Sol_140L2621Q0026.pdf
PDF 510 KB Posted
- Attached to
- BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL
- Solicitation number
- 140L2621Q0026
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L2621Q0026_Amd_0001.pdf | ||
| Maps.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140L2621Q0026
1. REQUEST NO.
5a. ISSUED BY
NAME
a. NAME
c. STREET ADDRESS
d. CITY
10. PLEASE FURNISH QUOTATIONS TO
THE ISSUING OFFICE IN BLOCK 5a ON
OR BEFORE CLOSE OF BUSINESS (Date)
2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.
UNDER BDSA REG. 2
AND/OR DMS REG.1
RATING
6. DELIVERY BY (Date)
7. DELIVERY
9. DESTINATION
a. NAME OF CONSIGNEE
b. STREET ADDRESS
PAGE OF PAGES
5b. FOR INFORMATION CALL: (No collect calls)
TELEPHONE NUMBER
AREA CODE NUMBER
8. TO:
b. COMPANY
e. STATE f. ZIP CODE
c. CITY
d. STATE e. ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
THIS RFQ
REQUEST FOR QUOTATION
(THIS IS NOT AN ORDER)
IS IS NOT A SMALL BUSINESS SET ASIDEX
05/10/2021 0040525253
1 64
1387 S. VINNELL WAY
BOISE ID 83709
BLM ID-STATE OFC HR&ADM SVC (ID953)
08/25/2021
BLM-ID BOISE DISTRICT OFFICE*
3948 DEVELOPMENT AVE
BOISE
ID 83705-5389
208 373-3911Thomas Parsons
05/25/2021 1000 MD
FOB DESTINATION
OTHER
(See Schedule)X
ITEM NO.
(a)
SUPPLIES/SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
Period of Performance: 06/07/2021 to 08/25/2021
00010 BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL
Product/Service Code: Y1PZ Product/Service Description: CONSTRUCTION OF
OTHER NON-BUILDING FACILITIES
Delivery: 08/25/2021
12. DISCOUNT FOR PROMPT PAYMENT
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS
NUMBER PERCENTAGE
NOTE: Additional provisions and representations
13. NAME AND ADDRESS OF QUOTER
b. STREET ADDRESS
c. COUNTY
d. CITY e. STATE f. ZIP CODE
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
16. SIGNER
a. NAME (Type or print)
c. TITLE (Type or print)
a. NAME OF QUOTER
AREA CODE
NUMBER
15. DATE OF QUOTATION
b. TELEPHONE are are not attached
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition not usable
STANDARD FORM 18 (REV. 6-95)
Prescribed by GSA - FAR (48 CFR) 53.215-1(a)
SOLICITATION NO: 14L2621Q0026
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 2
Type of Contract: Construction, Firm-Fixed Price (FFP) County: Owyhee, Idaho Type of Construction: Highway
Magnitude: Between $25,000 and $100,000 NAICS: 238990 Size Standard: $16.5 Million Set-Aside: Total Small Business
Bureau of Land Management Contracting Officer’s Representative (COR) Contracting Officer
Name: Caleb Ashby Patricia A. Fort
Email: cashby@blm.gov pfort@blm.gov
Site Visit: See Section L.7
Proposal Due Date: 25 May 2021, 10:00 Mountain Daylight Time
Award Selection Process: Lowest Price mailto:pfort@blm.gov
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 3
General
(a) The Bureau of Land Management (BLM) is seeking quotations for construction services as attached in the accompanying statement of work. The BLM intends to conduct this acquisition by use of simplified acquisition procedures in accordance with FAR Part 13. A single contract award will be made to the Offeror that submits a quotation that has been determined to be the lowest price reasonable offeror.
(b) The Government will not award any contract if the resulting contract would not represent a "best value" to the Government.
(c) To assure timely and equitable evaluation of quotations, respondents are cautioned to strictly comply with all instructions within this solicitation to ensure submission of a complete quotation. Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements. Failure to adhere to quotation requirements, at the time of submission, may result in the quotation being unacceptable to the Government and eliminated from consideration for award. It is the responsibility of offerors to ensure their quote is received by the recipient and by the due date and time.
(d) Offerors are cautioned to submit adequate information to enable the Government to fully ascertain each offeror’s capability to perform the requirements in accordance with the requirements of the request for quotation (RFQ).
(e) If a respondent believes that requirements in these instructions contain an error, omission, or are otherwise flawed, the respondent shall immediately notify the Contracting Officer in writing (email is the preferred method) with supporting rationale by the question deadline specified on the cover page of this document.
(f) This RFQ does not commit the Government to any costs incurred in the preparation and submission of a quote or for any other costs incurred by any firm submitting a quote in response to this solicitation. Note specifically that the Offeror will not be participating in a sealed bid procurement process under this acquisition method. Issuance of this RFQ does not constitute an award commitment on the part of the Government.
(g) Quotation must be valid for a minimum of 60 days.
(h) Respondents must complete the System for Award Management (SAM) at https://www.sam.gov/portal/public/SAM/ (previously ORCA and CCR). The Government will obtain respondent representations and certifications through this system.
