SF1442 12505B23R0007.pdf
PDF 798 KB Posted
- Attached to
- Replace Generator and Associated Repairs Federal contract opportunity
- Solicitation number
- 12505B23R0007
About this file
This is a solicitation for replacing a generator and associated repairs at a USDA Agricultural Research Service facility in Madison, Wisconsin. The project includes replacing an existing generator with a new unit and performing related electrical and structural work. The estimated value is between $250,000 and $500,000. The NAICS code is 238210 and it is set aside for small businesses with a size standard of $19 million. The period of performance is from September 2023 through August 2024. The solicitation includes pricing schedules, technical specifications, and standard contract clauses. Responses are due by September 2023 and award will be made within 60 days thereafter.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers.pdf | ||
| ARS-372.pdf | ||
| Drawings Madison WI-Replace Generator.pdf | ||
| Wage Determination.pdf | ||
| Statement of Work Madison WI-Replace Generator and Assoc Repairs.pdf | ||
| ARS-371.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
1094640
USDA ARS MWA AAO ACQ/PER PROP
1815 N UNIVERSITY STREET
PEORIA IL 61604
ARS-12505B
Joel Maas
ARS/AFM/MWAAO/Acquisitions 1815 N. University Street Peoria, IL 61604
JOEL MAAS 970-631-3433
1x 08/01/2023
12505B23R0007
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Replace Generator and Associated Repairs at the Dairy Forage Research Center (DFRC)
USDA-ARS in Madision , WI per the Statement of Work.
The North American Industry Classification System (NAICS) Code is 238210. The Small
Business Size Standard is $19.0 Million.
This is a 100% Total Small Business Set-Aside.
The magnitude of construction is estimated to be between $250,000 and $500,000.
NOTE: Email responses in Adobe PDF format are hereby authorized for the submittal of offers and proposal information.
POC: Joel Maas, Contract Specialist
Phone: 970-631-3433
Email: joel.maas@usda.gov
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
14 330 calendar days and complete it within ________________ ________________ calendar days after receiving
09/01/2023
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 8/2014)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USDA ARS MWA AAO ACQ/PER PROP
1815 N UNIVERSITY STREET
PEORIA IL 61604
ARS-12505B
ZACHARY E. SCHULER
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 8/2014) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 43
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12505B23R0007
Delivery: 08/09/2024
Delivery Location Code: ARS-12569T
MWA U.S. DAIRY FORAGE RESEARCH CENT
1925 LINDEN DRIVE
MADISON WI 53706 US
Period of Performance: 09/14/2023 to 08/09/2024
0001 Replace Generator and Associated Repairs Dairy
Forage Research Center (DFRC) USDA-ARS, Madison, WI
Product/Service Code: J030
Product/Service Description: MAINT/REPAIR/REBUILD
OF EQUIPMENT- MECHANICAL POWER TRANSMISSION
EQUIPMENT
1001 Bid Option 1-New wall construction
(Option Line Item)
Product/Service Code: J030
Product/Service Description: MAINT/REPAIR/REBUILD
OF EQUIPMENT- MECHANICAL POWER TRANSMISSION
EQUIPMENT
1002 Bid Option 2-In underground electrical duct bank installation, provide 4" thick concrete cap above conduit run in accordance with the Statement of
Work
(Option Line Item)
Product/Service Code: J030
Product/Service Description: MAINT/REPAIR/REBUILD
OF EQUIPMENT- MECHANICAL POWER TRANSMISSION
EQUIPMENT
1003 Bid Option 3- Provide new fence installation around new generator installation in accordance with the Statement of Work
(Option Line Item)
Product/Service Code: J030
Product/Service Description: MAINT/REPAIR/REBUILD
OF EQUIPMENT- MECHANICAL POWER TRANSMISSION
EQUIPMENT
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SOLICITATION 12905B23R0007
Madison, WI
Replace Generator and Associated Repairs
B - SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
C - SECTION C - DESCRIPTION/SPECS./WORK STATEMENT
D - SECTION D - PACKAGING AND MARKING
E - SECTION E - INSPECTION AND ACCEPTANCE
F - SECTION F - DELIVERIES OR PERFORMANCE
G - SECTION G - CONTRACT ADMINISTRATION DATA
H - SECTION H - SPECIAL CONTRACT REQUIREMENTS
I - SECTION I - CONTRACT CLAUSES
J - SECTION J - LIST OF ATTACHMENTS
L - SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
M - SECTION M - EVALUATION FACTORS FOR AWARD
Replace Generator and Associated Repairs
B - SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 PRICE SCHEDULE:
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Definition of CLIN – Contract Line Item Number.
ITEM# Description Price/Cost
0001 Replace Generator and Associated Repairs $ 1001 Bid Option 1-New Wall Construction $_______________ 1002 Bid Option 2-4” Concrete Cap Above Conduit Run $_______________ 1003 Bid Option 3-Provide new fence installation $_______________
End of this section
Replace Generator and Associated Repairs
C - SECTION C - DESCRIPTION/SPECS./WORK STATEMENT
C.1 DESCRIPTION OF WORK:
It is the intention of this contract to complete replace Generator and Associated Repairs in accordance with the Statement of Work and supporting documents.
C.2 GENERAL REQUIREMENTS:
C.2.1 Service Interruptions/Utility Outages If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the Contracting Officer Representative ten calendar days in advance to allow notification of affected tenants and customers. If the discontinued service is due to an emergency breakdown the Contractor shall notify the Contracting Officer Representative as soon as practicable.
At a minimum, include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.
C.2.2 Employee Conduct Contractor employees and Subcontractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.
C.2.3 Employee Appearance The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The Contracting Officer reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for required passes or badges.
Replace Generator and Associated Repairs
D - SECTION D - PACKAGING AND MARKING
(There are no Clauses in this Section)
Replace Generator and Associated Repairs
E - SECTION E - INSPECTION AND ACCEPTANCE
E.1 AGAR CONTRACT CLAUSES INCLUDED BY FULL TEXT:
AGAR 452.246-70 -- INSPECTION AND ACCEPTANCE
As prescribed in 446.370, insert the following clause:
INSPECTION AND ACCEPTANCE (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at: Madison, WI project site.
(End of clause)
E.2 FINAL INSPECTION:
(a) A final inspection shall be made only when all the materials have been furnished, all the work has been performed, and all the construction provided for by the contract in accordance with the terms has been completed. If, upon examination by the Contracting Officer and/or Government inspection personnel, the project is determined not sufficiently completed to have warranted a final inspection, the contractor may be charged with any additional cost of re-inspection when material and workmanship are not ready at the time specified by the Contractor for its inspection.
(b) The contractor shall give the Contracting Officer ten (10) calendar days advance notice, in writing, of the date the work will be fully completed and ready for final inspection.
(c) The Contractor's request for final inspection will not be approved unless all documentation required below, and all other contract requirements have been provided to the Contracting Officer:
-Guarantees and warranty schedule and contacts -Certified payroll records for all prime and subcontractor employees
(d) As soon as practicable, following final inspection, the Contracting Officer will inform the contractor, in writing, of any discrepancies and/or omissions noted at the final inspection. The Contracting Officer shall also state the time allowable for replacement of material and performance or re-performance o f any unsatisfactory work necessary for final acceptance.
E.3 FINAL ACCEPTANCE:
Upon written notification that all deficiencies identified during the final inspection have been corrected, the Contracting Officer will schedule a final acceptance inspection of the work. If all construction required by the contract is determined to be complete and all requisite contract deliverables (e.g., certified payroll records, as-built drawings, warranty documents, etc.) have been submitted and approved by the Government, the Contracting Officer shall notify the Contractor in writing of such acceptance. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
http://www.dm.usda.gov/procurement/policy/docs/AGAR_Updated_5May2016.pdf
Replace Generator and Associated Repairs
F - SECTION F - DELIVERIES OR PERFORMANCE
F.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:
FAR 52.211-10 -- Commencement, Prosecution, and Completion of Work.
