Sol_140P5220Q0047.pdf
PDF 497 KB Posted
- Attached to
- RESURFACE NATURE TRAIL HORSESHOE BEND NMP
- Solicitation number
- 140P5220Q0047
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MAP_HOBE_Nature Trail.pdf | ||
| DOL Wage Determination AL20200144 - Highway_beta.SAM.gov.pdf | ||
| A04 SOW 203359 Resurface Nature Trail.pdf | ||
| SF24-16d.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
Region 1, 2 and 4 – Contracting Office West-PSW 2680 Natchez Trace Parkway
Tupelo MS 38804
NOTICE TO OFFERORS
Solicitation Number: 140P5220Q0047
Request For Quotations (RFQ): This solicitation is issued as a Request for Quotation (RFQ), and incorporates all applicable provisions and clauses in effect through Federal Acquisition Circular FAC 2020-05D thru March 30, 2020. This acquisition will be conducted in accordance with FAR PART 13—SIMPLIFIED ACQUISITION PROCEDURES and SUBPART 36 Construction.
POSTING: beta.SAM.gov and FedConnect.net (check periodically for update or amendments)
SET-ASIDE: The acquisition is 100% Set-Aside Small Business. The applicable North American Industry Classification System (NAICS) code is 237310 Resurfacing, highway, road, or street and the corresponding Small Business size standard is $36.5 million average annual receipts.
SITE VISIT: Strongly recommended for prospective bidders. Please contact Steven K. Crowder Facility Manager, Horseshoe Bend NMP, W-256-234-7111 or C-256-537-1171 to schedule date and time of the Site visit.
PREPARATION OF QUOTATION/OFFER: Any prospective contractor desiring consideration must complete the SF-1442, BID SCHEDULE or detailed price breakdown on Letterhead Stationery and the applicable reps & certs in Section K or electronic annual representations and certifications at SAM accessed via https://www.acaquisition.gov.
OFFER DUE DATE/LOCAL TIME on or before 06/30/2020 / 10 AM CT. Electronic submission via FedConnect response builder or email andre_ward@nps.gov is authorized. Please do not submit hard copies.
EVALUATION PROCEDURES: Formal evaluation plans and establishing a competitive range, conducting discussions, and scoring quotations or offers are not required. Contracting officer must determine that the proposed price is fair and reasonable.
(1) Whenever possible, base price reasonableness on competitive quotations or offers.
(2) If only one response is received, include a statement of price reasonableness in the contract file.
BASIS OF AWARD: Responsive, responsible low price quote/offer, considering only price and the price-related factors.
Project Magnitude: Project total estimated price range is between $100,000 and $250,000.
System for Award Management: Offerors and quoters are required to be registered in SAM at the time an offer or quotation is submitted in order to comply with the annual representations and certifications requirements.
Offerors who are not registered in SAM should consider applying for registration immediately upon receipt of this solicitation. See https://ww.sam.gov for information on registration.
INQUIRIES: Point of Contact: Andre Ward, Contracting Officer, Phone: (850) 934-2614 Email: andre_ward@nps.gov or FedConnect. Please include the solicitation number in the subject line.
https://www.acaquisition.gov/ mailto:andre_ward@nps.gov
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040489814
NPS, SER - West MABO
2680 Natchez Trace Parkway
CO Andre Ward 850-232-4630 Tupelo MS 38804
PSW
Interior Region 2 South Atlantic Gulf
West Contracting Office Electronic Bids Submission Authorized FEDCONNECT or EMAIL: andre_ward@nps.gov
Evans Ward 850-934-2614
203359
06/08/2020
140P5220Q0047
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Repair and stabilize four segments of Horseshoe Bend NMP Nature Trail
Site of Work: (Tallapoosa County) Daviston, Alabama
MAGNITUDE OF CONSTRUCTION: A single, firm-fixed price construction contract.
ESTIMATED PRICE RANGE: Between $100,000 and $250,000.
SCOPE: resuface approximately 7562 linear ft. x four feet wide x 0.25 foot deep with crushed stone size 1 ½ inch down granite and commercial weed barrier landscape fabric; and also construct 2 retaining walls and 4 water bars to prevent erosion.
Work shall conform to the technical requirements and quality standards cited in the
Statement of Work (SOW) incorporated by attachment in Section J.
SET-ASIDE: 100% Total Small Business
NAICS Code: 237310 | Size Standard: $36.5 million
LABOR LAWS: 40 U.S.C. chapter 31 , subchapter IV, Wage Rate Requirements
(Construction), formerly known as the Davis-Bacon Act apply
DOL Wage Determination AL20200144 incorporated by attachment in Section J.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 120 calendar days and complete it within ________________ ________________ calendar days after receiving
Section F clause 52.211-10
06/30/2020
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
DOI, NPS, SER - GUIS Admin. Office 1801 Gulf Breeze Parkway
Gulf Breeze FL 32563
SW1
Evans Ward
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 31
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P5220Q0047
This solicitation is issued as a Request For
Quotation or Offer in accordance with FAR PART 13
- SIMPLIFIED ACQUISITION PROCEDURES and appropriate combination of the procedures in parts 13, 14, and 36.
Delivery: 120 Days After Notice to Proceed
Delivery Location Code: 0009060246
NPS, HORSESHOE BEND NMP
11288 HORSESHOE BEND ROAD
DAVISTON AL 36256-9751 US
Period of Performance: 07/20/2020 to 11/19/2020
00010 Resurface Four Segments of Nature Trail
Horseshoe Bend National Military Park
(Tallapoosa County) Daviston, Alabama
Also construct 2 small retaining walls and 4 water bars to prevent erosion.
Refer to the Statement of Work (SOW) incorporated by attachment and bid documents for more details.
Product/Service Code: Z2LB
Product/Service Description: REPAIR OR ALTERATION
OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
A - Solicitation/Contract Form B - Supplies or Services/Prices
B.1 Contract Price Schedule C - Description/Specifications
C.1 Statement of Work--Specifications D - Packaging and Marking E - Inspection and Acceptance F - Deliveries or Performance
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) G - Contract Administration Data
Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013) H - Special Contract Requirements I - Contract Clauses
52.222-6 Construction Wage Rate Requirements. (AUG 2018) 52.222-23 Notice of Requirement for Affirmative Action To Ensure Equal Employment Opportunity Construction. (FEB 1999) ...19 52.228-1 Bid Guarantee. (SEPT 1996) 52.228-15 Performance and Payment Bonds-Construction (OCT 2010) 52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014) 52.236-5 Material and Workmanship. (APR 1984) 52.236-7 Permits and Responsibilities. (NOV 1991)
J - List of Documents, Exhibits and Other Attachments K - Representations, Certifications, and Other Statements of Bidders
52.204-8 Annual Representations and Certifications. (MAR 2020) L - Instructions, Conditions, and Notices to Bidders
52.214-18 Preparation of Bids - Construction. (APR 1984) 52.236-27 Site Visit (Construction). (FEB 1995)
M - Evaluation Factors for Award
A - Solicitation/Contract Form
SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) (prospective contract must complete required fields on page 2 in Blocks 14 thru 20(c) and return signed executed form with quotation or offer).
Otherwise submit quotation or offer on letterhead stationery. As a minimum, offers must show—
(1) The solicitation number;
(2) The time specified in the solicitation for receipt of offers;
(3) The name, address, and telephone number of the offeror;
(4) A technical description of the items being offered in sufficient detail to evaluate compliance with the requirements in the solicitation.
(5) Terms of any express warranty;
(6) Price and any discount terms;
(7) “Remit to” address, if different than mailing address;
(8) A completed copy of the representations and certifications at FAR 52.212-3 (see FAR 52.212-3(b) for those representations and certifications that the offeror shall complete electronically);
(9) Acknowledgment of Solicitation Amendments
B - Supplies or Services/Prices
B.1 Contract Price Schedule
CONTRACT PRICE SCHEDULE
SOLICITATION NUMBER: 140P5220Q0047
PARK - PMIS: HOBE 203359
DEVELOPED AREA: Horseshoe Bend National Military Park
PROJECT TITLE: Resurface Nature Trail
Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all Bid Additives line items. Failure to do so may render the quote/offer unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.
