SCOPE OF WORK

ENVIRONMENTAL CONSULTING SERVICES

MUIR WOODS NATIONAL MONUMENT REDWOOD RENEWAL

MUWO – PMIS # 319872

CALIFORNIA CONSTRUCTION GENERAL PERMIT COMPLIANCE SERVICES

Prepared by: Tommy Daigle

ARTICLE I. GENERAL INFORMATION

In accordance with the terms and conditions of the GSA Federal Supply Schedule, the Consultant shall perform the work for the National Park Service (NPS) as described herein.

A. Performance Period: The work shall be provided from approximately September 1, 2022 through April 30, 2025

The work shall consist of the services described herein for the referenced project.

B. Location: The project is located at Muir Woods National Monument, Mill Valley, Marin

County California.

C. Project Identification: The project shall be referred to as Muir Woods SWPPP Services

PMIS # 319872 and listed on all project correspondence and submittals.

ARTICLE II. PROJECT BACKGROUND AND PURPOSE

A. Background:

The National Park Service (NPS) through administration at Golden Gate National

Recreation Area (GGNRA) is in the process of implementing construction projects at

Muir Woods National Monument (MUWO). MUWO is a unit of GGNRA consisting of old growth redwood trees, threatened and endangered (T&E) species, their critical habitat, and many other species. The T&E species potentially present in MUWO are

Coho Salmon, Steelhead Trout, California Red Legged Frogs, Marbled Murrelets, and

Northern Spotted Owls.

The State Water Resources Control Board lists Redwood Creek as a Class 1 creek with beneficial uses of cold freshwater habitat, fish spawning, and fish migration. This information is relevant to the SWPPP as it means the receiving water is a sensitive water body and it increases the risk level for traditional construction projects and for some

LUPs to risk level 2 or 3.

MUWO is a sensitive environment visited by millions of people each year. The park will remain open during construction. The visitors and surrounding community demand the utmost care from the NPS and our contractors while operating in Muir Woods. The public was involved in the planning process for the projects and will remain active during project implementation.

There are construction projects beginning in the Summer of 2023.

These projects all require coverage under the National Pollutant Discharge Elimination

System (NPDES) General Permit for Storm Water Discharges Associated with

Construction and Land Disturbance Activities Adopted Order 2009-0009-DWQ (As amended by 2010-0014-DWQ and 2012-0006-DWQ) (the Construction General Permit or CGP), and associated Stormwater Pollution Prevention Plans (SWPPP). Construction work may be conducted by multiple contractors and/or NPS staff. Due to the sensitive water ways and wetlands within MUWO, projects will also be operating within the constraints of 401 and 404 permits. United States Fish and Wildlife (USFW) and

National Marine Fisheries and Sanctuaries (NMFS) were consulted and provided biological opinions in support of the various projects. Environmental Assessments were conducted for all construction projects.

The typical construction season at Muir Woods is from June 1 to January 31. However, if projects are not completed and the permit cannot be closed prior to January 31 of each year then consultant will continue to provide services as required. If the work has concluded prior to January 31, 2024, the consultant shall complete final reporting and close all permits. New permits will be opened for work starting in June 2024.

The construction projects to be included in this request for quote are:

2023 Construction Season

• Redwood Creek Salmon Habitat Enhancement Project and Trail Improvement

Project-Anticipated construction June 2023 to November 2023.

Repair Culvert Blow-Out to Protect Conlon Road and Visitor Parking Area-Anticipated construction June 2023 to November 2023.

The Projects are anticipated to be constructed June-October 2023. The work is anticipated to be classified as Traditional Construction Risk Level 2 under the

Construction General Permit, and we therefore plan to complete all project work under one SWPPP.

2024 Construction Season

• Sustainable Access Project-Anticipated Construction June 2024-December

2024.

• Replacement of Bridges 2 and 3 and Associated Trail Work-Anticipated

Construction June 2024 to November 2024.

The Projects are anticipated to be constructed June-December 2024. The work is anticipated to be classified as Traditional Construction Risk Level 2 under the

Construction General Permit, and we therefore plan to complete all project work under one SWPPP.

B. Purpose:

Due to the overlapping of construction projects within a single geographic area, the

Purpose is to provide the NPS a single consultant to perform Construction General Permit document preparation, monitoring, inspections, and reporting. The consultant will be expected to provide unit pricing for each of these tasks. The consultant will be responsible for maintaining compliance with the Construction General Permit for the project specific SWPPPs. The consultant will report to the Contracting Officers

Representative (COR) or CORs responsible for construction in Muir Woods. Consultant shall not provide direction directly to the contractor(s).

ARTICLE III. SCOPE OF SERVICES

BASE BID:

1. SWPPP writing, filing and project management:

The Contractor shall:

a. Provide a written SWPPP for projects in the 2023 construction year. This deliverable will be due by November 9, 2022.

b. Combine and consolidate Government provided SWPPPs for the 2024 seasons into a single SWPPP. This deliverable will be due by August 1, 2023.

c. Provide general updating and revisions of SWPPPs as required due to actual start dates or changes in schedule.

d. Upload and maintain project documentation to

SMARTS. Approved Signatory: Kara Mirmelstein; Env. Protection Specialist –

Water Quality & Compliance - Kara_Mirmelstein@partner.nps.gov. LRP: Brian

Aviles – Brian_Aviles@nps.gov.

e. Utilize GGNRA provided reporting and tracking forms.

f. Consult on-site with NPS project related staff and contractors to become familiar with the site and project specific SWPPP requirements. The contractor will be required to coordinate site times with the NPS COR.

g. Download and track daily weather forecasts

h. Track inspections and prepare reduction in monitoring and/or area reports as required.

2. Training, Inspection and Sampling: The following services will be performed by the appropriate certification levels as required by the CGP. Inspections will occur during normal business hours, 7:00 AM to 4:00 PM Monday through Friday. All documentation and data collection will occur on NPS provided forms and templates. CGP information will be stored on-site at a designated location. Electronic copies of all collected data and completed forms will be emailed to the NPS Contracting Officer Representative on a weekly basis. Inspections are expected to be required from approximately June 1, 2023 to

January 31, 2024 and from June 1, 2024 to January 31, 2025. The following requirements apply to all Traditional Construction projects unless otherwise indicated or not required per the CGP.

a. The SWPPP consultant will provide on-site BMP awareness training for contractors and NPS staff.

i. Approximately two-hours of training plus travel.

ii. Include discussion of importance of pollution prevention, materials preparation, proper installation, and roles and responsibilities of the QSD, QSP/Inspectors, NPS COR, and Contractor.

iii. Informal tailgate style presentation.

iv. Include a per unit cost for a base bid quantity of four (4) separate training events (two per SWPPP).

b. Consultant will provide all REAPs, monitoring and inspection services required for compliance with the project specific SWPPPs and with the CGP.

i. If rain is forecasted for a weekend the consultant shall develop the REAP

(for projects requiring REAPs) and provide to COR any actions that must be taken by the contractor before Thursday at 1:00 PM. To accomplish this, necessary actions shall be communicated to the COR by Thursday at 8:00

AM. Include a per unit REAP cost.for a base bid assumed quantity of twenty-four (24) REAPs (12 per SWPPP).

ii. When rain is forecasted for a weekend, the consultant shall notify the COR by Wednesday at 3:30 PM. This is required to ensure contractor staff will be available at the end of the week. Contractors may traditionally work

Monday through Thursday, though contractors may work Friday-Sunday as well

iii. Update rain gauge log, rain event log

iv. Ad Hoc Reports when field sampling is required.

v. Lab costs for non-visible pollutant sampling shall not be included in this base bid and will be presented to the COR if required. No additional cost for this item is to be included in the base bid. However, the consultant shall be able to provide this service within the required timeframe if requested by the Contracting Officer. A Bid Option price per nonvisible pollutant sampling event shall be provided.

vi. The intent of this scope of work is provide a single unit cost per inspection with the assumption all inspection requirements shall occur during a single inspection site visit. Therefore, in the event one construction project starts sooner or ends later than other projects the unit cost per inspection shall remain same.

vii. Include a per unit inspection cost for a base bid assumed quantity of eighty (70) inspections (35 per construction season).

3. Annual Reporting and Termination

a. Prepare and upload to SMARTS Annual Reports as required by the CGP for each

Project. Consultant may have to compile reports and inspections completed by others.

b. Prepare and upload a Notice of Termination, including pre- and post-construction photo log, as required by the CGP for each SWPPP to terminate permit coverage upon project completion. In some cases, photos will be supplied for projects started before the notice to proceed is issued.

c. Prepare a zipped folder containing all digital documents associated with this project and provide to NPS COR at project completion. Files shall be organized by the week and by SWPPP.

d. Include a per unit cost per SWPPP for a base bit quantity of four (2) separate SWPPPs for items a-c (i.e. 2– Annual Reports; 2– NOTs; 2– Final

Document packages).

ARTICLE IV. GOVERNMENT-FURNISHED MATERIALS AND SERVICES

A. Prior to the submission of a proposal: Review Government furnished digital documents.

B. The NPS will provide the following materials and services:

1. Digital copy of the following documents:

i. Salmon Habitat Enhancement and Trail Improvement Design

Documents

ii. Colon Culvert Repair Design Documents

iii. Bridge Replacements and Trail Work Phase 1 Design Documents and SWPPP

iv. Sustainable Access Project Design Documents and SWPPP

2. GGNRA BMP Handbook.

3. NPS specific reporting forms and templates will be provided upon contract award.

4. Provide single point of contact (NPS PM) to interface with A/E PM on all aspects of project.

ARTICLE V. POINTS OF CONTACT

A. Contracting Officer: Patty Payne Phone: 559-730-6435 Email:

patty_payne@nps,gov

B. COR/PM: Tommy Daigle, 415-531-3076, Thomas_daigle@nps.gov, Fort Mason Building 201, San Francisco CA 94123

C. Legally Responsible Person: Brian Aviles, 415-561-4942, Brian_Aviles@nps.gov, Fort

Mason Building 201, San Francisco CA 94123

D. Approved Signatory: Kara Mirmelstein, 415.561.4974, Kara_Mirmelstein@nps.gov, Fort Mason Building 201, San Francisco CA 94123

ARTICLE VI. FEE AND PAYMENT

A. Comply with fee and payment requirements.

B. If the consultant suspects that they will exceed the negotiated fee in order to complete the services, the consultant shall notify the CO in writing as soon as possible. Likewise, any fees included in the approved consultant cost proposal that are not ultimately needed to be performed are not permitted to be invoiced.

C. Prior to creating your invoice in the U.S. Treasury’s Invoice Processing Platform

(IPP), submit a draft copy to the Contracting Officer Representative for concurrence. Then upload the approved invoice as an external attachment when creating the electronic invoice in the IPP. A completed Release of Claims form shall be submitted with the final invoice for the unpaid balance. Indicate clearly the actions taken and number of inspections performed in the invoiced period.

ARTICLE VII. FEE PROPOSAL

Base Bid will be the summation of the total costs for each base item listed below. Unit costs will be used for additional work required beyond that included in the base bid per the stated assumptions of Article III. Unit prices will be utilized to determine funds to be withheld for 1) failure to perform the work per the SOW or 2) The assumed value in the SOW exceeded the actual number provided per Article VI B above.

Task Item Quantity Unit Unit Cost Total Cost

1 – SWPPP

updating, filing and project management

2 Lump Sum

2a – Training 4 Each

2b - Inspections 70 Each

2b v – REAP 24 Each

3a – Annual

Report 2 Each

3b – Notice of

Termination 2 Each

3d – Final

Documents 2 Lump sum

Total Base Bid:

Bid Opt. – Non.

Visible Sample

Each

Bid Opt. – Trad.

RL 2 Inspection

Each

Total Bid Option:

Total Bid: