Solicitation 1282B123R0086 Pit Crushing Nez Perce Clearwater NF.pdf
PDF 18 MB Posted
- Solicitation number
- 1282B123R0086
- Issued by
-
Department of Agriculture Forest Service
About this file
This solicitation is for rock crushing services for the Nez Perce Clearwater National Forest in Idaho. The solicitation number is 1282B123R0086 and was issued by the Department of Agriculture Forest Service. Offerors are invited to submit bids for crushing rock to specified sizes to support road maintenance activities. The period of performance is one base year with four option years. Bids are due by April 15th and it is anticipated that the award will be made by May 1st. The set-aside is for small businesses only.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
See Schedule
USDA FOREST SERVICE
SPOC INTERMOUNTAIN
1400 INDEPENDENCE AVE SW MS-1138
WASHINGTON DC 20250-0001
82B1
GILBERT CHONJE 931-279-7740
IRA
x 08/25/2023
1282B123R0086
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
This contract is for Burpee Pit; Flat Iron Pit; and, Twin Ravens Pit Rock Crushing on the Nez Perce-Clearwater National Forest, Idaho County, Idaho.
Total magnitude of this project for all three sites is between $500,000 and
$1,000,000 in accordance with FAR 36.204. Applicable NAICS Code and Size Standard for this Acquisition is 237310/45.0 Million
Project will include mobilization, clearing and grubbing, drilling, blasting, sampling and testing, stockpile surveying for quality control and crushing and stockpiling of an aggregate material in accordance with the plans and specifications.
Requests for Information shall be submitted via email to gilbert.chonje@usda.gov no later than September 06, 2023. All received requests for information will be compiled and posted as an amendment to this solicitation tentatively on September
08, 2023.
Combined Period of Performance for all three sites is 487 calendar days after issuance of Notice to Proceed.
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 487 calendar days and complete it within ________________ ________________ calendar days after receiving
09/25/2023
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 8/2014)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
1 EST
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USDA FOREST SERVICE
SPOC INTERMOUNTAIN
1400 INDEPENDENCE AVE SW MS-1138
WASHINGTON DC 20250-0001
82B1
GILBERT C. CHONJE
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 8/2014) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 116
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
1282B123R0086
Priority Landscape
Burpee Pit Crushing (2023)
Red River Ranger District
Nez Perce-Clearwater National Forests
Period of Performance: 10/16/2023 to 02/14/2025
0001 Burpee Pit Rock Crushing
Requisition No: 1093591
Delivery Location Code: 0299
USDA FOREST SERVICE
NEZ PERCE CLEARWATER RED RIVER RGR
300 AMERICAN RIVER ROAD
ELK CITY ID 83525 US
0002 Flat Iron Pit Rock Crushing
Requisition No: 1093735
Delivery Location Code: 0299
USDA FOREST SERVICE
NEZ PERCE CLEARWATER RED RIVER RGR
300 AMERICAN RIVER ROAD
ELK CITY ID 83525 US
0003 Twin Ravens Pit Rock Crushing
Requisition No: 1093841
Delivery Location Code: 0278
USDA FOREST SERVICE
LOCHSA RANGER DIST KOOSKIA OFFICE
502 LOWRY STREET
KOOSKIA ID 83539 US
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
PART I - THE SCHEDULE
SECTION C - DESCRIPTION AND SPECIFICATIONS
2023 Burpee Pit Crushing
C-1 - PROJECT DESCRIPTION AND LOCATION
(a) Objectives and Background:
The objective of the Burpee Rock Crushing Project is to provide a stockpile of Gradation F, W crushed aggregate, and Class II Riprap. The project is being performed on the Red River Ranger District of the Nez Perce Clearwater National Forests.
(b) Description of Work:
This contract is for Burpee Pit Rock Crushing Project on the Nez Perce-Clearwater National Forest, Idaho County, Idaho. This project requires crushing 5,000 tons of type F Gradation, 1,000 tons of type W Gradation, and 1,000 tons of Class II Riprap. The Contractor shall furnish all labor, equipment, supervision, transportation, operating supplies, and incidentals necessary to complete the project as required by the contract, plans, and specifications.
(c) Project Location:
The project is SE of Elk City, Idaho. From Elk City, travel west on Highway 14 for 2.8 miles, and turn left on Red River Road (FSR 222). Continue down Road 222 for 24.8 miles and turn right 1188 road (turn left for stockpile location). Continue on the 1188 Road for 5.58 miles to access the pit. This project is located on the Red River Ranger District in Section 20, Township 3 South, Range 7 East of the Boise Meridian. Lat 45.572470°, Long -115.495300°. Stockpile Location is at Lat 45.615286°, Long -115.443249°.
(d) Price Range: See section (10) of solicitation.
(e) Pre-Bid Tour: None. Pit investigations available upon request.
(f) Period of Performance Estimated: 487 Days after issuance of Notice to Proceed. (See Section F, FAR Clause 52.211-10 Alt I).
(g) Government-Furnished Property (Also see Section I, FAR 52.245-4)
C-3 – TECHNICAL SPECIFICATIONS
Standard Specifications for Construction and Bridges on Federal Highway Projects, FP-14, U.S.
Customary Units are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of the solicitation and any resultant contract.
Copies of the Specifications are available on the internet at http://flh.fhwa.dot.gov/resources/specs/fp14 or performing a google search for the FP-14.
Stand-alone technical specifications have been prepared for Burpee Pit Crushing. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract. The technical specification are found in a separate attachment in Section J.
Copies of the Standard Specifications for Construction of Roads & Bridges on Federal Highway Projects (FP-14) are available in PDF format on the Western Federal Lands Highway Division website at www.wfl.fha.dot.gov/design/specs/fp03.htm.
C-3 - DRAWINGS – drawings are a part of this solicitation and any resulting contract they are found in a separate attachment entitled BURPEE PIT CRUSHING.
http://flh.fhwa.dot.gov/resources/specs/fp14 http://www.wfl.fha.dot.gov/design/specs/fp03.htm
PART 1 – THE SCHEDULE
SECTION B – SERVICES AND PRICES
BURPEE PIT DEVELOPMENT PROJECT
NEZ PERCE-CLEARWATER NATIONAL FORESTS
IDAHO COUNTY, IDAHO
B-1 SCHEDULE OF ITEMS
* Designated Method of
Measurement: CQ=Contract Quantity; AQ= Actual Quantity LS=Lump Sum
Pay Item
Number
Description Pay Unit
Method of
Measure
Unit Quantities Unit Price
Total Price
15101 Mobilization LS LS 1
30113A
Aggregate Surface Course Crushing, Grading F
Tons AQ
5,000 $________ $________
30113B
Aggregate Surface Course Crushing, Grading W
Tons AQ 1,000
30113C Riprap crushing, Class
II
Tons AQ 1,000
Total (all items) $________
03/07/2023
03/08/2023
DWG SHEET NO.
OF
SHEETCHECKEDDESIGNERDATEDRAWING TITLE
United States Department of Agriculture Forest Service
NO. DATEBYREVISION DESCRIPTION
PROJECT NAME
BURPEE PIT CRUSHING
NEZ PERCE / CLEARWATER NATIONAL FOREST
RED RIVER RANGER DISTRICT
NORTHERN REGION
REGION 1 SUMMARY OF
QUANTITIES &
WORKLIST
12/27/2022 2
SUMMARY OF QUANTITIES
WORKLIST
1/12/2023
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
AutoCAD SHX Text E
SHEETCHECKEDDESIGNERDATEDRAWING TITLE
United States Department of Agriculture Forest Service
NO. DATEBYREVISION DESCRIPTION
PROJECT NAME
BURPEE PIT CRUSHING
NEZ PERCE / CLEARWATER NATIONAL FOREST
RED RIVER RANGER DISTRICT
NORTHERN REGION
REGION 1 PIT DEVELOPEMENT PLAN
12/27/2022
1. CRUSH 5,000 TONS OF AGGREGATE (GRADING F), 1,000 TONS OF
AGGREGATE(GRADING W) AND 1,000 TONS OF CLASS II RIPRAP FOR
STOCKPILE.
2. ALL WORK SHALL CONFORM TO MINE SAFETY AND HEALTH (MSHA)
STANDARDS
3. THE CONTRACTOR IS RESPONSIBLE FOR SUBMITTING AND SIGNING
A TRAFFIC CONTROL PLAN FOR WHEN PIT OPERATIONS ARE
OCCURRING. THIS PLAN SHALL CONFORM TO ALL MSHA AND OSHA
REQUIREMENTS FOR THIS TYPE OF WORK.
4. MATERIAL SOURCE BOUNDARIES SHALL BE STAKED BY THE
CONTRACTOR AND APPROVED BY THE COR. ALL WORK PERTAINING TO
QUARRY DEVELOPMENT ARE SUBSIDIARY TO ITEM 30113A -
AGGREGATE SURFACE COURSE STOCKPILING, GRADING F, ITEM 30113B
- AGGREGATE SUBBASE STOCKPILING, GRADING W, AND ITEM
30113C - RIPRAP STOCKPILING, CLASS II.
5. THE CONTRACTOR IS RESPONSIBLE FOR LAYING OUT EXCAVATION
LIMITS IN ACCORDANCE WITH THE AGGREGATE SOURCE PLAN TO
ENSURE THERE IS SUFFICIENT QUANTITY OF MATERIAL TO PRODUCE
CONTRACT QUANTITIES OF AGGREGATE.
6. CLEARING, GRUBBING, AND SLASH CLEANUP SHALL CONFORM TO
FSSS 201 - CLEARING & GRUBBING SPECIFICATIONS. CLEARING LIMITS
SHALL BE 15 FEET BEYOND EXCAVATION LIMITS FOR THE PIT.
7. LOOSE, UNCONSOLIDATED MATERIAL SHALL BE STRIPPED DOWN TO
COMPETENT ROCK FOR AT LEAST 10 FEET HORIZONTALLY FROM THE
TOP OF THE EXCAVATION.
8. OVERBURDEN, TOPSOIL AND REJECT SHALL BE STOCKPILED IN
AREAS DESIGNATED BY THE FOREST SERVICE
9. ALL OVERSIZE ROCK ENCOUNTERED SHALL BE REDUCED IN SIZE
AND UTILIZED.
10. CUT AND FILL SLOPES REQUIRED FOR DEVELOPMENT AND/OR
RESTORATION SHALL NOT BE CONSTRUCTED STEEPER THAN 2:1.
11. AT THE CONCLUSION OF OPERATIONS:
A) NO OVERHANG OR LOOSE ROCK SHALL BE LEFT ON THE
QUARRY WALL.
B) THE FLOOR AND PROCESSING AREAS SHALL BE GRADED TO
PROMOTE DRAINAGE AND TO PREVENT PONDING OF SURFACE
WATER.
C) OVERBURDEN, TOPSOIL AND REJECT MATERIAL (SAVED IN
ITEM 8 ABOVE) SHALL BE UNIFORMLY SPREAD WITHIN THE
DEVELOPMENT PERIMETER IN AREAS AND TO THE GRADES
SPECIFIED BY THE COR/ER.
12. EROSION CONTROL AND/OR RESTORATION OF ROADS
ADJACENT TO THE DEVELOPMENT SITE MAY REQUIRE PLACING
AGGREGATE AND IS INCIDENTAL TO ITEM 30113A, 30113B, AND 30113C.
NOTES: THESE ITEMS WILL BE ADDRESSED IN THE
CONTRACTORS PIT DEVELOPMENT PLAN.
1/12/2023
ROAD 1188
BURPEE
PIT
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
SHEETCHECKEDDESIGNERDATEDRAWING TITLE
United States Department of Agriculture Forest Service
NO. DATEBYREVISION DESCRIPTION
PROJECT NAME
BURPEE PIT CRUSHING
NEZ PERCE / CLEARWATER NATIONAL FOREST
RED RIVER RANGER DISTRICT
NORTHERN REGION
REGION 1 STOCKPILE MAP
12/27/2022
1/12/2023
ROAD 222
ROAD 1188
ST
OC
KP
ILE
AR
EA
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
2023 Flat Iron Pit Crushing
The objective of the Flat Iron Rock Crushing Project is to provide a stockpile of Gradation F crushed aggregate, and to maintain Road 1810A to the project site. The project is being performed on the Red River Ranger District of the Nez Perce Clearwater National Forests.
(b) Description of Work:
This contract is for Flat Iron Rock Crushing Project on the Nez Perce-Clearwater National Forest, Idaho County, Idaho. This project requires crushing 12,000 tons of type F Gradation. In addition, roadway reconditioning, linear grading, and selective clearing will be performed to maintain the 1810A Road. The Contractor shall furnish all labor, equipment, supervision, transportation, operating supplies, and incidentals necessary to complete the project as required by the contract, plans, and specifications.
(c) Project Location:
The project is NE of Elk City, Idaho. From Elk City travel northeast on Highway 14 until it becomes Main Street. Turn left on American River Road (FSR 443). Continue for 2.1 miles, and then turn right on Flatiron Ridge Road (FSR 1809). After 3.09 Miles, turn right on FSR 1810.
Continue on the 1810 road for 1.84 Miles and turn Left on FSR 1810A. Drive 0.87 Miles on the 1810A Road. On the right is an old temp road. Continue 0.16 miles on the temp road to access Flat Iron Pit. This project is located on the Red River Ranger District in Section 8, Township 4 North, Range 9 East of the Boise Meridian. Lat 45.867401°, Long -115.376787°.
(e) Pre-Bid Tour: None.
Estimated: 487 Days after issuance of Notice to Proceed. (See Section F, FAR Clause 52.211-10 Alt I).
in these Specifications are hereby made a part of the solicitation and any resultant contract.
Copies of the Specifications are available on the internet at http://flh.fhwa.dot.gov/resources/specs/fp14 or performing a google search for the FP-14.
Stand-alone technical specifications have been prepared for Flat Iron Pit Crushing. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract. The technical specification are found in a separate attachment in Section J.
Copies of the Standard Specifications for Construction of Roads & Bridges on Federal Highway Projects (FP-14) are available in PDF format on the Western Federal Lands Highway Division website at www.wfl.fha.dot.gov/design/specs/fp03.htm
C-3 - DRAWINGS – drawings are a part of this solicitation and any resulting contract they are found in a separate attachment entitled FLAT IRON PIT CRUSHING.
FLAT IRON PIT DEVELOPMENT PROJECT
* Designated Method of Measurement: CQ=Contract Quantity; AQ= Actual Quantity
Number
Description Pay Unit Method of Measure
Unit Quantities Unit Price Total Price
15101 Mobilization LS LS 1 $________ $________
20209 Selective Clearing Miles AQ 0.87 $________ $________
21201 Linear Grading Miles AQ 0.16 $________ $________
30113 Aggregate Surface Course Crushing, Grading F Tons AQ 12000 $________ $________
30315 Roadway Reconditioning Miles AQ 0.87 $________ $________
03/07/2023
03/08/2023
SHEETCHECKEDDESIGNERDATEDRAWING TITLE
United States Department of Agriculture Forest Service
NO. DATEBYREVISION DESCRIPTION
PROJECT NAME
FLAT IRON PIT CRUSHING
NEZ PERCE / CLEARWATER NATIONAL FOREST
RED RIVER RANGER DISTRICT
NORTHERN REGION
REGION 1 SUMMARY OF
QUANTITIES &
WORKLIST
12/27/2022 2
SUMMARY OF QUANTITIES
1/26/2023
ACCESS ROUTE WORKLIST
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
SHEETCHECKEDDESIGNERDATEDRAWING TITLE
United States Department of Agriculture Forest Service
NO. DATEBYREVISION DESCRIPTION
PROJECT NAME
FLAT IRON PIT CRUSHING
NEZ PERCE / CLEARWATER NATIONAL FOREST
RED RIVER RANGER DISTRICT
NORTHERN REGION
REGION 1 WORKLIST
12/27/2022 3
WORKLIST ROAD 1810A
1/26/2023
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
SHEETCHECKEDDESIGNERDATEDRAWING TITLE
United States Department of Agriculture Forest Service
NO. DATEBYREVISION DESCRIPTION
PROJECT NAME
FLAT IRON PIT CRUSHING
NEZ PERCE / CLEARWATER NATIONAL FOREST
RED RIVER RANGER DISTRICT
NORTHERN REGION
REGION 1 TYPICALS AND DETAILS
12/27/2022 4
TYPICAL ROAD SECTION WITHOUT DITCH
NOT TO SCALE
3'
1'
INSLOPE, OUTSLOPE, OR CROWN WHEN
SPECIFIED IN THE WORKLIST. OTHERWISE
MAINTAIN EXISTING.
8'
CLEARING AND
GRUBBING
OUTER LIMITS
8'
CLEARING AND
GRUBBING
OUTER LIMITS
8'
CLEARING AND
GRUBBING OUTER
LIMITS8'
CLEARING AND
GRUBBING OUTER LIMITS
4" ASC
6" ABC
ASC = Aggregate Surface Course ABC = Aggregate Base Course
AGGREGATE SURFACE COURSE WHERE
SPECIFIED
AGGREGATE BASE COURSE WHERE
SPECIFIED
ROAD RECONDITIONING
TYPICAL SECTION
15'
15'
TYPICAL ROAD SECTION WITH DITCH
NOT TO SCALE
14'
14' 14
ROADSIDE CLEARING LIMITS WITHOUT DITCH
NOT TO SCALE
8'
ROADSIDE
CLEARING
OUTER LIMITS
8'
ROADSIDE
CLEARING
OUTER LIMITS
8'
ROADSIDE CLEARING
OUTER LIMITS
8'
ROADSIDE CLEARING
OUTER LIMITS
VARIES
VARIES
ROADSIDE CLEARING LIMITS WITH DITCH
NOT TO SCALE
1/26/2023
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
SHEETCHECKEDDESIGNERDATEDRAWING TITLE
United States Department of Agriculture Forest Service
NO. DATEBYREVISION DESCRIPTION
PROJECT NAME
FLAT IRON PIT CRUSHING
NEZ PERCE / CLEARWATER NATIONAL FOREST
RED RIVER RANGER DISTRICT
NORTHERN REGION
REGION 1 PIT DEVELOPEMENT PLAN
12/27/2022
1. CRUSH 12,000 TONS OF AGGREGATE (GRADING F) FOR STOCKPILE.
2. ALL WORK SHALL CONFORM TO MINE SAFETY AND HEALTH (MSHA)
STANDARDS
3. THE CONTRACTOR IS RESPONSIBLE FOR SUBMITTING AND SIGNING
A TRAFFIC CONTROL PLAN FOR WHEN PIT OPERATIONS ARE
OCCURRING. THIS PLAN SHALL CONFORM TO ALL MSHA AND OSHA
REQUIREMENTS FOR THIS TYPE OF WORK.
4. MATERIAL SOURCE BOUNDARIES SHALL BE STAKED BY THE
CONTRACTOR AND APPROVED BY THE COR. ALL WORK PERTAINING TO
QUARRY DEVELOPMENT ARE SUBSIDIARY TO ITEM 30113 -AGGREGATE
SURFACE COURSE STOCKPILING, GRADING F.
5. THE CONTRACTOR IS RESPONSIBLE FOR LAYING OUT EXCAVATION
LIMITS IN ACCORDANCE WITH THE AGGREGATE SOURCE PLAN TO
ENSURE THERE IS SUFFICIENT QUANTITY OF MATERIAL TO PRODUCE
CONTRACT QUANTITIES OF AGGREGATE.
6. CLEARING, GRUBBING, AND SLASH CLEANUP SHALL CONFORM TO
FSSS 201 - CLEARING & GRUBBING SPECIFICATIONS. CLEARING LIMITS
SHALL BE 15 FEET BEYOND THE PIT EXCAVATION LIMITS.
7. LOOSE, UNCONSOLIDATED MATERIAL SHALL BE STRIPPED DOWN TO
COMPETENT ROCK FOR AT LEAST 10 FEET HORIZONTALLY FROM THE
TOP OF THE EXCAVATION.
8. OVERBURDEN, TOPSOIL AND REJECT SHALL BE STOCKPILED IN
AREAS DESIGNATED BY THE FOREST SERVICE
9. ALL OVERSIZE ROCK ENCOUNTERED SHALL BE REDUCED IN SIZE
AND UTILIZED.
10. CUT AND FILL SLOPES REQUIRED FOR DEVELOPMENT AND/OR
RESTORATION SHALL NOT BE CONSTRUCTED STEEPER THAN 2:1.
11. AT THE CONCLUSION OF OPERATIONS:
A) NO OVERHANG OR LOOSE ROCK SHALL BE LEFT ON THE
QUARRY WALL.
B) THE FLOOR AND PROCESSING AREAS SHALL BE GRADED TO
PROMOTE DRAINAGE AND TO PREVENT PONDING OF SURFACE
WATER.
C) OVERBURDEN, TOPSOIL AND REJECT MATERIAL (SAVED IN
ITEM 8 ABOVE) SHALL BE UNIFORMLY SPREAD WITHIN THE
DEVELOPMENT PERIMETER IN AREAS AND TO THE GRADES
SPECIFIED BY THE COR/ER.
12. EROSION CONTROL AND/OR RESTORATION OF ROADS
ADJACENT TO THE DEVELOPMENT SITE MAY REQUIRE PLACING
AGGREGATE AND IS INCIDENTAL TO ITEM 30113.
NOTES: THESE ITEMS WILL BE ADDRESSED IN THE
CONTRACTORS PIT DEVELOPMENT PLAN.
1/26/2023
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
2023 Twin Ravens Pit Crushing
The objective of the Twin Ravens Rock Crushing Project is to provide a stockpile of Grade F and Grade W crushed aggregate. The project is being performed on the Moose Creek Ranger District of the Nez Perce Clearwater National Forests.
(b) Description of Work:
This contract is for Twin Ravens Rock Crushing Project on the Nez Perce-Clearwater National Forest, Idaho County, Idaho. This project requires crushing 11,000 tons of type F Gradation and 2,000 tons of type W Gradation. The Contractor shall furnish all labor, equipment, supervision, transportation, operating supplies, and incidentals necessary to complete the project as required by the contract, plans, and specifications.
(c) Project Location:
The project is Southeast of Kooskia, Idaho. From Kooskia, turn right on Broadway Ave (HWY 13). After 0.7 miles continue straight on Clearcreek Road. After 2.2 Miles, turn right to stay on Clearcreek Road. Continue for 9.3 miles, and then turn left on Pleasant Valley Road. After 0.6 Miles, turn Left on Main St (FSR 650). Continue 3.4 Miles and turn left on the 650I road. After
0.07 Miles the 650I road becomes the 650I1 road. Continue 0.22 miles to access Twin Cabins Pit. This project is located on the Lochsa Ranger District in Section 15, Township 31 North, Range 5 East of the Boise Meridian. Lat 46.027078°, Long -115.826009°.
(e) Pre-Bid Tour: None.
Estimated: 487 Days after issuance of the Notice to Proceed. (See Section F, FAR Clause 52.211-10 Alt I).
in these Specifications are hereby made a part of the solicitation and any resultant contract.
Copies of the Specifications are available on the internet at http://flh.fhwa.dot.gov/resources/specs/fp14 or performing a google search for the FP-14.
Stand-alone technical specifications have been prepared for Twin Ravens Pit Crushing. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract. The technical specification are found in a separate attachment in Section J.
Copies of the Standard Specifications for Construction of Roads & Bridges on Federal Highway Projects (FP-14) are available in PDF format on the Western Federal Lands Highway Division website at www.wfl.fha.dot.gov/design/specs/fp03.htm
C-3 - DRAWINGS – drawings are a part of this solicitation and any resulting contract they are found in a separate attachment entitled TWIN RAVENS PIT CRUSHING.
TWIN RAVENS PIT DEVELOPMENT PROJECT
* Designated Method of Measurement: CQ=Contract Quantity; AQ= Actual Quantity
Number
Description Pay Unit Method of Measure
Unit Quantities Unit Price Total Price
15101 Mobilization LS LS 1 $________ $________
30113A Aggregate Surface Course Crushing, Grading F Tons AQ 11000 $________ $________
30113B Aggregate Subbase Crushing, Grading W Tons AQ 2000 $________ $________
NO. DATEBYREVISION DESCRIPTION
SHEET NO.
SET NO.
PROJECT:
DATE:SHEET INDEX
CONSTRUCTION PLANS
SHEET 1
SHEET 2
SHEET 3
1/31/2023
N
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
REGION ONE
TWIN RAVENS PIT
CRUSHING
ROAD 650I1
NEZ PERCE-CLEARWATER NATIONAL FOREST
MOOSE CREEK RANGER DISTRICT
IDAHO COUNTY, IDAHO
AREA MAP
IDAHO INDEX MAP
PROJECT ENGINEER
NEZPERCE / CLEARWATER NATIONAL
FOREST
DATE
APPROVED BY:
RECOMMENDED BY:
LOCATION MAP
FOREST SUPERVISOR
NEZPERCE / CLEARWATER NATIONAL
FORESTS
DATE
APPROVED BY:
DESIGNED BY:
FOREST ENGINEER
NEZPERCE / CLEARWATER NATIONAL
FORESTS
DATE
DISTRICT RANGER
NEZPERCE / CLEARWATER NATIONAL
FORESTS
DATE
TITLE SHEET
SUMMARY OF QUANTITIES & WORKLIST
PPIT DEVELOPMENT PLAPIT DEVELOPMENT PLANPIT DEVELOPMENT PLANIT DEVELOPMENT PLAN
Vincent Spinazola 2/15/2023
03/08/2023
03/08/2023
03/09/2023
AutoCAD SHX Text E:\FY2022Projects\SadSob\PLANS AND SHEETSET\R01_Title.dwg
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
NOT TO SCALE
USER NOTES: (NO PLOT) VERIFY THE MAP RETAINS CLARITY WHEN PRINTED IN BLACK AND WHITE
SHEETCHECKEDDESIGNERDATEDRAWING TITLE
United States Department of Agriculture Forest Service
NO. DATEBYREVISION DESCRIPTION
PROJECT NAME
TWIN RAVENS PIT CRUSHING
NEZ PERCE / CLEARWATER NATIONAL FOREST
MOOSE CREEK RANGER DISTRICT
NORTHERN REGION
REGION 1 SUMMARY OF
QUANTITIES &
WORKLIST
12/27/2022 2
SUMMARY OF QUANTITIES
1/31/2023
WORKLIST ROAD 650I1
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
SHEETCHECKEDDESIGNERDATEDRAWING TITLE
United States Department of Agriculture Forest Service
NO. DATEBYREVISION DESCRIPTION
PROJECT NAME
TWIN RAVENS PIT CRUSHING
NEZ PERCE-CLEARWATER NATIONAL FOREST
MOOSE CREEK RANGER DISTRICT
NORTHERN REGION
REGION 1 PIT DEVELOPEMENT PLAN
12/27/2022
1. CRUSH 11,000 TONS OF AGGREGATE (GRADING F) AND 2,000 TONS
AGGREGATE (GRADE W) FOR STOCKPILE.
2. ALL WORK SHALL CONFORM TO MINE SAFETY AND HEALTH (MSHA)
STANDARDS
3. THE CONTRACTOR IS RESPONSIBLE FOR SUBMITTING AND SIGNING
A TRAFFIC CONTROL PLAN FOR WHEN PIT OPERATIONS ARE
OCCURRING. THIS PLAN SHALL CONFORM TO ALL MSHA AND OSHA
REQUIREMENTS FOR THIS TYPE OF WORK.
4. MATERIAL SOURCE BOUNDARIES SHALL BE STAKED BY THE
CONTRACTOR AND APPROVED BY THE COR. ALL WORK PERTAINING TO
QUARRY DEVELOPMENT ARE SUBSIDIARY TO ITEM 30113A -
AGGREGATE SURFACE COURSE STOCKPILING, GRADING F AND ITEM
30113B - AGGREGATE SUBBASE STOCKPILING, GRADING W.
5. THE CONTRACTOR IS RESPONSIBLE FOR LAYING OUT EXCAVATION
LIMITS IN ACCORDANCE WITH THE AGGREGATE SOURCE PLAN TO
ENSURE THERE IS SUFFICIENT QUANTITY OF MATERIAL TO PRODUCE
CONTRACT QUANTITIES OF AGGREGATE.
6. CLEARING, GRUBBING, AND SLASH CLEANUP SHALL CONFORM TO
FSSS 201 - CLEARING & GRUBBING SPECIFICATIONS. CLEARING LIMITS
SHALL BE 15 FEET BEYOND PIT EXCAVATION LIMITS.
7. LOOSE, UNCONSOLIDATED MATERIAL SHALL BE STRIPPED DOWN TO
COMPETENT ROCK FOR AT LEAST 10 FEET HORIZONTALLY FROM THE
TOP OF THE EXCAVATION.
8. OVERBURDEN, TOPSOIL AND REJECT SHALL BE STOCKPILED IN
AREAS DESIGNATED BY THE FOREST SERVICE
9. ALL OVERSIZE ROCK ENCOUNTERED SHALL BE REDUCED IN SIZE
AND UTILIZED.
10. CUT AND FILL SLOPES REQUIRED FOR DEVELOPMENT AND/OR
RESTORATION SHALL NOT BE CONSTRUCTED STEEPER THAN 2:1.
11. AT THE CONCLUSION OF OPERATIONS:
A) NO OVERHANG OR LOOSE ROCK SHALL BE LEFT ON THE
QUARRY WALL.
B) THE FLOOR AND PROCESSING AREAS SHALL BE GRADED TO
PROMOTE DRAINAGE AND TO PREVENT PONDING OF SURFACE
WATER.
C) OVERBURDEN, TOPSOIL AND REJECT MATERIAL (SAVED IN
ITEM 8 ABOVE) SHALL BE UNIFORMLY SPREAD WITHIN THE
DEVELOPMENT PERIMETER IN AREAS AND TO THE GRADES
SPECIFIED BY THE COR/ER.
12. EROSION CONTROL AND/OR RESTORATION OF ROADS
ADJACENT TO THE DEVELOPMENT SITE MAY REQUIRE PLACING
AGGREGATE AND IS INCIDENTAL TO ITEM 30113A AND 30113B.
NOTES: THESE ITEMS WILL BE ADDRESSED IN THE
CONTRACTORS PIT DEVELOPMENT PLAN.
1/31/2023
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
C-4 – BIOBASED PRODUCT UTILIZATION
The Contractor must comply with the Agriculture Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C.
8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy, and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, Transportation Management,” dated January 24, 2007; and Presidental Memorandom, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated Febuary 2012, to provide biobased products.
The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s Representative (COR).
The following is an example list of products that may be used in this contract for which biobased products are available. The list is not all inclusive. It is desirable that Contractors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.
Hydraulic Fluids Penetrating Lubricants Degreasers Absorbants Diesal Fuel Additives Greases Dust Suppressants 2-Cycle Engine Oil Sorbents Adhesive and Mastic Removers Cleaners Concrete/Asphalt Release Fluids Composite Panels Sealers Wood and Concrete Sealers Graffiti and Grease Removers Stain Removers Metalworking Fluids
Biobased products that are designed for preferred procurement under USDA’s Biopreferred Program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material.
In addition to the biobased products designed by the U.S. Department of Agriculture in the Biopreferred Program, the Contractor is encouraged to use other commercially available products.
Additionally, the winning Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes (see Section I, FAR Clause 52.223-2).
A demonstration of proper use, an effective training program, and technical assistance are essential to the success of the purchase and use of some biobased products that may function differently than a conventional product.
http://www.biopreferred.gov/
SUPPLEMENTAL
SPECIFICATIONS:
BURPEE PIT, TWIN
RAVENS PIT, AND FLAT
IRON PIT CRUSHING
Forest Service Supplemental Specifications
Table of Contents Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms. ...................................................................................... Error! Bookmark not defined.
101.03 Abbreviations
101.04 Definitions
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102. ................................................................................................. Error! Bookmark not defined.
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05. .............................................. Error! Bookmark not defined.
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04. ........................................................... Error! Bookmark not defined.
104.06 Use of Roads by Contractor
105 - Control of Material
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.02 Visual Inspection
107 - Legal Relations and Responsibility to the Public ...................................... Error! Bookmark not defined.
Delete Subsection 107.05. ...................................................................................... Error! Bookmark not defined.
108 - Prosecution and Progress ............................................................................ Error! Bookmark not defined.
Delete Section 108. ................................................................................................. Error! Bookmark not defined.
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09. .............................................. Error! Bookmark not defined.
109.01 Measurement of Work
109.02 Measurement Terms and Definitions
153 - Contractor Quality Control
153.02 Qualifications
153.03 Quality Control Plan
153.07 Records and control charts
155 - Schedules for Construction Contracts
Delete Section 155. ................................................................................................. Error! Bookmark not defined.
201 - Clearing and Grubbing
202 - Additional Clearing and Grubbing
203 - Removal of Structures and Obstructions
203.05 Disposing of Material
204 - Excavation and Embankment
Section 204. — EXCAVATION AND EMBANKMENT
205 - Rock Blasting
205.03 Regulations
205.06 Preblast condition survey and vibration monitoring and control
205.07 Test Blasting
205.08 Blasting
209 - Structure Excavation and Backfill
212 - Linear Grading
301 - Untreated Aggregate Courses
302 - Minor Crushed Aggregate
302.04 Placing Crushed Aggregate
302.05 Compacting and Finishing Crushed Aggregate
303 - Road Reconditioning
314 - Stockpiled Aggregates
314.01 Description
314.04 Stockpile Site
602 - Culverts and Drains
602.03 General
602.05 Laying Metal Pipe
703 - Aggregate
703.05 (c) Surface course aggregate. (3) Plastic Index
703.05 Subbase, Base, Surface Course, and Screened Aggregate
Preface Preface_wo_12_20_2022
The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.
101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016
101.03 Abbreviations.
(a) Acronyms.
AGAR — Agriculture Acquisition Regulations
AFPA — American Forest and Paper Association
FSAR — Forest Service Acquisition Regulations
MSHA — Mine Safety and Health Administration
NESC — National Electrical Safety Code
WCLIB — West Coast Lumber Inspection Bureau
(f) Miscellaneous unit abbreviations.
MP — milepost location ppm — parts per million volume
STA station location
101.04 Definitions.
Bid Schedule — The Schedule of Items.
Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.
Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.
Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.
Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.
Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.
Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Solicitation— (Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.
Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line — A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road — Temporary construction access built along the route of the project.
Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.
Utilization Standards — The minimum size and percent soundness of trees described in Public Works contract specifications or Timber Sale and IRTC contract provisions to determine merchantable timber.
Figure 101-1—Illustration of road structure terms.
102 - Bid¸ Award¸ and Execution of Contract
See respective site schedule and evaluation criteria.
103 - Scope of Work 103.00_National_11_9_2016
See respective site schedule.
104 - Control of Work 104.00_National_11_9_2016
104.06 Use of Roads by Contractor.
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.05_National_6_29_2020
105.05 Use of Material Found in the Work.
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material safely at government-approved location, at no additional cost to government.
106 - Acceptance of Work 106.01_National_7_18_2017
106.01 Conformity with Contract Requirements.
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work; providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
1. Sampling method;
2. Number of samples;
3. Sample transport;
4. Test procedures;
5. Testing laboratories;
6. Reporting;
7. Estimated time and costs; and
8. Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.
If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
1. Have the work accepted at a reduced price; or
2. Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.02 Visual Inspection.
Acceptance is based on visual inspection of the work for compliance with the specific contract requirements.
Use prevailing industry standards in the absence of specific contract requirements or tolerances.
108.00_National_11_9_2016
109 - Measurement and Payment 109.00_National_11_9_2016
109.01 Measurement of Work.
Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement Subsection of the section controlling the work being performed. Table 109-1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.
Table 109-1
Decimal Accuracy of Quantities for Final Payment
Pay Item Level of Precision Linear Foot 1
Exception--Timber, Steel, and concrete Piles 0.1 Station 0.1 Mile 0.01 Square Foot 0.1 Square Yard 0.1 Each 1 Acre 0.01 Gallon 1 M-Gals. 0.1 Cubic Yard 1
Exception--Structure Excavation; Sheathing Materials; Bedding, Bed Course, and Backfill Materials; Gabions;
0.1
Exception--Concrete; Masonry 0.01 Pound 1 Ton 0.1
Exception--Calcium Chloride;
Sodium Chloride; Hydrated Lime;
Bituminous Materials; Pavements;
Bed Course Materials
0.01
Hour 0.1
MFBM 0.01
Station Yard 1 Cubic Yard Mile 1 Ton Mile 1
109.02_National_11_9_2016
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
153 - Contractor Quality Control 153.02_National_10_26_2022
153.02 Qualifications.
Submit the following for approval with the quality control plan:
(a) Quality control manager (QCM). Furnish a QCM who has at least 2 years’ experience in construction, inspector, quality control and material testing on construction projects of similar type and scope.
(b) Testers. Provide testers with at least one…
This is the start of the file's text. The full file is on GovTribe.