTION PROJECT
SOCIAL AND HAMLET PUMPING STATIONS
TRASH RACK REPLACEMENT
US ARMY CORPS OF ENGINEERS
STATEMENT OF WORK
Woonsocket, RI.
I. GENERAL
1. Scope Furnish all equipment, materials and labor for the Woonsocket Flood Reduction Project (WFR), Social Pumping Station and Hamlet Pumping Station, replacement of existing steel coal tar epoxy coated trash racks with uncoated stainless steel, in Woonsocket, RI, for the purpose of facility maintenance.
2. Location The required services shall be performed at the following project site location:
Hamlet Pumping Station 151 Davidson Ave Woonsocket,RI Social Pumping Station 595 Clinton Street Woonsocket, RI.
3. Site Visits and Requests for Information Contact the Technical Point of Contact, Drew McInerny 978-318-8427 or drew.g.mcinerny@usace.army.mil to arrange a site visit.
4. Schedule The contractor shall commence work within 14 Calender days after Notice to Proceed. The period of performance shall be 120 days from Notice to Proceed.
The project area will be open to the contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.
5. Safety
a) General:
All work shall be conducted in accordance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed at the project office or electronically at the following link:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerMan uals/EM_385-1-1.pdf
Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.
b) Accident Prevention Plan:
The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include Activity Hazard Analyses (AHAs) as described below. A non-mandatory, fillable APP template is available upon request. However, the contractor is permitted to submit their own plan, at a minimum it must meet the requirements of EM 385-1-1, Appendix A.
A preparatory meeting shall be conducted by the prime contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
Weekly safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact (TPOC) upon request.
c) Activity Hazard Analysis:
An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.
d) Emergency Response:
Emergency procedures shall be documented in the Accident Prevention Plan and will include a map with directions to the nearest hospital, emergency contact numbers, and onsite First Aid/CPR responders.
e) Required Personnel:
The Contractor shall employ a minimum of one Competent Person (CP) at each project site to function as the Site Safety and Health Officer (SSHO).
The SSHO shall be present at the project site and report to the contractor’s upper management. The SSHO is required to have related construction experience and have at a minimum completed a 10 Hour OSHA training.
In addition, when emergency medical services are not accessible within 5 minutes of the work location and there are 2 or more workers onsite, at least 2 employees shall have (in-person) training in First Aid and CPR. Minimum qualifications are listed in EM 385-1-1, Section 03.A.02.c.
*Note: Other Competent or Qualified Persons may be required per EM 385-1- 1 and/or other sections of this Scope of Work, based on the characteristics of the project*
f) Accident Reporting:
All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the TPOC within four (4) hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D shall be immediately reported to the TPOC. ENG Form 3394 shall be completed and submitted to the TPOC within five (5) working days of the incident.
The Contractor shall compile employee work hours (including subcontractors) and forward the total hours to the TPOC no later than close of business on the 10th calendar day of the following month. The method of transmission by the prime contractor to the TPOC shall be electronically.
6. Preconstruction Conference
Prior to the start of any site work, the Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No site work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction conference the contractor shall provide to the name of the project superintendent with a telephone number for project coordination.
The following is a general list of items for discussion during this Preconstruction Conference:
Authority of the Technical Point of Contact.
Contractor’s Safety Program (including sub-contractors).
Accident Prevention Plan and Activity Hazard Analysis.
Weekly Safety Meetings (Documented on NED Form 251) Accident Reporting (ENG Form 3394) Safety Data Sheet (SDS) requirements Correspondence, Communication and Administrative Procedures.
Invoice and payment.
7. Permits
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.
8. Security The contractor will comply with all established security policies at the Project.
Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least 24 hour notice of any such closure.
9. Payment Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice and a completed, signed US Army Corps of Engineers ENG93 form to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days the contractor may request progress payment.
Invoice/Forms shall be mailed to:
US Army Corps of Engineers 518 East Hartford Ave., Uxbridge, MA 01569-1209 or emailed to joseph.l.zanca@usace.army.mil or faxed to the office at (508) 278-4234.
