SOLICITATION, OFFER AND AWARD 1. This Contract Is A Rated Order Under

DPAS (15 CFR 700)

Rating Page of Pages

2. Contract Number 3. Solicitation Number 4. Type of Solicitation 5. Date Issued 6. Requisition/Purchase Number Sealed Bid (IFB)

Negotiated (RFP)

7. Issued By Code 8. Address Offer To (If Other Than Item 7)

NOTE: In sealed bid solicitations ‘offer’ and ‘offeror’ mean ‘bid’ and ‘bidder’.

SOLICITATION

9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in item 8, or if handcarried, in the depository located in until (hour) local time (Date).

Caution - Late Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. For Information A. Name B. Telephone (No Collect Calls) C. E-mail Address

Call: Area Code Number Ext.

11. Table Of Contents

(X) Sec. Description Page(s) (X) Sec. Description Page(s)

Part I - The Schedule Part II - Contract Clauses A Solicitation/Contract Form I Contract Clauses

B Supplies or Services and Prices/Costs Part III - List Of Documents, Exhibits, And Other Attach.

C Description/Specs./Work Statement J List of Attachments D Packaging and Marking Part IV - Representations And Instructions E Inspection and Acceptance K Representations, Certifications, and F Deliveries or Performance Other Statements of Offerors G Contract Administration Data L Instrs., Conds., and Notices to Offerors H Special Contract Requirements M Evaluation Factors for Award

OFFER (Must be fully completed by offeror) NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

12. In compliance with the above, the undersigned agrees, if this offer is accepted within _____ calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. Discount For Prompt Payment 10 Calendar Days (%) 20 Calendar Days (%) 30 Calendar Days (%) Calendar Days (%) (See Section I, Clause No. 52.232-8)

14. Acknowledgment of Amendments (The offeror acknowledges Amendment No. Date Amendment No. Date receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):

15A. Name and Code Facility 16. Name and Title of Person Authorized to Sign Offer Address of (Type or Print) Offeror

15B. Telephone Number 15C. Check if Remittance Address is 17. Signature 18. Offer Date Area Code Number Ext. Different From Above – Enter such

Address In Schedule

AWARD (To be completed by Government)

19. Accepted As To Items Numbered 20. Amount 21. Accounting And Appropriation

22. Authority For Using Other Than Full And Open Competition: 23. Submit Invoices To Address Shown In Item

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

24. Administered By (If other than Item 7) Code 25. Payment Will Be Made By Code

26. Name of Contracting Officer (Type or Print) 27. United States Of America 28. Award Date

(Signature of Contracting Officer)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 33 (Rev. 9-97) Previous edition is unusable Prescribed By GSA-FAR (48 CFR) 53.214(c)

W56HZV-20-R-0162

X

2020MAY21

2020JUN2212:00pm

DOA4

2020MAY21 SEE SCHEDULE

W56HZV

ACC-DTA

6501 E. 11 MILE RD.

DETROIT ARSENAL, MI 48397-5000

LISA M. KOSKI

(586)282-5013

CCTA-ASG-C

LISA.M.KOSKI.CIV@MAIL.MIL

1 61

X 1

X 5 X 11

X 15 X 17 X 19

X 27

X 29

X 44

X 45

X 56

X 60

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: LISA M. KOSKI

Buyer Office Symbol/Telephone Number: CCTA-ASG-C/(586)282-5013

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

1. This solicitation will result in a Firm Fixed Price (FFP), Indefinite Delivery Indefinite Quantity (IDIQ) contract.

NSN:3040-01-166-2189

Noun Basic: Housing, Mechanical D

Minimum Quantity: 90

Maximum Quantity: 439

2. This solicitation is a 100% Small Business Set-Aside.

3. The Technical Data Package (TDP) is competitive with purchased part(s) estimated at less that 10% and limited to DOD and US DOD

Contractors only.QPL Specification(s) apply to this item.

*** END OF NARRATIVE A0002 ***

A.1 ARMY CONTRACTING COMMAND DETROIT ARSENAL (DTA) OMBUDSPERSON

Information regarding the Ombudsperson for this contract is located at the following website:

http://acc.army.mil/contractingcenters/acc-dta/CompMgmtOffice.html

A.2 Electronic Contracting

(a) All Army Contracting Command Warren solicitations will be publicized on the System for Award Management website

(https://www.sam.gov ). Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or links embedded in the solicitation.

