This document is a Repair Qualification Requirements (RQR) for a Power Supply (NSN: 6130-01-314-7781, P/N: 2001205-002) used in the AN/MST-T1(V) Mini-MUTES system. The document outlines detailed qualification criteria for potential repair sources, including requirements for facilities, testing capabilities, data verification, and repair process verification. Potential offerors must notify the government of their intent to qualify, demonstrate access to necessary facilities and equipment, verify complete technical documentation, and submit a qualification test plan for prior approval by 415 SCMS/GUMBB.
The document also includes six Source Qualification Waiver Criteria (QWC) that may allow partial or full waiver of qualification requirements under specific conditions, such as previous government supply, qualification on similar items, or corporate restructuring. The estimated cost for qualification testing is $13,000, with an expected completion time of 60 days. Offerors must be fully qualified before contract award, though qualification does not guarantee subsequent contract award. The qualification process is associated with a repair services solicitation for the Mini-MUTES program, closing on July 21, 2025, under the Department of the Air Force Materiel Command Air Force Sustainment Center.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ITMDESC_REPORT.pdf | ||
| FA825025Q0011.pdf | ||
| UIIEC_REPORT.pdf | ||
| QAIRQMT_REPORT.pdf | ||
| TRNSPDATA_REPORT.pdf | ||
| CDRLS.pdf | ||
| SPI.pdf | ||
| SOW.pdf | ||
| PWS.pdf | ||
| CAVAF.pdf | ||
| RDL_REPORT.pdf | ||
| PKGRQMT_REPORT.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIR QUALIFICATION REQUIREMENTS
NSN: 6130-01-314-7781
P/N: 2001205-002 Noun: Power Supply Application: AN/MST-T1(V) Mini-MUTES
25 Feb 2025 Section C 1/3
SECTION C:
1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE
a. Prequalification Notice: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this Power Supply.
b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to repair, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.
c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum Southwest Research Institute (26401) drawing 200827879-10. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.
d. Repair Process Verification: The offeror must repair this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUMBB. The offeror shall also identify its sources for materials and its standards for internally used processes.
e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 415 SCMS/GUMBB for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by ESA-approved engineering/technical data package.
f. Qualification Article Verification: N/A
g. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified are $13000.
h. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 60 days. This is based on complexity of the Power Supply and other factors.
P/N: 2001205-002
25 Feb 2025 Section C 2/3
i. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.
j. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.
P/N: 2001205-002
25 Feb 2025 Section C 3/3
2. SOURCE QUALIFICATION WAIVER REQUIREMENTS
Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:
a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).
b. QWC2: The potential source is qualified on the right-hand article and requests to be qualified on the left-hand article. If the right-and left-hand articles are mirror images of each other, then approval can generally be given.
c. QWC3: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.
d. QWC4: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.
e. QWC5: A source qualified to provide a similar or like item can be qualified to provide the required item. However, for approval, the engineering authority must verify that there is no increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written proof, such as purchase orders, shipping documents, etc., to show that the similar item was provided to the original equipment manufacturer or DoD.
f. QWC6: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the repair process.