10. Damage to Government and Private Property The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the firm’s operation. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm’s operations. The Contractor shall notify the Technical Point of
Contact immediately of damage to Government and private property and injury to any person resulting from the firms’ operation.
11. Point of Contact Requirements The Contractor shall provide to the Technical Point of Contact a telephone number and a point of contact for discussion of any contractual matters.
II. TECHNICAL
Requests for Information:
Requests concerning the work of this project should be directed to the Technical Point of Contact. Drew McInerny at (978) 318-8427 or drew.g.mcinerny@usace.army.mil Submittals:
Although the Government reviews submissions for technical data/information required by this Performance Work Statement, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and must be accepted by the Government prior to the commencement of any field activities.
Product specification sheets and cut sheets for new trash racks.
Product specification sheets and cut sheets for all associated hardware.
Manufacturer Warranty for any equipment and hardware.
Abbreviated Accident Prevention Plan (AAPP) – Prior to the start of field work Activity Hazard Analysis – Prior to the start of field work Manufacturer’s product Safety Data Sheets – Prior to ordering
Note: As part of the APP and AHAs include site specific COVID-19 monitoring procedures which address, at a minimum, the following elements:
Procedures for periodic sanitation inspections.
Procedures for disinfecting project sites in accordance with Centers for
Disease Control and Prevention (CDC) guidelines.
Site specific measures to practice social distancing while working on the project.
Employee training on the signs, symptoms, and protection measures in accordance with CDC guidelines.
A list of Personal Protective Equipment (PPE) to be used in accordance with CDC and state guidelines.
Clean Up:
The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area, the contractor shall remove any tools, equipment, and materials that are not the property of the government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.
Government Resources:
The contractor is responsible for providing all materials to complete the project.
Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources.
Omissions:
This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.
Quality Assurance:
The contractor is responsible for the quality control of the contract work. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.
Other Contracts:
The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.
Environmental Protection:
Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis.
No burning is permissible. Water, air and land resources shall not be adversely impacted during the course of the work. Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.
Receiving and Storing Materials:
The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material or supplies for the contractor and will not be responsible for damage to contractor equipment or material.
General:
Existing Conditions:
Social and Hamlet Pumping Stations utilize trash racks which were originally installed in 1969. This contract is to remove the existing worn steel trash racks which have a flaking protective coating (see images 1-3) and replace with new stainless-steel trash racks that meet or exceed the original design
Products:
Trash Racks, hatches, and all components will meet or exceed the specifications as listed below.
1. Social Pumping Station I. Trash Racks (x4)
a) Shall be approximately 7’ ½” (W) X 15’ 11” (H) each
b) Shall be compatible with existing pumping station design.
c) Shall be fit on existing concrete shelf.
d) Shall be made of 316 stainless steel conforming to ASTM standards
e) Shall be welded by certified welder and include copy of all certifications
f) Fittings, brackets, fasteners, and other ferrous metal components will be 316 stainless steel
g) Shall meet or exceed the original design as attached
II. Access Hatch (x1)
a) Shall be a minimum of 24” (W) X 60” (H)
b) Shall be equipped with a latch capable of accepting a
Government issued padlock
c) Shall be made of 316 Stainless Steel conforming to ASTM standards
d) Shall be welded by certified welder and include copy of all certifications
e) Fittings, brackets, fasteners, and other ferrous metal components will be 316 stainless steel
2. Hamlet Pumping Station I. Trash Racks (x2)
a) Shall be approximately 7’ ½” (W) X 15’ 1” (H) each
b) Shall be compatible with existing pumping station design.
c) Shall be fit on existing concrete shelf.
d) Shall be made of 316 stainless steel conforming to ASTM standards
e) Shall be welded by certified welder and include copy of all certifications
f) Fittings, brackets, fasteners, and other ferrous metal components will be 316 stainless steel
g) Shall meet or exceed the original design as attached
II. Access Hatch (x1)
a) Shall be a minimum of 24” (W) X 60” (H)
b) Shall be equipped with a latch capable of accepting a Government issued padlock
c) Shall be made of 316 Stainless Steel conforming to ASTM standards
d) Shall be welded by certified welder and include copy of all certifications
e) Fittings, brackets, fasteners, and other ferrous metal components will be 316 stainless steel
Execution:
Trash rack replacement and installation shall occur in accordance with the scope of work and local and federal laws and the National Building Cod. One pumping station shall be complete before moving on to the next pumping station. Sequence of replacement will be approved by the technical point of contact.
1. Work area will be restricted to contractors and USACE Employees.
2. Work schedule to be approved 48 hours in advance, for each location, due to fluctuating water levels, work must be completed with little to no water in channel
3. Existing coal tar epoxy steel trash rack and associated hardware shall be removed at one location approved by the technical point of contact.
4. New uncoated 316 stainless steel trash rack will be installed on existing concrete abutment at pumping station intake.
5. Contractor will be responsible for disposal of all items removed in this contract.
6. Contractor is responsible for the cleanup of the site.
7. Repeat steps 1-6 for second location as approved by the technical point of contact.
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 120 dys. ANP 1 WOONSOCKET FLOOD CONTROL
PROJECT
JOSEPH ZANCA
121 SOUTH MAIN STREET
WOONSOCKET RI 02895
978-318-8419 FOB: Destination
961314
Section H - Special Contract Requirements
SECURITY REQUIREMENTS
The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the Technical Point of Contact NLT 5 calendar days after the completion of the training.
WAGE DETERMINATION
"General Decision Number: RI20210001 03/05/2021
Superseded General Decision Number: RI20200001
State: Rhode Island
Construction Types: Building, Heavy (Heavy and Marine) and Highway
Counties: Rhode Island Statewide.
BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories) HEAVY, HIGHWAY AND MARINE
CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/01/2021 1 01/22/2021 2 03/05/2021
ASBE0006-006 12/01/2019
Rates Fringes
HAZARDOUS MATERIAL HANDLER
(Includes preparation, wetting, stripping, removal scrapping, vacuuming, bagging & disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems)..............$ 36.60 22.40
ASBE0006-008 09/01/2019
Rates Fringes
Asbestos Worker/Insulator Includes application of all insulating materials, protective coverings, coatings & finishes to all types of mechanical systems.$ 43.60 29.90
BOIL0029-001 01/01/2017
Rates Fringes
BOILERMAKER......................$ 42.42 24.92
BRRI0003-001 06/01/2020
Rates Fringes
Bricklayer, Stonemason, Pointer, Caulker & Cleaner.......$ 42.55 28.02
BRRI0003-002 03/01/2020
Rates Fringes
Marble Setter, Terrazzo Worker & Tile Setter.............$ 40.78 28.92
BRRI0003-003 03/01/2020
Rates Fringes
Marble, Tile & Terrazzo Finisher.........................$ 34.10 27.88
* CARP0330-001 01/01/2021
Rates Fringes
CARPENTER (Includes Soft Floor Layer).....................$ 39.72 28.66 Diver Tender.....................$ 40.72 28.66
DIVER............................$ 51.47 28.66
Piledriver.......................$ 39.72 28.66
WELDER...........................$ 40.72 28.66
FOOTNOTES:
When not diving or tending the diver, the diver and diver tender shall receive the piledriver rate. Diver tenders shall receive $1.00 per hour above the pile driver rate when tending the diver.
Work on free-standing stacks, concrete silos & public utility electrical power houses, which are over 35 ft. in height when constructed: $.50 per hour additional.
Work on exterior concrete shear wall gang forms, 45 ft. or more above ground elevation or on setback: $.50 per hour additional.
The designated piledriver, known as the ""monkey"": $1.00 per hour additional.
