SOLE SOURCE.pdf
PDF 203 KB Posted
- Attached to
- INSPECTION ARM Federal contract opportunity
- Solicitation number
- SPMYM2-21-Q-1053
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AMENDMENT 00002 for SOLICITATION SPMYM2-21-Q-1053.pdf | ||
| AMENDMENT of SOLICITATON SPMYM2-21-Q-1053.pdf | ||
| SOLICITATION SPMYM2-21-Q-1053.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JUSTIFICATION FOR SOLE SOURCE ($5k-$250k) Ref: FAR 13.106(b)
The service or material listed on (Document number)_1057-4740 thru 4746_ is sole source and competition must be restricted to one source, or to only one brand name for reasons indicated below. There are no substitutes available for this material.
Restricted to the following source or brand name. Provide original manufacturer's name.
(If a sole source manufacturer distributes via dealers, ALSO provide dealer information.)
Manufacturer: FARO Technologies, Inc.
Manufacturer POC & Phone Nr. Michael Perko 407-333-9911 Mfr. Address 250 Technology Park; Lake Mary, FL 32746-7115 Manufacturers Dealer/Rep N/A-Direct Dealer/Rep Address/Phone Number N/A-Direct
Description of the item or service required, the estimated cost, and required delivery date.
FARO 34000-415 inspection arm along with ($39,980.00):
SOFT10011 – CAM2 Probing Edition ($18,000.00);
11516 – Mount-G3+, Magnetic Mount ($3357.00);
COMP0121X64 – Super Power User Notebook ($7193.56);
473-000008-000 – Stand-Portable Folding Stand, Softcase ($7300.00);
21604 – Probe Kit-PK1, Probe extension Kit ($2919.74);
20780 – Probe Accsy-PK1, Adaptor for M4 Styli ($700.00) Total estimated cost to be $79,450.30 Delivery required by 4/11/2021
Specific characteristics of the material or service that limit the availability to a sole source or particular brand name (unique features, function of the item, etc.).
Describe in detail why only this suggested source can furnish the requirements to the exclusion of other sources.
• These machines will be used in conjunction with the current machines in the shop.
With the purchase of these machines, there will be no need to re-train the workforce on how to run them. There is also currently a method in place to program these machines that will not need to be changed or updated with these machines.
• These machines are currently in use throughout the shipyard in multiple shops. Using this manufacturer and types of machines will allow for the outside shops that use them on the waterfront to be familiar with the new addition, thus reducing training required and exposure when in use.
• The shop is experienced at maintaining these machines. Introducing additional machines of the same make will not cause for any additional training for the department.
The requested material or service represents the minimum requirements of the Government.
CHECK & FILL IN ALL APPLICABLE BLANKS BELOW
The material/service must be compatible in all aspects (form, fit and function) with existing systems presently installed. Justi Describe the equipment you have now and how the new item/service must coordinate, connect, or interface with the existing system.
There are currently 2ea FARO inspection arms in use in the Toolmakers area. They are both old and need of replacement. To change manufacturer and begin using a new system would require a complete overhaul of the inspection process. This would take inspectors off line for a minimum of a full week and require them to train fill-ins as soon as they return from training, costing the shop an estimated $20,000 in employee time lost due to training.
Using the same manufacturer will require a small amount of training to become familiar with the new interface. Using the systems that the inspectors are familiar with will reduce the chance of erroneous readings, improve the shops’ first time quality, and ensure that the customers are receiving the tooling required.
A patent, copyright, or proprietary data limits competition. The proprietary data is:
These are “direct replacements” parts/components for existing brand name equipment.
Other information to support a sole-source buy:
Signature Activity CREMEANS.MICHAEL.DAVI Digitally signed by Title D.1396467328
CREMEANS.MICHAEL.DAVID.1396467328
Date: 2021.03.01 13:50:41 -08'00'
I CERTIFY THAT STATEMENTS CHECKED, AND INFORMATION PROVIDED ABOVE, ARE COMPLETE AND CORRECT TO THE BEST OF MY KNOWLEDGE AND DO NOT CONTAIN CLASSIFIED INFORMATION. I UNDERSTAND THAT THE PROCESSING OF THIS SOLE-SOURCE JUSTIFICATION PRECLUDES THE USE OF FULL AND OPEN
COMPETITION.
Contracting Officer Signature Date_
DLA Maritime Puget Sound Justification for Sole Source 05/21/2018
| JUSTIFICATION FOR SOLE SOURCE ($5k-$250k) |
| CHECK & FILL IN ALL APPLICABLE BLANKS BELOW |
| Contracting Officer Signature Date_ |
| 2021-03-08T16:47:34-0800 | |
| VO.KIM.A.1502467421 |
File details come from the government source that posted it. Updated .