Sol_140P8322R0001.pdf
PDF 517 KB Posted
- Attached to
- Rehabilitate Parking Area, Ruby Beach, Olympic Nat Federal contract opportunity
- Solicitation number
- 140P8322R0001
About this file
This solicitation requests proposals for construction services to rehabilitate the Ruby Beach Parking area in Olympic National Park. The work includes site grading, paving roads and parking areas, concrete flatwork and curbing, accessibility components, storm drainage infrastructure, signs, and other site work. Proposals are due by February 28, 2022. The award will be a firm-fixed price contract to the responsible offeror providing the best value based on technical capability, past performance confidence, and price. The contractor must complete the work within 180 calendar days of the notice to proceed. A 20% bid guarantee is required. The set-aside is for small businesses. The soliciting agency is the National Park Service Pacific West Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8322R0001_Amd_0002.pdf | ||
| Attachment_G_DOL_Wage_Determination_0002.pdf | ||
| Attachment_F_site_visit_notes_and_initial_clarifications_0001.pdf | ||
| Sol_140P8322R0001_Amd_0001.pdf | ||
| Attachment_E_Forms_to_Return_with_Proposal.docx | DOCX document | |
| Attachment_B_Project_Drawings.pdf | ||
| Attachment_D_CertificationVaccinationPRAv7_Contractors.pdf | ||
| Attachment_A_Specifications.pdf | ||
| Attachment_C_DOL_Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040561577
NPS, PWR - OLYM MABO
600 E. Park Avenue
Port Angeles WA 98362-6757
PPY
Submit quote electronically (by email) to michael_beatty@nps.gov. per instructions in Section L
Michael Beatty 360-854-7219
1x 01/27/2022
140P8322R0001
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Request for Proposals #140P8322R001 is for construction services to improve the Ruby
Beach Parking Area, including all grading, concrete curbing and flatwork, storm drainage, paving, pavement markings and installation of site signage and appurtenances.
THIS IS NOT A GOVERNMENT ESTIMATE" In accordance with FAR 36.204 the Magnitude of
Construction: between $1,000,000 and $5,000,000.
This project is subject to Construction Wage Rate Requirements.
Set-Aside: This procurement is 100% set-aside for Small Business concerns in accordance with FAR part 19.5.
Site Visit: A site visit is planned for Thursday, February 10, 2022 at 11:00 am PT.
Kindly RSVP to bradley_metler@nps.gov by noon on February 9, 2022.
Location: Ruby Beach Parking area, milepost 164.5, US101, Olympic National Park, Jefferson County, Washington. Park in the Parking Rea at the End of the Access Road
- We will gather at the entrance to the Access Road.
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 180 calendar days and complete it within ________________ ________________ calendar days after receiving
See Section F
02/28/2022
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
DOI, NPS, PWR - OLYM MABO - NOCA
810 State Route 20
Sedro-Woolley WA 98284-1263
PY1
Sarah Welch
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 26
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P8322R0001
Type of Contract: a Firm-Fixed-Price contract will be awarded.
A Bid Guarantee is required with your proposal(IAW FAR clause 52.228-1 Bid Guarantee)
Instructions: To complete this SF1442, write the business name, address, DUNS number, and point of contact in Block 14 and complete Blocks 15 through 20C, including acknowledging all amendments in Block 19. Complete Price Schedule and return with documents listed in Section L.
Additional instructions and a list of forms are provided in Section L. Blank price schedule and other required and optional documents are hyperlinked to the solicitation at SAM.gov.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
RFP #140P8322R001, Rehabilitate Parking Area, Ruby Beach Olympic National Park
SECTION A: Solicitation/contract form (Standard Form 1442) (Pages 1-3)
SECTION B: Price Schedule
CONTRACT PRICE SCHEDULE
All work shall be performed in accordance with the attached specifications, drawings, and wage determination. All lines are “lump sum”. Refer to Attachments 1 and 2 for task definitions and descriptions.
Item 1: Site Preparation $__________________
Item 2 : Pavement $__________________
Item 3 : Pavement Markings $__________________
Item 4 : Concrete $__________________
Item 5 : Signs and Steel Overlook Appurtenances $__________________
TOTAL FOR ITEMS 1-5 : $__________________
SECTION C: Description/Specifications The work of this contract will rehabilitate the Ruby Beach Parking area, overlook, and access road from US Highway 101 to improve storm drainage, meet accessibility requirements, and improve traffic flows.
The Work includes:
• grading;
• paving the access road (approx. 1,000 LF) from Highway 101 and main parking lot (approx. 26,000 SF);
• painting pavement markings;
• fabricating concrete curb, sidewalks, and stairs;
• installing stair railing;
• constructing storm water catch basin, culvert and outfall;
• installing foot-trail tread surface;
• furnishing and installing traffic signs;
• furnishing and installing bicycle storage rack and gate as shown on the drawings.
Project Location: Olympic National Park, Ruby Beach Parking area, milepost 164.5, US101.
The contractor shall perform all work in accordance with the documents listed in Section J, which are attached and incorporated into this solicitation/contract.
SECTION D: Packaging and Marking (not used)
52.252-2 FAR Clauses Incorporated By Reference (Feb 1998) This contract incorporates one or more Federal Acquisition Regulation (FAR) and Department of the Interior Acquisition Regulation (DIAR) clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
FAR - https://www.acquisition.gov/?q=browsefar DIAR - http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl Clauses that are from the DIAR begin with “14”.
https://www.acquisition.gov/?q=browsefar
SECTION E: Inspection and Acceptance
52.246-12 Inspection of Construction. (AUG 1996) 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (Aug 1996)
SECTION F: Deliveries or Performance
52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work. (APR 1984)
52.211-10 Commencement, Prosecution, and Completion of Work, Alternate I. (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed (NTP), (b) prosecute the work diligently, and (c) complete the entire work within 180 calendar days after issuance of the NTP. The time stated for completion shall include final cleanup of the premises.
Period of Performance Dates and Seasonal Conditions Although NPS does not intend to suspend work during contract performance, seasonal weather conditions and may restrict the contractor’s construction activities. The Contractor’s construction schedule should take into account historic weather patterns when planning the work sequence. On-site work will occur after 4/4/22.
SECTION G: Contract Administration Data
1452.201-70 Authorities and Delegations (SEPT 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum.
The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
1452.204-70 Release of Claims—Department of the Interior (JUL 1996) After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
G.1 Appointment of Contractor Representative / Superintendent Prior to commencement of work on this contract, the contractor shall provide to the Contracting Officer and COR the name and telephone number of at least one responsible individual who will serve to respond to operational problems and/or emergencies on a daily basis. The contractor agrees that notice to the designated representative shall constitute notice to the contractor and agrees to be bound by any commitments or representations made by the representative.
G.2 Electronic Invoicing and Payment Requirements - Internet Payment Platform (IPP) (April 2013) Payment requests must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform System (IPP; https://www.ipp.gov).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions- Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice (upload your business invoice as an attachment to the IPP invoice before you click “submit” in IPP):
1. Contractor’s standard business invoice,
2. Signed certification required by FAR clause 52.232-5 (for progress payment requests only),
3. Schedule of values for work being invoiced, and
4. If submitting a final invoice, also upload the signed Release of Claims form.
Contractor’s failure to attach the required documentation as specified above will result in the IPP invoice being rejected and cause a delay in payment.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in www.SAM.gov record) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to contract award or within 3 - 5 business days after the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
G.3 NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING
SYSTEM (Dec 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The
Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 10 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
1. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
2. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
3. All information provided should be reviewed for accuracy prior to submission.
4. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
5. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
6. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
G.4 NPS Contact Information Contracting Officer: Sarah Welch 360-854-7220 sarah_welch@nps.gov Contract Specialist: Michael Beatty 360-854-7219 michael_beatty@nps.gov Contracting Officer’s Representative: Bradley Metler 360-565-3097 brad_metler@nps.gov
SECTION H: SPECIAL CONTRACT REQUIREMENTS
H.1 Wage Determination U.S. Department of Labor General Wage Decision no. WA20220001 (Clallam County, WA), is incorporated into this solicitation/contract, as shown in Section J.
H.2 Preconstruction Conference The Contracting Officer will conduct a preconstruction conference; the successful offeror will be notified and will be required to attend in person or by phone. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.
H.3 Notice of Required Bonds A Bid Bond, using Standard Form 24, for 20% of the offered amount is required with proposal submission. The awardee shall furnish a payment bond, using Standard Form 25, and a performance bond, using Standard Form 25A, within 10 days after contract award. The penal sum of the payment and performance bonds shall be 100% of the contract price.
H.4 Interpretations of Contract: Notice of Ambiguities This written contract and any and all identified writings or documents incorporated by reference herein or physically https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.gov/ mailto:sarah_welch@nps.gov attached hereto constitute the parties' complete agreement and no other prior or contemporaneous agreements either written or oral shall be considered to change, modify, or contradict it. Any ambiguity in the contract will not be strictly construed against the drafter of the contract language but shall be resolved by applying the most reasonable interpretation under the circumstances, giving full consideration to the intentions of the parties at the time of contracting.
It is the Contractor’s obligation to exercise due diligence to discover and to bring to the attention of the Contracting Officer at the earliest possible time any ambiguities, discrepancies, inconsistencies, or conflicts in or between the specifications and the applicable drawings or other documents incorporated. Failure to comply with such obligation shall be deemed a waiver and release of any and all claims for extra costs or delay arising out of such ambiguities, discrepancies, inconsistencies, and conflicts.
H.5 Worker’s Compensation Insurance Requirements The Contractor shall maintain compensation insurance for employees engaged in the work complying with the worker's compensation laws of the State in which the work is to be performed and shall maintain liability insurance protecting the Contractor from claims because of bodily injury (including death) and property damage arising under this Contract.
H.6 Limitations on Subcontracting Requirements The small business prime contractor agrees to pay not more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities.
Any work that a similarly situated entity further subcontracts will count toward the 85 percent subcontract amount that cannot be exceeded. Refer to Paragraph (e)(3) of FAR clause 52.219-14, Limitations on Subcontracting (SEP 2021). Prior to submitting the final invoice, the contractor shall complete and submit a report demonstrating compliance with the clause. Non-compliance with the limitations on subcontracting requirements will be noted in the CPARS evaluation (see G.3). The reporting form will be provided after contract award.
H.7 Archeological Findings Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover or their employees find any archeological remains, Contractor shall suspend operations at the site of discovery; notify Contracting Officer immediately of the findings;
and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, s/he will be compensated by an equitable adjustment under the General Provisions of the Contract.
H.8 Conduct of Operations At all times the Contractor shall conduct their organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. The park compendium is available at https://www.nps.gov/olym/learn/management/superintendent-s-compendium.htm; this document will be updated in early 2022; the contractor must comply with the compendium in effect at the time.
In addition, work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with prior approval of the Contracting Officer. Rowdy, disruptive behavior and/or sexual harassment will not be tolerated and the offending individual(s) will be removed from the site. Amplified playing of music or talk programs is prohibited on site or in buildings.
H.9 Infectious Disease Preparedness and Response – Coronavirus Pandemic (COVID-19)
a) Contractors are responsible for their employees’ safety and the safety of job site visitors during the performance of this contract. We encourage contractors to follow guidance from the Department of Labor, Occupational Safety and Health Administration (OSHA), the Centers for Disease Control and Prevention (CDC), and all other applicable NPS, local, city, and state mandates. We encourage contractors to develop policies for infection prevention and an Infectious Disease Preparedness and Response Plan.
b) To the extent appropriate, Contractors should include the protective health and safety measures they intend to implement related to COVID-19 in any accident prevention or safety submittals required under this contract.
These plans should contain preventive measures the contractor intends to follow while performing work on government property as well as responsive and corrective actions to be taken if an employee exhibits symptoms or tests positive for COVID-19.
c) Upon contract award, contractors should communicate with the Contracting Officer regarding contractor decisions and actions to protect the health and safety of workers for the duration of contract performance under which pandemic conditions exist.
SECTION I: Federal Acquisition Regulation (FAR) Contract Clauses
52.202-1 Definitions. (JUN 2020) 52.203-3 Gratuities. (APR 1984) 52.203-5 Covenant Against Contingent Fees. (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government. (JUN 2020) 52.203-7 Anti-Kickback Procedures. (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower
Rights (JUN 2020) 52.203-19 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or
Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUN 2020) 52.204-13 System for Award Management Maintenance. (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (NOV 2021) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky
Lab and Other Covered Entities (NOV 2021) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or
Equipment (NOV 2021) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or
Proposed for Debarment. (NOV 2021) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records—Negotiation (JUN 2020) 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997) 52.215-17 Waiver of Facilities Capital Cost of Money (Oct 1997) [Will be included in the contract only if the prospective contractor does not propose facilities capital cost of money in its offer. Refer to provision 52.215- 16 in Section L.5.]
52.215-19 Notification of Ownership Changes (OCT 1997) 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data—
Modifications (NOV 2021)
52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns. (OCT 2018) 52.219-14 Limitations on Subcontracting (SEP 2021) 52.219-28 Post-Award Small Business Program Rerepresentation. (SEP 2021) 52.222-3 Convict Labor. (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation. (MAY 2018) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds. (MAY 2014) 52.222-8 Payrolls and Basic Records. (JUL 2021) 52.222-9 Apprentices and Trainees. (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) 52.222-11 Subcontracts (Labor Standards). (MAY 2014) 52.222-12 Contract Termination - Debarment. (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014) 52.222-14 Disputes Concerning Labor Standards. (FEB 1988) 52.222-15 Certification of Eligibility. (MAY 2014) 52.222-21 Prohibition of Segregated Facilities. (APR 2015) 52.222-26 Equal Opportunity. (SEP 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015) 52.222-35 Equal Opportunity for Veterans. (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities. (JUN 2020) 52.222-37 Employment Reports on Veterans. (JUN 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (DEC 2010) 52.222-50 Combating Trafficking in Persons. (NOV 2021) 52.222-54 Employment Eligibility Verification. (NOV 2021) 52.222-55 Minimum Wages Under Executive Order 13658 (JAN 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011) 52.223-6 Drug-Free Workplace. (MAY 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (JUN 2020) 52.225-13 Restrictions on Certain Foreign Purchases. (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007) 52.228-2 Additional Bond Security. (OCT 1997) 52.228-5 Insurance - Work on a Government Installation. (JAN 1997) 52.228-11 Individual Surety Pledges of Assets. (FEB 2021) (DEVIATION APR 2020) 52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds - Construction. (JUN 2020) (DEVIATION APR 2020) 52.229-3 Federal, State, and Local Taxes. (FEB 2013)
52.229-12 Tax on Certain Foreign Procurements- Notice and Representation (FEB 2021) 52.232-5 Payments under Fixed-Price Construction Contracts. (JUN 2020) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims. (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts. (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (NOV 2021) 52.233-1 Disputes, Alt. 1. (MAY 2014, DEC 1991) 52.233-3 Protest after Award. (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) 52.236-2 Differing Site Conditions. (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) 52.236-5 Material and Workmanship. (APR 1984) 52.236-6 Superintendence by the Contractor. (APR 1984) 52.236-7 Permits and Responsibilities. (NOV 1991) 52.236-8 Other Contracts. (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984) 52.236-10 Operations and Storage Areas. (APR 1984) 52.236-11 Use and Possession Prior to Completion. (APR 1984) 52.236-12 Cleaning Up. (APR 1984) 52.236-14 Availability and Use of Utility Services. (APR 1984) 52.236-17 Layout of Work. (APR 1984) 52.236-21 Specifications and Drawings for Construction. (FEB 1997) 52.236-26 Preconstruction Conference. (FEB 1995) 52.242-13 Bankruptcy. (JUL 1995) 52.243-4 Changes. (JUN 2007) 52.244-6 Subcontracts for Commercial Products and Commercial Services. (Jan 2022) 52.246-21 Warranty of Construction. (MAR 1994) - Alternate I (APR 1984) 52.248-3 Value Engineering - Construction. (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) - Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction). (APR 1984) 52.252-6 Authorized Deviations in Clauses (NOV 2020)
(b) Department of the Interior (48 CFR 14) 52.253-1 Computer Generated Forms. (JAN 1991) 1452.215-70 Examination of Records by the Department of the Interior (APR 1984)
52.225-9 Buy American - Construction Materials. (NOV 2021)
(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal
Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A) The cost of its components mined, produced, or manufactured in the United States exceeds
55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United
States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the
Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (dollars)* Item1:
Foreign construction material Domestic construction material
Item2:
Foreign construction material Domestic construction material [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]
52.236-4 Physical Data (APR 1984) Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of, or conclusion drawn from the data or information by the Contractor. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by geotechnical, environmental, and hydrological investigators.
52.236-13 Accident Prevention. (NOV 1991) - Alternate I
(a) The Contractor shall provide and maintain work environments and procedures which will -
(1) Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities;
(2) Avoid interruptions of Government operations and delays in project completion dates; and
(3) Control costs in the performance of this contract.
(b) For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall -
(1) Provide appropriate safety barricades, signs, and signal lights;
(2) Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910; and
(3) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.
(c) If this contract is for construction or dismantling, demolition or removal of improvements with any Department of Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.
(d) Whenever the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting Officer shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor's representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued under this clause.
(e) The Contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.
(f) Before commencing the work, the Contractor shall -
(1) Submit a written proposed plan for implementing this clause. The plan shall include an analysis of the significant hazards to life, limb, and property inherent in contract work performance and a plan for controlling these hazards; and
(2) Meet with representatives of the Contracting Officer to discuss and develop a mutual understanding relative to administration of the overall safety program.
Addendum to 52.236-13:
As work proceeds, the Accident Prevention Plan (APP) shall be adapted to new situations and new conditions.
Changes and modifications to the accepted APP shall be made with the knowledge and concurrence of the safety office, site superintendent and Contracting Officer's Representative (COR). Should any unforeseen hazards become evident during the performance of work, the contractor shall bring such hazard to the attention of the COR, both verbally and in writing for resolution as soon as possible. In the interim necessary action shall be taken to re-establish and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public, and the environment. See also paragraph H.9.
1452.203-70 Restriction on Endorsements—Department of the Interior (JUL 1996) The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.
1452.228-70 Liability Insurance - Department of the Interior (JUL 1996)
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
Employer's liability $100,000 General liability $3,000,000 Construction
Per person $500,000 Per occurrence $1,000,000 Property damage $3,000,000
Architect-Engineer Per person $200,000 Per occurrence $500,000 Property damage $ 20,000
Automobile liability Per person $200,000 Per occurrence for bodily injury $500,000 (other than passenger liability) Per occurrence for property damage $20,000
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days…
This is the start of the file's text. The full file is on GovTribe.