CARP1121-002 01/06/2020
Rates Fringes
MILLWRIGHT.......................$ 39.07 29.15
ELEC0099-002 06/01/2020
Rates Fringes
ELECTRICIAN......................$ 41.61 57.24%
Teledata System Installer........$ 31.21 13.10%+14.93
FOOTNOTES:
Work of a hazardous nature, or where the work height is 30
ft. or more from the floor, except when working OSHA-approved lifts: 20% per hour additional.
Work in tunnels below ground level in combined sewer outfall:
20% per hour additional.
ELEV0039-001 01/01/2021
Rates Fringes
ELEVATOR MECHANIC................$ 55.03 35.825+A+B
FOOTNOTES:
A. PAID HOLIDAYS: New Years Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.
B. Employer contributes 8% basic hourly rate for 5 years or more of service of 6% basic hourly rate for 6 months to 5 years of service as vacation pay credit.
ENGI0057-001 12/01/2020
Rates Fringes
Operating Engineer: (power plants, sewer treatment plants, pumping stations, tunnels, caissons, piers, docks, bridges, wind turbines, subterranean & other marine and heavy construction work) GROUP 1.....................$ 42.55 27.70+a GROUP 2.....................$ 40.55 27.70+a GROUP 3.....................$ 36.17 27.70+a GROUP 4.....................$ 33.32 27.70+a GROUP 5.....................$ 39.60 27.70+a GROUP 6.....................$ 30.40 27.70+a GROUP 7.....................$ 24.40 27.70+a GROUP 8.....................$ 36.25 27.70+a GROUP 9.....................$ 40.17 27.70+a
a. BOOM LENGTHS, INCLUDING JIBS:
150 feet and over + $ 2.00 180 feet and over + $ 3.00 210 feet and over + $ 4.00 240 feet and over + $ 5.00 270 feet and over + $ 7.00 300 feet and over + $ 8.00 350 feet and over + $ 9.00 400 feet and over + $10.00
a. PAID HOLIDAYS:
New Year's Day, President's Day, Memorial Day, July Fourth, Victory Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day. a: Any employee who works 3 days in the week in which a holiday falls shall be paid for the holiday.
a. FOOTNOTES:
Hazmat work: $2.00 per hour additional.
Tunnel/Shaft work: $5.00 per hour additional.
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Cranes, lighters, boom trucks and derricks
GROUP 2: Digging machine, Ross Carrier, locomotive, hoist, elevator, bidwell-type machine, shot & water blasting machine, paver, spreader, graders, front end loader (3 yds.
and over), vibratory hammer & vacuum truck, roadheaders, forklifts, economobile type equipment, tunnel boring machines, concrete pump and on site concrete plants.
GROUP 3: Oilers on cranes.
GROUP 4: Oiler on crawler backhoe.
GROUP 5: Bulldozer, bobcats, skid steer loader, tractor, scraper, combination loader backhoe, roller, front end loader (less than 3 yds.), street and mobile-powered sweeper (3-yd. capacity), 8-ft. sweeper minimum 65 HP).
GROUP 6: Well-point installation crew.
GROUP 7: Utility Engineers and Signal Persons
GROUP 8: Heater, concrete mixer, stone crusher, welding machine, generator and light plant, gas and electric driven pump and air compressor.
GROUP 9: Boat & tug operator.
ENGI0057-002 11/01/2020
Rates Fringes
Power Equipment Operator (highway construction projects; water and sewerline projects which are incidental to highway construction projects; and bridge projects that do not span water) GROUP 1....................$ 35.70 27.70+a GROUP 2....................$ 30.40 27.70+a GROUP 3....................$ 24.40 27.70+a GROUP 4....................$ 30.98 27.70+a GROUP 5....................$ 34.68 27.70+a GROUP 6....................$ 34.30 27.70+a GROUP 7....................$ 29.95 27.70+a
GROUP 8....................$ 31.33 27.70+a GROUP 9....................$ 33.28 27.70+a
a. FOOTNOTE: a. Any employee who works three days in the week in which a holiday falls shall be paid for the holiday.
a. PAID HOLIDAYS: New Year's Day, President's Day, Memorial Day, July Fourth, Victory Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day & Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Digging machine, crane, piledriver, lighter, locomotive, derrick, hoist, boom truck, John Henry's, directional drilling machine, cold planer, reclaimer, paver, spreader, grader, front end loader (3 yds. and over), vacuum truck, test boring machine operator, veemere saw, water blaster, hydro-demolition robot, forklift, economobile, Ross Carrier, concrete pump operator and boats
GROUP 2: Well point installation crew
GROUP 3: Utlity engineers and signal persons
GROUP 4: Oiler on cranes
GROUP 5: Combination loader backhoe, front end loader (less than 3 yds.), forklift, bulldozers & scrapers and boats
GROUP 6: Roller,skid steer loaders, street sweeper
GROUP 7: Gas and electric drive heater, concrete mixer, light plant, welding machine, pump & compressor
GROUP 8: Stone crusher
GROUP 9: Mechanic & welder
ENGI0057-003 12/01/2020
BUILDING CONSTRUCTION
Rates Fringes
Power Equipment Operator GROUP 1....................$ 41.82 27.70+a GROUP 2....................$ 39.82 27.70+a GROUP 3....................$ 39.60 27.70+a GROUP 4....................$ 35.60 27.70+a GROUP 5....................$ 32.75 27.70+a GROUP 6....................$ 38.90 27.70+a GROUP 7....................$ 38.47 27.70+a GROUP 8....................$ 35.79 27.70+a a.BOOM LENTHS, INCLUDING JIBS:
150 ft. and over: + $ 2.00 180 ft. and over: + $ 3.00 210 ft. and over: + $ 4.00 240 ft. and over: + $ 5.00 270 ft. and over: + $ 7.00 300 ft. and over: + $ 8.00 350 ft. and over: + $ 9.00 400 ft. and over: + $10.00
a. PAID HOLIDAYS: New Year's Day, President's Day, Memorial Day, July Fourth, Victory Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day & Christmas Day. a: Any employee who works 3 days in the week in which a holiday falls shall be paid for the holiday.
a. FOOTNOTE: Hazmat work: $2.00 per hour additional.
Tunnel/Shaft work: $5.00 per hour additional.
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Cranes, lighters, boom trucks and derricks.
GROUP 2: Digging machine, Ross carrier, locomotive, hoist, elevator, bidwell-type machine, shot & water blasting machine, paver, spreader, front end loader (3 yds. and over), vibratory hammer and vacuum truck
GROUP 3: Telehandler equipment, forklift, concrete pump & on-site concrete plant
GROUP 4: Fireman & oiler on cranes
GROUP 5: Oiler on crawler backhoe
GROUP 6: Bulldozer,skid steer loaders,bobcats, tractor, grader, scraper,combination loader backhoe, roller, front end loader (less than 3 yds.), street and mobile powered sweeper (3 yds. capacity), 8-ft. sweeper (minimum 65 hp)
GROUP 7: Well point installation crew
GROUP 8: Heater, concrete mixer, stone crusher, welding machine, generator for light plant, gas and electric driven pump & air compressor
IRON0037-001 09/16/2020
Rates Fringes
IRONWORKER.......................$ 37.43 29.62
LABO0271-001 06/02/2019
BUILDING CONSTRUCTION
Rates Fringes
LABORER
GROUP 1.....................$ 31.80 25.05
GROUP 2.....................$ 32.05 25.05
GROUP 3.....................$ 32.55 25.05
GROUP 4.....................$ 32.80 25.05
GROUP 5.....................$ 33.80 25.05
LABORERS CLASSIFICATIONS
GROUP 1: Laborer, Carpenter Tender, Mason Tender, Cement Finisher Tender, Scaffold Erector, Wrecking Laborer, Asbestos Removal [Non-Mechanical Systems]
GROUP 2: Asphalt Raker, Adzemen, Pipe Trench Bracer, Demolition Burner, Chain Saw Operator, Fence & Guard Rail Erector, Setter of Metal Forms for Roadways, Mortar Mixer, Pipelayer, Riprap & Dry Stonewall Builder, Highway Stone Spreader, Pneumatic Tool Operator, Wagon Drill Operator, Tree Trimmer, Barco-Type Jumping Tamper, Mechanical Grinder Operator
GROUP 3: Pre-Cast Floor & Roof Plank Erectors
GROUP 4: Air Track Operator, Hydraulic & Similar Self-Powered Drill, Block Paver, Rammer, Curb Setter, Powderman & Blaster
GROUP 5: Toxic Waste Remover
LABO0271-002 06/02/2019
HEAVY AND HIGHWAY CONSTRUCTION
Rates Fringes
LABORER
COMPRESSED AIR
Group 1....................$ 49.23 23.50 Group 2....................$ 38.75 23.50 Group 3....................$ 51.23 23.50
FREE AIR
Group 1....................$ 41.30 23.50 Group 2....................$ 38.75 23.50 Group 3....................$ 43.30 23.50
LABORER
Group 1....................$ 31.80 23.05 Group 2....................$ 32.05 23.05 Group 3....................$ 32.80 23.05 Group 4....................$ 25.30 23.05
Group 5....................$ 33.80 23.05
OPEN AIR CAISSON,
UNDERPINNING WORK AND
BORING CREW
Bottom Man.................$ 37.80 23.05 Top Man & Laborer..........$ 36.85 23.05
TEST BORING
Driller....................$ 38.25 23.05 Laborer....................$ 36.85 23.05
LABORER CLASSIFICATIONS
GROUP 1: Laborer; Carpenter tender; Cement finisher tender;
Wrecking laborer; Asbestos removers [non-mechanical systems]; Plant laborer; Driller in quarries
GROUP 2: Adzeperson; Asphalt raker; Barcotype jumping tamper; Chain saw operators; Concrete and power buggy operator; Concrete saw operator; Demolition burner; Fence and guard rail erector; Highway stone spreader; Laser beam operator; Mechanical grinder operator; Mason tender; Mortar mixer; Pneumatic tool operator; Riprap and dry stonewall builder; Scaffold erector; Setter of metal forms for roadways; Wagon drill operator; Wood chipper operator;
Pipelayer; Pipe trench bracer
GROUP 3: Air track drill operator; Hydraulic and similar powered drills; Brick paver; Block paver; Rammer and curb setter; Powderperson and blaster
GROUP 4: Flagger & signaler
GROUP 5: Toxic waste remover
LABORER - COMPRESSED AIR CLASSIFICATIONS
GROUP 1: Mucking machine operator, tunnel laborer, brake person, track person, miner, grout person, lock tender, gauge tender, miner: motor person & all others in compressed air
GROUP 2: Change house attendant, powder watchperson, top person on iron
GROUP 3: Hazardous waste work within the ""HOT"" zone
LABORER - FREE AIR CLASSIFICATIONS
GROUP 1: Grout person - pumps, brake person, track person, form mover & stripper (wood & steel), shaft laborer, laborer topside, outside motorperson, miner, conveyor operator, miner welder, heading motorperson, erecting operator, mucking machine operator, nozzle person, rodperson, safety miner, shaft & tunnel, steel & rodperson, mole nipper, concrete worker, form erector (wood, steel and all accessories), cement finisher (this type of work only), top signal person, bottom person (when heading is 50' from shaft), burner, shield operator and TBM operator
GROUP 2: Change house attendant, powder watchperson
GROUP 3: Hazardous waste work within the ""HOT"" zone
PAIN0011-005 06/01/2020
Rates Fringes
PAINTER
Brush and Roller............$ 35.62 22.55 Epoxy, Tanks, Towers, Swing Stage & Structural Steel.......................$ 37.62 22.55 Spray, Sand & Water Blasting....................$ 38.62 22.55 Taper.......................$ 36.37 22.55 Wall Coverer................$ 36.12 22.55
PAIN0011-006 06/01/2020
Rates Fringes
GLAZIER..........................$ 39.18 22.55
FOOTNOTES:
SWING STAGE: $1.00 per hour additional.
PAID HOLIDAYS: Labor Day & Christmas Day.
PAIN0011-011 06/01/2020
Rates Fringes
Painter (Bridge Work)...........$ 52.25 22.55
PAIN0035-008 06/01/2011
Rates Fringes
Sign Painter.....................$ 24.79 13.72
PLAS0040-001 06/03/2019
BUILDING CONSTRUCTION
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 36.00 27.15
FOOTNOTE: Cement Mason: Work on free swinging scaffolds under 3 planks width and which is 20 or more feet above ground and any offset structure: $.30 per hour additional.
PLAS0040-002 07/01/2019
HEAVY AND HIGHWAY CONSTRUCTION
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 32.85 22.20
PLAS0040-003 07/01/2019
Rates Fringes
PLASTERER........................$ 37.55 27.50
PLUM0051-002 08/31/2020
Rates Fringes
Plumbers and Pipefitters.........$ 44.69 31.20
ROOF0033-004 12/01/2020
Rates Fringes
ROOFER...........................$ 39.40 28.06
SFRI0669-001 01/01/2021
Rates Fringes
SPRINKLER FITTER.................$ 45.92 26.60
SHEE0017-002 12/01/2020
Rates Fringes
Sheet Metal Worker...............$ 38.58 36.73
TEAM0251-001 05/01/2019
HEAVY AND HIGHWAY CONSTRUCTION
Rates Fringes
TRUCK DRIVER
GROUP 1....................$ 27.96 26.8525+A+B+C
GROUP 2....................$ 27.61 26.8525+A+B+C
GROUP 3....................$ 27.66 26.8525+A+B+C
GROUP 4....................$ 27.71 26.8525+A+B+C
GROUP 5....................$ 27.81 26.8525+A+B+C
GROUP 6....................$ 28.21 26.8525+A+B+C
GROUP 7....................$ 28.41 26.8525+A+B+C
GROUP 8....................$ 27.91 26.8525+A+B+C
GROUP 9....................$ 28.16 26.8525+A+B+C
GROUP 10....................$ 27.96 26.8525+A+B+C
FOOTNOTES:
A. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day, plus Presidents' Day, Columbus Day, Veteran's Day & V-J Day, providing the employee has worked at least one day in the calendar week in which the holiday falls.
B. Employee who has been on the payroll for 1 year or more but less than 5 years and has worked 150 Days during the last year of employment shall receive 1 week's paid vacation; 5 to 10 years - 2 weeks' paid vacation; 10 or more years - 3 week's paid vacation.
C. Employees on the seniority list shall be paid a one hundred dollar ($100.00) bonus for every four hundred (400) hours worked, up to a maximum of five hundred dollars ($500.00)
All drivers working on a defined hazard material job site shall be paid a premium of $2.00 per hour over applicable rate.
TRUCK DRIVER CLASSIFICATIONS
GROUP 1: Pick-up trucks, station wagons, & panel trucks
GROUP 2: Two-axle on low beds
GROUP 3: Two-axle dump truck
GROUP 4: Three-axle dump truck
GROUP 5: Four- and five-axle equipment
GROUP 6: Low-bed or boom trailer.
GROUP 7: Trailers when used on a double hook up (pulling 2 trailers)
GROUP 8: Special earth-moving equipment, under 35 tons
GROUP 9: Special earth-moving equipment, 35 tons or over
GROUP 10: Tractor trailer
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.
OCT 2020
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.219-6 (Dev) Notice of Total Small Business Set-Aside (DEVIATION 2020-O0008).
NOV 2020
52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records AUG 2018 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
AUG 2018
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
JUN 2020
52.228-2 Additional Bond Security OCT 1997 52.228-11 Individual Surety--Pledge of Assets FEB 2021 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-15 Performance and Payment Bonds--Construction JUN 2020 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .