This is a Request for Quotation (RFQ) schedule document issued by the State of Colorado for Architectural and Engineering (AE) services related to the modernization of the SOB RR (State Office Building Rail Road) project, identified as RFQ 2027-017M26. The RFQ solicits qualified architectural and engineering firms to provide design and planning services for the modernization initiative. The document establishes the scheduling framework and procedural requirements for interested vendors to submit qualifications and proposals. Key procedural dates, submission requirements, and evaluation criteria are outlined to guide the competitive selection process for awarding the AE contract.
The RFQ specifies the submission deadlines, qualification requirements, and evaluation methodology that prospective firms must follow to be considered for the project. Pricing and fee structures are to be submitted in accordance with the state's standard requirements for professional services contracts. The selection process prioritizes technical qualifications, relevant experience with similar modernization projects, and the ability to meet the project timeline and deliverables. Additional details regarding funding sources, project scope specifics, and contract terms would be contained within the complete RFQ documents and supporting exhibits that accompany this scheduling addendum.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2027-017M26 SOB RR RFQ_AE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ-AE R3
Rev 09/2025
a. Qualifications made by a respondent in executing this form may render a submittal non-responsive as determined by the State.
IV. PRE-SUBMITTAL CONFERENCE AND SITE TOUR
To ensure sufficient information is available to firms preparing submittals, a pre-submittal conference and site tour has been scheduled. The intent of this conference is to tour the site and to have Department of Personnel & Administration staff able to discuss the project.
Firms preparing submittals must attend and sign-in to have their submittals accepted.
A Pre-Submission Meeting will be held at:
Building Address: 1525 Sherman St, Denver CO 80203
Room: 104
Date/Time Monday 7/13, 9:30am
V. SCHEDULE
The following is a tentative schedule of events for the Submittal process and an outline of the schedule for the balance of the project. All dates are subject to change and changes in the schedule will be issued via addendum.
Request for Qualifications Issued July 2nd, 2026
Pre-Submittal Conference and Tour July 13th, 2026 – 9:30am MT
Request for Clarifications Due July 16th, 2026 – 5:00pm MT
Final Addendum Issued (anticipated) July 21st, 2026
Submittals Due (Prequalification: Step I) July 27th, 2026 – 5:00pm MT
Interview Short List Announced July 31th, 2026
Oral Interviews August 2026
Selection Announced August 2026
Negotiation of Contract August 2026 Anticipated Design Start September 2026
Anticipated Construction Start/Finish February 2027 – July 2027
The above schedule is tentative. Responding firms shall be notified of revisions in a timely manner by email or posted on ColoradoVSS. Respondents may elect to verify times and dates by email, but no earlier than 36 hours before the scheduled date and time.
VI. QUESTIONS, CLARIFICATIONS AND ADDENDA
Owner initiated changes to this RFQ will be issued under numerically sequenced addenda.
Owner initiated changes to this RFQ will be posted in the form of addenda on ColoradoVSS.
Questions and requests for clarifications regarding this project shall be submitted before the deadline listed in the above Schedule.
Communication regarding the project during the procurement, outside of this submission process or scheduled procurement milestones is not permitted.