Shroud Explosive Bolt - SOW.pdf
PDF 187 KB Posted
- Attached to
- QE Testing of Shroud Explosive Bolts
- Solicitation number
- N00174-21-RFPREQ-E2-0042
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW-EBOLT-2021
23 July 2021
Attachment ( )
STATEMENT OF WORK
FOR
QUALITY EVALUATION TESTING OF
TOMAHAWK SHROUD EXPLOSIVE BOLT (P/N 2220628)
1.0 INTRODUCTION
1.1 Scope. This statement of work (SOW) defines the efforts to conduct non-destructive and functional testing of twelve (12) Shroud Explosive Bolts (Raytheon P/N 2220628) at the new test location Pacific Scientific EMC in Chandler, AZ. The explosive bolt test sample will be furnished by the Naval Surface Warfare Center, Indian Head Division (NSWC IHD).
1.2 Background. This will be the third Service Life Assessment Program (SLAP) for the Shroud Explosive Bolts. Past SLAP testing was conducted at Pacific Scientific EMC in Hollister, CA facility under contract N00174-14-D-0014 / D.O. N00174-18-F-0283.
2.0 APPLICABLE DOCUMENTS
2.2 Drawings.
2.2.1 Pacific Scientific Hollister Drawing 93670, Explosive Bolt Assembly
2.2.2 Pacific Scientific Hollister Drawing F93851, Bolt Firing Fixture
2.2.3 Raytheon Drawing 2220628, Explosive Bolt Assembly
2.3 Specifications.
2.3.1 Specification No. 60782, Explosive Bolt Assembly
2.4 Test Procedures.
2.4.1 Pacific Scientific Hollister Acceptance Test Procedure, TP-93670, Rev H
3.0 REQUIREMENTSGovernment Furnished Property.
3.1.1 The Government will furnish the following Government Furnished Property (GFP) to the Contractor for use in performance of this contract:
ITEM: QUANTITY:
__Shroud Explosive Bolts (Raytheon P/N 2220628)_ ______12____
3.1.2 The property will be delivered at the Government’s expense at or near the contractor facility.
3.1.3 Only the property listed above and on the GFP Attachment will be furnished by the Government. All other property required for performance of this contract shall be furnished by the contractor.
3.1.4 Within 30 days after GFP is determined by the contractor to be lost, damaged, destroyed, no longer usable, or no longer needed for the performance of the contract, the Contractor shall notify the Contracting Officer, in writing, thereof.
3.1.5 Disposition instructions are as follows:
• Material will be destroyed by the contractor
3.1.6 The contractor’s GFP inventory shall be reported in accordance with the Government Property Inventory Report. (CDRL A001)
3.2 On-Site Visit and Coordination. Pacific Scientific shall notify NSWC IHD at least ten (10) days prior to functional testing so representatives can make travel arrangements to witness testing. During on-site visit, NSWC IHD technical representative shall observe non-destructive and functional test setups and all testing.
3.3 Acceptance Test Procedure. The contractor shall update the current Hollister acceptance test procedure ATP TP-93670, Rev H to include modifications required for changing the test location to the Chandler, AZ facility. The revised test procedure shall be submitted to the Government for review and approval at least 15 days prior to testing. (CDRL A002)
3.4 Non-destructive Testing (NDT). No NDT shall be conducted that could result in the damage or degradation of the integrity of the unit. Testing shall be performed as shown in Table 1. All non-destructive test and inspection results shall be recorded and provided in the Acceptance Test Report (ATR). (CDRL A003)
3.4.1 The visual inspection shall be conducted in accordance with Pacific Scientific Acceptance Test Procedure (ATP) TP-93670 section 4.3 on the units shown in SOW Table 1. Units shall be visually inspected for defects in workmanship, service-related damage, and conformance to applicable drawings. If not already, units identified in Table 1 shall be marked with the assigned test control number (TCN) to track the items through the test sequence. Photographs (prior to testing) shall be taken to document any non-conformance or damage. Visual inspection results and photographs shall be provided in the Acceptance Test Report.
3.4.2 The bridgewire resistance test shall be conducted on the units two times in accordance with Table 1 and Pacific Scientific ATP TP-93670 section 4.4a. Units shall be tested before and after no-fire testing as required in Table I. Photograph(s) shall be taken of test setup. Bridgewire resistance test results, in ohms, shall be provided the Acceptance Test Report.
3.4.3 The insulation resistance test shall be conducted on the units in Table 1 in accordance with Pacific Scientific ATP TP-93670 section 4.5. Photograph(s) shall be taken of test setup. Insulation resistance test results, in ohms, shall be provided the Acceptance Test Report.
3.4.4 The electrostatic discharge (ESD) test shall be conducted on the units in Table 1 in accordance with Pacific Scientific ATP TP-93670 section 4.6. Photograph(s) shall be taken of test setup. Electrostatic discharge test results shall be provided in the Acceptance Test Report.
3.4.5 The radiographic examination shall be conducted on the units in Table 1 in accordance with Pacific Scientific ATP TP-93670 section 4.8. Radiographic inspection report and copy of X-ray(s) shall be provided in the Acceptance Test Report.
3.5 Functional Testing (Destructive). Testing shall be performed as shown in Table 1. All test data and inspection results shall be recorded and provided in the Acceptance Test Report
(ATR). (CDRL A003)
3.5.1 The no-fire test shall be conducted on the units in Table 1 in accordance with Pacific Scientific ATP TP-93670 section 5.3. Photograph(s) shall be taken of test setup. No-fire test results and, if applicable, associated non-conformance reports, shall be provided in the Acceptance Test Report.
3.5.2 Prior to functional testing, the units shall be temperature conditioned and then functionally tested in accordance with Table 1 and ATP TP-93670 sections 5.4 and 5.5.
Photograph(s) shall be taken of test setup.
Table 1: Test Matrix
TEST
SOW SECTION
REQUIREMENT A B TOTAL
Visual Inspection 3.4.1 6 6 12 Bridgewire Resistance* 3.4.2 6 6 12 Insulation Resistance* 3.4.3 6 6 12 Electrostatic Discharge* 3.4.4 6 6 12 Radiographic Inspection (X-ray)* 3.4.5 6 6 12 No-Fire Current* 3.5.1 6 6 12 Bridgewire Resistance* 3.4.2 6 6 12 Functional Test*
Cold Temperature (+28 °F) 3.1.3.2 6 6 Hot Temperature (+167 °F) 3.1.3.2 6 6
*These tests shall be conducted in the sequence as shown.
Shroud Explosive Bolts
(GROUPS)
3.6 Test Dates. Functional testing shall be completed within 20 weeks after receipt of government-furnished material.
3.7 Acceptance Test Report (CDRL A003).
3.7.1 All non-destructive test and inspection results shall be included in the Acceptance Test Report. Photographs of units prior to test and each test set up configuration shall be included in the Acceptance Test Report.
3.7.2 Test data shall include record of bridgewire resistance, firing current, test temperature, time-application of current to bridgewire burn-out, bolt separation in the specified zone, and function time. Current and time traces shall be recorded. The no-fire results and functional test results (data and traces) and any non-conformance reports shall be delivered as part of the Acceptance Test Report. An electronic file of the current vs.
time data traces, in a file format that is compatible with Excel spreadsheets (e.g., .csv files) shall be delivered with the Acceptance Test Report.
3.7.3 The post-functional visual inspection shall be conducted on the units in Table 1. All fired units shall be inspected for complete function, any hardware anomalies, or hot gas leakage. Anomalies shall be documented. Photographs shall be taken of each post-functional test unit, including any anomalies and of the break plane to document post-fire condition. Post-functional visual inspection results and photographs shall be included in the Acceptance Test Report.
3.8 Disposal of Test Sample: All functioned units shall be properly disposed of by the contractor after all CDRLs have been accepted by NSWC IHD.
4.0 DELIVERABLES
4.1 Government Property Inventory Report (CDRL A001).
First Submission – Report shall be submitted within 30 days after functional testing.
4.2 Test Plan/Acceptance Test Procedure (CDRL A002).
First Submission – The revised Acceptance Test Procedure ATP TP-93670, Rev I to address facility changes from Hollister, CA location to Chandler, AZ location shall be submitted for government review and approval at least 15 days prior to testing.
Subsequent Submission – Comments and questions shall be addressed in the subsequent submission within 5 days of receipt of comments from the government.
4.3 Technical Report–Study/Services/Acceptance Test Report (CDRL A003).
First Submission – A copy of functional test data sheets (including bridgewire resistance, firing current, test temperature, time-application of current to bridgewire burn-out, bolt separation in the specified zone, and function time), no-fire results, NDT results, and test equipment list and calibration information, shall be provided to the NSWC IHD within 2 days after the completion of the functional testing. Any non-conformance report shall be provided for any unit(s) that does not meet the NDT or functional test requirements.
Subsequent Submission – An electronic copy of current versus time traces, in a file format compatible with Excel spreadsheets (e.g., .csv files), photographs, shall be provided to the
NSWC IHD within 30 days of completion of functional testing. Radiographic inspection reports and a copy of X-rays shall be provided to the NSWC IHD within 30 days of completion of testing.
4.4 CDRL Summary
Table 2: CDRL Submittals
CDRL
NUMBER
TITLE FIRST SUBMISSION SUBSEQUENT
SUBMISSION
CDRL A001 Government Property
Inventory Report (SOW section 3.1.6 & 4.1)
Within 30 days of completion of functional testing.
CDRL A002 Test Plan/ATP (SOW section 3.3 & 4.2)
15 days prior to testing Within 5 days after comments
CDRL A003 Technical Report– Study/Services/ ATR (SOW section 3.4, 3.5, 3.7 & 4.3)
Within 2 days of completion of functional testing
Within 30 days of completion of functional testing
4.5 Point of Contact
NSWC IHD Technical Repsentative:
Tony Quebral, CODE E24TQ 301-744-2312 Anthony.Quebral@navy.mil
Delivery Address:
NSWC IHD
4393 BENSON ROAD SUITE 101
INDIAN HEAD, MD 20640-5092
Attn: Tony Quebral, CODE E24TQ Anthony.Quebral@navy.mil mailto:Anthony.Quebral@navy.mil mailto:Anthony.Quebral@navy.mil
| 1.0 INTRODUCTION |
| 1.1 Scope. This statement of work (SOW) defines the efforts to conduct non-destructive and functional testing of twelve (12) Shroud Explosive Bolts (Raytheon P/N 2220628) at the new test location Pacific Scientific EMC in Chandler, AZ. The explosive... |
| 1.2 Background. This will be the third Service Life Assessment Program (SLAP) for the Shroud Explosive Bolts. Past SLAP testing was conducted at Pacific Scientific EMC in Hollister, CA facility under contract N00174-14-D-0014 / D.O. N00174-18-F-0283. |
| 2.0 APPLICABLE DOCUMENTS |
| 2.1 |
| 2.2 Drawings. |
| 2.2.1 Pacific Scientific Hollister Drawing 93670, Explosive Bolt Assembly |
| 2.2.2 Pacific Scientific Hollister Drawing F93851, Bolt Firing Fixture |
| 2.2.3 Raytheon Drawing 2220628, Explosive Bolt Assembly |
| 2.3 Specifications. |
| 2.3.1 Specification No. 60782, Explosive Bolt Assembly |
| 2.4 Test Procedures. |
| 2.4.1 Pacific Scientific Hollister Acceptance Test Procedure, TP-93670, Rev H |
| 3.0 REQUIREMENTS |
| 3.1 Government Furnished Property. |
| 3.1.1 The Government will furnish the following Government Furnished Property (GFP) to the Contractor for use in performance of this contract: |
| 3.1.2 The property will be delivered at the Government’s expense at or near the contractor facility. |
| 3.1.3 Only the property listed above and on the GFP Attachment will be furnished by the Government. All other property required for performance of this contract shall be furnished by the contractor. |
| 3.1.4 Within 30 days after GFP is determined by the contractor to be lost, damaged, destroyed, no longer usable, or no longer needed for the performance of the contract, the Contractor shall notify the Contracting Officer, in writing, thereof. |
| 3.1.5 Disposition instructions are as follows: |
| 3.1.6 The contractor’s GFP inventory shall be reported in accordance with the Government Property Inventory Report. (CDRL A001) |
| 3.2 On-Site Visit and Coordination. Pacific Scientific shall notify NSWC IHD at least ten (10) days prior to functional testing so representatives can make travel arrangements to witness testing. During on-site visit, NSWC IHD technical representati... |
| 3.3 Acceptance Test Procedure. The contractor shall update the current Hollister acceptance test procedure ATP TP-93670, Rev H to include modifications required for changing the test location to the Chandler, AZ facility. The revised test procedure ... |
| 3.4 Non-destructive Testing (NDT). No NDT shall be conducted that could result in the damage or degradation of the integrity of the unit. Testing shall be performed as shown in Table 1. All non-destructive test and inspection results shall be recor... |
| 3.4.1 The visual inspection shall be conducted in accordance with Pacific Scientific Acceptance Test Procedure (ATP) TP-93670 section 4.3 on the units shown in SOW Table 1. Units shall be visually inspected for defects in workmanship, service-related... |
| 3.4.2 The bridgewire resistance test shall be conducted on the units two times in accordance with Table 1 and Pacific Scientific ATP TP-93670 section 4.4a. Units shall be tested before and after no-fire testing as required in Table I. Photograph(s) ... |
| 3.4.3 The insulation resistance test shall be conducted on the units in Table 1 in accordance with Pacific Scientific ATP TP-93670 section 4.5. Photograph(s) shall be taken of test setup. Insulation resistance test results, in ohms, shall be provide... |
| 3.4.4 The electrostatic discharge (ESD) test shall be conducted on the units in Table 1 in accordance with Pacific Scientific ATP TP-93670 section 4.6. Photograph(s) shall be taken of test setup. Electrostatic discharge test results shall be provide... |
| 3.4.5 The radiographic examination shall be conducted on the units in Table 1 in accordance with Pacific Scientific ATP TP-93670 section 4.8. Radiographic inspection report and copy of X-ray(s) shall be provided in the Acceptance Test Report. |
| 3.5 Functional Testing (Destructive). Testing shall be performed as shown in Table 1. All test data and inspection results shall be recorded and provided in the Acceptance Test Report (ATR). (CDRL A003) |
| 3.5.1 The no-fire test shall be conducted on the units in Table 1 in accordance with Pacific Scientific ATP TP-93670 section 5.3. Photograph(s) shall be taken of test setup. No-fire test results and, if applicable, associated non-conformance reports... |
| 3.5.2 Prior to functional testing, the units shall be temperature conditioned and then functionally tested in accordance with Table 1 and ATP TP-93670 sections 5.4 and 5.5. Photograph(s) shall be taken of test setup. |
| 3.6 Test Dates. Functional testing shall be completed within 20 weeks after receipt of government-furnished material. |
| 3.7 Acceptance Test Report (CDRL A003). |
| 3.7.1 All non-destructive test and inspection results shall be included in the Acceptance Test Report. Photographs of units prior to test and each test set up configuration shall be included in the Acceptance Test Report. |
| 3.7.2 Test data shall include record of bridgewire resistance, firing current, test temperature, time-application of current to bridgewire burn-out, bolt separation in the specified zone, and function time. Current and time traces shall be recorded. ... |
| 3.7.3 The post-functional visual inspection shall be conducted on the units in Table 1. All fired units shall be inspected for complete function, any hardware anomalies, or hot gas leakage. Anomalies shall be documented. Photographs shall be taken ... |
3.8 Disposal of Test Sample: All functioned units shall be properly disposed of by the contractor after all CDRLs have been accepted by NSWC IHD.
| 4.0 DELIVERABLES |
| 4.1 Government Property Inventory Report (CDRL A001). |
| 4.2 Test Plan/Acceptance Test Procedure (CDRL A002). |
| 4.3 Technical Report–Study/Services/Acceptance Test Report (CDRL A003). |
| 4.4 CDRL Summary |
| 4.5 Point of Contact |
File details come from the government source that posted it. Updated .