This Statement of Work outlines requirements for electronics development services for the Quantitative Elemental Reconnaissance Instrument (QuERI) to be performed by Noqsi Aerospace in Billerica, MA. The core objective is to design electronics for a two-channel SDD system for spectroscopy and timing, building upon NICER heritage design while integrating an FPGA in place of the microcontroller.

The contractor's duties include translating science requirements into engineering requirements, developing electronic architecture and schematics, providing netlists and materials lists, testing fabricated electronics, making design revisions, preparing documentation, and participating in team meetings. The period of performance runs from December 15, 2024 through September 30, 2025. This appears to be a sole source requirement from NASA's Shared Services Center, with solicitation number 80NSSC25889289Q.

View the file

Other files

File Type Posted
SATPC0037078 Tab 06 RDSS..pdf PDF
SATPC0037078 Tab 07 Capability Statement SAM.gov.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

John P Doty, PhD, Noqsi Aerospace

1. Objective/Requirements

The development of the Quantitative Elemental Reconnaissance Instrument (QuERI) requires the design of electronics for a two-channel SDD system for spectroscopy and timing. Working the from the NICER heritage design, the electronics will integrate an FPGA in place of the microcontroller. Additionally, the electronic architecture will be designed to interface and/or control other system components

(e.g., mechanical shutter, S-ray source electronics).

2. Characteristics, Scope, and Specs

The contractor shall perform the following duties:

• Translation of science requirements to engineering requirements

• Participate in the preparation of interface control documents

• Develop electronic architecture and detailed schematics

• Provide netlists and bill of materials for layout and fabrication and consult on these activities

• Test and characterize the fabricated electronics

• Make revisions to the design as required by the test results

• Prepare detailed engineering documentation

• Prepare reports and participate in team meetings

3. Place of Performance

Noqsi Aerospace, Ltd, Billerica MA

4. Period of Performance

Activities shall be performed December 15, 2024 through September 30, 2025.