CONTRACT
LINE ITEM
NUMBER
(CLIN)
CONTRACT LINE ITEM (CLI)
TITLE
QUANTITY
UNIT OF
MEASURE UNIT PRICE EXTENDED
AMOUNT
Resurface Nature Trail (four sections with fabric 4 ft.
wide and min 3 inches thick of crushed stone)
7,562 LF
Water bars, (6” round timber GFM) ½” rebar driven 2 ft. into ground 4 EA
Retaining Walls (7 ft. long and 1 foot high) (8 ft. long and 1 ft. high)
2 EA
TOTAL BASE PRICE (Contract Line Item Number 1 through X) ------------------------------------
TOTAL PROPOSED PRICE (Contract Line Item Numbers thru 3) ----------- $________________
All measurement and payment information is included in the SOW project specifications.
(Section I clause 52.232-5).
C - Description/Specifications
C.1 Statement of Work--Specifications
STATEMENT OF WORK:
The contractor shall furnish all necessary personnel, materials, and equipment to resurface segments of Horseshoe Bend NMP Nature Trail by filling in segments with crushed stone, fabric, adding water bars and small retaining walls to prevent erosion. This trail is located in nearby Daviston, Alabama.
Park Address: 11288 Horseshoe Bend Rd.
Additional technical requirements and quality standards are cited in the STATEMENT OF WORK incorporated by attachment in Section J and make part of this solicitation/contract.
D - Packaging and Marking
This SECTION not used.
E - Inspection and Acceptance
52.236-15 Schedules for Construction Contracts. (APR 1984)
52.246-12 Inspection of Construction. (AUG 1996)
F - Deliveries or Performance
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 days after Notice To Priceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
G - Contract Administration Data
Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice [upload Vendor's Pay Application with Schedule of Values and Requisite Certification as required under this contract]:
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
H - Special Contract Requirements
52.236-13 Accident Prevention. (NOV 1991) - Alternate I (NOV 1991)
1452.204-70 Release of Claims (JUL 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
AUTHORITIES AND DELEGATIONS (SEPT 2011)
Authorities and Delegations (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting
Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor.
Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum.
The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
Detours, Traffic Control Plan, Traffic Barricades, Warning and Safety Protection Devices
DETOURS. TRAFFIC CONTROL PLAN, TRAFFIC BARRICADES,
WARNING AND SAFETY PROTECTION DEVISES
(a) The Contractor shall adequately protect work under construction, as well as protect the public from accident and unnecessary inconvenience, with barricades, warning, and safety devices.
(b) Any barricades detour, and directional signs required for implementing the establishment of a detour and/or equipment entrance points, shall be furnished, erected and maintained by the Contractor. No separate compensation shall be allowed for permits, bonding of roads, traffic barricades, warning and safety protection devices, as it shall be considered part of the Contract bid lump sum price for mobilization and demobilization. Damaged, lost and/or stolen warning and safety protection devices shall be replaced with same by the Contractor within 12 hours with no additional compensation allowed for replacement of repair of such devices.
(c) The Contractor shall contact the State or local authority responsible for roads and highways regarding the requirements for the maintenance of traffic along any affected roadways for the duration of the contract.
(End of clause)
Safety, Regulations, Laws to be Observed
SAFETY, REGULATIONS, LAWS TO BE OBSERVED (NOV 2007)
(a) The Contractor, its employees, and its subcontractors and employees shall abide by all safety rules applicable at the site of the work and shall comply with all applicable laws, ordinances, orders, codes, rules, regulations, etc. The Contractor shall furnish employees, including those of subcontractors, with recognized approved safety equipment, devices, and sanitary facilities and enforce compliance in their use consistent with accepted practices and applicable rules. The Contractor shall provide barricades, signs, and other safety equipment as required by Federal, State, or local codes.
(b) The Contractor shall comply with all regulations of the Occupational Safety and Health Act (OSHA) of 1970. The Government shall not be liable for any citations received by the Contractor as a result of failure to comply with applicable OSHA standards.
(c) All appropriate Township, County, State, and Federal Regulations, codes, and ordinances shall apply to this Contract. It shall be the Contractor’s sole responsibility to be aware of these regulations and to comply with them. The Government shall not be liable for any citations received by the Contractor.
(d) The Contractor, at all times, shall observe, comply with, and post as required all Federal, State and local laws, ordinances, and regulations in any manner affecting the conduct of the work applying to employees on the project, as well as all orders or decrees which have been or may be promulgated or enacted by any legal bodies or tribunals having authority or jurisdiction over the work, materials, employees, or contract.
(e) The Contractor shall be aware that the Government may request periodic inspections of the Contractor¿s operations, facilities and equipment, by any applicable governing regulatory agency.
(f) If the Contractor fails or refuses to promptly comply with any of the requirements of this special provision, the Contracting Officer, or his authorized representative, shall notify the Contractor of the noncompliance and indicate to the Contractor the corrective action to be taken. The Contractor shall, after receipt of such notice, immediately correct the conditions to which attention has been directed.
Such notice, either oral or written, when served on the Contractor or his authorized representative(s) at the site of the work, shall be deemed sufficient notice of noncompliance and of the need for corrective action.
(g) In the event the Contractor fails or refuses to promptly take corrective action, the Contracting Officer or his authorized representative may issue an order to suspend all or any part of the work. When satisfactory corrective action is taken, an order to resume work will be issued. The Contractor shall not be entitled to any extension of time, nor to any claim for damages or to excess costs by reason of either the directive or the suspension order. Failure of the Contracting Officer or his authorized representative to order discontinuance of any or all of the Contractor’s operations shall not relieve the Contractor of his responsibility for the safety of personnel and property.
(h) Compensation for compliance with any of the above items is to be included in the various items of the Contract for the expense involved.
I - Contract Clauses
52.204-12 Unique Entity Identifier Maintenance. (OCT 2016)
52.204-13 System for Award Management Maintenance. (OCT 2018)
52.204-18 Commercial and Government Entity Code Maintenance. (JUL 2016)
52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)
52.213-4 Terms and Conditions - Simplified Acquisitions (Other Than Commercial Items). (JAN 2020)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(ii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) (Section 1634 of Pub. L. 115-91).
(iii) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (AUG 2019) (Section 889(a)(1)(A) of Pub. L. 115-232).
(iv) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).
(v) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
(vi) 52.222-26, Equal Opportunity (SEP 2016) (E.O. 11246).
(vii) 52.225-13, Restrictions on Certain Foreign Purchases (JUN 2008) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
(viii) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(ix) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78 (19 U.S.C. 3805 note).
(2) Listed below are additional clauses that apply:
(i) 52.232-1, Payments (APR 1984).
(ii) 52.232-8, Discounts for Prompt Payment (FEB 2002).
(iii) 52.232-11, Extras (APR 1984).
(iv) 52.232-25, Prompt Payment (JAN 2017)
(v) 52.232-39, Unenforceability of Unauthorized Obligations (JUN 2013).
(vi) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (DEC 2013).
(vii) 52.233-1, Disputes (MAY 2014).
(viii) 52.244-6, Subcontracts for Commercial Items (AUG 2019).
(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2018) (Pub. L.
109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at $30,000 or more).
(ii) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (JAN 2020) (E.O. 13126).
(Applies to contracts for supplies exceeding the micro-purchase threshold).
(iii) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000 (MAY 2014) (41 U.S.C. chapter 65) (Applies to supply contracts over $15,000 in the United States, Puerto Rico, or the U.S. Virgin Islands).
(iv) 52.222-35, Equal Opportunity for Veterans (OCT 2015) (38 U.S.C. 4212) (applies to contracts of $150,000 or more).
(v) 52.222-36, Equal Employment for Workers with Disabilities (JUL 2014) (29 U.S.C. 793) (Applies to contracts over $15,000, unless the work is to be performed outside the United States by employees recruited outside the United States). (For purposes of this clause, "United States" includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)
(vi) 52.222-37, Employment Reports on Veterans (FEB 2016) (38 U.S.C. 4212) (Applies to contracts of $150,000 or more).
(vii) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf).
(viii)(A) 52.222-50, Combating Trafficking in Persons (JAN 2019) (22 U.S.C. chapter 78 and E.O. 13627) (Applies to all solicitations and contracts).
(B) Alternate I (MAR 2015) (Applies if the Contracting Officer has filled in the following information with regard to applicable directives or notices: Document title(s), source for obtaining document(s), and contract performance location outside the United States to which the document applies).
(ix) 52.222-55, Minimum Wages Under Executive Order 13658 (DEC 2015) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia)).
(x) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia.))
(xi) 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2011) (E.O. 13423) (Applies to services performed on Federal facilities).
(xii) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O. 13693)(applies to contracts for products as prescribed at FAR 23.804(a)(1)).
(xiii) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (JUN 2016) (E.O. 13693) (Applies to maintenance, service, repair, or disposal of refrigeration equipment and air conditioners).
(xiv) 52.223-15, Energy Efficiency in Energy-Consuming Products (DEC 2007) (42 U.S.C. 8259b) (Unless exempt pursuant to 23.204, applies to contracts when energy-consuming products listed in the ENERGY STAR® Program or Federal Energy Management Program (FEMP) will be-
(A) Delivered;
(B) Acquired by the Contractor for use in performing services at a Federally-controlled facility;
(C) Furnished by the Contractor for use by the Government; or
(D) Specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance).
(xv) 52.223-20, Aerosols (JUN 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons as a propellant or as a solvent; or contracts for maintenance or repair of electronic or mechanical devices).
(xvi) 52.223-21, Foams (JUN 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons as a foam blowing agent; or contracts for construction of buildings or facilities.
(xvii) 52.225-1, Buy American-Supplies (MAY 2014) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold and the acquisition-
(A) Is set aside for small business concerns; or
(B) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $25,000).
(xviii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (MAY 2014) (42 U.S.C.
1792) (Applies to contracts greater than $25,000 that provide for the provision, the service, or the sale of food in the United States).
(xix) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (OCT 2018) (Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) as its source of EFT information).
(xx) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (JUL 2013) (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information.)
(xxi) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C.
App. 1241) (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d).)
(2) Listed below are additional clauses that may apply:
(i) 52.204-21, Basic Safeguarding of Covered Contractor Information Systems (JUN 2016) (Applies to contracts when the contractor or a subcontractor at any tier may have Federal contract information residing in or transiting through its information system.
(ii) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015) (Applies to contracts over $35,000).
(iii) 52.211-17, Delivery of Excess Quantities (SEP 1989) (Applies to fixed-price supplies).
(iv) 52.247-29, F.o.b. Origin (FEB 2006) (Applies to supplies if delivery is f.o.b. origin).
(v) 52.247-34, F.o.b. Destination (NOV 1991) (Applies to supplies if delivery is f.o.b. destination).
(c) FAR 52.252-2, Clauses Incorporated by Reference (FEB 1998). This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.acquisition.gov
(d) Inspection/Acceptance. The Contractor shall tender for acceptance only those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. The Government must exercise its postacceptance rights-
(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence, such as acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(f) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges that the Contractor can demonstrate to the satisfaction of the Government, using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred that reasonably could have been avoided.
(g) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(h) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(End of clause)
52.214-29 Order of Precedence - Sealed Bidding. (JAN 1986)
52.219-6 Notice of Total Small Business Set-Aside. (MAR 2020)
52.222-6 Construction Wage Rate Requirements. (AUG 2018)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (AUG 2018)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance With Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-23 Notice of Requirement for Affirmative Action To Ensure Equal Employment Opportunity Construction. (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
29.9%
Goals for female participation for each trade
6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled Affirmative Action Compliance Requirements for Construction, and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S.
Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the-
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the covered area is AL Tallapoosa, Daviston.
(End of provision)
52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. (SEP 2013)
52.228-1 Bid Guarantee. (SEPT 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20% percent of the bid price or $3 million, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of clause)
52.228-2 Additional Bond Security. (OCT 1997)
52.228-5 Insurance - Work on a Government Installation. (JAN 1997)
52.228-11 Pledges of Assets (AUG 2018)
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)
52.228-15 Performance and Payment Bonds-Construction (OCT 2010)
(a) Definitions. As used in this clause- Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection. (i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of the Treasury, Financial Management, Service Surety Bond Branch, 3700 East West Highway, Room 6 F01, Hyattsville, MD 20782.
Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
(1) The Contractor's request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer.
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if -
(i) Consideration is specifically authorized by this contract; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that -
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
(Name)
(Title)
(Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the unearned amount), the Contractor shall -
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until -
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds.