B08_Solicitation_Attachment_1_Specifications.pdf
PDF 844 KB Posted
- Attached to
- CAPE COD NS - BALANCE THREE PHASE POWER AT BIO LAB Federal contract opportunity
- Solicitation number
- 140P4326R0016
About this file
This is a Project Specifications document for a federal construction contract at Cape Cod National Seashore in Massachusetts. The project, identified as PMIS No. 305352, involves balancing three-phase power at the Bio-Lab facility located at Building 45, 32 Old Dewline Road, Truro, Massachusetts, with a final construction document submission deadline of February 28, 2025.
The base bid scope of work requires the contractor to provide complete engineering, procurement, and construction (EPC) services to deliver a fully operational three-phase, 4-wire, 225-ampere panelboard designated "New Panel Main-2" to replace the existing 120/208V, 2-pole, 3-wire panelboard. The contractor is responsible for all turnkey installation activities including removal of existing tap and conductors, provision of new service conductors from a new splice point to the existing main distribution panel, conversion of the existing Panel Main-2 enclosure to a splice cabinet with listed terminal strips, installation of a new three-phase, four-wire, 150-ampere feeder, extension of branch circuits, and splicing to existing circuits. The contract requires the contractor to perform all system calculations including arc flash and fault current analysis to ensure compliance with NEC 2023 and Massachusetts State Electrical Code (527 CMR 12.00), and final payment is contingent upon providing calculations, required labels, arc flash labeling with standoff distance and incident energy, and demonstration of successful system operation. The work is limited to a single prime contract with construction operations confined to the Bio-Lab Utility room (room 132) and Corridor (room 109), during normal business hours of 7:00 a.m. to 4:30 p.m., Monday through Friday, with noisy activities restricted to 8:00 a.m. to 12:00 p.m. Power shutdowns are restricted to Saturday or Sunday only, not exceeding one 8-hour outage, and the contractor must provide two portable 5kW generators to power refrigerators and freezers during outages.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4326R0016_Amd_0001.pdf | ||
| Sol_140P4326R0016.pdf | ||
| B08_Solicitation_Attachment_3_DOL_Wage_Determination_MA20260001_01_02_2026.pdf | ||
| B08_Solicitation_Attachment_4_Construction_Contract_Administration.docx | DOCX document | |
| B08_Solicitation_Attachment_2_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CAPE COD NATIONAL SEASHORE MASSACHUSETTS
BALANCE THREE PHASE POWER AT BIO-LAB
PMIS NO. 305352
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE CAPE COD NATIONAL SEASHORE
FINAL CONSTRUCTION DOCUMENT SUBMISSION FEBRUARY 28, 2025
SECTION 00 01 10 - TABLE OF CONTENTS
DIVISION 01 -- GENERAL REQUIREMENTS
01 11 00 - Summary of Work
01 26 01 - Contract Modification Procedures
01 27 00 - Definition of Contract Line Items
01 31 00 - Project Management & Coordination
01 32 16 - Construction Schedule
01 32 33 - Photo Documentation
01 33 23 - Submittal Procedures
01 35 23 - Safety Requirements
01 40 00 - Quality Requirements
01 50 00 - Temporary Facilities and Controls
01 57 19.12 - Noise & Acoustics Management
01 73 40 - Execution
01 77 00 - Closeout Procedures
01 78 23 - Operation and Maintenance Data
01 79 00 - Demonstration and Training
DIVISION 02 -- EXISTING CONDITIONS
02 41 13 - Selective Site Demolition
DIVISION 26 – ELECTRICAL
26 05 00 – Common Work Results for Electrical
26 05 19 – Low-Voltage Electrical Power Conductors and Cables
26 05 26 – Grounding and Bonding for Electrical Systems
26 05 29 – Hangers and Supports for Electrical Systems
26 05 33 – Raceways and Boxes for Electrical Systems
26 05 44 – Sleeves and Sleeve Seals for Electrical Raceways and Cabling
26 05 53 – Identification for Electrical Systems
26 05 74 – Overcurrent Protective Device Arc Flash
26 24 16 – Panelboards
END OF SECTION
CACO - 305352
01 11 00 - 4
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
10. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Building 45 (NAC/Bio-Lab), Cape Cod National Seashore, 32 Old Dewline Road, Truro, Massachusetts.
B. The base bid consists of the following:
1. This item provides all engineering, procurement, and construction (EPC) required to provide a fully operational three phase, 4 wire, 225-amp panelboard denoted as “New Panel Main-2” to replace the existing 120/208V, 2-pole, 3-wire, “Existing Panel Main 2”. The work includes removal of existing tap and conductors feeding Existing Panel Main-2; providing new service conductors from new splice point to the existing main distribution panel; converting existing Panel Main-2 enclosure to a splice cabinet with listed and labelled terminal strips; providing new three-phase, four-wire, 150-amp feeder to New Panel Main-2; extending branch circuits from New Panel Main-2 to the splice cabinet; and splicing to existing branch circuits. Provide new arc flash label and panelboard label for new “panel main-2”. The Contractor shall be solely responsible for turnkey installation including calculations, engineering, shop drawings, procurement, construction, testing, and commissioning.
This work includes providing and coordinating outages, investigations, demolition, and utility verification. The Contractor shall be responsible for all system calculations including arc flash and fault current analysis to ensure compliance with NEC 2023 and Massachusetts State Electrical Code (527 CMR 12.00). Final acceptance and payment is contingent upon providing calculations, required labels, the panelboard arc flash label indicating standoff distance and incident energy and demonstrating successful system operation.
C. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which
01 11 00 - 5 the Work is indicated.
1. Limits: Confine constructions operations to staging area to the Bio-Lab Utility room (room 132) and Corridor (room 109) as defined on drawings.
B. Storage of Materials: Confine storage of materials to staging area defined on drawings.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.4 PUBLIC USE OF SITE
A. T h e adjacent parking lot, roadway and site will not be closed to the public and government personnel during construction. Areas outside the limit of work and areas adjacent to construction staging area will also be open to the public and government personnel during construction and remain accessible.
1.5 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
b. With the exception of the approved electrical outages, electrical systems shall remain fully operational. Any modifications shall require tests and inspections to be successfully completed prior to turn over to the government. On completion of tests
01 11 00 - 6 and beneficial use inspection, the Government will operate and maintain the electrical systems serving the Bio-Lab/NAC (BLDG 45).
c. Upon an accepted final inspection and resolution of all punch list items, the, Government will assume responsibility for maintenance, grounds and custodial services for areas within the limit of work and areas affected within occupied portions of building.
1.6 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests seven (7) days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.7 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours from 7:00 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: To be requested in writing to the CO and approved at least fourteen (14) days in advance.
2. Early Morning Hours: None.
3. Hours for noisy activity: 8:00 a.m. to 12:00 p.m.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer of proposed dates, start and end time and impacts associated with electrical investigatory work.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities unless permitted and arranged in advance.
1. Notify Contracting Officer not less than 1 4 d a y s in advance.
2. Do not proceed without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: P o w e r s h u t d o w n s a r e r e s t r i c t e d t o
S a t u r d a y o r S u n d a y o n l y . T h e w h o l e b u i l d i n g s hutdowns shall not exceed one (1) 8-hour outage. It’s understood that there may be smaller localized outages required to complete the new work. All new work shall be installed, tested and ready for final connection prior to the outage. Provide two (2) portable 5kW generator, fuel and extension cords as required to power the Bio-Lab refrigerators and freezers (120V, 60Hz).
01 11 00 - 7
D. Nonsmoking/non-Vaping Building: Smoking and Vaping are not permitted on government property.
1.8 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: Contractor may use a project website for communication and document management.
1. See Section 01 31 00 “Project Management and Coordination”.
B. One (1) on-site meeting to review Contractor’s existing utility plan prior to starting work.
C. One (1) on-site meeting to review emergency generator staging and equipment to be powered during outage(s).
D. Seasonal Restrictions
1. Not used.
1.9 SOILS INVESTIGATION REPORT
A. Not used
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
01 26 01 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
01 26 01 - 2
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
01 26 01 - 3
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the
Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate
01 26 01 - 4
Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
01 26 01 - 5
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized, then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead ....................... 10% Profit ....................... 8%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, then the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3, E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
01 26 01 - 6
PART 2 - PRODUCTS
PART 3 – EXECUTION
END OF SECTION 01 26
CACO - 305352 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No.1 – Base Bid – Modify electrical system at Building 45 (Bio-Lab/NAC) and provide new “Panel Main 2”.
1. This item includes all engineering, procurement, and construction (EPC) required to provide a fully operational three phase, 4 wire, 225-amp panelboard denoted as “New Panel Main-2” to replace the existing 120/208V, 2-pole, 3-wire, “Existing Panel Main 2”. The work includes removal of existing tap and conductors feeding Existing Panel Main-2; providing new service conductors from new splice point to the existing main distribution panel; converting existing Panel Main-2 enclosure to a splice cabinet with listed and labelled terminal strips; providing new three-phase, four-wire, 150-amp feeder to New Panel Main-2; extending branch circuits from New Panel Main-2 to the splice cabinet; and splicing to existing branch circuits. Provide new arc flash label and panelboard label for new “panel main-2”. The Contractor shall be solely responsible for turnkey installation including calculations, engineering, shop drawings, procurement, construction, testing, and commissioning.
This work includes providing and coordinating outages, investigations, demolition, and utility verification. The Contractor shall be responsible for all system calculations including arc flash and fault current analysis to ensure compliance with NEC 2023 and Massachusetts State Electrical Code (527 CMR 12.00). Final acceptance and payment contingent upon providing calculations, required labels, and demonstrating successful system operation.
2. Payment will be based on the percentage of work completed, as determined by the scheduled value of this line item.
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Requests for Information (RFIs).
5. Project Communications.
6. Project meetings.
7. Environmental Coordination.
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
3. Section 01 1 1 0 0 “Summary of Work”.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Formal written coordination memoranda are not required for this project. Coordination may be accomplished through email and routine field discussions.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress.
01 31 00 - 2
A dministrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Delivery and processing of submittals.
4. Project meetings.
5. Pre-installation and shutdown meetings.
6. Project closeout activities.
1.3 SUBMITTALS
A. Division 01 submittals (as applicable):
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
B. Submit items prior to start of construction unless otherwise approved by CO.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Submit RFIs promptly upon discovery of need for interpretation. RFIs may be submitted by email or using a project form, as directed by the Contracting Officer.
1. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI shall include:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section and drawing reference.
5. Description of issue.
6. Contractor’s suggested resolution (if any).
C. CO will review RFIs and respond. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
D. RFIs are not to be used for:
1. Submittal approvals.
2. Substitution requests.
01 31 00 - 3
3. T Means and methods.
4. Contract time or cost requests.
1.5 PROJECT COMMUNICATION
A. A formal project website is not required for this project.
B. Primary communication shall be by email between Contractor and Contracting Officer.
C. Submittals, RFIs, meeting notes, and schedules may be transmitted electronically in PDF format.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: One (1) on-site or virtual meeting prior to start of work.
Agenda shall include:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Outage Coordination
5. Submittal procedures.
6. Staging and Access .
B. Progress Meetings: Meetings will be held only if requested by the Contracting Officer or Contractor.
C. Preinstallation Conferences are not required for this project.
a. Temporary facilities and controls.
1.7 PERMITS
A. Contractor shall obtain and comply with all required Federal, State, and local permits at no additional cost to the Government.
B. No Government-furnished permits are anticipated.
C. Potential Permits: There are no permits required. listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is
D. Coordinate with Agencies Having Jurisdiction as required.
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
CACO - 237974
01 32 16 -4
CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
1.1 SUMMARY
A. This section specifies requirements for preparation, submission, and maintenance of a simple construction schedule for the Project.
B. The Construction Schedule shall be used to plan, coordinate, and track the Contractor’s work and to support progress payment evaluation.
1.2 SCHEDULE TYPE AND FORMAT
A. Provide a simple bar chart (Gantt-style) schedule showing major activities and milestones. CPM scheduling is not required.
B. Schedule shall be prepared using spreadsheet software (Excel), Microsoft Project, or similar.
C. Schedule shall include, at a minimum:
1. Notice to Proceed.
2. Submittals and approvals.
3. Procurement of major materials.
4. Outage coordination.
5. Demolition.
6. Installation of new panelboard and feeders.
7. Testing and energization.
8. Substantial Completion.
1.3 BASELINE SCHEDULE SUBMITTAL
A. Submit Baseline Construction Schedule within 10 calendar days after Notice to Proceed.
B. Schedule shall show activity durations, start and finish dates, and total contract duration.
C. Acceptance of schedule by Contracting Officer does not relieve Contractor of responsibility to complete the Work within Contract Time.
1.4 SCHEDULE UPDATES
A. Provide schedule updates monthly with progress payment request or upon request by Contracting Officer.
B. Updates shall show actual progress, revised remaining durations, and projected completion date.
CACO - 237974
01 32 16 -5
CONSTRUCTION SCHEDULE
C. If schedule indicates completion later than Contract Completion Date, submit a brief narrative describing corrective actions.
1.5 COORDINATION WITH PAYMENTS
A. Schedule shall support evaluation of progress payments.
B. Failure to provide required schedule or updates may delay processing of payment requests.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION 01 32 16
CACO-305352 01 32 33 -1
PHOTO DOCUMENTATION
SECTION 01 32 33 – PHOTO DOCUMENTATION
A. This Section includes administrative and procedural requirements for the following:
1. Existing Condition images.
2. Periodic construction images.
B. See Division 01 Section "Closeout Procedures" for a complete listing of closeout documents.
C. See Division 01 Section "Demonstration and Training" for submitting videotapes of demonstration of equipment and training of NPS personnel.
1.2 SUBMITTALS
A. Construction Images: Submit images electronically within seven days of taking the image.
Include the following for each:
1. Include Date, time and number (sequentially number all images) in filename.
2. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.
3. Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.
B. Closeout: Submit a complete set of digital image electronic files as a Project Record Document.
Submit on either a Compact Disc (CD) or Digital Video Disc (DVD).
1. Provide an index as a separate file on the Disc. List each image as a file name with number, date, and time. Include description and or vantage point image was taken.
2. Submit images that have the same aspect ratio as the sensor, un-cropped.
2.1 FORMAT REQUIREMENTS
A. Media: CD-R Archival Gold or DVD-R Archival Gold
B. Media Labels: Archival CD/DVD labeling markers, archival labels, or direct print CD
C. Images: Provide sRGB color images in JPEG format. Minimum sensor size of eight mega pixels, and at an image resolution of not less than 3200 x 2400 pixels.
CACO-305352 01 32 33 -2
PHOTO DOCUMENTATION
3.1 CONSTRUCTION IMAGES
A. General: Take digital images using the maximum range of depth of field, and that are in focus, to clearly show the Work. Images with blurry or out-of-focus areas will not be accepted.
1. Maintain index with each set of Construction images that identifies the number, date, time, and description for each.
2. Maintain one set of images accessible in the field office at the Project site, available at all times for reference.
B. Existing Condition Images: Before commencement of demolition, take color digital images of Project site.
C. Periodic Construction Images: Take color, digital daily images daily.
END OF SECTION 01 32 33
01 33 23 -1
SUBMITTAL PROCEDURE CACO-305352
SECTION 01 33 23 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for Contractor submittals including Shop Drawings, Product Data, Samples, and other submittals.
B. Submittals are limited to items necessary to demonstrate compliance with the Contract Documents for this small electrical construction project.
1.2 DEFINITIONS
A. Action Submittals: Submittals requiring Government review and approval prior to installation.
B. Informational Submittals: Submittals for record or information; Government action not required.
C. Portable Document Format (PDF): Portable Document Format.
1.3 GENERAL SUBMITTAL PROCEDURES
A. Submit only submittals specifically required by the Contract Documents.
B. Contractor shall review, approve, and coordinate all submittals prior to submission.
C. Electronic Submissions: Submit submittals electronically in PDF format via the NPS/DSC
SharePoint Project Website using the CM-SPE Transmittal Form. .
D. Identification: Each submittal shall include:
1. Project name and contract number.
2. Specification Section number and title.
3. Submittal title.
4. Sequential submittal number and revision.
5. Contractor name.
E. Review Times (unless otherwise noted):
1. Action Submittals: 14 calendar days.
2. Informational Submittals: 7 calendar days. that Contractor:
F. Re-submittals: Clearly identify all revisions and reference previous submittal.
G. Use for Construction: Only submittals marked “Approved” or “Approved with Notations” may be used for construction.
01 33 23 -2
H. Re-submittals: Make re-submittals using the same process used with the initial submittal.
1.4 CONTRACTOR’S USE OF DRAWING FILES
A. General: At Contractor’s written request, copies of drawing pdf files will be provided to Contractor for Contractor’s use in connection with Project, subject to the following conditions:
1. Files will be provided as is; no format or other changes to files or changes to the objects in the drawing will be done by the Government.
2.1 ACTION SUBMITTALS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer’s product specifications.
b. Manufacturer’s installation instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to Contracting Officer and keep another complete set of instructions at the project site until substantial completion.
c. Manufacturer’s catalog cuts: Submit only pertinent pages; mark each page of standard printed data to identify specific products proposed for use.
d. Wiring diagrams showing factory-installed wiring.
e. Printed performance curves.
f. Operational range diagrams.
g. Compliance with specified referenced standards.
h. Testing by recognized testing agency.
4. Submit product data in PDF file format before or concurrent with samples.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Shopwork manufacturing instructions.
g. Templates and patterns.
h. Schedules.
01 33 23 -3
i. Notation of coordination requirements.
j. Notation of dimensions established by field measurement.
k. Relationship to adjoining construction clearly indicated.
l. Seal and signature of professional engineer if specified.
m. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
2. Submit shop drawings as a PDF electronic file.
C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Complete and post the CM-SPE on the NPS SharePoint website for processing and documentation of action on submitted samples.
3. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Submittal Number and title of appropriate Specification Section.
4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
5. Samples for Initial Selection: Submit manufacturer’s color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit two full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer’s product line. Contracting Officer will return submittal with options selected.
6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for testing and inspection.
a. Number of Samples: Submit four sets of Samples. Contracting Officer will retain three Sample sets; remainder will be returned.
D. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by individual Specification Sections.
01 33 23 -4
1. Post informational submittals as PDF electronic files directly to the NPS SharePoint website.
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Informational submittals that do not comply with the requirements specified in the Contract Documents will be rejected and one copy will be returned.
B. Coordination Drawings: Comply with the requirements specified in Section 01 31 00 “Project Management and Coordination.”
C. Contractors Construction Schedule: Comply with the requirements specified in Section 01 32 16 “Construction Schedule.”
D. Accident Prevention Plan: Comply with the requirements specified in Section 01 35 23 “Safety Requirements.”
E. Schedule of Values: Comply with the requirements specified in Section 01 32 16 “Construction Schedule.”
F. Waste Recycling Plan: N o t U s e d .”
G. Quality Control Plan: Comply with the requirements specified in Section 01 40 00 “Quality Requirements.”
H. Indoor Air Quality Management Plan: Comply with the requirements specified in Section 01 57
19.11 “Indoor Air Quality Management.”
I. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.
J. Welding Certificates: Prepare written certification that welding procedures and personnel comply with the requirements in the Contract Documents. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.
K. Installer Certificates: Prepare written statements on manufacturer’s letterhead certifying that Installer complies with the requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
L. Manufacturer Certificates: Prepare written statements on manufacturer’s letterhead certifying that manufacturer complies with the requirements in the Contract Documents. Include evidence of manufacturing experience where required.
M. Product Certificates: Prepare written statements on manufacturer’s letterhead certifying that product complies with the requirements in the Contract Documents.
N. Material Certificates: Prepare written statements on manufacturer’s letterhead certifying that material complies with the requirements in the Contract Documents.
O. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting test results of material for compliance with the requirements in the Contract Documents.
01 33 23 -5
P. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with the requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
Q. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.
R. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
S. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
T. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with the requirements in the Contract Documents.
U. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with the requirements specified in Section 01 78 23 “Operation and Maintenance Data.”
V. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations.
Include page numbers.
W. Manufacturer’s Instructions: Prepare written or published information that documents manufacturer’s recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
X. Manufacturer’s Field Reports: Prepare written information documenting factory-authorized service representative’s tests and inspections. Include the following, as applicable:
1. Statement on condition of substrates and their acceptability for installation of product.
2. Summary of installation procedures being followed, whether they comply with the requirements and, if not, what corrective action was taken.
3. Results of operational and other tests and a statement of whether observed performance complies with the requirements.
Y. Permit Compliance Products: Prepare required information for compliance with permit provisions. Products include written notification of project startup, suspension, and completion of work; photo documentation of site conditions; reports; and drawings.
3.1 CONTRACTOR’S REVIEW
01 33 23 -6
A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.
3.2 CONTRACTING OFFICER’S ACTION
A. General: Submittals will be disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor’s approval.
1. Any work done or orders for materials or services placed before approval shall be at the Contractor’s own risk.
B. Action Submittals: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the CM-SPE Transmittal Form. The submittal will be marked in one of three ways as defined below:
1. APPROVED: Acceptable with no corrections.
2. APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
3. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
C. Informational Submittals: Contracting Officer will review each submittal and will either accept or reject it.
D. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.
END OF SECTION 01 33 23
SUBMITTAL LIST AND REVIEW ESTIMATE
SUBMITTALS LIST
CACO 305352 – BALANCE 3 PHASE POWER BIO-LAB
SUBMITTAL REQUIREMENTS(indicate with an "X")
Spec.
Sec.
Par. No.
Description
INFORMATIONAL ACTION
C
ER
T.
/L
A B
T
ES
T
RE
PO
R T/
C
AL
C.
O R
P
LA
N
M fg
. D
AT
A
IN
ST
R
UC
TI
NS
TH
ER
SH
P
DR
AW
IN
G
SA
PL
E
M fg
. D
AT
A
IN
ST
R
UC
TI
26 05 19 1.3 Action Submittals X
1.4 Information Submittals X X
2.1 Copper Building Wire X
2.2 Connectors and Splices X
26 05 26 1.2 Action Submittals X
1.3 Information Submittals X
2.3 Conductors X
2.4 Connectors X
2.5 Intersystem Bonding Termination Device X
2.6 Grounding Electrodes X
26 05 29 1.2 Action Submittals X
2.1 Support, Anchorage, and Attachment Components X X
26 05 33 1.3 Actional Submittals X X
2.1 Metal Conduits, Tubing, and Fittings X
2.2 Metal Wireways and Auxiliary Gutters X
2.3 Boxes, Enclosures, and Cabinets X X
26 05 44 1.2 Action Submittals X
2.1 Wall Sleeves X
2.2 Sleeve Seal Systems X
2.3 Sleeve Seal Fittings X
2.4 Grout X
2.5 Silicone Sealants X
CACO 305352 – BALANCE 3 PHASE POWER AT THE BIO-LAB
C
ER
T.
/L
A B
T
ES
T
RE
PO
R T/
C
P
. D
AT
A
IN
ST
R
UC
TI
P
DR
AW
PL
E
M fg
. D
AT
A
IN
ST
R
UC
TI
26 05 74 1.3 Action Submittals X
1.4 Information Submittals X X
26 24 16 1.3 Action Submittals X
1.4 Information Submittals X X
2.2 Distribution Panelboards X X
2.3 Lighting and Appliance Branch Circuit Panelboards X X
2.4 Disconnecting and Overcurrent Protective Devices X
CACO 305352 – BALANCE 3 PHASE POWER AT THE BIO-LAB
C
ER
T.
/L
A B
T
ES
T
RE
PO
R T/
C
P
. D
AT
A
IN
ST
R
UC
TI
P
DR
AW
PL
E
M fg
. D
AT
A
IN
ST
R
UC
TI
6 29 13.0 1.2 Action Submittals X X
1.3…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .