RFQ 27-1003 Addendum One.pdf

PDF 254 KB Posted

Attached to
RFQ 27-1003, Construction Manager at Risk Services Consolidated Security Screening Checkpoint Project
Solicitation number
CMR-127441
Issued by
Henrico County, Roanoke City, Virginia

About this file

This is an addendum to Request for Qualifications (RFQ) 27-1003 issued by the Capital Region Airport Commission for Construction Manager at Risk (CMaR) preconstruction and construction services for the Consolidated Security Screening Checkpoint Project at Richmond International Airport in Virginia. The project involves an estimated construction cost of approximately $215 million. This procurement follows a two-step competitive negotiation process in which Step 1 requires submission of Statements of Qualifications from qualified Virginia Class A general contractors. An optional Pre-Submittal Conference and site visit are scheduled for Thursday, September 3, 2026, at 2:00 PM EDT in the South Rear Conference Room, with Statements of Qualifications due on Monday, September 28, 2026, at 3:00 PM EDT. No price, fee, cost proposal, or Guaranteed Maximum Price shall be submitted with the initial qualifications; shortlisted offerors will be invited to proceed to Step 2 negotiations.

The addendum modifies or clarifies terms of the original RFQ 27-1003. Specific pricing and payment terms, set-asides, incumbent contractor information, funding sources, and other contract requirements are detailed within the addendum document. Prospective bidders must review both the complete RFQ and this addendum to understand all submission requirements and project specifications prior to responding.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CAPITAL REGION AIRPORT COMMISSION

RICHMOND INTERNATIONAL AIRPORT

SEPTEMBER 2, 2026

NOTICE OF ADDENDUM ONE

REQUEST FOR QUALIFICATIONS #27-1003

CONSTRUCTION MANAGER AT RISK SERVICES FOR THE CONSOLIDATED

SECURITY SCREENING CHECKPOINT PROJECT

The Capital Region Airport Commission (the “Commission”) hereby issues this Addendum to supplement, modify, delete from, or add to the original Request for Qualifications noted above, and all requirements of this Addendum are hereby made a part of the Request for Qualifications and any resulting contract documents. This Addendum, additional information related to this procurement, and the complete Request for Qualifications package are available electronically for download at https://eva.virginia.gov.

The Request for Qualifications (“RFQ”) document shall be amended as follows:

SECTION IV.B - OPTIONAL PRE-SUBMITTAL CONFERENCE AND SITE VISIT, first paragraph, is hereby deleted in its entirety and replaced with the following:

The Commission will conduct an optional, non-mandatory Pre-Submittal Conference at 2:00 PM EDT on Thursday, September 3, 2026, in the South Rear Conference Room at Richmond International Airport. Offerors may attend the conference portion either in person or virtually. Virtual participants may join through Microsoft Teams using the following link: Join the RFQ 27-1003 Optional Pre- Submittal Conference. A site visit will follow immediately and will be available only to in-person attendees.

All remaining provisions of Section IV.B, including the identification and escort requirements applicable to the site visit, remain unchanged.

SECTION I.D - CONCEPTUAL PROJECT SCHEDULE AND PHASING, final paragraph, is hereby deleted in its entirety and replaced with the following:

The anticipated contract award and execution will occur following Commission approval, which is currently scheduled for January 26, 2027. The tentative construction Notice to Proceed is targeted for February 2027, subject to completion of the procurement, Commission approval, and contract execution.

https://eva.virginia.gov/ https://teams.microsoft.com/meet/230357049841304?p=UiKogx4AyviFdU8rqf https://teams.microsoft.com/meet/230357049841304?p=UiKogx4AyviFdU8rqf

ATTACHMENT I - PROCUREMENT SCHEDULE is hereby deleted in its entirety and replaced with the following:

ATTACHMENT I

PROCUREMENT SCHEDULE - SUBJECT TO ADJUSTMENT

Public RFQ Milestones - Step 1

Milestone Date and Time

RFQ Issued Friday, August 28, 2026

Optional Pre-Submittal Conference

Thursday, September 3, 2026, at 2:00 PM EDT (in-person and virtual attendance available)

Site Visit Immediately following the Pre-Submittal Conference (in-person attendees only)

Final Questions Due Thursday, September 10, 2026, at 4:00 PM EDT

Commission Responses/Addendum Thursday, September 17, 2026, at 4:00 PM EDT

SOQs Due Monday, September 28, 2026, at 3:00 PM EDT

Procurement Administrative Responsiveness Review Tuesday, September 29, 2026

Individual SOQ Evaluation September 30-October 5, 2026

Consensus Meeting/Shortlist Recommendation Tuesday, October 6, 2026

Shortlist Notices and Step 2 RFP Issued Wednesday, October 7, 2026

Revised Step 2 Milestones

Milestone Date and Time

Step 2 RFP Issued Wednesday, October 7, 2026

Step 2 Questions Due Monday, October 19, 2026

Step 2 Addendum Issued Monday, October 26, 2026

Step 2 Proposals Due Monday, November 9, 2026

Individual Proposal Evaluation November 9-13, 2026

Step 2 Consensus Meeting Tuesday, November 17, 2026

Offeror Interviews, if needed November 18-19, 2026

Discussions/Clarifications/Negotiations, if needed November 20-December 4, 2026

BAFOs, if needed Week of December 7, 2026

Final Evaluation/Selection Meeting Week of December 14, 2026

Milestone Date and Time

Recommendation/P&C Package Preparation December 15, 2026-January 4, 2027

Planning & Construction Committee Thursday, January 14, 2027

Commission Meeting Tuesday, January 26, 2027

Anticipated Contract Award/Execution Following Commission approval

Tentative Construction NTP February 2027

All dates are tentative and remain subject to adjustment by the Commission through written notice or addendum, as applicable.

EXHIBIT B - NON-SENSITIVE CONCEPTUAL LAYOUT PLANS is hereby issued and incorporated into the RFQ.

The document titled “Exhibit B - Conceptual Plans and Section.pdf,” provided as a separate attachment to this Addendum, replaces the reserved Exhibit B placeholder in the RFQ and constitutes Exhibit B to the RFQ.

THIS WILL END ADDENDUM NUMBER ONE.

Offerors must take note and acknowledge accordingly.

Arquesia S. Haskins, ACE, VCO, VCA

Senior Procurement Specialist

File details come from the government source that posted it. Updated .