This is a Request for Proposal (RFP) for a construction project issued by the National Park Service, Contracting Operations East, New England Major Acquisition Buying Office.
The solicitation seeks a contractor to balance three-phase power in the bio lab at Cape Cod National Seashore Park in Truro, Massachusetts. The work requires furnishing all labor, supervision, materials, tools, supplies, transportation, licenses, certificates, permits, personal protection equipment, professional services, and equipment as specified in the contract documents. The contract is firm fixed-price with a lump-sum pricing structure for Contract Line Item Number 00010. The contractor must commence work within 14 calendar days of receiving the notice to proceed and complete all work by February 19, 2027, with performance and payment bonds required at 100 percent of the original contract price. Proposals are due by 1000 hours local time on May 15, 2026, with an organized site visit scheduled for April 29, 2026, at 10:00 am ET at 99 Marconi Site Road, Wellfleet, MA 02667. The Government intends to award one contract and will evaluate proposals based on four factors: Technical Capability and Relevant Experience, Management Approach and Staffing Plan, Past Performance, and Price. All non-price factors carry equal weight and are approximately equally important to price. Offerors must be registered in the System for Award Management (SAM.gov) and must comply with Davis-Bacon prevailing wage requirements, Construction Wage Rate Requirements (52.222-6), and various federal contract clauses including Buy American construction materials provisions. Proposals must be submitted electronically in two separate volumes with a maximum email size of 30 MB per submission.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4326R0016_Amd_0001.pdf | ||
| B08_Solicitation_Attachment_2_Drawings.pdf | ||
| B08_Solicitation_Attachment_1_Specifications.pdf | ||
| B08_Solicitation_Attachment_3_DOL_Wage_Determination_MA20260001_01_02_2026.pdf | ||
| B08_Solicitation_Attachment_4_Construction_Contract_Administration.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
NEGOTIATED (RFP) REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF
SEALED BID (IFB) INVITATION FOR BID
9. FOR
INFORMATION CALL
PAGES
140P4326R0016
NPS, NER - NE MABO
Boston National Historical Park Charlestown Navy Yard Building I-1 Boston MA 02129-4543
Jason Albright Jason_Albright@ios.doi.gov
0044039992
PNN
Jason Albright 6175196145
04/15/2026
05/15/2026
14 140 Section H
The National Park Service, Contracting Operations East, New England Major Acquisition Buying Office, issues this Request for Proposal (RFP) for a construction requirement at Cape Cod National Seashore Park in Truro, Massachusetts. Work will consist of furnishing all labor, supervision, materials, tools, supplies, transportation, license, certificates, permits, personal protection equipment, professional services, and equipment as required to balance the three-phase power in the bio lab as detailed in the
Specifications and Drawings, included with the solicitation documents.
Provisions and clauses - 04/15/2026
Attachment 1 - Specifications - 02/28/2025
Attachment 2 - Drawings - 02/20/2026
Attachment 3 - DOL Construction Wage Rate Determination - 01/02/2026
Attachment 4 - Construction Contract Administration - 04/15/2026
An organized site visit has been scheduled for April 29, 2026, at 10:00 am ET. Participants will meet at
99 Marconi Site Road, Wellfleet, MA, 02667.
1 61
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Continued...
AMENDMENT
NUMBER
DATE.
NPS, NER - NE MABO
Boston National Historical Park Charlestown Navy Yard Building I-1 Boston MA 02129-4543
PNN
Jason Albright
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P4326R0016
Delivery: 02/19/2027
Delivery Location Code: 0011282786
NPS, Cape Cod Ntl Seashore
99 Marconi Site Road
Wellfleet MA 02667 US
Period of Performance: 06/01/2026 to
02/19/2027
00010 Balance Three Phase Power at Bio Lab
Product/Service Code: J061
Product/Service Description:
MAINT/REPAIR/REBUILD
OF EQUIPMENT- ELECTRIC WIRE AND POWER
DISTRIBUTION EQUIPMENT
Solicitation 04/15/2026
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore – Balance Three Phase Power at Bio Lab
PART I – THE SCHEDULE
SECTION A – SOLICITATION / CONTRACT FORM
Solicitation, Offer, and Award (SF-1442) - pages 1- 3 of this package
SECTION B – BID SCHEDULE
CONTRACT PRICE SCHEDULE
SOLICITATION NUMBER: 140P4326R0016
PARK - PMIS: Cape Cod National Seashore PROJECT TITLE: Balance Three Phase Power at Bio Lab
Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for Base line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of summation error, the total corrected amounts govern. Round totals & extended prices to whole dollars. Refer to section “H” of this solicitation for additional information regarding contract options.