As prescribed in 11.404(b), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated. The clause may be changed to accommodate the issuance of orders under indefinite-delivery contracts for construction.
Commencement, Prosecution, and Completion of Work (Apr 1984) The Contractor shall be required to
(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 330 days after the Notice to Proceed The time stated for completion shall include final cleanup of the premises.
(End of Clause) http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/11.htm#P198_30162
Replace Generator and Associated Repairs
G - SECTION G - CONTRACT ADMINISTRATION DATA
G.1 CONTRACTING OFFICER'S REPRESENTATIVE
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
The COR will be named at time of award.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers having been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers exceeding the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G.2 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS - INVOICE PROCESSING
PLATFORM (IPP):
Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform System (IPP). The IPP website address is: https://www.ipp.gov.
“Payment requests” means any request for contract financing payment or invoicing payment by the Contractor. To constitute a proper invoice, the payment request shall comply with FAR 52.232-27, Prompt Payment for Construction Contracts, and include the items listed in paragraphs (a)(2)(i) through (a)(2)(xi) of the clause.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3-5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
Attachments are required to be uploaded to IPP.gov.
https://www.ipp.gov/
Replace Generator and Associated Repairs
Prior to submitting an invoice to IPP.gov, the contractor is strongly encouraged to coordinate with the designated Contracting Officer’s Representative (COR), for review and verification of any measured quantities (if applicable) for payment and for compliance with the applicable progress payment requirements of this contract. Failure to do so, may cause a delay in approval and/or rejection of submitted invoices.
Pursuant to the payment terms contained in this contract, the contractor shall prepare and submit requests for payments (invoices) by following the instructions as described below:
1. To ensure timely processing of invoices under the contract/agreement, the contractor must submit all invoices to the following e-mail address:
joel.maas@usda.gov
2. A proper invoice shall be submitted by email concurrent with submission to IPP and shall include the information as required by the payment terms and conditions contained in this contract.
3. The subject line of the email shall be formatted to read as follows:
Contract Number, Invoice Number Example: 12905B20C0022 Invoice No. 1
4. The Invoice shall be attached to the email and named using the following format:
Contract Number, Contractor Name, Invoice Number, Invoice Amount Example: 12905B20C0022 Contractor ABC Inv No 1-$5,678.00
5. Invoices shall not include information that would compromise Personally Identifiable Information, such as full social security numbers, dates of birth, etc.
6. The final invoice shall be submitted and will be approved in accordance with the payment terms and conditions contained in the contract, after all, if any, settlement actions are complete. The contractor must clearly identify the last payment as the “Final Invoice”.
Emailed Support documents must include, but are not limited to, the following documents:
Invoices must be submitted with ARS-371 and ARS-372, along with certified payroll records, Contractor Certification, and updated CPM Schedule.
mailto:joel.maas@usda.gov
Replace Generator and Associated Repairs
H - SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:
AGAR 452.236-71 -- PROHIBITION AGAINST THE USE OF LEAD-BASED PAINT
As prescribed in 436.571, insert the following clause:
PROHIBITION AGAINST THE USE OF LEAD-BASED PAINT (NOV 1996)
Neither the Contractor nor any subcontractor performing under this contract shall use paints containing more than
0.06 of 1 percent lead by weight (calculated as lead metal) in the total nonvolatile content of the paint, or the equivalent measure of lead in the dried film of paint already applied, or both.
(End of Clause)
AGAR 452.236-72 -- USE OF PREMISES
As prescribed in 436.571, insert the following clause
USE OF PREMISES (NOV 1996)
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the camp site or trailer parking area of any employee working on the project for the Contractor.
(b) Unless excepted elsewhere in the contract, the Contractor shall(i)provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.
(End of Clause)
AGAR 452.237-74 -- KEY PERSONNEL (FEB 1988)
(a) The contractor shall assign to this contract the following key personnel: Title(s): Name(s):
Site Superintendent
(b) During the first ninety (90) days of performance, the contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-period, the contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.
Proposed substitutes should have comparable qualifications to those of the person(s) being replaced. The Contracting Officer will notify the contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
(End of Clause)
RESTRICTIONS AGAINST DISCLOSURE (FEB 1988)
(a) The Contractor agrees, in the performance of this contract, to keep all information contained in source documents or other media furnished by the Government in the strictest confidence. The Contractor also agrees not to publish or otherwise divulge such information in whole or in part in any manner or form, or to authorize or permit others to do so, taking such reasonable measures as are necessary to restrict access to such information while in the Contractor's possession, to those employees needing such information to perform the work provided herein, i.e., on a "need to know" basis. The Contractor agrees to immediately notify in writing, the Contracting Officer, named herein, in the event that the Contractor determines or has reason to suspect a breach of this requirement.
(b) The Contractor agrees not to disclose any information concerning the work under this contract to any persons or individual unless prior written approval is obtained from the Contracting Officer. The Contractor agrees to insert the substance of this clause in any consultant agreement or subcontract hereunder.
(End of Clause)
H.2 UTILITIES OUTAGE
Any interruption of utilities or services that would interfere with the operation of the facility will be permitted only
Replace Generator and Associated Repairs with prior written approval from the Contracting Officer. Any utilities or service connections made at other than normal working hours will be at no additional cost to the Government. Permission to make such an interruption shall be requested in writing to the Contracting Officer, at least three (3) days prior to the day of interruption. Failure by the Contractor to comply with this requirement will cause the Contractor to be subject to liability for actual damages.
H.3 COOPERATION WITH OTHER CONTRACTORS
During the period of construction for the work covered by this contract, other contractors performing work for the Government may be operating concurrently at the site. To minimize interference and delay to the construction progress of all concerned, all contractors shall cooperate with each other and coordinate their construction operations to the fullest extent. As far as practicable, all contractors performing work for the Government at the site shall have equal rights to the use of all referenced facilities. In a dispute regarding the use of such facilities, the matter shall be referred to the Contracting Officer.
H.4 SUBMITTALS AND SHOP DRAWINGS
(a) The Contractor shall submit for approval, shop drawings of all manufactured products required in the construction for which such drawings are hereinafter required. When approved, one set will be retained; one set forwarded to the Government representative on the job and two sets forwarded to the Contractor. When changes or corrections are necessary, two sets will be returned to the Contractor with such corrections noted thereon, and he shall resubmit revised prints.
(b) Shop drawings shall be marked with the contract number and Work Order Number, project description, name of the Contractor, and accompanied by a letter of transmittal. If the shop drawings show variations from the contract requirements because of standard shop practice or other reason, the Contractor shall make specific mention of such variations in his letter of transmittal.
(c) Approval of shop drawings will be general and will not relieve the Contractor from the responsibility of furnishing material and work required by the contract.
(d) Shop drawings shall be submitted for approval in ample time to permit checking of the drawings, allow the Contractor to make any corrections and resubmit drawings prior to the time construction is started on work covered by any drawings.
(e) Non-approval of equipment due to failure to meet specifications, or non-approval of the Contractor’s drawings due to submission of incomplete or incorrect information cannot be considered as a basis for extension of time for completion of the contract.
(f) The quantity of shop drawings required are subject to change. This will occur only when the Government is under contract with an A-E firm to approve shop drawings. In this respect, A-E will coordinate final quantity required between all interested parties.
H.5 LIST OF MATERIALS
(a) The Contractor shall submit for approval a complete list, in duplicate, of brands, type, and make of various equipment and materials proposed to be used. If the Contractor fails to submit such a list, or names of equipment which does not comply with the specifications, or if the manufacturers named are unsatisfactory, the Government reserves the right to reject same and to select satisfactory substitute materials. This selection shall be final and binding upon the Contractor, and the work shall be installed on this basis without change in contract price.
(b) In order to properly identify and to prove compliance with the requirements of the specifications, the Contractor shall give the following data for each product included in the list of materials.
Section heading of the specifications under which material is specified.
Manufacturer’s name and address.
Grade, type, trade or catalog number.
Size, capacity, and other pertinent data.
Compliance with Buy American Act and Bio-preferred
(c) All materials, fixtures, and equipment furnished and installed under this contract shall be new and of the best quality; shall be standard cataloged products or reputable manufacturers products or of special manufacture, satisfying completely the contract requirements.
(d) Similar items, unless otherwise specified herein or approved by the Contracting Officer, shall be the product of the same manufacturer, and those fulfilling the same requirements as to size and construction shall be identical.
(e) Substitutions and/or Approved Equal: Where particular make, brand or type of material or equipment is
Replace Generator and Associated Repairs mentioned in these specifications, it is to denote quality standard of article desired, but does not restrict contractor to brand specified; however, any substitution must be met with approval of the Contracting Officer. Other products comparable in type, quality, utility, and price are acceptable if approved by the Contracting Officer. Burden of proof of equality shall rest with the Contractor. The Contracting Officer shall be sole judge of paralleled quality.
H.6 PROPERTY DAMAGE LIABILITY INSURANCE
The Contractor shall ensure that the property damage liability insurance policy (or rider) required by FAR 52.228-5, Insurance-Work on a Government Installation, is in full compliance with all the terms and conditions of this contract.
The policy shall not contain any exclusions or exceptions that would limit or adversely affect the Government’s rights and remedies under any other clause in this contract or other Federal regulation or law. Should there be any exclusions or exceptions contained in the policy that limits or adversely affects the Government’s rights, the Contractor shall be responsible for the full amount of any damages that occur to the immediate facilities, adjacent facilities/property, and other Government property under the control of the Contractor due to fraud, negligence, vandalism, willful misconduct, or violation of Federal, state, or local safety regulations, building codes and laws. The Contractor shall have full responsibility and is liable for these facilities and properties until the Government has accepted the contract as being completed in full and a release from claims has been received from the Contractor.
For those areas where the Government has taken "beneficial occupancy" prior to completion and acceptance of the whole contract, the contractor shall not be responsible for those specific areas under Government control, except in such instances where damage occurs to those areas as a result of negligence, fraud, vandalism, willful misconduct, or violation of Federal, state, or local safety regulations, building codes, or laws in those areas under the control of the Contractor.
This liability and responsibility includes the activities of all the Contractor’s personnel, their subcontractors and suppliers.
H.7 SUBCONTRACTORS, OUTSIDE ASSOCIATES AND CONSULTANTS
Any subcontractors, outside associates or consultants required by the Contractor in connection with the services covered by the contract will be limited to individuals or firms that were specifically identified at time of award or agreed upon during negotiations. The Contractor shall obtain the Contracting Officer’s written consent before making any substitution for these individuals or firms.
Replace Generator and Associated Repairs
I - SECTION I - CONTRACT CLAUSES
PART II - CONTRACT CLAUSES
I.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:
FAR 52.204-21 -- Basic Safeguarding of Covered Contractor Information Systems.
As prescribed in 4.1903 , insert the following clause:
BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)
(a) Definitions. As used in this clause– Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.
Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).
Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
Safeguarding means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures.
(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements.This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems
Replace Generator and Associated Repairs generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.
(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.
(End of clause)
FAR 52.217-7 -- Option for Increased Quantity-Separately Priced Line Item.
As prescribed in 17.208(e), insert a clause substantially the same as the following:
OPTION FOR INCREASED QUANTITY-SEPARATELY PRICED LINE ITEM (Mar 1989) The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 90 days after contract award.
Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
FAR 52.222-35 -- Equal Opportunity for Veterans.
As prescribed in 22.1310(a)(1), insert the following clause:
Equal Opportunity for Veterans (Jun 2020)
(a) Definitions. As used in this clause-- “Active duty wartime or campaign badge veteran,” “Armed Forces service medal veteran,” “disabled veteran,” “protected veteran,” “qualified disabled veteran,’ and “recently separated veteran” have the meanings given at Federal Acquisition Regulation (FAR) 22.1301.
(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-300.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified protected veterans and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.
(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts valued at or above the threshold specified in FAR 22.1303(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of Clause) Alternate I (Jul 2014). As prescribed in 22.1310(a)(2), add the following as a preamble to the clause:
Notice: The following term(s) of this clause are waived for this contract: _____________________ [List term(s)].
FAR 52.222-36 – Equal Opportunity for Workers With Disabilities As prescribed in 22.1408(a), insert the following clause:
Equal Opportunity for Workers With Disabilities (Jun 2020)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60.741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of the threshold specified in Federal Acquisition Regulation (FAR) 22.1408(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance.
Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of clause) https://www.acquisition.gov/?q=/browse/far/22 https://www.acquisition.gov/?q=/browse/far/22 https://www.acquisition.gov/?q=/browse/far/22 https://www.acquisition.gov/?q=/browse/far/22
Replace Generator and Associated Repairs
Alternate I (Jul2014).As prescribed in 22.1408(b), add the following as a preamble to the clause:
Notice: The following term(s) of this clause are waived for this contract: _______________ [List term(s)].
FAR 52.223-20 – Aerosols.
As prescribed in 23.804(a)(3), insert the following clause:
Aerosols (Jun 2016)
(a) Definitions. As used in this clause-- “Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide’s global warming potential is defined as 1.0.
“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G. with supplemental tables of alternatives available at http://www.epa.gov/snap/).
“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.
(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, or emissions of high global warming potential hydrofluorocarbons, when feasible, from aerosol propellants or solvents under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as--
(1) In-use emission rates, energy efficiency;
(2) Safety, such as flammability or toxicity;
(3) Ability to meet technical performance requirements; and
(4) Commercial availability at a reasonable cost.
(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap/.
FAR 52.223-21 -- Foams.
As prescribed in 23.804(a)(4), insert the following clause:
Foams (Jun 2016)
(a) Definitions. As used in this clause– “Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide's global warming potential is defined as 1.0.
“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82 subpart G with supplemental tables of alternatives available at http://www.epa.gov/snap/.
“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.
(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, and emissions of high global warming potential hydrofluorocarbons and refrigerant blends containing hydrofluorocarbons, when feasible, from foam blowing agents, under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as–
(1) In-use emission rates, energy efficiency, and safety;
(2) Ability to meet performance requirements; and
(3) Commercial availability at a reasonable cost.
(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82 subpart G with supplemental tables available at http://www.epa.gov/snap/.
FAR 52.225-9 -- Buy American–Construction Materials.
As prescribed in 25.1102(a), insert the following clause:
Buy American-Construction Materials (Nov 2021)
(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item— http://farsite.hill.af.mil/reghtml/Regs/far2afmcfars/fardfars/Far/23.htm#P364_49080 http://www.epa.gov/snap/ http://www.epa.gov/snap/ https://www.acquisition.gov/far/html/Subpart%2023_8.html#wp1073926 http://www.epa.gov/snap/ http://www.epa.gov/snap/ https://www.acquisition.gov/far/part-25#FAR_25_1102
Replace Generator and Associated Repairs
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
https://www.acquisition.gov/far/part-2#FAR_2_101
Replace Generator and Associated Repairs
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is…