(b) As of 10 August 2015, vendors are required to submit a quote or proposal on beta.SAM.gov, however until beta.SAM.gov can accept proposals offerors should follow the instructions in paragraph (c) below.

(c) With the recent transition from www.FBO.gov to www.beta.sam.gov the site have been experiencing a number of issues.

Interested Offerors shall submit a proposal via email to the Contract Specialist "mailto:LISA.M.KOSKI.CIV@MAIL.MIL " with the subject header: Proposal Submission - W56HZV-20-R-0162(company name). Once a proposal is received, the Contract Specialist/Contracting Officer will reply with the respective Offeror stating receipt of proposal submission.

(1) Maximum size of each e-mail shall be 10 megabytes. You may use multiple e-mail messages for each bid/submission, however, you must annotate the subject lines as described above for each message, and number them in this manner: Message 1 of 3, 2 of 3, 3 of 3.

Bids can be submitted can be submitted using any of the following electronic formats:

(2) Microsoft Office Products ; Word, Excel, or PowerPoint. Spreadsheets must be sent in a format that includes all formulate macro and format information. Print image is not acceptable.

(3) Files in Adobe PDF (Portable Document Format). Scanners should be set to 300 dots per inch.

(4) Files in HTML (Hypertext Markup Language). HTML documents must not contain active links to live Internet sites or pages.

All linked information must be contained within your electronic bid/offer and be accessible offline.

(5) Other electronic formats are not acceptable.

Ensure that filenames of attachments DO NOT contain spaces to limit virus scanners rejecting the email as unscannable.

(d) Please pay close attention to the Issued By block location on the cover page of the solicitation for closing date and time. The closing date and time is based on the local time of the listed location of the Issued By office. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.

2 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(e) It is the responsibility of the Offeror to ensure the proposal/quote is received by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if the proposal/quote was not received at the initial point of entry to the

Government infrastructure (in this case, received through SAM) by the exact date and time specified on the cover page of this solicitation, it will be determined late. Proposal/quote is defined to mean ALL volumes or parts required in the solicitation are included in the electronic submission.

Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.

(f) Solicitations may remain posted on beta.SAM.gov after the solicitation closing date. If the response deadline has passed for the solicitation, vendors will no longer be able to submit electronic responses.

(g) Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of the Governments intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or Pricing data/information. If an Offeror objects to such release in the base contract or contract modifications, the

Offeror must notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for the objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.

(h) Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. For technical assistance in doing business with the Government, and doing business electronically, please visit the

Procurement Technical Assistance Center (PTAC) website at http://www.aptac-us.org/ to locate a regional center.

A.3 ACKNOWLEDGEMENT OF AMENDMENTS

Acknowledge all the amendments received from the Government by identifying the amendment number and its issue date below:

Amendment Number: Date: __________________ _____

A.4 DISTRIBUTION AND DESTRUCTION OF EXPORT CONTROL TECHNICAL DATA PACKAGE

(a) This solicitation and resulting contract contains technical data whose export is restricted by the Arms Export Control Act (Title

22, U.S.C., Sec 2751, et. seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.

This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

(b) To be eligible to gain access to this export controlled TDP (via sam.gov) an offeror must have a current DD 2345, Militarily

Critical Technical Data Agreement certification on file with the Defense Logistics Information Service (DLIS). To obtain certification, contractors must submit a DD Form 2345 to the United States (U.S.)/Canada Joint Certification Office (JCO), along with a copy of supporting documentation. DD Form 2345 and instructions can be found on the Joint Certification Program website at:

http://www.dla.mil/HQ/InformationOperations/Offers/Products/LogisticsApplications/JCP.aspx Processing time is estimated at six (6) to ten (10) weeks after receipt. FBO will allow access to export controlled TDPs once certification is confirmed. Upon receipt of certification, an offeror may request the TDP in accordance with the instructions stated in the solicitation's Section C.

(c) Upon completion of the purposes for which Government Technical Data has been provided, the offeror, and all subcontractors, vendors, and sub-vendors of the offeror, are required to destroy all documents, including all reproductions, duplications, or copies

3 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

thereof as may have been further distributed.

(d) Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the

TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

A.5 NOTICE OF QUALIFICATION REQUIREMENTS

(a) This solicitation, and any resulting contract, includes documents in the Technical Data Package (TDP) which require electrical connectors (Federal Stock Class (FSC) 5935) from the Qualified Products List (QPL), either as an end item or as a component of the end item. Offerors may use a supplier from the QPL or follow the instructions in paragraph (b) of FAR Clause 52.209-1 Qualification

Requirements, in Section E, to become qualified to provide the electrical connectors.

(b) Offerors submitting a proposal in response to this solicitation are certifying the electrical connectors delivered are compliant with the QPL in accordance with FAR Clause 52.209-1 Qualification Requirements. If using a source from the QPL, Offerors shall verify compliance of the QPL source by reviewing current Government Industry Data Exchange Programs (GIDEP) notices. See http://www.gidep.org/ to review GIDEP notices for current known issues with electrical connectors (FSC 5935).

A.6 ALL OR NONE

Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.

(1) ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.

(2) OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION WILL BE DEEMED NONRESPONSIVE.

*** END OF NARRATIVE A0001 ***

4 61

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

SUPPLIES OR SERVICES AND PRICES/COSTS:

IN THE FOUR DIGIT ITEM NUMBERS

(CLINS) THAT FOLLOW, THE NUMBERING SYSTEM

THAT IS USED IS AS FOLLOWS:

THE FIRST THREE DIGITS SIGNIFY ITEM AND

THE FOURTH (LAST) DIGIT SIGNIFIES THE

APPLICABLE CONTRACT YEAR, i.e., CLIN 0011

IS FOR THE FIRST ITEM - FIRST ORDERING

YEAR, CLIN 0012 IS FOR THE FIRST ITEM -

SECOND ORDERING YEAR, CLIN 0013 IS FOR THE

FIRST ITEM - THIRD ORDERING YEAR, ETC.

THE FINAL LINE ITEM(S) ASSOCIATED WITH EACH

PART, SUCH AS FAT, TECHNICAL MANUALS, SERVICES,

OR TRAINING, WILL BECOME THE LAST ITEM NUMBER

IN NUMERICAL SEQUENCE FOR EACH ITEM, e.g.

0016 (5 YEAR LONG TERM CONTRACT) OR 0014

(3 YEAR LONG TERM CONTRACT). IF MORE THAN

ONE ITEM IS BEING PROCURED, THE NUMBERS WILL

BE 0026 OR 0024 DEPENDING ON THE LENGTH OF THE

LONG TERM CONTRACT.

THE FOLLOWING DEFINITIONS APPLY TO THE

ENTIRE SOLICITATION AND RESULTING CONTRACT:

FIRST ORDERING YEAR OF THE CONTRACT IS THE DATE____________________

OF AWARD PLUS 364 DAYS.

SECOND ORDERING YEAR OF THE CONTRACT IS 365 DAYS_____________________

THROUGH 729 DAYS AFTER CONTRACT AWARD.

THIRD ORDERING YEAR OF THE CONTRACT IS 730 DAYS____________________

THROUGH 1,094 DAYS AFTER CONTRACT AWARD.

FOURTH ORDERING YEAR OF THE CONTRACT IS 1,095_____________________

DAYS THROUGH 1,459 DAYS AFTER CONTRACT AWARD.

FIFTH ORDERING YEAR OF THE CONTRACT IS 1,460____________________

DAYS THROUGH 1,824 DAYS AFTER CONTRACT AWARD.

NOTE: THE PRICE APPLICABLE TO AN INDIVIDUAL

ORDER IS THE PRICE FOR THE ORDERING YEAR IN

WHICH THE ORDER IS ISSUED. THE DELIVERY DATE

DOES NOT DETERMINE THE ORDERING YEAR.

The information presented below applies to

Item No. 0011 Through 0015:

Minimum 5-Year Quantity: 90 EACH

(It is anticipated that this will be ordered at the time of the basic contract award)

Maximum 5 Year Quantity: 439 EACH

(Inclusive of Option Years, if applicable)

ONLY THE MINIMUM 5 YEAR QUANTITY IS

GUARANTEED.

5 61

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

NOTE: EACH ORDERING YEAR ESTIMATE, AS WELL

AS EACH OPTION YEAR ESTIMATE, IF APPLICABLE,

IS A 12 MONTH AVERAGE MONTHLY DEMAND WITH

CONTRACT FACTORS BUILT IN AND A 25% INCREASE

PER YEAR.

1. TDP is competitive at purchased parts estimated at less than 10%.

2. QPL specifications apply to this item.

(End of narrative A001)

0011 FIRST ORDERING YEAR 112 (E) EA $ $ ___________________ ______________ __________________

NSN: 3040-01-166-2189

COMMODITY NAME: HOUSING, MECHANICAL

CLIN CONTRACT TYPE:

Firm Fixed Price

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12321710(19207)

REVISION: C

DATE: 06-MAR-2007

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

FOB POINT: Origin

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

6 61

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0012 SECOND ORDERING YEAR 77 (E) EA $ $ ____________________ ______________ __________________

NSN: 3040-01-166-2189

COMMODITY NAME: HOUSING, MECHANICAL

CLIN CONTRACT TYPE:

Firm Fixed Price

SECOND ORDERING YEAR OF THE CONTRACT IS 365 DAYS

THROUGH 729 DAYS AFTER CONTRACT AWARD.

NOTE: THE PRICE APPLICABLE TO AN INDIVIDUAL

ORDER IS THE PRICE FOR THE ORDERING YEAR IN

WHICH THE ORDER IS ISSUED. THE DELIVERY DATE

DOES NOT DETERMINE THE ORDERING YEAR.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12321710 (19207)

REVISION: C

DATE: 06-MAR-2007

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

FOB POINT: Origin

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

7 61

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0013 THIRD ORDERING YEAR 80 (E) EA $ $ ___________________ ______________ __________________

NSN: 3040-01-166-2189

COMMODITY NAME: HOUSING, MECHANICAL

CLIN CONTRACT TYPE:

Firm Fixed Price

THIRD ORDERING YEAR OF THE CONTRACT IS 730 DAYS

THROUGH 1,094 DAYS AFTER CONTRACT AWARD.

NOTE: THE PRICE APPLICABLE TO AN INDIVIDUAL

ORDER IS THE PRICE FOR THE ORDERING YEAR IN

WHICH THE ORDER IS ISSUED. THE DELIVERY DATE

DOES NOT DETERMINE THE ORDERING YEAR.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12321710 (19207)

REVISION: C

DATE: 06-MAR-2007

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

FOB POINT: Origin

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

8 61

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0014 FOURTH ORDERING YEAR 89 (E) EA $ $ ____________________ ______________ __________________

NSN: 3040-01-166-2189

COMMODITY NAME: HOUSING, MECHANICAL

CLIN CONTRACT TYPE:

Firm Fixed Price

FOURTH ORDERING YEAR OF THE CONTRACT IS 1,095

DAYS THROUGH 1,459 DAYS AFTER CONTRACT AWARD.

NOTE: THE PRICE APPLICABLE TO AN INDIVIDUAL

ORDER IS THE PRICE FOR THE ORDERING YEAR IN

WHICH THE ORDER IS ISSUED. THE DELIVERY DATE

DOES NOT DETERMINE THE ORDERING YEAR.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12321710 (19207)

REVISION: C

DATE: 06-MAR-2007

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

FOB POINT: Origin

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

9 61

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0015 FIFTH ORDERING YEAR 81 (E) EA $ $ ___________________ ______________ __________________

NSN: 3040-01-166-2189

COMMODITY NAME: HOUSING, MECHANICAL

CLIN CONTRACT TYPE:

Firm Fixed Price

FIFTH ORDERING YEAR OF THE CONTRACT IS 1,460

DAYS THROUGH 1,824 DAYS AFTER CONTRACT AWARD.

NOTE: THE PRICE APPLICABLE TO AN INDIVIDUAL

ORDER IS THE PRICE FOR THE ORDERING YEAR IN

WHICH THE ORDER IS ISSUED. THE DELIVERY DATE

DOES NOT DETERMINE THE ORDERING YEAR.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12321710 (19207)

REVISION: C

DATE: 06-MAR-2007

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING INSTRUCTIONS

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

FOB POINT: Origin

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

10 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C.1 TECHNICAL DATA PACKAGE INFORMATION

The following Xd item applies to this solicitation:

[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.

[X] 2. The TDP for this solicitation resides within the DOD Safe Site (https://safe.apps.mil/ ). Offerors shall email the Contracting

Specialist (lisa.m.koski.civ@mail.mil), with subject header: TDP Pick-up W56HZV-20-R-0162 (company name). The email shall have the following information:

Names of person picking up

Email of person picking up (company email only)

CAGE Code

* Note: One pick-up request per offeror *

Once a request for a "Pick-up" is received, the Contract Specialist will set up the TDP "Drop Off" DOD Safe Site, an automatic notification will be generated via DOD Safe Site to the Offeror giving the contractor access to the TDP.

Making a Pick-up

There are two ways to pick-up files that have been dropped off (*Note: if encryption was used in the drop-off, you will be prompted to enter a passphrase. Please contact the contract specialist to share the passphrase securely.):

- All users can click on the link provided in the notification email they were sent.

- All users can click on the Pick-up link and manually enter the Claim ID and Claim Passcode provided to them through email or other means.

When viewing a drop-off, the user will see some of the following information:

- The list of files that were uploaded

- The sender and recipient information that the sender entered when the drop-off was created

- A list of pick-ups that have been made if the drop-off was created by the logged-in user

The recipient has 7 days to pick-up the files. Each night, drop-offs that are older than 7 days are removed from the system.

a. TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Title 22, U.S.C., Sec 2751,et.seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq..

b. Further dissemination must be in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

c. To obtain these TDPs, contractors must have a current DD 2345, Militarily Critical Technical Data Agreement on file with Defense

Logistics Information Service (DLIS). To obtain certification, go to https://public.logisticsinformationservice.dla.mil/jcp/search.aspx

d. Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor.

Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

e. If multiple individuals in the contractors organization need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP.

Those same individuals MUST be registered in SAM. Any individuals no longer with the company should be deleted. Questions related to registration in SAM should be directed to https://www.sam.gov/ The SAM helpdesk phone number is (866) 606-8220. Vendors are responsible for placing correct information in Beta.SAM.

f. It is strongly suggested that contractors submit the explicit access request and provide the buyer with the completed Use and Non-

Disclosure Agreement at the same time if the solicitation requires both to gain access to view the TDP.

11 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

C.2 DRAWING LIMITATIONS

(a) The drawings supplied with this contract are not shop or process drawings. The drawings are engineering design drawings, are ___ adequate to permit manufacture, and:

(1) depict the completed (item(s), and

(2) serve as the basis for inspection of the completed item(s).

(b) These drawings DO NOT cover intermediate drawings/specifications or steps in the manufacturing process. As a result, even if all the dimensions and tolerances specified in the engineering design drawing for each individual part are met, a cumulative unacceptable fit for the contract item could result.

(c) The Contractor is responsible for producing the shop or process drawings needed to cover intermediate steps in the manufacturing process.

(d) The Contractor agrees that he has obtained all specifications and drawings necessary to manufacture the items being solicited in accordance with the TDP including all incorporated specifications and drawings. The contractor is responsible for having all drawings and specifications. Delivery delays are not excusable where the contractor asserts that it did not have a specification or drawing and has failed to request, in writing, the specification from either the Contracting Officer or Contract Specialist prior to the solicitation closing date.

(e) Failure to produce an end item with a cumulative fit that conforms to Government drawings, specifications or other supplemental manufacturing documentation will result in the Contractor being responsible for correcting this condition at no additional cost to the

Government and no delivery schedule extension.

C.3 ACQUISITION OF MANUFACTURER'S PART NUMBER: COMPONENTS

One or more of the drawings for part of the contract item set forth in the Schedule and in the Technical Data Package specify manufacturer's part numbers. Since complete Government technical data for such part or parts are not available, it is understood that the Contractor, by accepting this contract, agrees to furnish only the listed manufacturer's part number(s) for those components of the contract item. It is further understood and agreed that references to manufacturer's part numbers herein shall be deemed to include all changes or revisions thereto which the approved manufacturer has made effective as of the first date of delivery of any of the items under this contract; provided, that no change or revision that affects the interchangeability (ability to be interchanged with previous parts and to match with all mating parts when assembled) of the listed manufacturer's part shall be incorporated into the contract item without the prior written approval of the Procuring Contracting Officer.

C.4 TRUSTED ASSOCIATE SPONSORSHIP SYSTEM (TASS) PROGRAM

(a) The contractor is responsible for processing applications for Common Access Cards (CAC) for every contractor employee who deploys with the military force, OR who has need to access any government computer network in accordance with FAR 52.204-9, Personal Identity

Verification of Contractor Personnel.

(b) The contractor is responsible for managing requests for new or renewal CAC cards in sufficient time to ensure that all contractor employees have them when needed to perform work under this contract. The norm is at least ten calendar days advance notice to the

Trusted Agent* (TA), unless there are extenuating circumstances approved by the Contracting Officers Representative (COR) or

Contracting Officer. *The COR will be the TA for this contract.

(c) The contractor shall obtain an Army Knowledge Online (AKO) email address for each applicant, including subcontractors, who may be deployed or require logical access to a government computer network. This can be done by going to http://www.us.army.mil and register as an Army Guest with the sponsor being the COR. Note: If a contractor employee loses the privilege to access AKO, they lose the ability to renew their CAC. Therefore, it is critical that contractor employees maintain their AKO accounts.

(d) It is recommended that a Corporate Facility Security Officer (FSO) be established to serve as the firms single point of contact for

Trusted Associate Sponsorship System (TASS). If a FSO is not established, each contractor employee requiring a CAC card will be required to process their own applications.

(e) CAC applications must be processed through the DODs TASS. The contractors FSO or contractor employee shall submit requests for a

12 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

CAC via email to the TASS Trusted Agent (TA) (CORS E-MAIL) before accessing the TASS website.

(f) The government will establish a TASS application account for each CAC request and will provide each contractor employee a USER ID and Password via email to the FSO. The FSO or contractor employee shall access the TASS account and complete the CAC application

(entering/editing contractor information as applicable) at https://www.dmdc.osd.mil/tass/operator/consent?continueToUrl=%2Ftass%2Findex.jsp .

(g) The FSO or contractor employee will submit completed applications in TASS, and will follow up to ensure that the TA is processing the request.

(h) The government will inform the contractors applicant via email of one of the following:

- Approved*. Upon approval, the information is transferred to the Defense Enrollment Eligibility Reporting System

(DEERS) database and an email notification is sent to the contractor with instructions on obtaining their CAC. The contractor proceeds to a Real-Time Automated Personnel Identification System (RAPIDS) station (https://www.dmdc.osd.mil/rsl/ provides

RAPIDS locations).

- Rejected*. Government in separate correspondence will provide reason(s) for rejection.

- Returned. Additional information, or correction to the application, required by the contractor employee.

*The contractor will maintain records of all approved and rejected applications.

(i) At the RAPIDS station, the RAPIDS Verification Officer will verify the contractor by SSN, and two forms of identification, one of which must be a picture ID. The Verification Officer will capture primary and alternate fingerprints and picture, and updates to DEERS and will then issue a CAC.

(j) Issued CACs shall be for a period of performance not longer than three (3) years or the individuals contract end date (inclusive of any options) whichever is earlier.

(k) The contractor shall return issued CACs to the DEERS office upon return from deployment, departure or dismissal of each contractor employee. A receipt for each card must be obtained and provided to the TA/COR.

(l) A CAC cannot be issued without evidence that a National Agency Check with Written Inquires (NACI) has at least been initiated by the FSO. TASS will be linked to the Joint Personnel Adjudication System (JPAS) in the near future. The TA will have to verify via JPAS that the NACI has been initiated by the FSO before he/she can approve a contractor request for a CAC.

(m) Details and training on TASS are available on AKO at https://www.us.army.mil/suite/portal/index.jsp or by contacting the CAC helpdesk at cacsupport@mail.mil or 866-738-3222.

C.5 REQUIREMENT FOR AN OPSEC STANDING OPERATION PROCEDURE/PLAN

(a) The contractor is subject to provisions of the TACOM LCMC OPSEC Standing Operating Procedures (SOP/Plan), or other U.S. Government

OPSEC plan, per AR 530-1, Operations Security. This SOP/Plan specifies the governments critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it.

(b) The contractor will receive a copy of the SOP/Plan at time of award. Local form STA Form 7114 (or similar) will be used to document and record security OPSEC reviews which are conducted by G2, TACOM LCMC or individual organizations supporting OPSEC Officers.

(c) The contractor shall identify an individual who will be an OPSEC Coordinator. The contractor will ensure that this individual is

OPSEC Level I.

C.6 OPSEC TRAINING REQUIREMENT

Per AR 530-1, Operations Security, new contractor employees must complete Level I OPSEC training within 30 calendar days of reporting for duty. All contractor employees must complete annual OPSEC awareness training. OPSEC awareness training is available at:

https://securityawareness.usalearning.gov/opsec/index.htm . Within 10 days of completing the training, the Contractor shall provide certificates/proof of completion to the Contracting Officers Representative (COR), if assigned to the contract, or the Procuring

Contracting Officer (PCO).

13 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

*** END OF NARRATIVE C0001 ***

14 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION D - PACKAGING AND MARKING

D.1 PACKAGING REQUIREMENTS (SPECIAL PACKAGING INSTRUCTIONS)

(a) Military preservation, packing, and marking for this contract/order shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1, and the Special Packaging Instruction, see below.

(1) LEVEL OF PRESERVATION: Military

(2) LEVEL OF PACKING: A

(3) QUANTITY PER UNIT PACKAGE: 001

(4) SPECIAL PACKAGING INSTRUCTION NUMBER. AK11662189

(a) REVISION C

(b) DATE OF REVISION 3-6-07

(c) THE REQUIRED SPECIAL PACKAGING INSTRUCTION (SPI) IS AVAILABLE ON THE WEB AT THE FOLLOWING URL: SPI ATTACHED AS

PRIMARY CONTENT

(Note: You must have the Adobe Acrobat reader installed on your PC to view the SPI. See Adobes website (http://get.adobe.com/reader/ ) for information on obtaining the latest version of the reader. If you're experiencing problems opening the Special Packaging

Instructions in Adobe .PDF images using Internet Explorer, try the following: Go to "Tools," then "Internet Options." Click on the

"Advanced" tab. Scroll down to the "Security" section. Uncheck "Do not save encrypted pages to disk." Click "Apply." Click "OK.")

(b) Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The preferred pallet is a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.

(c) Marking:

(1) In addition to any special markings called out on the SPI, all unit packages, intermediate packs, exterior shipping containers, and, as applicable, unitized loads shall be marked in accordance with MIL-STD-129). The contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract/order or not.

Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel.

(2) Passive RFID tagging is required in all contracts that contain DFARS clause 252.211-7006. For details and most recent information, see "http://www.acq.osd.mil/log/sci/ait.html " l (best viewed with Internet Explorer 11 or higher) for the current DoD ___________________________________________

Suppliers Passive RFID Information Guide. When an item is assigned a Unique Item Identifier (UII) as indicated by the inclusion of contract clause DFARS 252.211-7003, refer to the DoD Guide to Uniquely Identifying Items (available at http://dodprocurementtoolbox.com/page/unique-id/tools ) for development of the UII and MIL-STD-129 for UII package marking requirements. Contractors must verify the RFID and UII clauses cited above are included in this solicitation/contract.

(d) Heat Treatment and Marking of Wood Packaging Materials (WPM):

(1) In accordance with DOD 4140.65-M and the requirements of the International Standards for Phytosanitary Measures 15 (ISPM), Regulation of Wood Packaging Material in International Trade, current edition, (hereinafter ISPM 15), the following commercial heat treatment and marking process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging

Material (WPM). Foreign manufacturers shall comply with ISPM 15, and have the WPM heat treatment and marking verified in accordance with their National Plant Protection Organizations compliance program.

(2) Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. All WPM using a conventional steam or dry kiln heat chamber (treatment code for the mark: HT) shall be heat treated to a minimum core temperature of 56 degrees Celsius for a minimum of 30 minutes, and certified by an agency accredited by the ALSC in accordance with Wood Packaging

Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org ). WPM heat treated wood using dielectric heating (treatment code for the mark: DH) shall follow the requirements in ISPM 15, and shall be certified by an agency accredited by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL:

http://www.alsc.org ). The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure the materials used

15 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

in manufacture can be traced to the original source of heat treatment, and that the original source of the heat treatment obtained the necessary certifications.

(3) Marking: Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention Standard.

The ALS approved quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens. Pallet markings shall be applied to the side of the stringer or end of the block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp. Foreign manufacturers shall comply with ISPM -15 and shall have the marking of WPM verified in accordance with their National Plant Protection Organizations compliance program.

(e) Hazardous Materials (As applicable):

(1) Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated.

(This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)

(2) Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements herein for the mode of transport and the applicable performance packaging contained in the following documents:

- International Air Transport Association (IATA) Dangerous Goods Regulations

- International Maritime Dangerous Goods Code (IMDG)

- Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49

- Joint Service Regulation AFJMAN24-204(I)/TM38-250/NAVSUPPUB 505/MCO P4030.19(I)/DLAM 4145.3(I) (for military air shipments).

(3) If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the

United Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers. A Product Material Safety Data Sheets (MSDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.

(f) This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the

SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the SPI. Minor dimensional and size changes are acceptable provided contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to

PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.

(g) SUPPLEMENTAL INSTRUCTIONS: See attached Special Packaging Instructions (SPI) as primary content.

*** END OF NARRATIVE D0001 ***

16 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION E - INSPECTION AND ACCEPTANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

For FAR clauses: https://www.acquisition.gov/

For DFARS clauses: https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________

E-1 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996

E-2 52.246-15 CERTIFICATE OF CONFORMANCE APR/1984

E-3 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984

E.1 USE OF MIL-STD 1916

(a) The Government will not accept lots whose samples submitted for acceptance contain non-conformances unless appropriately documented and approved by the contracting officer. The contractor shall use MIL-STD 1916, DOD Preferred Methods of Acceptance of Product. The

Verification Level (VL) shall be VL IV for major characteristics and VL II for minor characteristics.

(b) MIL-STD HDBK-1916 provides guidance on the use of MIL-STD 1916. This handbook is not contractually binding.

E.2 DRAWINGS FOR INSPECTION

(a) When requested, the Contractor shall make available to the Government Inspector, the drawings, specifications and any applicable

Engineering Exceptions associated to the drawings, to which the product was manufactured. Upon completion of product inspection and acceptance by the Government Inspector, all drawings, specifications and Engineering Exceptions, will be returned to the Contractor.

(b) If the contractor is not the actual manufacturer of the item being procured (i.e. dealer, distributor, etc.) the contractor shall ensure that subcontractor drawings are available for review to support the Government's inspection requirements.

E.3 INSPECTION AND ACCEPTANCE POINTS: ORIGIN

The Government's inspection and acceptance of the supplies offered under this contract/purchase order shall take place at ORIGIN.

Offeror must specify below the exact name, address, and CAGE of the facility where supplies to be furnished under this contract/purchase order will be available for inspection/acceptance.

INSPECTION POINT: __________________________________________

(Name) (CAGE)

(Address) (City) (State) (Zip)

ACCEPTANCE POINT: __________________________________________

(Name) (CAGE)

(Address) (City) (State) (Zip)

17 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

*** END OF NARRATIVE E0001 ***

18 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION F - DELIVERIES OR PERFORMANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

For FAR clauses: https://www.acquisition.gov/

For DFARS clauses: https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________

F-1 52.211-17 DELIVERY OF EXCESS QUANTITIES SEP/1989

F-2 52.242-15 STOP-WORK ORDER AUG/1989

F-3 52.242-17 GOVERNMENT DELAY OF WORK APR/1984

F-4 52.247-29 F.O.B. ORIGIN FEB/2006

F-5 52.247-30 F.O.B. ORIGIN, CONTRACTOR'S FACILITY FEB/2006

F-6 52.247-58 LOADING, BLOCKING, AND BRACING OF FREIGHT CAR SHIPMENTS APR/1984

F-7 52.247-59 F.O.B. ORIGIN--CARLOAD AND TRUCKLOAD SHIPMENTS APR/1984

F-8 52.247-65 F.O.B. ORIGIN, PREPAID FREIGHT--SMALL PACKAGE SHIPMENTS JAN/1991

F-9 252.211-7008 USE OF GOVERNMENT-ASSIGNED SERIAL NUMBERS SEP/2010

F-10 52.211-8 TIME OF DELIVERY JUN/1997

(a) The Government requires delivery to be made according to the following schedule:

REQUIRED DELIVERY SCHEDULE

ITEM NO. QUANTITY WITHIN DAYS

AFTER DATE OF

CONTRACT

0011 EST 112 EA 210 days after receipt of Delivery Order at a rate of 120 every 30 days

0012 EST 077 EA 210 days after receipt of Delivery Order at a rate of 120 every 30 days

0013 EST 080 EA 210 days after receipt of Delivery Order at a rate of 120 every 30 days

0014 EST 089 EA 210 days after receipt of Delivery Order at a rate of 120 every 30 days

0015 EST 081 EA 210 days after receipt of Delivery Order at a rate of 120 every 30 days

The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.

OFFERORS PROPOSED DELIVERY SCHEDULE

ITEM NO. QUANTITY WITHIN DAYS

AFTER DATE OF

CONTRACT

(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed, or otherwise furnished to the successful offeror, results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day award is dated. Therefore, the offeror should compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the

Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the

Contractors date of receipt of the contract or notice of award by adding

(1) five calendar days for delivery of the award through the ordinary mails, or

19 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term working day excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.

(End of Clause)

F-11 52.247-60 GUARANTEED SHIPPING CHARACTERISTICS JAN/2017

(a) The offeror is requested to complete subparagraph (a)(1) of this clause, for each part or component which is packed or packaged separately. This information will be used to determine transportation costs for evaluation purposes. If the offeror does not furnish sufficient data in subparagraph (a)(1) of this clause, to permit determination by the Government of the item shipping costs, evaluation will be based on the shipping characteristics submitted by the offeror whose offer produces the highest transportation costs or in the absence thereof, by the Contracting Officers best estimate of the actual transportation costs.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .