RFQ #11-25 Addendum 1.pdf
PDF 139 KB Posted
- Solicitation number
- 66482
- Issued by
- Covington City, Virginia
About this file
This document is an addendum to Request for Qualifications (RFQ) #11-25 for Historic Preservation Consulting Services issued by the Department of Economic Development and Tourism for the City of Hopewell, Virginia. The RFQ seeks to engage a consultant to provide on-call historic preservation consulting services for various projects over a 36-month contract term, with options for three 12-month extensions. The addendum clarifies requirements such as the placement of signed forms, the number of proposal copies, the use of project examples, the requested information for project schedules and budgets, the length of resumes, and the requirements for references.
The RFQ specifies that each sealed bid submission shall include one original and one electronic (USB) version. Respondents may use project examples more than once, and the requested information regarding design schedules, bidding, and budgets is applicable. Short form resumes should be a maximum of 1-2 pages, and reference project descriptions in the appendices are cumulative with those in the resumes. A minimum of three references is required, including the company name, contact information, and other details.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Where should the signed forms be placed in the proposal?
The forms should remain in the order they were provided in.
2. How many copies of the proposal should be submitted?
All bids must be submitted in a sealed envelope. Each Sealed Bid submission shall include one (1) original and one (1) electronic [USB] version.
3. Can a project example be used more than once?
Yes.
4. In the RFP, it states “e. Demonstrated ability to meet schedules. List a maximum of three projects providing such information as design schedule, bidding and award schedule, construction schedule and how these timeframes were met.” The information that is asked to be provided for each example is typically for engineering projects (design schedule, bidding and award schedule). Is the requested information correct for the project examples requested for this RFP?
Yes it is applicable as it relates to sub-consultants
5. In the RFP, it states “f. Demonstrated ability to stay within budget. List a maximum of three projects providing such information as original total project budget, Firm’s estimate at bid time, accepted bid price, change orders and the reason for the change, and all other issues affecting the overall project cost.” The information that is asked to be provided for each example is typically for engineering projects (Firm’s estimate at bid time, accepted bid price, change orders and the reason for the change). Is the requested information correct for the project examples requested for this RFP?
Yes it is applicable as it relates to sub consultants
6. Can you please clarify what length “short form resumes” should be.
Each short form resume should be a maximum of 1-2 pages long
7. The RFP states, “d.…and a maximum of five reference project descriptions in Appendices.” Is this in addition to the projects that will be listed in each of the resumes?
This would be cumulative and not in addition.
8. What is the minimum or maximum number of references required in the Appendices?
A minimum of three (3) references is required.
ADDENDUM # 1
RFQ #11-25 HISTORIC PRESERVATION
CONSULTING SERVICES
DEPARTMENT OF ECONOMIC
DEVELOPMENT AND TOURISM
CITY OF HOPEWELL
JUNE 14, 2024
9. What information is required for the references in the Appendices?
Reference Information Should Include: Company Name, Contact Name/Title, Telephone Number, and Email Address.
10. In the RFP it states under Appendices, “b….personnel by discipline and office location.” Do you want all personnel disciplines and office locations for the entire company or just cultural resources staff only?
Only the staff that are pertinent to the specifications of the project should be included.
Please sign and include this form as part of your bid response to verify receipt of Addendum # 1.
Arquesia S. Haskins
Procurement Officer
Signature of Receipt of Addendum # 1
Date
Company Name