Schedule of Material Submittals AF66.xlsx
XLSX spreadsheet 75 KB Posted
- Attached to
- RPR Storage Warehouse 970 Federal contract opportunity
- Solicitation number
- FA557520B0003
About this file
This solicitation is for a storage warehouse project at Moron Air Base in Spain. The project scope includes construction of a new storage warehouse estimated to cost between $500,000 and $1,000,000. A pre-proposal conference will be held on July 15, 2020 where questions may be submitted until July 22. Proposals must be received by August 3, 2020. In accordance with the agreement between the U.S. and Spain, Spanish materials, labor, and equipment should be used where feasible. Funding has not yet been obligated for this effort, so no award will be made until funds are available. The Air Force reserves the right to cancel the solicitation before or after the closing date.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers.pdf | ||
| Drawings.pdf | ||
| Specifications.pdf | ||
| Price Schedule.xlsx | XLSX spreadsheet | |
| Solicitation - FA557520B0003.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Sch. (ENG)
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | |||
| QUUG 07-1020 | PROJECT TITLE: | |||
| RPR STORAGE WAREHOUSE, 970 | SOLICITATION / CONTRACT NO. |
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (MM/DD/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
SUBMITTAL NUMBERS
fergusog: Enter the Submittal Number
DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL
fergusog: Enter Resubmittal Number
FINAL APPROVAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
REMARKS
fergusog: Enter any comments pertaining to the submittal
APPROVED
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DISAPPROVED
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date fergusog: Enter any comments pertaining to the submittal
| SECTION 01 11 00 | ||||||||||||
| 1 | Existing Facilities Shutoff Schedule | 1 | Demolition Works-15 | |||||||||
| 2 | Work Plan | 1 | NTP + 5 | |||||||||
| 3 | Construction Schedule | 1 | NTP + 5 | |||||||||
| 4 | Operation and Maintenance Manuals | 1 | FI+15 | |||||||||
| 5 | Salvage Plan | 1 | NTP+15 | |||||||||
| SECTION 01 11 01 | ||||||||||||
| 6 | 2 Years Standard Contractor Warranty | 1 | Prior Final Inspection | |||||||||
| 7 | Work Clearance Request | 1 | NTP + 5 | |||||||||
| 8 | Hot Work Request and Procedures | 1 | Hot Works-10 | |||||||||
| 9 | Access Routes Plan | 1 | NTP + 10 | |||||||||
| 10 | Work Schedule | 1 | NTP + 10 | |||||||||
| 11 | Mobility Plan | 1 | NTP+15 | |||||||||
| 12 | Quality Control Plan | 1 | NTP+15 | |||||||||
| 13 | Waste and Construction Debris | 1 | Final Inspection | |||||||||
| 14 | As-Built Drawings | 1 | FI+15 | |||||||||
| 15 | Organizational Chart | 1 | Commencing-5 | |||||||||
| 16 | Safety Plan | 1 | Commencing-5 | |||||||||
| 17 | Environmental Protection Plan | 1 | NTP+15 | |||||||||
| SECTION 02 41 00 | ||||||||||||
| 18 | Demolition and Deconstruction Plan | 1 | ||||||||||
| 19 | Receipts | 1 | ||||||||||
| 20 | Manager of waste from demo and construction | 1 | ||||||||||
| 21 | Authorized dump or treatment & recovery plant | 1 | ||||||||||
| 22 | Delivery & disposal certificate of waste from cons & demo | 1 | ||||||||||
| SECTION 03 30 00 | ||||||||||||
| 23 | Quality Control Plan | 1 | ||||||||||
| 24 | Materials and Forms | 1 | ||||||||||
| 25 | Reinforcement | 1 | ||||||||||
| 26 | Concrete Datasheet | 1 | ||||||||||
| SECTION 05 05 23.16 | ||||||||||||
| 27 | Welding Procedure Qualifications | 1 | ||||||||||
| 28 | Welder, Welding Operator, and Tacker Qualification | 1 | ||||||||||
| 29 | Welding Electrodes and Rods | 1 | ||||||||||
| 30 | Certified Welder Performance | 1 | ||||||||||
| SECTION 05 12 00 | ||||||||||||
| 31 | Erection Shop Drawings | 1 | ||||||||||
| 32 | Shop Primer | 1 | ||||||||||
| 33 | Welding Electrodes and Rods | 1 | ||||||||||
| 34 | Non-Shrink Grout | 1 | ||||||||||
| 35 | Steel | 1 | ||||||||||
| 36 | Bolts Nuts and Washers | 1 | ||||||||||
| 37 | Galvanizing | 1 | ||||||||||
| SECTION 07 41 00 | ||||||||||||
| 38 | Panels installation | 1 | ||||||||||
| 39 | Supports Installation | 1 | ||||||||||
| 40 | Flashing Installation | 1 | ||||||||||
| 41 | Fall Arresting System | 1 | ||||||||||
| 42 | Roofing Panels | 1 | 1 | |||||||||
| 43 | Siding Panels | 1 | 1 | |||||||||
| 44 | Fasteners | 1 | ||||||||||
| 45 | Gutters and Downspouts | 1 | ||||||||||
| 46 | Fall Arresting System Components | 1 | ||||||||||
| 47 | Color Chart Samples | 1 | ||||||||||
| 48 | Roofing and Siding Panels | 1 | ||||||||||
| 49 | Fall Arresting System. Certificate of Conformity | 1 | ||||||||||
| 50 | Roofing and Siding Panels Warranty | 1 | ||||||||||
| SECTION 07 72 00 | ||||||||||||
| 51 | Roof Ventilators | 1 | 1 | 1 | ||||||||
| 52 | Manufacturers Installation Instructions | 1 | ||||||||||
| SECTION 08 34 16.10 | ||||||||||||
| 53 | Door and Components Shop Drawings | 1 | ||||||||||
| 54 | Manufacturer's Qualifications | 1 | ||||||||||
| 55 | Installer's Qualifications | 1 | ||||||||||
| 56 | Installer's Warranty | 1 | ||||||||||
| SECTION 08 51 23 | ||||||||||||
| 57 | Louvers | 1 | ||||||||||
| 58 | Steel Framing Materials | 1 | ||||||||||
| 59 | Fasteners | 1 | ||||||||||
| SECTION 09 67 23.14 | ||||||||||||
| 60 | Sealer and Resin | 1 | ||||||||||
| 61 | Certification | 1 | ||||||||||
| 62 | Flooring System | 1 | ||||||||||
| 63 | Warranty | 1 | ||||||||||
| 64 | Application | 1 | ||||||||||
| SECTION 09 90 00 | ||||||||||||
| 65 | Steel Structure Treatment | 1 | ||||||||||
| 66 | Coating | 1 | 1 | |||||||||
| 67 | Manufacturer's Technical Datasheets | 1 | ||||||||||
| 68 | Sealants | 1 | ||||||||||
| 69 | Color Samples | 1 | ||||||||||
| 70 | Applicator´s Qualifications | 1 | ||||||||||
| 71 | Application Instructions | 1 | ||||||||||
| 72 | Mixing | 1 | ||||||||||
| 73 | Manufacturers Safety Data Sheets | 1 | ||||||||||
| SECTION 10 14 00.20 | ||||||||||||
| 74 | Installation | 1 | ||||||||||
| 75 | Warranty | 1 | ||||||||||
| SECTION 10 14 53 | ||||||||||||
| 76 | Traffic Sign Post | 1 | ||||||||||
| SECTION 10 44 16 | ||||||||||||
| 77 | Manufacturers Data | 1 | ||||||||||
| 78 | Fire Exinguishers | 1 | 1 | |||||||||
| 79 | Cabiners | 1 | ||||||||||
| 80 | Manufacturers Warranty | 1 | ||||||||||
| SECTION 21 13 13.00 20 | ||||||||||||
| 81 | Shop Drawings | 1 | ||||||||||
| 82 | Piping, Fittings, Valves | 1 | ||||||||||
| 83 | Alarm Valves, Valves, Couplings, Alarm Switches | 1 | ||||||||||
| 84 | Sprinklers | 1 | ||||||||||
| 85 | Hangers, Suports | 1 | ||||||||||
| 86 | Fire Department Connections | 1 | ||||||||||
| 87 | Seismic Bracing | 1 | ||||||||||
| 88 | Hydraulic Calculations | 1 | ||||||||||
| 89 | System Designer Qualifications | 1 | ||||||||||
| 90 | Preliminary Test Report | 1 | ||||||||||
| 91 | Final Acceptance Test Report | 1 | ||||||||||
| 92 | Inspection by Fire Protection Engineer | 1 | ||||||||||
| 93 | Fire Protection Engineer Data | 1 | ||||||||||
| 94 | Sprinkler System Installer | 1 | ||||||||||
| 95 | As-Built Drawings | 1 | ||||||||||
| SECTION 22 00 00 | ||||||||||||
| 96 | Hose Bibb and Hose Connection Vacuum breaker | 1 | ||||||||||
| 97 | Steel Pipes and Fittings | 1 | ||||||||||
| 98 | HDPE Pipes and Fittings | 1 | ||||||||||
| 99 | Valves | 1 | ||||||||||
| 100 | Eyewash Station Alarm | 1 | 1 | |||||||||
| 101 | Water Meter | 1 | ||||||||||
| 102 | Valve Box | 1 | ||||||||||
| 103 | Flanged T | 1 | ||||||||||
| 104 | Universal Coupling | 1 | ||||||||||
| 105 | Backflow Prevention Assemblies | 1 | ||||||||||
| 106 | Tests, Flushing and Disinfection | 1 | ||||||||||
| 107 | Plumbing System | 1 | ||||||||||
| 108 | Tightness Test Report | 1 | ||||||||||
| SECTION 23 00 00 | ||||||||||||
| 109 | Room Air Conditioning Unit | 1 | 1 | |||||||||
| 110 | Manufacturers Installation Instructions | 1 | ||||||||||
| SECTION 26 20 00 | ||||||||||||
| 111 | RMC Conduits and Fittings | 1 | ||||||||||
| 112 | FMC Flexible Metal Conduit and Fittings | 1 | ||||||||||
| 113 | Flexible Non-Metallic Conduit and Fittings | 1 | ||||||||||
| 114 | Junction and pull boxes | 1 | ||||||||||
| 115 | Outlet boxes and covers | 1 | ||||||||||
| 116 | Wires and cables | 1 | ||||||||||
| 117 | Splices and termination components | 1 | ||||||||||
| 118 | Circuit breakers | 1 | ||||||||||
| 119 | Device Plates | 1 | ||||||||||
| 120 | Receptacles | 1 | ||||||||||
| 121 | Toggle switches | 1 | ||||||||||
| 122 | Surge Protection Device | 1 | ||||||||||
| 123 | Panel boards | 1 | ||||||||||
| 124 | Labels | 1 | ||||||||||
| 125 | Wiring Diagrams of Panelboards | 1 | ||||||||||
| 126 | Devices Subject To manual Operation | 1 | ||||||||||
| 127 | 1000-Volt Wiring Test | 1 | ||||||||||
| 128 | Grounding System Test | 1 | ||||||||||
| SECTION 26 41 00 | ||||||||||||
| 129 | Overall Lightning Protection System | 1 | ||||||||||
| 130 | Each Major Component | 1 | ||||||||||
| 131 | Air Terminals | 1 | ||||||||||
| 132 | Conductors | 1 | ||||||||||
| 133 | Ground Rods | 1 | ||||||||||
| 134 | Lightning Protection System Hardware | 1 | ||||||||||
| 135 | Grounding Test/Bar Wells | 1 | ||||||||||
| 136 | Grounding Bars | 1 | ||||||||||
| 137 | Cable and Air Terminals Fixation Fittings | 1 | ||||||||||
| 138 | Exothermic Welding | 1 | ||||||||||
| 139 | Lightning Protection and Grounding System Test | 1 | ||||||||||
| 140 | Grounding System Test | 1 | ||||||||||
| SECTION 26 51 00 | ||||||||||||
| 141 | Luminaires Type A | 1 | ||||||||||
| 142 | Luminaires Type B | 1 | ||||||||||
| 143 | Luminaires Type C with Power supplies and ballasts | 1 | ||||||||||
| 144 | Luminaires Type D | 1 | ||||||||||
| 145 | Luminaires Type E | 1 | ||||||||||
| 146 | Light Sources | 1 | ||||||||||
| 147 | Automatic Lighting Control Devices | 1 | ||||||||||
| 148 | Led Uminaire Warranty | 1 | ||||||||||
| 149 | Luminaire Design Data | 1 | ||||||||||
| 150 | Exit Signs | 1 | ||||||||||
| 151 | Luminaire Useful Life Certificate | 1 | ||||||||||
| 152 | Lighting Fixtures Test Report | 1 | ||||||||||
| SECTION 26 56 00 | ||||||||||||
| 153 | LED Luminaires | 1 | 1 | |||||||||
| 154 | Luminaire Light Sources | 1 | ||||||||||
| 155 | Lighting Contactor | 1 | ||||||||||
| 156 | Luminaires Useful Life Certificate | 1 | ||||||||||
| 157 | Lighting Fixtures Field Test Report | 1 | ||||||||||
| SECTION 28 31 63.00 20 | ||||||||||||
| 158 | Point-to-Point Wiring Diagrams | 1 | ||||||||||
| 159 | Plan View | 1 | ||||||||||
| 160 | List of Device Adresses and Messages | 1 | ||||||||||
| 161 | Fire Alarm System | 1 | 1 | |||||||||
| 162 | Battery Power Calculations | 1 | ||||||||||
| 163 | Fire Alarm Control Panel | 1 | ||||||||||
| 164 | Manual Stations | 1 | ||||||||||
| 165 | Batteries | 1 | ||||||||||
| 166 | Smoke Sensor | 1 | ||||||||||
| 167 | Wiring and Cable | 1 | ||||||||||
| 168 | Addressable Interface Devices | 1 | ||||||||||
| 169 | Qualifications of Installer | 1 | ||||||||||
| 170 | Certificates of Installation Completion | 1 | ||||||||||
| 171 | Remote Annunciator | 1 | ||||||||||
| 172 | Audio-Strobes | 1 | ||||||||||
| SECTION 31 23 00.00 20 | ||||||||||||
| 173 | Dewatering Work Plan | 1 | ||||||||||
| 174 | Borrow Soil Properties | 1 | ||||||||||
| 175 | Excavation Plan | 1 | ||||||||||
| 176 | Excavation Time Schedule and Procedures | 1 | ||||||||||
| 177 | Formula Job-Mix | 1 | ||||||||||
| 178 | Certificates of Compliance | 1 | ||||||||||
| 179 | Product Data sheet | 1 | ||||||||||
| 180 | Borrow Site Testing | 1 | ||||||||||
| 181 | Fill and Backfill test | 1 | ||||||||||
| 182 | Select Material Tests | 1 | ||||||||||
| 183 | Density Tests | 1 | ||||||||||
| 184 | Moisture Contect Tests | 1 | ||||||||||
| 185 | Test and Report of Soil Contamination | 1 | ||||||||||
| SECTION 32 12 17 | ||||||||||||
| 186 | Job Mix Formula | 1 | ||||||||||
| 187 | Characteristics of Materials | 1 | ||||||||||
| 188 | Specificat Gravity Test of Asphalt | 1 | ||||||||||
| 189 | Coarse Aggregate Tests | 1 | ||||||||||
| 190 | Weight of Slag Test | 1 | ||||||||||
| 191 | Percent of crushed pieces in gravel | 1 | ||||||||||
| 192 | Fine Aggregate Tests | 1 | ||||||||||
| 193 | Specific Gravity of Mineral Filler | 1 | ||||||||||
| 194 | Bituminous Mixture Tests | 1 | ||||||||||
| 195 | Aggregates Tests | 1 | ||||||||||
| SECTION 32 17 23 | ||||||||||||
| 196 | Application Equipment list | 1 | ||||||||||
| 197 | Exterior Surface Preparation | 1 | ||||||||||
| 198 | Safety Datasheets | 1 | ||||||||||
| 199 | Exterior Pavement Paint | 1 | 1 | |||||||||
| SECTION 32 31 13 | ||||||||||||
| 200 | Fence Assembly | 1 | 1 | |||||||||
| 201 | Gate Assembly | 1 | 1 | |||||||||
| 202 | Gate Hardware and Accessories | 1 | 1 | |||||||||
| 203 | Concrete | 1 | ||||||||||
| SECTION 33 40 00 | ||||||||||||
| 204 | Pipe for Culverts and Storm Drains | 1 | ||||||||||
| 205 | Frame and Covert for Gratings | 1 | ||||||||||
| 206 | Post-Installation Inspection Report | 1 | ||||||||||
| 207 | Precast Concrete Curb Line | 1 | ||||||||||
| 208 | Lineal Drain Channel | 1 | ||||||||||
| 209 | Enbankment Downspout | 1 | ||||||||||
| SECTION 33 71 02 | ||||||||||||
| 210 | Precast Underground Structures | 1 | ||||||||||
| 211 | Precast Concrete Structures | 1 | ||||||||||
| 212 | Manhole Frames and Covers | 1 | ||||||||||
| 213 | Conduits and Spacers | 1 | ||||||||||
| 214 | Cables and conductors | 1 | ||||||||||
| 215 | Warning and identification tape | 1 | ||||||||||
| 216 | Grounding Conductors | 1 | ||||||||||
| 217 | Grounding Rods | 1 | ||||||||||
| 218 | Grounding Test Bars and Wells | 1 | ||||||||||
| 219 | Field Acceptance Check and Tests | 1 | ||||||||||
| 220 | Cable Installation Plan and Procedure | 1 | ||||||||||
| 221 | Manhole Certificates | 1 |
&"Arial,Negrita"&8QUUG 07-1020. 100% DESIGN SUBMITTAL Schedule of Material Submittals, April 2018 Page &P of &N
Material Submittals Sch. (ESP)
| RESUMEN MUESTRAS DE MATERIAL | NÚMERO PROYECTO: | ||
| QUUG 07-1020 | TÍTULO DE PROYECTO: |
RPR STORAGE WAREHOUSE, 970
SOLICITACIÓN / CONTRATO NO.
| (A cumplimentar por el ingeniero del proyecto) | (A cumplimentar por administrador del contrato) | ||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||
| LÍNEA NÚMERO | PARTIDA O DESCRIPCIÓN DE PARTIDA, REFERENCIA DEL CONTRATO, TIPO DE PRESENTACIÓN | CERTIFICADO DE CUMPLIMIENTO | PLANOS DE TALLER | MUESTRAS | SELECCIÓN DE COLOR | RECOMENDACIONES DEL FABRICANTE | GARANTÍA DEL FABRICANTE | DATOS DE CATÁLOGO | INSTRUCCIONES DE FUNCIONAMIENTO | PROGRAMAS, LISTADOS, INFORMES, PLANES | DATOS TÉCNICOS | PRUEBAS | INFORMES DE TRABAJOS DE CAMPO | FECHA DE ENTREGA |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
FECHA RECEPCIÓN EN CONTRATACIÓN
fergusog: Enter the date received from the Contractor. (MM/DD/YY) FECHA EN INGENIERíA CIVIL fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
FECHA LÍMITE DE DEVOLUCIÓN
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
NÚMERO DE MUESTRA
fergusog: Enter the Submittal Number
FECHA NOTIFICACIÓN A CONTRATISTA SEGUNDA PRESENTACIÓN DEL CONTRATISTA
fergusog: Enter Resubmittal Number
APROBACIÓN FINAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
OBSERVACIONES
fergusog: Enter any comments pertaining to the submittal
APROBADO
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DESAPROBADO
fergusog: Enter date the Contractor was notified of submittal disapproval fergusog: Enter the submittal final approval date fergusog: Enter any comments pertaining to the submittal
| SECTION 01 11 00 | ||||||||||||
| 1 | Desconexiones y Corte de Instalaciones | 1 | Demolition Works-15 | |||||||||
| 2 | Plan de Trabajo | 1 | NTP + 5 | |||||||||
| 3 | Planning de Construcción | 1 | NTP + 5 | |||||||||
| 4 | Manuales de Operación y Mantenimiento | 1 | FI+15 | |||||||||
| 5 | Plan de Conservación de Materiales | 1 | NTP+15 | |||||||||
| SECTION 01 11 01 | ||||||||||||
| 6 | Garantía Estándar Contratista 2 años | 1 | Prior Final Inspection | |||||||||
| 7 | Solicitud de Pase de Trabajo | 1 | NTP + 5 | |||||||||
| 8 | Solicitud y Proceso para Trabajos con Calor | 1 | Hot Works-10 | |||||||||
| 9 | Plan de Rutas de Accesos | 1 | NTP + 10 | |||||||||
| 10 | Cuadro de Programación | 1 | NTP + 10 | |||||||||
| 11 | Plan de Movilidad | 1 | NTP+15 | |||||||||
| 12 | Plan de Control de Calidad | 1 | NTP+15 | |||||||||
| 13 | Residuos y Escombros de Construcción | 1 | Final Inspection | |||||||||
| 14 | Planos AS-BUILT | 1 | FI+15 | |||||||||
| 15 | Organigrama | 1 | Commencing-5 | |||||||||
| 16 | Plan de Seguridad | 1 | Commencing-5 | |||||||||
| 17 | Plan de Protección Medioambiental | 1 | NTP+15 | |||||||||
| SECTION 02 41 00 | ||||||||||||
| 18 | Plan de Demoliciones y Desmontaje | 1 | ||||||||||
| 19 | Comprobantes de Recepción | 1 | ||||||||||
| 20 | Gestor de Residuos de Demol. Y Constr. | 1 | ||||||||||
| 21 | Vertedero Autorizado | 1 | ||||||||||
| 22 | Certificado de Entregas y Eliminación de Resid. | 1 | ||||||||||
| SECTION 03 30 00 | ||||||||||||
| 23 | Plan de Control de Calidad | 1 | ||||||||||
| 24 | Materiales para Encofrados | 1 | ||||||||||
| 25 | Armaduras | 1 | ||||||||||
| 26 | Ficha del Hormigón | 1 | ||||||||||
| SECTION 05 05 23.16 | ||||||||||||
| 27 | Calificaciones del Procedimiento de Soldadura | 1 | ||||||||||
| 28 | Soldador, Operador de Soldadura. Cualificación | 1 | ||||||||||
| 29 | Electrodos y Varillas de Soldadura | 1 | ||||||||||
| 30 | Cualificación de Soldador Certificado | 1 | ||||||||||
| SECTION 05 12 00 | ||||||||||||
| 31 | Planos de Montaje | 1 | ||||||||||
| 32 | Imprimación en Taller | 1 | ||||||||||
| 33 | Electrodos y Varillas de Soldadura | 1 | ||||||||||
| 34 | Mortero sin Retracción | 1 | ||||||||||
| 35 | Acero | 1 | ||||||||||
| 36 | Pernos, Tuercas y Arandelas | 1 | ||||||||||
| 37 | Galvanizado | 1 | ||||||||||
| SECTION 07 41 00 | ||||||||||||
| 38 | Instalación de Paneles | 1 | ||||||||||
| 39 | Instalación de Soportes | 1 | ||||||||||
| 40 | Instalación de Remates | 1 | ||||||||||
| 41 | Sistema de Protección anticaidas | 1 | ||||||||||
| 42 | Paneles de Cubierta | 1 | 1 | |||||||||
| 43 | Paneles de Revestimiento | 1 | 1 | |||||||||
| 44 | Accesorios | 1 | ||||||||||
| 45 | Canalones y Bajantes | 1 | ||||||||||
| 46 | Componentes del Sistema Anticaidas | 1 | ||||||||||
| 47 | Muestra de Carta de Color | 1 | ||||||||||
| 48 | Paneles de Cubierta y Cerramiento | 1 | ||||||||||
| 49 | Certificado de Conformidad del Sistema Anticaidas | 1 | ||||||||||
| 50 | Garantía de Paneles de Cubierta y Fachada | 1 | ||||||||||
| SECTION 07 72 00 | ||||||||||||
| 51 | Extractor Eólico por Gravedad | 1 | 1 | 1 | ||||||||
| 52 | Instrucciones de Instalación del Fabricante | 1 | ||||||||||
| SECTION 08 34 16.10 | ||||||||||||
| 53 | Planos de Montaje de Puerta | 1 | ||||||||||
| 54 | Cualificaciones del Fabricante | 1 | ||||||||||
| 55 | Cualificaciones del Instalador | 1 | ||||||||||
| 56 | Garantías del Instalador | 1 | ||||||||||
| SECTION 08 51 23 | ||||||||||||
| 57 | Rejillas | 1 | ||||||||||
| 58 | Materiales del Marco de Acero | 1 | ||||||||||
| 59 | Fijaciones | 1 | ||||||||||
| SECTION 09 67 23.14 | ||||||||||||
| 60 | Sellador y Resina | 1 | ||||||||||
| 61 | Certificados | 1 | ||||||||||
| 62 | Sistema de Pavimento | 1 | ||||||||||
| 63 | Garantía del Fabricante | 1 | ||||||||||
| 64 | Aplicación | 1 | ||||||||||
| SECTION 09 90 00 | ||||||||||||
| 65 | Tratamiento de la Estructura de Acero | 1 | ||||||||||
| 66 | Revestimientos | 1 | 1 | |||||||||
| 67 | Hojas de Datos Técnicos del Fabricante | 1 | ||||||||||
| 68 | Sellante | 1 | ||||||||||
| 69 | Muestras de Color | 1 | ||||||||||
| 70 | Cualificaciones de los Aplicadores | 1 | ||||||||||
| 71 | Instrucciones de Aplicación | 1 | ||||||||||
| 72 | Mezcla | 1 | ||||||||||
| 73 | Hojas de Datos de Seguridad del Fabricante | 1 | ||||||||||
| SECTION 10 14 00.20 | ||||||||||||
| 74 | Instalación | 1 | ||||||||||
| 75 | Garantía | 1 | ||||||||||
| SECTION 10 14 53 | ||||||||||||
| 76 | Poste de Señal de Tráfico | 1 | ||||||||||
| SECTION 10 44 16 | ||||||||||||
| 77 | Información del Fabricante | 1 | ||||||||||
| 78 | Extintores | 1 | 1 | |||||||||
| 79 | Armarios | 1 | ||||||||||
| 80 | Garantía del Fabricante | 1 | ||||||||||
| SECTION 21 13 13.00 20 | ||||||||||||
| 81 | Planos de Fabricación | 1 | ||||||||||
| 82 | Tuberías, Uniones, Válvulas | 1 | ||||||||||
| 83 | Válvulas de Alarma, Uniones | 1 | ||||||||||
| 84 | Rociadores | 1 | ||||||||||
| 85 | Soportes | 1 | ||||||||||
| 86 | Conexiones del Departamento de Bomberos | 1 | ||||||||||
| 87 | AbrazaderasSísmicas | 1 | ||||||||||
| 88 | Cálculos Hidráulicos | 1 | ||||||||||
| 89 | Cualificaciones del Diseñador del Sistema | 1 | ||||||||||
| 90 | Reporte del test Preliminar | 1 | ||||||||||
| 91 | Reporte del Test de Aceptación Final | 1 | ||||||||||
| 92 | Inspección del Ingeniero de PCI | 1 | ||||||||||
| 93 | Datos del Ingeniero de PCI | 1 | ||||||||||
| 94 | Instalador del Sistema de Rociadores | 1 | ||||||||||
| 95 | Planos AS-BUILT | 1 | ||||||||||
| SECTION 22 00 00 | ||||||||||||
| 96 | Toma de Manguera y Rompedor de Vacío | 1 | ||||||||||
| 97 | Tubería de Acero y Accesorios | 1 | ||||||||||
| 98 | Tubería de Polietileno y Accesorios | 1 | ||||||||||
| 99 | Válvulas | 1 | ||||||||||
| 100 | Alarma de Estación lavaojos | 1 | 1 | |||||||||
| 101 | Contador de Agua | 1 | ||||||||||
| 102 | Caja de Válvulas | 1 | ||||||||||
| 103 | Brida T | 1 | ||||||||||
| 104 | Acoplamiento Universal | 1 | ||||||||||
| 105 | Backflow Prevention Assemblies | 1 | ||||||||||
| 106 | Pruebas de Vaciado y Desinfección | 1 | ||||||||||
| 107 | Sistema de Fontanería | 1 | ||||||||||
| 108 | Informe del Test de Estanqueidad | 1 | ||||||||||
| SECTION 23 00 00 | ||||||||||||
| 109 | Unidad Aire Acondicionado | 1 | 1 | |||||||||
| 110 | Instrucciones de Instalación del Fabricante | 1 | ||||||||||
| SECTION 26 20 00 | ||||||||||||
| 111 | Conducto Rígido Metálico y Accesorios | 1 | ||||||||||
| 112 | Conducto Metálico Flexible y Accesorios | 1 | ||||||||||
| 113 | Conducto Flexible No Metálico y Accesorios | 1 | ||||||||||
| 114 | Cajas de Conexión y Derivación | 1 | ||||||||||
| 115 | Enchufes y Cubiertas | 1 | ||||||||||
| 116 | Hilos y Cables | 1 | ||||||||||
| 117 | Empalmes y Components de Terminación | 1 | ||||||||||
| 118 | Breakers de Circuitos | 1 | ||||||||||
| 119 | Placas de Dispositivos | 1 | ||||||||||
| 120 | Tomas Eléctricas | 1 | ||||||||||
| 121 | Interruptores de Palanca | 1 | ||||||||||
| 122 | Proteccion contra Sobre Tensiones Transitorias | 1 | ||||||||||
| 123 | Cuadros Eléctricos | 1 | ||||||||||
| 124 | Etiquetas | 1 | ||||||||||
| 125 | Planos de Taller del Sistema | 1 | ||||||||||
| 126 | Dispositivos Sujetos a Operación Manual | 1 | ||||||||||
| 127 | Prueba de Cableado de 1000-Voltios | 1 | ||||||||||
| 128 | Prueba de Puesta a Tierra | 1 | ||||||||||
| SECTION 26 41 00 | ||||||||||||
| 129 | Sistema Global de Protección contral el Rayo | 1 | ||||||||||
| 130 | Cada componente Principal | 1 | ||||||||||
| 131 | Terminales Aéreas | 1 | ||||||||||
| 132 | Conductores | 1 | ||||||||||
| 133 | Picas de Puesta a Tierra | 1 | ||||||||||
| 134 | Equipos del Sistema de Protección contra el Rayo | 1 | ||||||||||
| 135 | Arquetas de Testeo/Pica de Puesta a Tierra | 1 | ||||||||||
| 136 | Barras de Puesta a Tierra | 1 | ||||||||||
| 137 | Accesorios de Fijación de Conductores y Puntas | 1 | ||||||||||
| 138 | Soldadura Exotérmica | 1 | ||||||||||
| 139 | Prueba del Sistema de Protección contral el Rayo | 1 | ||||||||||
| 140 | Prueba del Sistema de Puesta a Tierra | 1 | ||||||||||
| SECTION 26 51 00 | ||||||||||||
| 141 | Luminaria Tipo A | 1 | ||||||||||
| 142 | Luminaria Tipo B | 1 | ||||||||||
| 143 | Luminaria Tipo C con fuente de alimentación de emergencia y balastos | 1 | ||||||||||
| 144 | Luminaria Tipo D | 1 | ||||||||||
| 145 | Luminaria Tipo E | 1 | ||||||||||
| 146 | Fuentes Lumínicas | 1 | ||||||||||
| 147 | Dispositivos de Control Automático de la Ilum. | 1 | ||||||||||
| 148 | Garantía de Luminarias LED | 1 | ||||||||||
| 149 | Luminaire Design Data | 1 | ||||||||||
| 150 | Señales de Salida | 1 | ||||||||||
| 151 | Certificado de Vida Útil de Luminaria | 1 | ||||||||||
| 152 | Prueba de Luminarias | 1 | ||||||||||
| SECTION 26 56 00 | ||||||||||||
| 153 | Luminarias LED | 1 | 1 | |||||||||
| 154 | Fuentes de Luz de Luminarias | 1 | ||||||||||
| 155 | Contactador de Iluminación | 1 | ||||||||||
| 156 | Certificado de Vida Útil de Luminaria | 1 | ||||||||||
| 157 | Lighting Fixtures Test Report | 1 | ||||||||||
| SECTION 28 31 63.00 20 | ||||||||||||
| 158 | Cableado Punto a Punto | 1 | ||||||||||
| 159 | Dibujos en Planta | 1 | ||||||||||
| 160 | Direcciones de Dispositivos y Mensajes | 1 | ||||||||||
| 161 | Sistema de Alarma Contra Incendios | 1 | 1 | |||||||||
| 162 | Cálculos de Baterías | 1 | ||||||||||
| 163 | Panel de Control de Alarma Contra Incendios | 1 | ||||||||||
| 164 | Estaciones Manuales | 1 | ||||||||||
| 165 | Baterías | 1 | ||||||||||
| 166 | Smoke Sensor | 1 | ||||||||||
| 167 | Wiring and Cable | 1 | ||||||||||
| 168 | Addressable Interface Devices | 1 | ||||||||||
| 169 | Qualifications of Installer | 1 | ||||||||||
| 170 | Certificado de Finalización de la Instalación | 1 | ||||||||||
| 171 | Anunciador Remoto | 1 | ||||||||||
| 172 | Dispositivos de Aviso AudioVisuales | 1 | ||||||||||
| SECTION 31 23 00,00 20 | ||||||||||||
| 173 | Plan de Trabajo de Desecación | 1 | ||||||||||
| 174 | Propiedades del Suelo de Préstamo | 1 | ||||||||||
| 175 | Plan de Excavación | 1 | ||||||||||
| 176 | Planning y Procesos de Excavación | 1 | ||||||||||
| 177 | Fórmula | 1 | ||||||||||
| 178 | Certificados de Cumplimiento | 1 | ||||||||||
| 179 | Hoja de Datos del Producto | 1 | ||||||||||
| 180 | Informe de Pruebas de Tierras de Préstamo | 1 | ||||||||||
| 181 | Pruebas de Relleno | 1 | ||||||||||
| 182 | Prueba de Material Seleccionado | 1 | ||||||||||
| 183 | Prueba de Densidad | 1 | ||||||||||
| 184 | Prueba de Contenido de Humedad | 1 | ||||||||||
| 185 | Test y Reporte de Contaminación del Suelo | 1 | ||||||||||
| SECTION 32 12 17 | ||||||||||||
| 186 | Fórmula de Mezcla de Trabajo | 1 | ||||||||||
| 187 | Características de los Materiales | 1 | ||||||||||
| 188 | Ensayo de Gravedad Específica del Asfalto | 1 | ||||||||||
| 189 | Ensayo de Árido Grueso | 1 | ||||||||||
| 190 | Ensayo de Porcentaje en Peso de Escoria | 1 | ||||||||||
| 191 | Porcentaje de Piezas trituradas en Grava | 1 | ||||||||||
| 192 | Ensayo de Áridos Finos | 1 | ||||||||||
| 193 | Peso Específico del Relleno Mineral | 1 | ||||||||||
| 194 | Pruebas de Mezclas Bituminosas | 1 | ||||||||||
| 195 | Test de suelo agregado | 1 | ||||||||||
| SECTION 32 17 23 | ||||||||||||
| 196 | Lista de Equipos de Aplicación | 1 | ||||||||||
| 197 | Preparación de la Superficie Exterior | 1 | ||||||||||
| 198 | Ficha de Datos de Seguridad | 1 | ||||||||||
| 199 | Pintura Pavimento Exterior | 1 | 1 | |||||||||
| SECTION 32 31 13 | ||||||||||||
| 200 | Montaje de la Valla | 1 | 1 | |||||||||
| 201 | Montaje de la Puerta | 1 | 1 | |||||||||
| 202 | Hardware y Accesorios de la Puerta | 1 | 1 | |||||||||
| 203 | Hormigón | 1 | ||||||||||
| SECTION 33 40 00 | ||||||||||||
| 204 | Tuberías para Alcantarillas y Drenajes | 1 | ||||||||||
| 205 | Marco y Tapa para Rejillas | 1 | ||||||||||
| 206 | Informe de Inspección Post Instalación | 1 | ||||||||||
| 207 | Rigola Prefabricada de Hormigón | 1 | ||||||||||
| 208 | Rejilla Lineal | 1 | ||||||||||
| 209 | Bajante de Talud | 1 | ||||||||||
| SECTION 33 71 02 | ||||||||||||
| 210 | Estructuras Enterradas Prefabricadas | 1 | ||||||||||
| 211 | Estructuras Prefabricadas de hormigón | 1 | ||||||||||
| 212 | Marcos y Cubiertas de Arquetas | 1 | ||||||||||
| 213 | Conductos y Espaciadores | 1 | ||||||||||
| 214 | Cables y Conductores | 1 | ||||||||||
| 215 | Cinta de advertencia e identificación | 1 | ||||||||||
| 216 | Conductores de Tierra | 1 | ||||||||||
| 217 | Picas de Tierra | 1 | ||||||||||
| 218 | Placas de Prueba de puesta a tierra y arquetas | 1 | ||||||||||
| 219 | Comprobaciones y Pruebas para Aprobación In Situ | 1 | ||||||||||
| 220 | Plan y Procedimiento de Instalación de Cables | 1 | ||||||||||
| 221 | Certificados de las Arquetas | 1 |
&"Arial,Negrita"&8QUUG 07-1020. 100%DESIGN SUBMITTAL Resumen de muestras de material, Abril 2018 Página &P de &N