Section_J_-_Att_No__001_Contract_Price_Schedule.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- FORT CRONKHITE DRAINAGE Federal contract opportunity
- Solicitation number
- 140P8624Q0023
About this file
This document is a Contract Price Schedule template for a federal contract opportunity related to drainage improvements at the Fort Cronkhite area of the Golden Gate National Recreation Area, managed by the National Park Service's Pacific West Region.
The template includes a list of 16 base line items with detailed pricing information, such as 4" perforated and solid drainage pipe, drain rock, geotextile fabric, concrete sidewalk removal and replacement, and revegetation work. It also includes 3 option line items for eaves gutters, downspouts, and splash pad/downspout filters. The total base price for the 16 line items is $187,224.92, and the total price for the base plus all options is $222,081.57. Offerors are required to submit pricing for the base and all option line items.
The related federal contract opportunity has a solicitation number of 140P8624Q0023 and is for the "Fort Cronkhite Drainage" project, to be awarded by the Department of the Interior's National Park Service, Pacific West Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8624Q0023_Amd_0003.pdf | ||
| Section_J_-_Att_No__006_Site_Visit_Sign_In_Sheet_0003.pdf | ||
| Sol_140P8624Q0023_Amd_0002.pdf | ||
| Sol_140P8624Q0023_Amd_0001.pdf | ||
| Sol_140P8624Q0023.pdf | ||
| Section_J_-_Att_No__002_Specifications.pdf | ||
| Section_J_-_Att_No__003_Maps.pdf | ||
| Section_J_-_Att_No__005_Technical_Information.pdf | ||
| Section_J_-_Att_No__004_WD__CA20240007_Mod_12.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Template
| Contract Price Schedule | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | TBD | ||||
| PARK - PMIS: | GOGA - 225134 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Fort Cronkhite | ||||
| Project Title: | Fort Cronkhite Drainage Improvements | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | 4" Diameter Perforated Pipe (French Drain) | 530 | Linear Feet (LF) | $31.56 | $16,725.81 |
| 2 | 4" Diameter Solid Pipe (French Drain) | 83 | Linear Feet (LF) | $32.93 | $2,733.21 |
| 3 | Mitered Drain Grate (French Drain Outfall) | 5 | Each (EA) | $186.60 | $933.02 |
| 4 | 3/4" Drain Rock (French Drain) | 44 | Cubic Yards (CY) | $1,185.49 | $52,161.48 |
| 5 | Crushed Rock @ 3" Depth (French Drain) | 7 | Cubic Yards (CY) | $312.84 | $2,189.86 |
| 6 | Geotextile Filter Fabric (French Drain) | 3,345 | Square Feet (SF) | $8.23 | $27,537.91 |
| 7 | Native Soil Backfill (French Drain) | 8 | Cubic Yards (CY) | $60.37 | $482.98 |
| 8 | Clean Existing French Drain at Building 1068 | 95 | Linear Feet (LF) | $8.23 | $782.09 |
| 9 | Conc Sidewalk Removal & Replacement | 167 | Square Feet (SF) | $54.88 | $9,165.58 |
| 10 | Earth Excavation | 55 | Cubic Yards (CY) | $359.49 | $19,771.86 |
| 11 | Soil Testing (One per every 10 CY of Excavation) | 6 | Each (EA) | $139.95 | $839.72 |
| 12 | Disposal of Contaminated Soil | 46 | Cubic Yards (CY) | $315.58 | $14,516.74 |
| 13 | Straw Blanket (Revegetation) | 2,358 | Square Feet (SF) | $3.29 | $7,764.95 |
| 14 | Planting Plugs (Revegetation) | 262 | Each (EA) | $46.65 | $12,222.60 |
| 15 | Safety Fencing | 1,722 | Linear Feet (LF) | $10.75 | $18,518.96 |
| 16 | Construction Signs | 10 | Each (EA) | $87.81 | $878.14 |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 16) --------------------------------------------------------------------------------- | $187,224.92 | ||||
| 17 | Eaves Gutters | 551 | Linear Feet (LF) | $57.63 | $31,752.97 |
| 18 | Downspouts (10' Segments) | 60 | Linear Feet (LF) | $48.02 | $2,881.40 |
| 19 | Splash Pad/Downspout Filter | 6 | Each (EA) | $37.05 | $222.28 |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 17 through 19) ----------------------------------------------------------- | $34,856.65 |
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 19) -------------------------- | $222,081.57 |
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
Price Schedule Template (2)
| Contract Price Schedule | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | TBD | ||||
| PARK - PMIS: | GOGA - 225134 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Fort Cronkhite | ||||
| Project Title: | Fort Cronkhite Drainage Improvements | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Phase 1 - Install French Drains and Site Grading | 1 | Lump Sum | $XXXXXXXXXXXXX | $ |
| 2 | Phase 2 - Revegetation | 1 | Lump Sum | $XXXXXXXXXXXXX | $ |
| 3 | Phase 3 - Vegetation Watering | 1 | Lump Sum | $XXXXXXXXXXXXX | $ |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 3) ------------------------------------------------------------------------------------- | $ | ||||
| 4 | Eaves Gutters | 551 | Linear Feet (LF) | $ | $ |
| 5 | Downspouts (10' Segments) | 60 | Linear Feet (LF) | $ | $ |
| 6 | Splash Pad/Downspout Filter | 6 | Each (EA) | $ | $ |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 4 through 6) ----------------------------------------------------------- | $ | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 6) -------------------------- | $ | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |