This Scope of Work document outlines modifications to the existing metal roof and soffit systems at the Iowa Fairfield District Office. The project requires contractors to install pre-finished white aluminum soffit panels with V-groove detailing spaced at 8-inch intervals running east and west across all soffit areas, including elevator overhangs, north stairwell overhangs, and areas above structural outriggers. The work involves mounting these panels over a new 40-mil SBS rubberized asphaltic self-adhering membrane (basis of design: Henry Co. Blueskin SA or equal) with full sealing over existing steel decking and vertical surface intersections. Pre-finished aluminum J-channels must be installed at perimeters and along outriggers, and existing siding layers require removal and reinstallation to ensure proper membrane sealing against sheathing, with existing Tyvek taped over the membrane. A 20-mil peel-and-stick EPDM layer secured to existing surfaces provides additional weatherproofing. The project encompasses modifications at multiple building locations including elevator overhangs, north stairwell areas, and various soffit conditions detailed across five pages of specifications. The contract posting date was March 22, 2026, with a compressed two-business-day proposal submission deadline of March 24, 2026.
The document does not specify pricing terms, budget allocations, or funding sources. No set-asides, disadvantaged business enterprise requirements, incumbent vendor information, or specific award timelines are detailed in the scope. Insurance minimums, bonding requirements, and complete bid specifications are not included in this scope document. Prospective bidders are advised to contact the Iowa contracting authority directly to obtain comprehensive procurement details necessary for bid preparation given the expedited timeline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1378124-event.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ELEVATOR OVERHANG
OVERHANG ABOVE
ELEVATOR
NORTH STAIRWELL OVERHANG
3 sim
1 1 sim 1
2 2
ALL SOFFIT AREAS TO RECEIVE
NEW PREFINISHED ALUMINUM
EXTRUDED SOFFT PANELS
MOUNTED OVER A NEW 40 MIL,
SBS RUBBERIZED ASPHALTIC,
SELF ADHERING
MEMBRANE(BASIS OF DESIGN IS
HENRY CO. BLUESKIN SA OR
EQUAL). ENSURE FULL SEAL OF
MEMBRANE OVER EXISTING
STEEL DECKING AND
INTERSECTION WITH VERTICAL
SURFACES. TYPICAL. SEE
DETAILS.
E - W COL.
GRID LINE
EXISTING BOXED-OUT
STRUCTURAL OUTRIGGER
PRE-FIN. (WHITE) ALUM. J-CHANNELS TYP.
@ PERIMETER & ALONG OUTRIGGER(S)
PRE-FIN. (WHITE) ALUM. SOFFIT PANELS
w/ V-GROOVE @ 8" o.c. (NON-VENTED)
RUNNING E & W
20 MIL PEAL-N-STICK EPDM SECURED
TO EXISTING
PREFIN. CEMENT BD. SIDING & TRIM, TYP. OVER
AIR/MOISTURE BARRIER
ALL SOFFIT AREAS TO RECEIVE
NEW PREFINISHED ALUMINUM
EXTRUDED SOFFT PANELS
MOUNTED OVER A NEW 40 MIL,
SBS RUBBERIZED ASPHALTIC,
SELF ADHERING
MEMBRANE(BASIS OF DESIGN IS
HENRY CO. BLUESKIN SA OR
EQUAL). ENSURE FULL SEAL OF
MEMBRANE OVER EXISTING
STEEL DECKING AND
INTERSECTION WITH VERTICAL
SURFACES. TYPICAL. SEE
DETAILS.
40 MIL, SBS RUBBERIZED ASPHALTIC, SELF
ADHERING MEMBRANE(BASIS OF DESIGN IS
HENRY CO. BLUESKIN SA OR EQUAL). ENSURE
FULL SEAL OF MEMBRANE OVER EXISTING
STEEL DECKING AND INTERSECTION WITH
VERTICAL SURFACES. TYPICAL. SEE DETAILS.
REMOVE AND REINSTALL EXISTING SIDING
LAYER TO ENSURE SBS MEMBRANE FULLY
SEALS AGAINST EXISTING SHEATHING.
TAPE EXISTING TYVEK OVER MEMBRANE
20 MIL PEAL-N-STICK EPDM SECURED
TO EXISTING
PRE-FIN. (WHITE) ALUM. SOFFIT PANELS
w/ V-GROOVE @ 8" o.c. (NON-VENTED)
RUNNING E & W
PRE-FIN. (WHITE) ALUM. J-CHANNELS TYP. @
PERIMETER & ALONG OUTRIGGER(S)
EXISTING BOXED-OUT STRUCTURAL
OUTRIGGER
BOTTOM END SIMILAR TO TOP END DTL.
E - W COL.
GRID LINE
PREFIN. CEMENT BD.
SIDING & TRIM, TYP. OVER
AIR/MOISTURE BARRIER
40 MIL, SBS RUBBERIZED ASPHALTIC, SELF ADHERING
MEMBRANE(BASIS OF DESIGN IS HENRY CO. BLUESKIN SA OR
EQUAL). ENSURE FULL SEAL OF MEMBRANE OVER EXISTING STEEL
DECKING AND INTERSECTION WITH VERTICAL SURFACES. TYPICAL.
SEE DETAILS.
REMOVE & REINSTALL EXISTING SIDING
LAYER TO ENSURE SBS MEMBRANE FULLY
SEALS AGAINST EXISTING SHEATHING.
SIM. TO DTL. 6/SO503
E - W COL.
GRID LINE
20 MIL PEAL-N-STICK EPDM
SECURED TO EXISTING
METAL DECKING, ETC.
PRE-FIN. (WHITE) ALUM.
J-CHANNELS TYP. @
PERIMETER
NON-ACOUSTICAL METAL
ROOF DECKING
PRE-FIN. (WHITE) ALUM.
SOFFIT PANELS
w/ V-GROOVE @ 8" o.c.
(NON-VENTED)
RUNNING E & W
40 MIL, SBS RUBBERIZED ASPHALTIC,
SELF ADHERING MEMBRANE(BASIS
OF DESIGN IS HENRY CO. BLUESKIN
SA OR EQUAL). ENSURE FULL SEAL
OF MEMBRANE OVER EXISTING
STEEL DECKING AND INTERSECTION
WITH VERTICAL SURFACES. TYPICAL.
SEE DETAILS.
REMOVE & REINSTALL EXISTING SIDING
LAYER TO ENSURE SBS MEMBRANE FULLY
SEALS AGAINST EXISTING SHEATHING.
INTERIOR:
EXTERIOR:
PRE-FIN. (WHITE) ALUM.
J-CHANNELS TYP. @
PERIMETER
PRE-FIN. (WHITE) ALUM.
SOFFIT PANELS w/ V- GROOVE @ 8" o.c. (NON-
VENTED) RUNNING E & W
20 MIL PEAL-N-STICK
EPDM SECURED TO
EXISTING
N - S COL.
GRID LINE
40 MIL, SBS RUBBERIZED ASPHALTIC, SELF
ADHERING MEMBRANE(BASIS OF DESIGN IS HENRY
CO. BLUESKIN SA OR EQUAL). ENSURE FULL SEAL
OF MEMBRANE OVER EXISTING STEEL DECKING AND
INTERSECTION WITH VERTICAL SURFACES. TYPICAL.
SEE DETAILS.
REMOVE AND REINSTALL EXISTING SIDING
LAYER TO ENSURE SBS MEMBRANE FULLY
SEALS AGAINST EXISTING SHEATHING. TAPE
EXISTING TYVEK OVER MEMBRANE