(i) Award is subject to and based on the availability of funds. This project is currently funded based upon an independent cost estimate.
(j) Including all other factors, to qualify for award, a respondent must be determined responsible in accordance with Federal Acquisition Regulation Part 9.
(k) Respondents shall not contact any government personnel related to this requirement other than the Contracting Officer.
(l) All questions should be emailed directly to the Contracting Officer. Only written RFI’s will be considered and responded to by the Government. BLM responses to RFIs will be posted as an amendment to the solicitation.
(m) The successful Offeror shall submit appropriate Performance and Payment Bonds in accordance with clause 52.228-1 or Alternative Payment Protection in accordance with clause 52.228-13 within 10 days of contract award.
SUBMIT ONLY REQUESTED ITEMS NOT THE ENTIRE SOLICITATION
https://www.sam.gov/portal/public/SAM/
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 4
TABLE OF CONTENTS
Part I - The Schedule
Section A - Solicitation/Contract Form See Standard Form 18
Section B - Bid Schedule 5
Section C - Specifications/Drawings 7
Section D - Packaging and Marking 20
Section E - Inspection and Acceptance 21
Section F - Deliveries or Performance 21
Section G - Contract Administration Data 23
Section H - Special Contract Requirements 25
Part II - Contract Clauses
Section I - Contract Clauses 28
Part III - List of Documents, Exhibits, and Other Attachments
Section J - List of Attachments 44
Part IV - Representations and Instructions
Section K - Representations, Certifications, and Other Statements of Offerors 56
Section L - Instructions, Conditions and Notices to Offerors 62
Section M - Evaluation Factors for Award 66
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 5
PART I - THE SCHEUDLE
SECTION B: BID SCHEDULE
Offerors are to complete Blocks 13 - 16 of the SF-18.
Item No. Description Estimated Quantity Units Unit
Price Total
Amount New Permanent Fence – CCC Spring
02824-01 4-wire Fence Construction 16.0’ Spacing (Feet) with 4-foot wood stays 2,250 Feet $ $
02824-02 Barbed Wire Gate (4-Wire) 1 Each $ $ 02824-03 5 Post Corner (Pipe) 7 Each $ $ 02824-04 3 Post Stress (Pipe) 3 Each $ $ 02824-05 Tree Cutting (20 ft.) 1340 Feet $ $ 02824-06 Steel Rock Jacks 2 Each $ $
Item No. Description Estimated Quantity Units Unit
Price Total
Amount New Permanent Fence – Little Willow
02824-07 4-wire Fence Construction 16.0’ Spacing (Feet) with 4-foot wood stays 1,350 Feet $ $
02824-08 Barbed Wire Gate (4-Wire) 1 Each $ $ 02824-09 5 Post Corner (Pipe) 4 Each $ $ 02824-10 3 Post Stress (Pipe) 1 Each $ $
Item No. Description Estimated Quantity Units Unit
Price Total
Amount
Repair Existing Fence (5 Wire) – Two Springs
02824-11 Splice, Stretch, Clip, Staple Existing 5-Wire Fence 500 Feet $ $
02824-12 Remove/Replace Burnt Wood Stress Panel with Steel Pipe Two-Post Stress Panel 1 Each $ $
02824-13 Removed Burnt Wood Corner Panel and replace with Steel Pipe Three-Post Panel 4 Each $ $
02824-14 Remove/Replace 4-Wire Gate 1 Each $ $
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 6
Item No. Description Estimated Quantity Units Unit
Price Total Amount
Complete Fence Removal – West Duck
02824-15 3-wire Fence with 22.0’ Post Spacing Complete Removal 21,000 Feet $ $
02824-16 Barbed Wire Gate (4-Wire) Removal 5 Each $ $ 02824-17 Easy Fence End Panels Removal 5 Each $ $ 02824-18 East Fence Stress Panels Removal 1 Each $ $ 02824-19 Steel Rock Jacks Removal 15 Each $ $ 02824-20 Wildlife Fence Markers Removal 3,820 Each $ $
Item No. Description Estimated Quantity Units Unit
Price Total Amount
Temporary Fence Removal – Juni
02824-21 3-wire Fence with 22.0’ Post Spacing Complete Removal 34,691 Feet $ $
02824-22 Barbed Wire Gate (4-Wire) Removal 5 Each $ $ 02824-23 Easy Fence Corner Panel Removal 5 Each $ $ 02824-24 Easy Fence End Panel Removal 13 Each $ $ 02824-25 Easy Fence Stress Panel Removal 24 Each $ $
Item No. Description Estimated Quantity Units Unit
Price Total Amount
Temporary Fence Removal – Cat
02824-26 3-wire Fence Construction 22.0’ Spacing (Feet) 36,600 Feet $ $
02824-27 Barbed Wire Gate (4-Wire) Removal 10 Each $ $ 02824-28 Easy Fence End Panel Removal 21 Each $ $ 02824-29 Easy Fence Stress Panel Removal 11 Each $ $ 02824-30 Easy Fence Corner Panel Removal 9 Each $ $ 02824-31 Steel Rock Jacks Removal 1 Each $ $
Total - All or None $ ____________
ESTIMATED START DATE: 6/07/2021
ESTIMATED END DATE: 08/25/2021
CONTRACT TIME: 79 Calendar Days
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 7
SECTION C: SPECIFICATIONS/DRAWINGS
SECTION 01009 - GENERAL INFORMATION AND REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
Construct with Government supplied material, 4-wire fence (top and middle wires barbed and bottom wire smooth) with steel t-posts, steel pipe structures and steel rock jack structures as shown in the drawings. Repair damaged 4-wire fence with steel t-posts, and steel rock jack structures.
A. Description of Work: Furnish labor and equipment to construct/repair/remove the specified typical barbed wire fence (3-wire and 4-wire).
B. Location of Fence Construction and Repair Work Sites as Shown on Work Location Maps: The project sites are located approximately 40 miles south of Jordan Valley Oregon.
1. CCC Spring – Fence is located in rolling terrain with rocky areas. Main unpaved road provide access to the site, accessible by 4-WD vehicles. The majority of the project fence line is then accessible by 4-WD vehicle, Off Road Vehicles, or foot traffic. 20 foot maximum of tree clearing along the fence line may be performed. No scraping or blading of any kind is permitted.
2. Two Spring – Fence is located in rolling terrain with rocky areas. Main unpaved road provide access to the site, accessible by 4-WD vehicles. The majority of the project fence line is then accessible by 4-WD vehicle, Off Road Vehicles, or foot traffic.
3. Little Willow Spring - Fence is located in rolling terrain with rocky areas. Main unpaved road provide access to the site, accessible by 4-WD vehicles. The majority of the project fence line is then accessible by 4-WD vehicle, Off Road Vehicles, or foot traffic.
Average elevation varies between project units and ranges from approximately 3,700-5,500 feet.
Permanent Fence Construction and Repair: T11S R05W Sec 19 and 30.
C. Location of Fence Removal Work Sites as Shown on Work Location Maps:
1. West Duck Fence Removal – Project site is approximately 110 miles south of Mtn Home, ID. Take highway 51 south of Mtn. Home to state line and continue south on highway 225 into the Duck Valley Indian Reservation. Turn west onto Boney lane which is first road on west side of highway 225 past Our Grocery Store. Travel this road approximately 5.6 miles to a metal sign that points west and says Owhyee River. Turn west at sign and travel approximately 15 miles to two-track road located on south side of main road. Turn south onto two-track road and travel approximately 2 miles and road will intersect project area. There is a two-track that parallels fence repair in the southwest corner of the project.
West Duck Temporary Fence Removal: T16S R01E Sec 18 and T16S R01W Sec 13,23,24 and 26.
2. Juni Fence Removal – Fence is located in rolling terrain with rocky areas directly west of the Duck Valley Indian Reservation on the Idaho Nevada border. Access to the site is provided off of State Highway 51 then traveling 15 miles west on 45 Ranch Road/Boney Lane. The majority of the project fence line is then accessible by 4-WD vehicle, Off Road Vehicles, or foot traffic.
Juni Temporary Fence Removal: T15S 01W Section 26,35 and T16S R02W Section 2-4
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 8
3. Cat Fence Removal - Project site is approximately 80 miles from Mtn. Home, ID. Take Hwy 51 south of Mtn. Home towards Grasemere, ID. Turn east on to Rowland road between mile markers 33 and 32, approximately 60 miles. To access the northern project area travel on Rowland road approximately 17.8 miles then turn east on an unnamed road and travel an additional 2 miles. The project site will be on the north and south sides of the road. To assess the southern project site travel on Rowland road approximately 28.2 miles. The project site will be on the north side of the road.
Cat Temporary Fence Removal: T14S R06E Sec 25, 36. T15S R06E Sec 1, 12 and T16S R06E Sec 14,15,22 and 23.
C. Work Data Sheet: Designates the type and quantity of work required at each project location.
1.2 DEFINITIONS
A. Approvals: Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the Drawings and Specifications brought to the Contracting Officer's attention in writing. After approval of an item, submit a substitute for approval when the approved item cannot be purchased or delivered in time to avoid delay in completion of the project.
1.3 SUBMITTALS
A. Scope: Submittals include design computations, shop drawings, manufactures' literature, as built drawings, samples, and maintenance manuals.
B. Requirements: Refer to individual Specifications for submittals required. Submittals shall be delivered to the Contracting Officer. Allow at least 5 working days for review.
C. Identification of Submittals: Completely identify each submittal by showing at least the following information:
1. Name and address of submitter, plus name and telephone number of the individual to contact for further information.
2. Name of project as it appears in these Specifications.
3. Contract number, Drawing number, and Specification section number to which the submittal applies.
4. Whether this is an original submittal or resubmittal.
5. Each item shall clearly note the manufacturer's name and address, trade name, product, lot, style, color, catalog designation or model number, and locations of use.
1.4 QUALITY ASSURANCE
A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work as listed in the individual sections of these Specifications and as shown on the Drawings.
B. Conflict: Where a conflict occurs between Reference Documents and Project Specifications, the Project Specifications shall govern.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Delivery: Protect products incorporated into the work from damage while in transit to the site.
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 9
B. Storage: Provide temporary storage facilities for products which will protect them from damage until installation on the project and final acceptance.
C. Handling: Load and unload products protecting them from damage.
1.6 PROJECT / SITE CONDITIONS
A. Access to the work site: Vehicle traffic is permitted along proposed fence line, existing fence lines and existing trails in designated areas. To mitigate the disturbance of sensitive wildlife species on the West Duck project area associated activities (e.g., transporting materials) will only occur from 9:00 am to 6:00 pm (March 1 - May 15) in avoidance areas indicated on project maps.
B. The Cat, West Duck and Juni fence removal project areas are located in relatively flat terrain, surface rock with rock outcroppings and subsurface rock is present. Main unpaved roads provide access to the general project area traveling accessible by 4-WD vehicles. The majority of the project fence line is then accessible by off highway vehicles, or foot traffic. The Pole Creek fence construction/repair project area is in rolling terrain accessible by ATV/UTV or 4-wheel drive vehicle.
C. No cross-country travel with motorized vehicles shall take place except on designated roads, trails and fence corridors.
E. Camping at or near the job site is permitted as long as it does not exceed a maximum of 14 days in any one location. Camping is prohibited within 100 yards of any isolated water source springs, seeps, water troughs, windmills, small reservoirs, etc.) Toilet facility requirements shall follow all Federal and State regulations. When a camp site is longer needed, all garbage and fence building supplies must be removed and properly disposed of.
These areas shall be approved in advance by the Contracting Officer.
F. Clean-up: All trash and excess materials must be removed from the project site on completion of construction and disposed on in a manner, and at a location, approved by the Contracting Officer.
G. Fuels and Fire: The fence is located in areas of light fuels (annual grasses, rabbit brush and low sagebrush) with some areas crossing into areas that have recently burned. The contractor shall obey and enforce fire prevention measures such as spark arresters, avoidance of high fuel areas were possible and all other instructions from the Contracting Officer.
H. Cultural Considerations: Because fragile and irreplaceable culture resources may be present in the area, project activities and any other action which causes disturbance of the earth's surface shall be limited to those areas approved by the BLM. Deviations from routes flagged or shown on the drawings are not allowable without prior approval of the Contracting Officer. The Contractor shall insure that he, his employees, or his representatives do not collect archaeological artifacts. Should the condition of the cultural resources in the area be altered during construction due to unauthorized activity by the Contractor or his employees, the Contractor shall be responsible for all costs of mitigating the cultural resources involved. If deterioration of the archaeological sites is found to be occurring during the construction phase, work on the project shall be terminated until a data recovery plan is prepared and completed in accordance with the National Historic Preservation Act
1.7 SEQUENCING AND SCHEDULING
A. Work Schedule: The schedule shall be submitted at the pre-work conference. When requested, submit an updated schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the estimate
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 10
PART 2: MATERIALS/SPECIFICATIONS/DESCRIPTIONS
A. Contractor Returned Materials
1. Returned materials: Wire, wire stays, hose clamps, 7 ft. T-posts and wood materials are deemed salvage and will be properly recycled or disposed of by contractor. All other materials not able to be used on CCC Spring, Two Spring or Little Willow Spring construction/repair projects will be returned to Government and bundled as outline under work data sheet 5.3.
2. Location: Government property will be returned to the Bureau of Land Management Ware yard at 1962 Commerce Avenue, Boise, Idaho 83705.
3. Time: Property return will be available Monday through Thursday, from 8:00 am to 3:30 pm except on holidays. A pre-scheduled appointment with 24-hour advanced notice is required to assure that a warehouseman is available. A contact list for scheduling appointments will be provided to contractor at the pre-work meeting.
B. Fence Removal Specifications
Description Quantity Complete Fence Removal – West Duck
3-wire Fence with 22.0’ Post Spacing Complete Removal 21,000 Ft.
(3.9 Miles)
Barbed Wire Gate (4-Wire) Removal 5 Easy Fence End Panels Removal 5 East Fence Stress Panels Removal 1 Steel Rock Jacks Removal 15 Wildlife Fence Markers Removal 3,820
Description Quantity Complete Fence Removal – Juni
3-wire Fence with 22.0’ Post Spacing Complete Removal 34,691 Ft.
(6.5 Miles)
Barbed Wire Gate (4-Wire) Removal 5 Easy Fence Corner Panel Removal 5 Easy Fence End Panel Removal 13 Easy Fence Stress Panel Removal 24
Description Quantity Complete Fence Removal – Cat
3-wire Fence with 22.0’ Post Spacing Complete Removal 36,600 Ft.
(6.9 Miles)
Barbed Wire Gate (4-Wire) Removal 10 Easy Fence End Panel Removal 21 Easy Fence Stress Panel Removal 11 Easy Fence Corner Panel Removal 9 Steel Rock Jacks Removal 1
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 11
PART 3 - EXECUTION
3.1 PROJECT MEETINGS
A. Pre-Work Conference:
1. Will be held prior to the start of work on each Order. The Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
2. The Contractor, subcontractors, and persons responsible for coordination of the work shall be present at the meeting.
3. Be prepared to summarize and explain procedures planned for the project.
B. Progress Meetings:
1. To be held at the project site, or as determined by the Contracting Officer.
2. May be called by either the Contracting Officer or the Contractor. The request shall state who should attend and include an agenda.
C. Final Inspection:
1. To be held at the project site, or as determined by the Contracting Officer.
2. Notify the Contracting Officer in writing at least 3 working days before the completion date so the
Government can schedule final inspection.
3. The Contractor or the Contractor's authorized representative shall be present during this inspection.
3.2 PREPARATION
A. Work Layout: The Government will set flags or fence posts within site distance to give the Contractor lines and angles necessary for the work executed under the Contract. Where new fences are to replace existing fences, corners, gates, and end panels shall be located in the same place as the existing fence. Stress panels shall be located as specified for each type of fence.
3.3 SALVAGEABLE ITEMS
A. Requirements: Except as noted in section 5.3 all salvageable items from West Duck, Juni or Cat fire fence removal shall be used for existing fence repair and fence construction or provided back to BLM.
3.4 DISPOSAL OF DEBRIS
A. Requirements: Items or debris not designated as salvage for the Government shall become the property of the Contractor. Disposal of materials in a legal manner and payment of fees required is the Contractor's responsibility. Burning of removed materials is not permitted on the work site.
PART 4 - MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: The work described in this Section will not be measured for payment.
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 12
4.2 BASIS OF PAYMENT
A. Payment: No direct payment for the work described under this Section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.
END OF SECTION 01009
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 13
SECTION 01019 - GOVERNMENT-FURNISHED PROPERTY
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes fencing materials to be furnished by the Government and their locations.
1.2 DELIVERY, STORAGE, AND HANDLING
A. Location: The Government-furnished property will be provided by the Bureau of Land Management at the BLM Ware yard at 3948 S. Development Avenue, Boise, Idaho 83705.
B. Time: Property will be available Monday through Friday, from 8:00 am to 3:30 pm except on holidays. An appointment is required to assure that a warehouseman is available. Appointments are made by calling the phone number listed on each Order a minimum of 24 hours prior to intended pickup time.
C. Return of Unused Property: Return unused materials to the same place as they were picked up unless the Contracting Officer states otherwise.
D. Loading, Offloading and Transporting Property: The Contractor is responsible for providing the necessary material-handling equipment to load and offload materials at the work site. The Contractor shall transport materials to the work site. Unless otherwise noted, a Government forklift and operator will be available at the Ware yard.
PART 2 - PRODUCTS
2.1 MATERIALS
A. All materials for the project will be furnished by the Government:
Estimated Fence Materials QUANTITY UNIT 1 Steel Posts 5.5' 220 EACH 2 Barbed Wire 12.5 ga 9 ROLL 3 Barbless Wire 12.5 ga 5 ROLL 4 Wire Fasteners (Clips) 100/pkg 10 BAG 5 Wood Stays (For gates and fence) 235 EACH 6 Steel Pipe Posts 2 3/8" x 7' 77 EACH 7 Steel Pipe Brace Posts 1 5/8" x 8' 56 EACH 8 Galvanized Post Caps 75 EACH 9 Rebar #4 2' 61 EACH 10 Steel Rock Jacks 2 EACH
Galvanized Brace Band Clamp 2 3/8" w/ nuts and bolts 172 EACH
12 Brace Rail Connector 112 EACH 13 Staples 1.5" (70/lb.) 20 LB
PART 3 - EXECUTION
(There are no applicable requirements.)
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 14
PART 4 - MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: The work described in this Section will not be measured for payment.
4.2 BASIS OF PAYMENT
A. Payment: No direct payment for the work described under this Section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.
END OF SECTION 01019
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 15
SECTION 02824 - WIRE FENCES AND GATES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes installing with Government-Furnished property, barbed wire and woven wire fences, and repair of existing fences.
B. Furnish all labor, tools, equipment, supervision, and any other resources necessary to complete fence projects.
C. Related Sections:
General Information and Requirements Section 01009.
PART 2 - PRODUCTS
2.1 GOVERNMENT-FURNISHED MATERIALS (as applicable to project requirements)
A. Barbed Wire: A strand of two 12-1/2-gauge galvanized wires twisted together with 2-point barbs of 14-gauge wire spaced 4 inches apart. Wire and barbs shall be zinc-coated steel, with a zinc coating of at least 0.3 oz/ft2 of coated surface area. The minimum breaking strength of each wire shall be 950 lb. force. The barbed wire shall conform to ASTM A 121.
B. Barbless Wire: A strand of two 12-1/2-gauge galvanized wires twisted together. Wire shall be zinc-coated steel wire of at least 0.3 oz/ft 2 of coated surface area. The minimum breaking strength of each wire shall be 950 lb. force. The barbless wire shall conform to ASTM A 121.
C. Brace Wires: Four wires of 9-gauge smooth, galvanized wire or 2 wires of galvanized, 12-1/2-gauge barbless wire. The minimum weight of zinc coating for 9-gauge wire shall be at least 0.4 oz of zinc/ft2 of coated surface area; for 12-1/2-gauge wire at least 0.3 oz of zinc/ft2 of coated surface area.
D. Clip-Type Wire Fastener: Galvanized wire, 8-gauge.
E. Mechanical Gate Closures: Assembly must include the following salient features:
1. A rigid steel strap or 9-gauge smooth wire loop 6 inches from the ground securely connected to the gate post and shaped so the gate stay will be securely held in place.
2. An adjustable cable or chain, or rigid steel strap fastened to a cam lever device located 6 inches from the top of the gate post. The closer shall be capable of securely holding the gate stay in place.
3. Gate latch by Toland & Sons, P.O. Box 1970, Winnemucca, NV 89446, or approved equal.
F. Miscellaneous Wire: Wire for ties, gate loops and fastening wood stays shall be 9 or 12-1/2-gauge galvanized wire.
G. Staples: Bright-finish or galvanized 9-gauge with slash-cut points 1-3/4 inches long.
H. Wood Gate and Fence Stays: Sound and straight pieces, 1-1/2 to 3-1/2-inch diameter of the species pine or fir
(with bark removed), honey locust, western red cedar (full stem with bark removed), juniper, osage orange, and white oak. Treatment with preservative is not required. Stays shall be of uniform length sufficient to touch the ground. Total length shall be 4'-0".
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 16
I. Steel Pipe: ASTM F 1083 SS40. Post pipe shall be 2-1/2 inch (2.375-inch O.D., 3.12 lb./ft); brace pipe, 1-5/8 inch, (1.66-inch O.D., 1.84 lb./ft). Brace clamps and fittings shall be galvanized.
PART 3: EXECUTION
3.1 INSTALLATION
A. Drive steel fence posts into the ground to the depth shown on the Drawings or until the anchor plate is slightly below the ground surface. Posts shall be driven plumb. When rock formations prevent driving remove anchor plate and drill holes a minimum of 18 inches deep and slightly smaller than the diameter of the post. Drive posts solidly into the holes.
B. Wire: Stretch tightly and staple to wood posts or securely attach to steel posts with standard wire clips. Wire is properly stretched when it is springy to the touch. Drive staples into wood until the staple comes in contact with the wire against the post, but not so tight as to crimp the wire. Do not drive staples parallel to the grain of the wood. Terminate wire at each end post, gate post, corner post, or stress panel by wrapping wire around the post two times and tie off by uniformly wrapping the incoming wire a minimum of four times.
C. Brace Wires: All panels shall be wrapped with two complete wraps of barbless wire and twisted tight with a tensioning device (wood stay stick, rebar, or digger link). Leave one end of the tensioning device long enough to fasten behind the horizontal brace to prevent wire from unwinding.
D. Corner Panel, Stress Panel, and End Panel Assemblies: Construct as shown on the Drawings or as staked in the field. Construct stress panels on crests of hills, and a maximum of 1320 feet center-to-center for barbed wire. In addition, stress panels are required at points between which wire is to be stretched. Construct end panels at the end of fence runs and on each side of a gate unless shown otherwise on the Maps or Drawings.
E. Rock Jacks: With the approval of the Contracting Officer, steel rock jacks may be used in lieu of steel end panels, corner panels, and stress panels where rock formations prevent dug holes. Rock jacks will be paid for at the same unit price as the substituted item. Construct as shown on the Drawings. Figure fours shall not be used in place of line posts.
F. Gates: Shall be installed according to the Work Data Sheet and the Drawings. Fulcrum-type gate openers shall be installed on all gates using 4-foot-long wood stays, or as approved by the Contracting Officer. Wire Gates:
Shall be constructed of smooth wire, wood stays, and wire stays. Gate should be constructed to a width of 14’ unless otherwise noted by flagged area at project site.
G. Wood Stay Installation: Shall be installed at the spacing and quantities as shown on the Work Data Sheet.
Stays shall be secured with 1.75” staples. Drive staples into wood until the staple comes in contact with the wire against the stay, but not so tight as to crimp the wire.
H. Items or debris (including layout flags), not designated as salvage for return to the government, shall become the property of the Contractor. The Contractor is responsible for the disposal of materials in a legal manner and the payments of all disposal fees. Burning of removed materials is not permitted on the work site.
I. Steel Pipe Assemblies: Steel pipe panels shall be constructed in accordance with the Drawings and will include galvanized pipe caps on the tops of the structures. If loose soil conditions cause corner panels to lift when the fence wire is stretched, a steel post shall be driven parallel and adjacent to the corner pipe a minimum of 2'-6" deep and wired to the panels. When rock formations prevent driving pipe, drill holes 18 inches deep and the same diameter as the pipe. Drive pipe solidly into the holes.
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 17
PART 4 - MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: The work described in this Section will be measured and paid for by the linear foot for each type of fence constructed or repaired as measured along the ground surface next to the completed fence or as measured with GPS as indicated in the Order, including distance across gate openings; end, stress, and corner panels; and drainage crossings. The quantities of end, stress, and corner panels, gates, rock cribs, and stiles to be paid for will be the actual number of these items. Note: Gates do not include adjacent end or corner panels.
These are separate items.
4.2 BASIS OF PAYMENT
A. Payment: Prices and payment will be full compensation for the work described in this Section. Payment will be made under:
Pay Item Estimated Pay Unit
New Permanent Fence – CCC Spring 02824-01 4-wire Fence Construction 16.0’ Spacing (Feet) 2,250 Feet 02824-02 Barbed Wire Gate (4-Wire) 1 Each 02824-03 5 Post Corner (Pipe) 7 Each 02824-04 3 Post Stress (Pipe) 3 Each 02824-05 Tree Cutting (20 ft.) 1340 Feet 02824-06 Steel Rock Jacks 2 Each
New Permanent Fence – Little Willow 02824-07 4-wire Fence Construction 16.0’ Spacing (Feet) 1,350 Feet 02824-08 Barbed Wire Gate (4-Wire) 1 Each 02824-09 5 Post Corner (Pipe) 4 Each 02824-10 3 Post Stress (Pipe) 1 Each
Repair Existing Fence (5 Wire) – Two Springs
02824-11 Splice, Stretch, Clip, Staple Existing 5-Wire Fence 500 Feet
02824-12 Remove/Replace Burnt Wood Stress Panel with Steel Pipe Two-Post Stress Panel 1 Each
02824-13 Removed Burnt Wood Corner Panel and replace with Steel Pipe Three-Post Panel 4 Each
02824-14 Remove/Replace 4-Wire Gate 1 Each Complete Fence Removal - West Duck
02824-15 3-wire Fence with 22.0’ Post Spacing Complete 21,000 Feet Complete Fence Removal – Juni
02824-16 3-wire Fence with 22.0’ Post Spacing Complete 34,691 Feet Complete Fence Removal – Cat
02824-17 3-wire Fence with 22.0’ Post Spacing Complete 36,600 Feet
END OF SECTION 02824
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 18
PART 5 – WORK DATA SHEETS
SECTION 02824 WIRE FENCES AND GATES
5.1 NEW PERMANENT FENCE (CCC Spring and Little Willow)
Fence Type: 3,600 feet of 4-wire fence, 3-strands barb, 1-strand smooth wire with 16.5' max steel post spacing. Posts spacing will be such that consistent wire spacing is maintained in variable terrain.
Wire locations/dimensions in inches (typical spacing): Type of Wire:
12" (Top) 12 ½ gauge barbed 6" (Middle) 12 ½ gauge barbed 6" (Middle) 12 ½ gauge barbed 18" (Bottom) 12 ½ gauge smooth
Line Post Spacing (L): 16.5’feet maximum. Posts spacing will be such that consistent wire spacing is maintained in variable terrain
Wood Stay Spacing: 1 wood stay evenly spaced between each line post secured with 4 1- 3/4-inch staples
Length of steel line post: 5 foot 6 inches
Depth of steel line post in ground: 1 foot 6 inches
Depth of Steel Pipe in ground: 3 foot 3 inches
Tree Cutting 1,340 feet x 20 feet (10 feet each side of fence line) of Western Juniper tree removal is permitted in area designated on map to allow the construction of fence. The use of mechanized large equipment to blade or scrape the any fence line is strictly prohibited. Removed trees shall be pulled 10 feet away from the fence line.
SPECIAL CONSIDERATIONS
New permanent fence project segments have been flagged on steel posts. Red flags indicate structures (corners, gates). Stress Panels locations are not flagged, general locations are depicted on the map. White flags indicate fence line between structures.
Only rocks within the immediate proximity of the fence line will be used in the construction of rock jack structures. Rocks near land survey markers of any kind shall not be disturbed for the construction or repair of any fence segments.
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 19
SECTION 02824 WIRE FENCES AND GATES
5.2 PERMANENT FENCE REPAIR (Two Spring)
Fence Type: 500 feet of Splice, Stretch, Clip, Staple Existing 5-Wire Fence with 16.5' max steel post spacing. Posts spacing will be such that consistent wire spacing is maintained in variable terrain.
Wire locations/dimensions in inches (typical spacing): Type of Wire:
12" (Top) 12 ½ gauge barbed 6" (Middle) 12 ½ gauge barbed 6" (Middle) 12 ½ gauge barbed 6" (Middle) 12 ½ gauge barbed 18" (Bottom) 12 ½ gauge smooth
Line Post Spacing (L): 16.5’feet maximum. Posts spacing will be such that consistent wire spacing is maintained in variable terrain
Stay Spacing: 1 stay evenly spaced between each line post.
Length of steel line post: 5 foot 6 inches
Depth of steel line post in ground: 1 foot 6 inches
Depth of Steel Pipe in ground: 3 foot 3 inches
SPECIAL CONSIDERATIONS
Only rocks within the immediate proximity of the fence line will be used in the construction of rock jack structures. Rocks near land survey markers of any kind shall not be disturbed for the construction or repair of any fence segments.
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 20
5.3 EXISTING TEMPORARTY FENCE REMOVAL
3-Wire Fence
Removal 22’0” Spacing
Barbed Wire Gate (4-Wire)
Easy Fence End
Panels
Easy Fence Corner Panels
Easy Fence Stress Panels
Steel Rock Jacks
Wildlife Fence
Markers Removal
92,291 20 39 14 36 16 3,820
Returned Bundling
Specifications
Contractor will recycle or dispose of all wire, steel stays, 7' T-posts and hose clamps.
Unbent 5'6" T-posts shall be bundled in 200 count units and secured with a minimum of 3 wraps of smooth wire.
Wire and wood disposed of.
H’s and A’s bundled separately in 10 per bundle.
H’s and A’s bundled separately in 10 per bundle.
H’s and A’s bundled separately in 10 per bundle.
Each unit disassembled and bound securely with a minimum of
3 wraps of smooth wire.
Bolts reinserted and loosely tightened.
Contractor will dispose of damaged markers. All other markers will be bundled in bags or boxes approximately 500 per unit.
Fence Type: 92,291 feet of 3-wire barbed wire fence, 1-strand smooth wire, 2 strand barbed wire with 22.0' max steel post spacing.
PART 6 - SPECIAL CONSIDERATIONS
6.1 SPECIAL CONSIDERATIONS
A. Section 5.3 EXISTING TEMPORARTY FENCE REMOVAL of the project will be completed first to reduce additional material transportation costs. Barbed wire, smooth wire and hose clamps will not be reused from removal project.
B. Only rocks within the immediate proximity of the fence line will be used in the construction or repair of rock jack structures. Rocks near land survey markers of any kind shall not be disturbed for the construction or repair of any fence segments.
C. New fence project segment have been flagged on steel posts. Red flags indicate structures (corners, gates).
Stress Panels locations are not flagged, general locations are depicted on the map. White flags indicate fence line between structures. General fence repair segments and repair items and structures have been identified on project maps. Individual posts, wire, and structures needing repair or replacement will not be flagged.
Contractor and Project Inspector will work together in assuring the items can be identified on the ground.
D. Items removed from fence: Wood removed from fence can either be packed out or cut into small sections and scattered away from existing fence line. Steel T-posts, wire and wildlife markers which are not reusable must be removed from worksite and disposed of in a proper manner by contractor.
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 21
SECTION D: PACKAGING AND MARKING
Packaging and marking of deliverables shall be IAW the Contractor’s standard commercial practices.
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 22
SECTION E: INSPECTION AND ACCEPTANCE
E.1 52.252-2 Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/browse/index/far#
Clause Title Date 52.246-12 Inspection of Construction August 1996 52.246-13 Inspection -- Dismantling, Demolition, or Removal of Improvements August 1996
E.2 Final Inspection and Acceptance
Final completion of the punch list items, submission of all required submittals, and final cleanup of the project site shall be completed before the contract’s required completion date. The Contracting Officer or his/her designated representative will perform final inspection. Acceptance of the work will occur only upon written notice of acceptance by the ordering Contracting Officer or any other Warranted Contracting Officer employed by the Bureau of Land Management (BLM) and performing authorized duties in conjunction with this contract.
https://www.acquisition.gov/browse/index/far#
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 23
SECTION F: DELIVERIES OR PERFORMANCE
F.1 52.252-2 Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/browse/index/far#
Clause Title Date 52.211-13 Time Extensions September 2000 52.211-18 Variation in Estimated Quantity April 1984 52.236-11 Use and Possession Prior to Completion April 1984
F.2 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)
The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 79 calendar days after receipt of notification. *The time stated for completion shall include final cleanup of the premises.
*The Government recognizes that seasonal climatic conditions may occur that restrict or prohibit normal construction activities. The anticipated length of the seasonal delay for this project is 0 days. This number of days has been included in calculating the stated period of performance. Therefore, the contract period of performance will not be extended due to normal seasonal weather delays.
F.3 52.211-12 Liquidated Damages--Construction (Apr 1984)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $533.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
F.4 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 24
Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
F.5 Simultaneous Performance
If a Contractor receives award of more than one contract, simultaneous performance will be required. All work must be completed within the timeframe allowed for each contract.
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 25
SECTION G: CONTRACT ADMINISTRATION DATA
G.1 Authorities and Delegations (Sep 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum.
The Contractor need not proceed with direction that it considers to have been issued without proper authority.
The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G.2 Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Apr 2013)
Payment requests must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform System (IPP).
PROJECT DESCRIPTION: BDO FY21 SPRING FENCE CONSTRUCTION/REMOVAL Page 26
"Payment request" means any request for contract financing payment or invoice payment by the Contractor.
To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions- Commercial Items included in commercial item contracts. The IPP website address is:
https://www.ipp.gov.
Under this contract, the…