STATEMENT OF WORK

Objective/Requirements

1. Preventive and corrective maintenance of one building generator, one uninterrupted power supply (UPS) (and associated batteries) and one switch gear.

2. Daily facility equipment inspections and logging, before and after significant storm inspections and logging, (1) hour response time for corrective action call outs, 48 hours of hurricane ride-out crew (staff in our safe and secure office next door to NSSC monitoring the NSSC building throughout the storm) per year at no charge, OEM involvement in annual maintenance., UPS monthly battery trending.

The contractor shall perform the following duties:

Generators

Periodic facility inspections.

• Physical check on the units each work day. (Approximately 5 times each week and before/after significant storms)

Monthly load testing

• Operate generator under load. Check voltage and frequency.

• Publish a monthly report reflecting all maintenance actions performance by contractor and/or the OEM.

Quarterly Maintenance

• Engine lubrication system: visual check for leaks, change lube oil and filters every 12month or 500 operating hours, whichever occurs first.

• Engine Air cleaners: clean or replace filter as needed.

• Ignition system: check magneto, set timing, as needed.

• Governor. Check and set speed (to OEM spec), sensitivity and oil level.

• Engine Cooling System: Check general condition; check antifreeze and add, if needed.

Check belts and hoses.

• Engine Electric System: Hydrometer test battery; clean and lubricate battery posts cables, load test batteries, check alternator belts, check battery charger for proper operation and output.

• Engine Fuel System: Visually check for leaks, check all visible connections, and flexible hoses; change fuel strainers. Replace flexible hoses as needed, check for water in fuel tank.

• Engine Exhaust System: Visually check for leaks or corrosion, check drain condensation trap and muffler condition and drain condensation trap as needed.

• AC Generator: Visually inspect generator condition, check slip rings and commentator for wear, check lubrication of rear generator bearing.

Miscellaneous:

• Check all instruments for proper operations, check timers and relays for proper operation, check all connections for tightness, check safety circuit, shutdowns and alarms systems.

• Operation: Run engine loaded. Transfer load to make adjustment, if needed.

• Clean up: Wipe down unit, remove used fluids and materials from NSSC location and dispose of them in accordance with EPA, state regulations and contractor facility

Annual Maintenance

All items mentioned in the quarterly maintenance plus;

• Change all fluids using OEM authorized oil and filter.

• Perform hydrometer check to ensure cooling system protections of minimum 0degrees.

Adjust as required.

• Check all electrical connections, inspect insulation for fraying and heat damage.

• Publish annual report for all maintenance performed for the year.

UPS

Periodic facility inspection.

• Physical check on the units each work day.

• Monthly load testing. (includes physical inspection of the unit and recording of all readings)

• Publish a monthly report reflecting all the maintenance actions performed by the contractor and/or the OEM.

Semi Annual Maintenance

• Record Utility Voltage on each log.

• Record current on each log.

• Record DC current on rectifier and battery.

• Record DC Float Voltage.

• Record inverter output voltage.

• Record generator voltage. G. Record generator current.

• Record motor power factor at above load.

• Record all test point voltage.

• Record logic lead.

• Record bypass angle.

• Check fans M. Check hot spot.

• Check m/g vibrations

• Check air filters

• Check UPS room appearance.

• Visual check of obvious signs of over heating.

• Record number of faults.

• Record UPS room temperature.

• Record unit hours.

• Add OEM approved bearing grease, if needed.

• All items mentioned in quarterly maintenance plus; B. Load test UPS (building load, unless otherwise specified and agreed upon with customer)

Batteries

Periodic Facility Inspections

• Physical Check on the units each day. (5 times a week and before/after significant storms)

Monthly Maintenance

• Record each battery voltage reading.

• Record AC ripple.

• Inspect each battery for damage.

• Publish a monthly report reflecting all maintenance actions performed by contractor and/or the OEM.

• Load Testing. Physical inspection of units and record all readings per OEM.

Quarterly Maintenance

• Record each battery voltage reading.

• Record AC ripple.

• Inspect each battery for damage.

• Record impedance reading of each battery.

• All items mentioned in quarterly maintenance plus;

• Annual load test as recommended by OEM.

• Load test each battery.

• Publish annual report covering all maintenance for year.

Automatic Transfer Switch (ATS)

(ANNUAL TASK)

• Log each Automatic Transfer Switch and general condition.

• Log any alarm diagnostic conditions and operations of each ATS.

• Log & visually inspect & check overall ATS environmental temperature / humidity conditions and the mechanical equipment area for any abnormal conditions.

• Log & visually inspect each ATS operational mode & switch configuration for “ready on-line” operational mode.

• Inspect general condition of ATS mechanical equipment room and clean as required.

• Check & log voltage, amps, & frequencies per phase.

• Check all indicator lights, gauges, informational display systems for proper operation.

• Functionally check & log ATS operation in both Manual & Automatic mode. Log time delays for proper sequence & durations.

• Check all indicator lights, gauges, informational display systems for proper operation.

• Visually inspect all electrical connections for discoloration, pitting, tightness & signs of abnormality.

• Visually inspect all electrical contacts & blades for discoloration, pitting, tightness & signs of abnormality.

• Lubricate all moving parts with OEM approved lubricants.

• Inspect ATS’s internal power supplies conditions for proper operation and voltage.

• Inspect and replace internal batteries.

Place of Performance NASA Shared Services Center, Building 1111, Stennis Space Center

Period of Performance

Base with 3 one-year Option Periods

Base Performance will be from May 1st. 2023 to through April 30t, 2024

Option period 1: 05/01/2024 to 04/30/2025 Option period 2: 05/01/2025 to 04/30/2026 Option period 3: 05/01/2026 to 04/30/2027