This document contains the project specifications for the Fort Cronkhite Drainage project at the Golden Gate National Recreation Area in Sausalito, California. The project consists of drainage improvements to reduce water damage to historical buildings, including installing French drains around selected building foundations, revegetating disturbed areas, and potentially installing roof eaves gutters and downspouts. The work is to be completed in three phases over an estimated 60-day period, with the vegetation installation and watering occurring during a specific planting window. The contractor will receive government-furnished materials, including grass plugs for the revegetation. Detailed requirements are provided for the work, site use, occupancy, safety, and environmental management. Options are included for the contractor to bid on installing roof gutters and downspouts. The solicitation number is 140P8624Q0023, issued by the National Park Service Pacific West Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Section_J_-_Att_No__006_Site_Visit_Sign_In_Sheet_0003.pdf | ||
| Sol_140P8624Q0023_Amd_0003.pdf | ||
| Sol_140P8624Q0023_Amd_0002.pdf | ||
| Sol_140P8624Q0023_Amd_0001.pdf | ||
| Sol_140P8624Q0023.pdf | ||
| Section_J_-_Att_No__003_Maps.pdf | ||
| Section_J_-_Att_No__004_WD__CA20240007_Mod_12.pdf | ||
| Section_J_-_Att_No__001_Contract_Price_Schedule.xlsx | XLSX spreadsheet | |
| Section_J_-_Att_No__005_Technical_Information.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GOLDEN GATE NATIONAL RECREATION AREA
SAUSALITO, MARIN COUNTY, CALIFORNIA
FORT CRONKHITE DRAINAGE PROJECT
GOGA
PMIS Number 225134
PROJECT SPECIFICATIONS
ISSUED FOR CONSTRUCTION (IFC)
June 4, 2024
NATIONAL PARK SERVICE (NPS)
RFQ 140P8624Q0023
Section J - Att No. 002
Table of Contents (TOC)
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 26 01 Contract Modification Procedures
01 27 00 Definition of Contract Line Items
01 31 00 Project Management and Coordination
01 32 16 Construction Schedule
01 33 23 Submittal Procedures
01 35 13.22 Archeological Protection
01 35 23 Safety Requirements
01 40 00 Quality Requirements
01 42 00 Reference Standards
01 50 00 Temporary Facilities and Controls
01 57 19.12 Noise and Acoustics Management
01 57 23 Temporary Storm Water Pollution Prevention (UPPP) Under-an-Acre
01 67 00 Product Requirements
01 67 01 Imported Soil
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
01 89 31 Soils Management
DIVISION 02 – SITE
02 41 00 Demolition
02 62 00 Concrete Walks
DIVISION 03 – CONCRETE
03 30 00 Cast-In-Place Concrete
DIVISION 07 – SHEET METAL
07 71 23 Manufactured Gutters & Downspouts
DIVISION 31 – EARTHWORK
31 00 00 Earthwork
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 92 00 Revegetation
DIVISION 33 – FRENCH DRAIN
33 46 00 French Drain
APPENDIX A
CATEGORICAL EXCLUSION (CE) AND STANDARD OPERATING PROCEDURES (SOP)
National Environmental Policy Act (NEPA) - Categorical Exclusion (CE) 9/19/23
Ft. Cronkhite Drainage – PMIS #225134
051121
01 11 00 -
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Phases
3. Work Under Other Contracts
4. Government-Furnished Materials
5. Contractor Use of Site
6. Public Use of Site
7. Occupancy Requirements for Buildings
8. Conduct of Operations
9. Work Restrictions
10. Special Construction Requirements
11. Soils Investigation Report
12. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Fort Cronkhite Golden Gate National Recreation Area near Rodeo
Cove/Beach/Lagoon along Mitchell Road in Sausalito, Marin County, California.
B. The Work consists of:
1. Drainage improvements to reduce water damage to historical buildings. Install French
Drains around selected building foundations and revegetate disturbed area. Optional task to install roof eaves gutters and downspouts to channelize stormwater to underground piping. Minor grading to direct building parking area stormwater to underground piping.
C. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in three (3) phases:
1. Phase 1 includes preparing site, receiving construction equipment, storing construction materials, excavation and installation of French Drain, install optional roof eave gutters and downspouts, site grading to direct stormwater to underground drainage system, placing straw mulch, and reinstalling sidewalks and other infrastructure removed to install the specified work. This work should be completed within 60 days after Notice to Proceed
(NTP).
2. Phase 2 includes preparing the site to receive the vegetation, receiving the vegetation from the NPS supplier, storing the vegetation (if necessary), planting the vegetation, and site cleanup. This work shall be conducted during the period of November 1st to March 1st.
01 11 00 -
3. Phase 3 includes watering the vegetation once per month during the specified time period. Work of this phase shall be after the vegetation is planted until the following October 15th.
1.4 WORK UNDER OTHER CONTRACTS
A. No other associated contracts.
1.5 GOVERNMENT-FURNISHED MATERIALS
A. In case of Government -furnished materials:
1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.
2. Contractor is responsible for initial inspection, receiving, unloading, and handling
Government-furnished items at Project site.
3. Government will inspect delivered items for damage after delivery. Contractor shall be present for and assist in Government's inspection.
4. Government will arrange for replacement if Government-furnished items are damaged, defective, or missing.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged because of Contractor's operations, Contractor shall repair or replace them.
7. Contractor shall install and otherwise incorporate Government-furnished items into the work.
B. Government-Furnished Materials:
1. Vegetation: The Government will furnish “Grass Plugs” for installation within project area.
Grass Plugs include a mixture of Red Fescue, Needle Grass Yarrow, and Aster which are grown in stubby leach tubes. Contractor is to receive Grass Plugs from the NPS supplier and install. If there is a period between receiving and installing the grass plugs, the contractor is to store the grass plugs in the manner recommended by the NPS supplier.
Soil preparation includes a dressing of straw applied before the Grass Plugs are planted to keep the weeds down.
1.6 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
01 11 00 -
B. General: Contractor shall have limited use of site for construction operations. Limit use of premises to work in areas indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to 20-feet of each side of pipes shown in work areas.
2. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.
C. Storage of Materials: Allowed at the roads and trails storage area located above the site. Contractor must give Contracting Officer 3-days advanced notice before storing materials at this location.
D. Parking: Contractor's employee work force is allowed to park personal passenger vehicles in designated parking spaces within park, especially parking lot just west of the project site.
E. Stockpiling: Allowed at the roads and trails storage area located above the site. Contractor must give Contracting Officer’s Representative (COR) 3-days advanced notice before stockpiling materials at this location.
F. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
COR and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
G. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government employees, and emergency vehicles always. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
H. Construction Camp: Establishment of a camp within park will not be permitted.
I. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
01 11 00 -
J. Bridge and Tunnel Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
1.7 PUBLIC USE OF SITE
A. The Park will be open to the public during construction.
B. Contractor shall conduct his operations to ensure the least inconvenience to public.
1. Contractor’s Option - contractor is allowed to temporarily close Kirkpatrick Street upon adequate notice to NPS and contracting officer. NPS to review and approve contractor's requested closure schedule.
2. Kirkpatrick Street closure could be secured by temporary gates on both ends, at contractor's cost. NPS to review and approve contractor's notification signs placed on gates.
3. Orange-colored (ESA-type) safety fencing with construction warning signs would be placed behind buildings 1065, 1066, 1067, 1069, 1070, 1077, and 1044. See plans for locations.
4. Contractor’s Option - contractor is allowed to temporarily close buildings 1065, 1066, 1067, 1068, 1069, 1070, 1077, and 1044, upon adequate notice to NPS and contracting officer. NPS to review and approve contractor's requested closure schedule. NPS to review and approve contractor's notification signs placed on buildings.
1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Full Government Occupancy: Government will occupy buildings near construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from COR.
b. Maintain existing building in weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and occupants during construction period.
2. Partial Government Occupancy: Government will occupy premises during entire construction period, with exception of areas under construction. Cooperate with
Government during construction operations to minimize conflicts and facilitate
Government usage. Perform Work so as not to interfere with Government’s operations.
Maintain existing exits, unless otherwise indicated.
01 11 00 -
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from COR.
1.9 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Contractor shall comply with the Categorical Exclusions listed in Appendix A.
C. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the COR. Submit requests 3 business/calendar days in advance of the work to the
COR for approval.
D. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the COR.
1.10 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: No weekend work unless submitted to COR for approval beforehand.
B. Existing Utilities
1. Existing Utilities: Notify COR and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify COR not less than three (3) business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without COR’s written permission.
3. Hours and length of Utility Shutdowns: Dependent on Utility disposition.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within
25 feet of entrances, operable windows, or outdoor air intakes.
01 11 00 -
1.11 SPECIAL CONSTRUCTION REQUIREMENTS
A. None
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
012721
01 26 01 - 11
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 MODIFICATION QUOTE PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Quote (RFQ) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of
Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement.
3. Requests for extensions of contract time as a result of change must be justified with a
Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
01 26 01 - 12
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense
Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army
Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in
01 26 01 - 13 this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead ....................... 10%
Profit .............................. 10%
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 01 26 01
01 27 00 - 14
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
3.1 LIST OF CONTRACT LINE ITEMS
All quantities given are estimates and should be verified by the Contractor.
3.1.1 Contract Line Item 1 - Phase 1
A. 4" Diameter Perforated Pipe (French Drain)
1. This item consists of furnishing and installing perforated pipe section of French Drain installation.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity required is 530 linear feet.
B. 4" Diameter Solid Pipe (French Drain)
1. This item consists of furnishing and installing solid pipe section of French Drain installation.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity required is 83 linear feet.
C. Mitered Drain Grate (French Drain Outfall)
1. This item consists of furnishing and installing the outfall pipe section of French Drain installation.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity required is 5 each.
D. 3/4" Drain Rock (French Drain)
1. This item consists of furnishing and installing drain rock portion of French Drain installation.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity required is 44 cubic yards.
01 27 00 - 15
E. Crushed Rock @ 3" Depth (French Drain)
1. This item consists of furnishing and installing crushed rock portion of French Drain installation.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity required is 7 cubic yards.
F. Geotextile Filter Fabric (French Drain)
1. This item consists of furnishing and installing filter fabric wrapping for French Drain installation.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity required is 3,345 square feet.
G. Native Soil Backfill (French Drain)
1. This item consists of installing native soil backfill for French Drain installation.
1. Measurement for payment will be by checking conformation to drawings and specifications.
2. Payment will be made at the contract lump sum price.
3. Estimated quantity required is 8 cubic yards.
H. Clean Existing French Drain at Building 1068
1. This item consists of cleaning and making functional the existing French Drain at the location specified.
1. Measurement for payment will be by checking conformation to drawings and specifications.
2. Payment will be made at the contract lump sum price.
3. Estimated quantity to clean is 95 linear feet.
I. Concrete Sidewalk Removal & Replacement
1. This item consists of removing and replacing the sidewalk over new French Drain installation.
1. Measurement for payment will be by checking conformation to drawings and specifications.
2. Payment will be made at the contract lump sum price.
3. Estimated quantity to remove and replace is 167 square feet.
J. Earth Excavation
1. This item consists of excavating earth for French Drain installation.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity is 55 cubic yards.
K. Soil Testing (One per every 10 CY of Excavation)
1. This item consists of texting excavated soil preparing for French Drain installation.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity is 6 each.
L. Disposal of Contaminated Soil
1. This item consists of disposing of contaminated soil that is estimated during Design Phase
01 27 00 - 16 for possible implementation during construction. Contaminated soil determined by Soil
Testing.
1. Measurement for payment will be by checking conformation to drawings and specifications.
2. Payment will be made at the contract lump sum price.
3. Estimated quantity is 46 cubic yards.
M. Straw Blanket
1. This item consists of soil preparation for Grass Plug installation and furnishing and installing straw blanket.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity is 2,358 square feet.
N. Safety Fencing
1. This item consists of furnishing and installing site safety fencing at areas shown on plans.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity is 1,722 linear feet.
O. Construction Signs
1. This item consists of furnishing and placing construction signs at various locations within project site.
2. Measurement for payment will be by checking conformation to drawings and specifications.
3. Payment will be made at the contract lump sum price.
4. Estimated quantity is 10 each.
3.1.2 Contract Line Item 2 - Phase 2
A. Revegetation
1. This item consists of obtaining and installing planting plugs. Contractor to receive planting plugs from NPS Supplier, store appropriately, and install in areas shown on plans.
1. Measurement for payment will be by checking conformation to drawings and specifications.
2. Payment will be made at the contract lump sum price.
3. Estimated quantity is 262 each.
3.1.3 Contract Line Item 3 - Phase 3
A. Vegetation Watering
1. This item consists of watering each vegetation plug one time per month from March 1 after the time of planting until the following date of October 15.
4. Measurement for payment will be by checking conformation to drawings and specifications.
5. Payment will be made at the contract lump sum price.
6. Estimated quantity is 8 waterings.
3.1.3 Optional Items
A. Optional Items for Contractor Bidding
1. Contract Line Item 4, Optional Item - Eaves Gutters
01 27 00 - 17
a. This item consists of furnishing and installing eaves gutters along section of existing building roof line.
b. Measurement for payment will be Linear Feet.
c. Payment will be made at the contract price per linear foot.
d. Estimated quantity is 551 linear feet.
2. Contract Line Item 5, Optional Item - Downspouts (10' Segments)
a. This item consists of furnishing and installing downspouts connected to eaves gutters mounted to existing building surface.
b. Measurement for payment will be Linear Feet.
c. Payment will be made at the contract price per linear foot.
d. Estimated quantity is 60 linear feet.
3. Contract Line Item 6, Optional Item - Splash Pad/Downspout Filter
a. This item consists of furnishing and installing splash pads and downspout filters at the stormwater exit from downspouts into French Drain system.
b. Measurement for payment will be Each.
c. Payment will be made at the contract price per each.
d. Estimated quantity is 6 each.
END OF SECTION 01 27 00
042123
01 31 00 - 18
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. Project Meetings
7. Environmental Coordination
8. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1.3 SUBMITTALS
A. As-Built Drawings: Submit as-built drawings as part of the close-out procedures.
B. Division 1 documents:
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Safety Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
01 31 00 - 19
9. Quality Control Plan
10. Temporary Under an Acre Pollution Prevention Plan (UPPP)
C. Provide items listed to Contracting Officer at least one week prior to Pre-Construction
Conference, or as directed by Contracting Officer.
1. Failure to submit items may result in:
a. Construction conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies.
b. Work shall not commence until written Notice to Proceed has been issued and
Certificates of Insurance and SF1413 documents are received for Contractor and all
Subcontractors.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of
Contract Documents, Contractor shall prepare and submit a RFI form available at https://www.nps.gov/dscw/con_rfi217.htm or may use the Contractor’s own form that at a minimum contains the same information.
1. COR will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. COR’s Action: COR will review each RFI, determine action required, and respond. COR will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
01 31 00 - 20
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. COR's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. COR's action on RFIs may result in need for a change to Contract Time or Contract Sum.
All contract changes will be processed following terms and conditions of contract.
1.5 PROJECT COMMUNICATIONS
A. Communications will be by email, phone and online meeting software. Contractor may use their own software or website. Contractor shall give NPS access to the software without NPS having to purchase a license or download anything to access it. NPS shall be able to download reports in pdf or Word format and not in documents that need special access to the software to read.
Website must also be compatible with government security, (example: Dropbox is not accessible on government systems).
1. Project directory
2. Project correspondence
3. Meeting agendas and minutes
4. Contract modifications forms and logs
5. RFI form and processing
6. Task and issue management
7. Photo documentation
8. Baseline schedule, schedule updates and calendar management
9. Submittal form and processing
10. Payment coordination documentation
11. Drawing and specification document hosting, viewing, and updating
12. Online document collaboration
13. Reminder and tracking functions
14. Archiving functions
15. Notification of submittal and RFI statuses and current responsible party
16. Permits and addendums
B. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using unsecured means.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange a meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
01 31 00 - 21
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. NPS/DSC Project website
17. Acceptance/rejection of work
18. Progress meetings
19. Submittal procedures
20. NPS Final Accessibility Inspection
21. Environmental requirements
22. Permit requirements
23. As-constructed drawings/operation and maintenance (O&M) manuals.
24. Saturday, Sunday, holiday and night work.
25. Reference materials
26. Value engineering
27. Schedule of Values
B. Progress Meetings: COR will schedule regular meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the
Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, may attend meeting. Advise COR of
01 31 00 - 22 scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
x. Protection of adjacent work
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing
Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; experienced with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, 01 31 00 - 23 including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Storm Water Pollution Prevention Plan (SWPPP).
d. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
e. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Noise and Acoustics Management
4. Temporary Storm Water Pollution Prevention Environmental Management
5. Construction Waste Management
C. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, and Storm Water Pollution Prevention Plan.
1.8 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the
Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the
Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. Approval of Storm Water Plan will be required by COR. The Agency(ies) with Jurisdiction for this permit is NPS.
2. Approval of Safety Plan by NPS Safety Officer.
C. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist
Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work.
Only “permits” anticipated to be required will be NPS approval of Storm Water Plan and Safety Plan.
01 31 00 - 24
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
01 32 16 - 1
CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and
Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.
1.2 DEFINITIONS
A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.
E. Float: Measure of leeway in starting and completing an activity.
1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.
2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
01 32 16 - 2
3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.
F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
A. Electronic Copies: Contractor to make all submittal electronically (via email or granted access to their self-operated software). No paper copies needed. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.
B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit the baseline schedule, to show entire schedule for entire construction period. Utilize
Schedule of Values in preparation of Construction Baseline Schedule.
D. Critical Path Method (CPM) Reports: Concurrent with CPM schedule, submit the report showing enough detail to be relevant.
E. Construction Schedule Updates: On or before 7th day preceding progress payment request date, submit estimates of percent completion of each schedule activity and necessary supporting data.
F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision, submit a Time Impact Analysis. Incorporate a Fragmentary Network (Fragnet) into currently accepted Construction Schedule that demonstrating how Contractor proposes to incorporate a modification, change, delay, or Contractor request.
1.4 QUALITY ASSURANCE
A. Contractor shall meet with COR if schedule is changed or impacted by other circumstances.
B. Contractor's Schedule Representative: Before the preconstruction conference, designate an authorized representative to be responsible for preparing and maintaining the Construction
Schedule.
1.5 COORDINATION
A. Coordinate Construction Baseline Schedule with Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing Construction Baseline Schedule, ensure Subcontractor’s work at all tiers, and prime Contractor’s work, is included and coordinated.
01 32 16 - 3
2. Secure time commitments for performing critical elements of work from parties involved.
3. Coordinate each construction activity in network with other activities and schedule in proper sequence.
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested. Work activities broken out within schedule of values shall be integrated into and made a logical part of the construction baseline schedule. Total costs for the component work activities shall equal contract price for that lump-sum item. Contracting
Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. Total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments and the Construction Schedule.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a cost and resource-based, time-scaled Critical Path Method network analysis diagram for the Work.
1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing work within applicable completion dates, regardless of Governments acceptance of schedule.
2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using preliminary Critical Path Method network diagram, prepare a skeleton network to identify probable critical paths.
1. Milestones: Include milestones indicated in Contract Documents in schedule, including, but not limited to, Notice to Proceed, and Substantial Completion.
01 32 16 - 4
3.1 CONSTRUCTION SCHEDULE UPDATES
A. Monthly Schedule Updates:
1. General: Update Construction Schedule on monthly basis to reflect construction progress and activities throughout entire contract period and until project substantial completion..
3.2 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DELAYS
AND CONTRACTOR REQUESTS:
1. Requirements: When contract modifications or changes are initiated, delays experienced, or Contractor desires to revise currently accepted Construction Schedule, Contractor shall submit to COR a written time impact analysis illustrating the influence of modification, change, delay, or Contractor request on contract time.
2. Time Extensions: Activity delays, resulting in a late completion date projection, shall not automatically mean an extension of contract time is warranted or due to Contractor. It is possible a modification, change, or delay will not affect existing critical path activities orcause non-critical activities to become critical. A modification, change, or delay may result in absorbing a part of available total float that may exist within an activity chain of the Schedule, not causing any effect on contract time. Time extensions will be granted in accordance with terms of contract.
3. Extension of contract time will be granted only to the extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.
4. Procedure: Each time impact analysis shall be submitted within time period stated in a request for proposal, or time period designated under the clauses entitled Changes or
Default. In cases where Contractor does not submit a written request for extension of time and a time impact analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract time. Upon acceptance, time impact analysis shall be incorporated into currently accepted Construction Schedule at next monthly schedule update.
5. Contract Modifications: Prepare time-impact analysis using fragnets to demonstrate effect of proposed change on overall Construction Schedule for each proposed contract modification concurrent with submission.
END OF SECTION 01 32 16
101921
01 33 23 - 1
SUBMITTAL PROCEDURE
SECTION 01 33 23 - SUBMITTAL PROCEDURES
A. Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
A.…
This is the start of the file's text. The full file is on GovTribe.