Labor Category and Rate Pricing Table
CONTRACT LINE
ITEM NUMBER
(CLIN)
CONTRACT LINE ITEM (CLIN)
TITLE
QUANTITY
UNIT OF
MEASURE
BASE PRICE
00010 Base – Balance Three Phase Power at Bio Lab
1 LUMP SUM $__________
TOTAL EVALUATED PRICE (Contract Line Item Number 00010) --- $__________
All measurement and payment information are included in the project specifications.
SECTION C – SPECIFICATIONS / DRAWINGS
The work of this contract is for a construction requirement at Cape Cod National Seashore in Truro, MA. Work will consist of providing all labor, qualified supervision, material, tools, equipment, supplies, and incidentals to balance the three phase power at the bio lab in accordance with contract drawings, specifications, and other supporting documentation.
Project Location: Cape Cod National Seashore at Wellfleet, MA.
Specifications and drawings are attached and incorporated herein by reference. Refer to section J.
SECTION D – PACKING AND MARKING
No clauses included.
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may—
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of clause)
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
SECTION F – DELIVERIES OR PERFORMANCE
52.242-14 SUSPENSION OF WORK (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(End of clause)
SECTION G – CONTRACT ADMINISTRATION DATA
1452.201-70 AUTHORITIES AND DELEGATIONS (SEPT 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
(written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (JUL 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING
SYSTEM (DEC 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in CPARS for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c. All information provided should be reviewed for accuracy prior to submission.
d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in CPARS marked as “Pending” with or without comments and whether or not it has been closed.
f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of Notice)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INTERNET PAYMENT PLATFORM
(FEB 2021)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
The contractor shall submit a draft Invoice Package, including copies of the following documents, to the National Park Service’s (NPS) Construction Management Representative (CMR) a minimum of 5 working days prior to submittal of the formal Invoice through IPP. Within 5 working days of receipt, the CMR shall provide an acceptability recommendation to both the NPS Contracting Officer’s Representative (COR) and the contractor. If the CMR recommends acceptance, the contractor shall submit a copy of the final version of the CMR’s checklist and the Invoice Package to the NPS through IPP.
1. Completed copy of the CMR’s final Construction Payment Request Checklist (Submit only with the formal submittal to IPP)
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
2. Completed copy of the Pay Estimate Form (including signed certification of subcontractor payments)
3. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts
4. A copy of the current construction schedule (refer to project specification section 013216)
5. A copy of the current Schedule of Values. (refer to project specification section 013216)
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Clause)
SECTION H – SPECIAL CONTRACT REQUIREMENTS
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
The Contractor shall be required to (a) commence work under this contract within 14 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than February 19, 2027. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by October 1, 2026. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are incorporated by reference (by Citation Number, Title, and Date) per the clause at FAR “52.252-2 CLAUSES INCORPORATED BY REFERENCE” in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to a clause’s full text.
52.202-1 DEFINITIONS (JUN 2020)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN 2020)
52.203-7 ANTI-KICKBACK PROCEDURES (JUN 2020)
52.203-8 CANCELLATION, RECESSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY
(MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (JUN 2020)
52.203-14 DISPLAY OF HOTLINE POSTER(S) (NOV 2021)
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR
STATEMENTS (JAN 2017)
52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS (JUN 2020)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)
52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS (OCT 2016)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)
52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUNE 2023)
52.209-6 PROTECTING THE GOVERNMENT’S INTEREST WHEN SUB-CONTRACTING WITH CONTRACTOR’S
DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (JAN 2025)
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT
2018) 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)
52.215-2 AUDIT AND RECORDS-NEGOTIATIONS (JUN 2020)
52.215-8 ORDER OF PRECEDENCE - UNIFORM CONTRACT FORMAT (OCT 1997)
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)(DEVIATION JAN 2026)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (JAN 2025)(DEVIATION JAN 2026)
52.219-28 POST AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025) (DEVIATION JAN 2026)
52.222-3 CONVICT LABOR (JUN 2003)
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS-OVERTIME COMPENSATION (MAR 2018)
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (AUG 2018)
52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
52.222-8 PAYROLLS AND BASIC RECORDS (JUL 2021)
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
52.222-12 CONTRACT TERMINATION - DEBARMENT (MAY 2014)
52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIRMENTS AND RELATED REGULATIONS
(MAY 2014)
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)
52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUN 2020)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (OCT 2025)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (JAN 2025)
52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2022)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2024)
52.223-21 FOAMS (MAY 2024)
52.224-1 PRIVACY ACT NOTIFICATION (APR 1984)
52.224-2 PRIVACY ACT (APR 1984)
52.224-3 PRIVACY TRAINING (JAN 2017)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB 2021)
52.226-7 DRUG-FREE WORKPLACE (MAY 2024)
52.226-8 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (MAY 2024)
52.227-1 AUTHORIZATION AND CONSENT (JUN 2020)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (JUN 2020)
52.227-4 PATENT INDEMNITY—CONSTRUCTION CONTRACTS (DEC 2007)
52.227-17 RIGHTS IN DATA – SPECIAL WORKS (DEC 2007)
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (DEC 2022)
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.229-12 TAX ON CERTAIN FOREIGN PROCUREMENTS (FEB 2021)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-17 INTEREST (MAY 2014)
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS CONTRACTORS (MAR 2023)
52.233-1 DISPUTES (MAY 2014) – ALTERNATE 1 (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984) (DEVIATION JAN 2026)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984) (DEVIATION JAN 2026)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984) (DEVIATION JAN 2026)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984) (DEVIATION JAN 2026)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991) (DEVIATION JAN 2026)
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
52.236-8 OTHER CONTRACTS (APR 1984) (DEVIATION JAN 2026)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (APR 1984) (DEVIATION JAN 2026)
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984) (DEVIATION JAN 2026)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984) (DEVIATION JAN 2026)
52.236-12 CLEANING UP (APR 1984) (DEVIATION JAN 2026)
52.236-13 ACCIDENT PREVENTION (NOV 1991) (DEVIATION JAN 2026)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984) (DEVIATION JAN 2026)
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984) (DEVIATION JAN 2026)
52.236-17 LAYOUT OF WORK. (APR 1984) (DEVIATION JAN 2026)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) (DEVIATION JAN 2026)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
52.242-13 BANKRUPTCY (JUL 1995)
52.243-4 CHANGES (JUN 2007) (DEVIATION OCT 2025)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994) ALT 1 (APR 1984)
52.248-3 VALUE ENGINEERING – CONSTRUCTION (OCT 2025)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012), ALT 1 (SEP
1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS (NOV 2023)
(a) This contract and employees working on this contract will be subject to the whistleblower rights and remedies established at 41 U.S.C. 4712 and Federal Acquisition Regulation (FAR) 3.900 through 3.905.
(b) The Contractor shall inform its employees in writing, in the predominant language of the workforce, of employee whistleblower rights and protections under 41 U.S.C. 4712, as described in FAR 3.900 through 3.905.
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts.
(End of clause)
52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES
DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED ENTITIES (DEC 2023)
(a) Definitions. As used in this clause—
Kaspersky Lab covered article means any hardware, software, or service that–
(1) Is developed or provided by a Kaspersky Lab covered entity;
(2) Includes any hardware, software, or service developed or provided in whole or in part by a Kaspersky Lab covered entity; or
(3) Contains components using any hardware or software developed in whole or in part by a Kaspersky Lab covered entity.
Kaspersky Lab covered entity means–
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
(1) Kaspersky Lab;
(2) Any successor entity to Kaspersky Lab, including any change in name, e.g., “Kaspersky”;
(3) Any entity that controls, is controlled by, or is under common control with Kaspersky Lab; or
(4) Any entity of which Kaspersky Lab has a majority ownership.
(b) Prohibition. Section 1634 of Division A of the National Defense Authorization Act for Fiscal Year 2018 (Pub. L.
115-91) prohibits Government use of any Kaspersky Lab covered article. The Contractor is prohibited from—
(1) Providing any Kaspersky Lab covered article that the Government will use on or after October 1, 2018; and
(2) Using any Kaspersky Lab covered article on or after October 1, 2018, in the development of data or deliverables first produced in the performance of the contract.
(c) Reporting requirement.
(1) In the event the Contractor identifies a Kaspersky Lab covered article provided to the Government during contract performance, or the Contractor is notified of such by a subcontractor at any tier or any other source, the Contractor shall report, in writing, to the Contracting Officer or, in the case of the Department of Defense, to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.
(2) The Contractor shall report the following information pursuant to paragraph (c)(1) of this clause:
(i) Within 3 business days from the date of such identification or notification: the contract number; the order number(s), if applicable; supplier name; brand; model number (Original Equipment Manufacturer (OEM) number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of submitting the report pursuant to paragraph (c)(1) of this clause: any further available information about mitigation actions undertaken or recommended. In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of a Kaspersky Lab covered article, any reasons that led to the use or submission of the Kaspersky Lab covered article, and any additional efforts that will be incorporated to prevent future use or submission of Kaspersky Lab covered articles.
(d) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts including subcontracts for the acquisition of commercial products or commercial services.
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND
VIDEO SURVEILLANCE SERVICES AND EQUIPMENT (NOV 2021)
(a) Definitions. As used in this clause—
Backhaul means intermediate links between the core network, or backbone network, and the small subnetworks at the
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore – edge of the network (e.g., connecting cell phones/towers to the core telephone network). Backhaul can be wireless (e.g., microwave) or wired (e.g., fiber optic, coaxial cable, Ethernet).
Covered foreign country means The People’s Republic of China.
Covered telecommunications equipment or services means–
(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities);
(2) For the purpose of public safety, security of Government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);
(3) Telecommunications or video surveillance services provided by such entities or using such equipment; or
(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
Critical technology means–
(1) Defense articles or defense services included on the United States Munitions List set forth in the International Traffic in Arms Regulations under subchapter M of chapter I of title 22, Code of Federal Regulations;
(2) Items included on the Commerce Control List set forth in Supplement No. 1 to part 774 of the Export Administration Regulations under subchapter C of chapter VII of title 15, Code of Federal Regulations, and controlled-
(i) Pursuant to multilateral regimes, including for reasons relating to national security, chemical and biological weapons proliferation, nuclear nonproliferation, or missile technology; or
(ii) For reasons relating to regional stability or surreptitious listening;
(3) Specially designed and prepared nuclear equipment, parts and components, materials, software, and technology covered by part 810 of title 10, Code of Federal Regulations (relating to assistance to foreign atomic energy activities);
(4) Nuclear facilities, equipment, and material covered by part 110 of title 10, Code of Federal Regulations (relating to export and import of nuclear equipment and material);
(5) Select agents and toxins covered by part 331 of title 7, Code of Federal Regulations, part 121 of title 9 of such Code, or part 73 of title 42 of such Code; or
(6) Emerging and foundational technologies controlled pursuant to section 1758 of the Export Control Reform Act of 2018 ( 50 U.S.C. 4817).
Interconnection arrangements means arrangements governing the physical connection of two or more networks to allow the use of another's network to hand off traffic where it is ultimately delivered (e.g., connection of a customer of telephone provider A to a customer of telephone company B) or sharing data and other information resources.
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of the producer or provider of covered telecommunications equipment or services used by the entity that excludes the need to include an internal or third-party audit.
Roaming means cellular communications services (e.g., voice, video, data) received from a visited network when unable to connect to the facilities of the home network either because signal coverage is too weak or because traffic is too high.
Substantial or essential component means any component necessary for the proper function or performance of a piece of equipment, system, or service.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. The Contractor is prohibited from providing to the Government any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract, or extending or renewing a contract, with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract.
(c) Exceptions. This clause does not prohibit contractors from providing—
(1) A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(2) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(d) Reporting requirement.
(1) In the event the Contractor identifies covered telecommunications equipment or services used as a substantial or essential component of any system, or as critical technology as part of any system, during contract performance, or the Contractor is notified of such by a subcontractor at any tier or by any other source, the Contractor shall report the information in paragraph (d)(2) of this clause to the Contracting Officer, unless elsewhere in this contract are established procedures for reporting the information; in the case of the Department of Defense, the Contractor shall report to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.
(2) The Contractor shall report the following information pursuant to paragraph (d)(1) of this clause
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
(i) Within one business day from the date of such identification or notification: the contract number; the order number(s), if applicable; supplier name; supplier unique entity identifier (if known); supplier Commercial and Government Entity (CAGE) code (if known); brand; model number (original equipment manufacturer number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of submitting the information in paragraph (d)(2)(i) of this clause: any further available information about mitigation actions undertaken or recommended. In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of covered telecommunications equipment or services, and any additional efforts that will be incorporated to prevent future use or submission of covered telecommunications equipment or services.
(e) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (e) and excluding paragraph (b)(2), in all subcontracts and other contractual instruments, including subcontracts for the acquisition of commercial products or commercial services.
(End of clause)
52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—PROHIBITION
(DEC 2023)
(a) Definitions. As used in this clause—
Covered article, as defined in 41 U.S.C. 4713(k), means—
(1) Information technology, as defined in 40 U.S.C. 11101, including cloud computing services of all types;
(2) Telecommunications equipment or telecommunications service, as those terms are defined in section 3 of the Communications Act of 1934 ( 47 U.S.C. 153);
(3) The processing of information on a Federal or non-Federal information system, subject to the requirements of the Controlled Unclassified Information program (see 32 CFR part 2002); or
(4) Hardware, systems, devices, software, or services that include embedded or incidental information technology.
FASCSA order means any of the following orders issued under the Federal Acquisition Supply Chain Security Act (FASCSA) requiring the removal of covered articles from executive agency information systems or the exclusion of one or more named sources or named covered articles from executive agency procurement actions, as described in 41 CFR 201–1.303(d) and (e):
(1) The Secretary of Homeland Security may issue FASCSA orders applicable to civilian agencies, to the extent not covered by paragraph (2) or (3) of this definition. This type of FASCSA order may be referred to as a Department of Homeland Security (DHS) FASCSA order.
(2) The Secretary of Defense may issue FASCSA orders applicable to the Department of Defense (DoD) and national security systems other than sensitive compartmented information systems. This type of FASCSA order may be referred to as a DoD FASCSA order.
(3) The Director of National Intelligence (DNI) may issue FASCSA orders applicable to the intelligence community and sensitive compartmented information systems, to the extent not covered by paragraph (2) of this definition. This type of FASCSA order may be referred to as a DNI FASCSA order.
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
Intelligence community, as defined by 50 U.S.C. 3003(4), means the following—
(1) The Office of the Director of National Intelligence;
(2) The Central Intelligence Agency;
(3) The National Security Agency;
(4) The Defense Intelligence Agency;
(5) The National Geospatial-Intelligence Agency;
(6) The National Reconnaissance Office;
(7) Other offices within the Department of Defense for the collection of specialized national intelligence through reconnaissance programs;
(8) The intelligence elements of the Army, the Navy, the Air Force, the Marine Corps, the Coast Guard, the Federal Bureau of Investigation, the Drug Enforcement Administration, and the Department of Energy;
(9) The Bureau of Intelligence and Research of the Department of State;
(10) The Office of Intelligence and Analysis of the Department of the Treasury;
(11) The Office of Intelligence and Analysis of the Department of Homeland Security; or
(12) Such other elements of any department or agency as may be designated by the President, or designated jointly by the Director of National Intelligence and the head of the department or agency concerned, as an element of the intelligence community.
National security system, as defined in 44 U.S.C. 3552, means any information system (including any telecommunications system) used or operated by an agency or by a contractor of an agency, or other organization on behalf of an agency—
(1) The function, operation, or use of which involves intelligence activities; involves cryptologic activities related to national security; involves command and control of military forces; involves equipment that is an integral part of a weapon or weapons system; or is critical to the direct fulfillment of military or intelligence missions, but does not include a system that is to be used for routine administrative and business applications (including payroll, finance, logistics, and personnel management applications); or
(2) Is protected at all times by procedures established for information that have been specifically authorized under criteria established by an Executive order or an Act of Congress to be kept classified in the interest of national defense or foreign policy.
Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of any covered articles, or any products or services produced or provided by a source. This applies when the covered article or the source is subject to an applicable FASCSA order. A reasonable inquiry excludes the need to include an internal or third-party audit.
Sensitive compartmented information means classified information concerning or derived from intelligence sources, methods, or analytical processes, which is required to be handled within formal access control systems established by the Director of National Intelligence.
Document No.
140P4326R0016
Document Title
ConOps East- Boston – Cape Cod National Seashore –
Sens…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .