This Request for Proposal (RFP) is for a 120 US Ton All-Terrain Crane for the Oak Ridge National Laboratory (ORNL), managed by UT-Battelle, LLC for the U.S. Department of Energy. The RFP seeks a firm fixed-price subcontract for a crane, with a required delivery date between 03/28/2025 and 09/15/2025. The solicitation is not a small business set-aside and will be awarded using a Lowest Price Technically Acceptable (LPTA) method, with the intent to make a single award to the lowest-priced, technically compliant offeror.
Key proposal details include a response deadline of 03/28/2025 at 3:00 PM, with proposals to be submitted via email to Johnny Hill at hilljl@ornl.gov. The technical proposal is limited to 15 pages and must demonstrate a thorough understanding of the specifications. Payment terms are net 30 days upon final acceptance, with all payments made in U.S. Dollars via electronic funds transfer. Proposals must include a technical proposal, official quote, exceptions/non-compliance statement, conditions of proposal, and supplementary requirements. The NAICS code for this procurement is 333923 for Overhead Traveling Crane, Hoist and Monorail System Manufacturing.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment D_Reps-and-Certs-Abbreviated - 02.10.2025.pdf | ||
| Attachment A_Terms-Conditions-Commerical-Item-August-29-2023 (2).pdf | ||
| Attachment B_UT-Battelle Prime Supplemental Flowdown Document.pdf | ||
| Attachment C_ Specifications 120 US Ton All-Terrain Crane.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL (RFP)
RFP No.:RFP PR355095 For a 120 US Ton All-Terrain Crane
Request for Proposal
BSD-CS-2282
August 9, 2023
REQUEST FOR PROPOSAL (RFP)
1. INTRODUCTION / RFP INFORMATION
RFP issue Date: 03/20/2025 RFP Number: RFP PR355095 RFP Description: 120 US Ton All-Terrain Crane RFP Closing Date and Time: 03/28/2025
Subject/Description: This RFP is to acquire a 120US Ton All-Terrain Crane In Response Refer to: RFP PR355095 120 US Ton All-Terrain Crane
ORNL Procurement Officer: Johnny Hill Phone: 865-576-4451 Email: hilljl@ornl.gov
RFP INFORMATION
NAICS Code: 333923 - Overhead Traveling Crane, Hoist and Monorail System Manufacturing - 1,250 employees
Subcontract Type Anticipated: Firm Fixed Price Small Business Set-Aside: No Description of Supplies/Services Sought: 120 US Ton All-Terrain Crane Required Delivery Date: 03/28/2025 – 09/15/2025
The Oak Ridge National Laboratory (ORNL) is the largest US Department of Energy (DOE) science and energy laboratory, conducting basic and applied research to deliver transformative solutions to compelling problems in energy and security. ORNL is managed and operated by UT-Battelle, LLC (UT-B). ORNL’s diverse capabilities span a broad range of scientific and engineering disciplines, enabling the Laboratory to explore fundamental science challenges and to carry out the research needed to accelerate the delivery of solutions to the marketplace.
UT-B, herein referred to as “Buyer,” is pleased to invite your company, herein referred to as “Offeror,” to submit a proposal in support of the subject effort, as outlined in the attached Statement of Work or Specification and/or Technical Direction.
Buyer reserves the right to update this RFP by amendment prior to date of award.
The Offeror’s proposal shall be prepared in accordance with the information provided in this RFP. Specific responses to the Buyer's requirements are necessary to enable the Buyer to evaluate Offeror’s understanding of, and capability to accomplish the stated objectives. Throughout the proposal, the Offeror shall provide sufficient detail to substantiate the validity of all stated claims, comments, or positions. All proposed concepts must be shown to be technically feasible and achievable within the allotted time limitations, and all performance and schedule requirements must be shown to be realistic. The response shall correspond to the requirements of this RFP, unless otherwise specified in writing by the Buyer.
mailto:hilljl@ornl.gov
BSD-CS-2282
August 9, 2023
2. LIST OF RFP ATTACHMENTS
Attachment No. Description Document Title (Date/Revision)
Attachment A ORNL Terms and Conditions Terms and Conditions – Commercial Item – BSD-
CS-2146 (08/29/2023)
Attachment B Prime Contract T&C Flow Downs
UT-Battelle Prime Supplemental Flowdown Document [Additional Terms and Conditions for Subcontracts/Purchase Orders under Prime Contract No. DE-AC05-00OR22725] (BSD-CS- 2258 dated 11/25/2024)
Attachment C Technical Specification Attachment C_ Specifications 120 US Ton All- Terrain Crane
Attachment D Representations and Certifications
Representations & Certifications – Abbreviated (BSD-CS-2260, dated 02-10-2025)
3. SPECIFICATIONS
Attachment C_ Specifications 120 US Ton All-Terrain Crane
4. PROPOSAL PREPARATION
Preparation of Offers. (a) Offerors are expected to examine the drawings, specifications, descriptions, terms and conditions, and all instructions. Failure to do so will be at the Offeror's risk. (b) Each Offeror shall furnish the information required by the solicitation. The Offeror shall sign the offer. Erasures or other changes must be initialed by the person signing the offer. (c) Unit price for each unit offered shall be shown and such price shall include packing unless otherwise specified. A total price shall be entered for each item offered. In case of discrepancy between a unit price and total price, the unit price will be presumed to be correct. (d) Offeror must state a definite time for delivery of supplies or performance of services unless otherwise specified in the solicitation. Time, if stated as a number of days, will include Saturdays, Sundays, and holidays. (e) Offers in strict accordance with the solicitation are desired. Any exceptions shall be referenced to related documents by title, page, and paragraph, and shall be set forth in detail. (f) This request does not commit ORNL to pay for any costs incurred in the preparation and submission of an offer or for any other costs incurred prior to the execution of an Agreement.
Explanation to Prospective Offerors. Any explanation desired by a prospective Offeror regarding the meaning or interpretation of the solicitation, drawings, specification, etc., must be requested with sufficient time allowed for a reply to reach all prospective Offerors before submission of their offers. Any information given to a prospective Offeror will be furnished to all prospective Offerors if such information is necessary in submitting offers or if the lack of such information would be prejudicial to any other prospective Offerors.
https://contracts.ornl.gov/terms-and-conditions/ https://contracts.ornl.gov/special-articles-and-forms/ https://contracts.ornl.gov/special-articles-and-forms/ https://contracts.ornl.gov/wp-content/uploads/2025/02/Reps-and-Certs-Abbreviated-02.10.2025.pdf https://contracts.ornl.gov/wp-content/uploads/2025/02/Reps-and-Certs-Abbreviated-02.10.2025.pdf
BSD-CS-2282
August 9, 2023
Proposal Format. Offeror is requested to submit their proposal in MS Excel, MS Word, or PDF formats.
Proposals must be submitted on the forms furnished by the Buyer. If no form is provided, Offeror may submit their proposal in a format of their choosing. Refer to Section 6 Competition for additional details on technical and business proposal format.
Contractual / Administrative Authority. No direction to proceed or other instruction to begin work shall be binding upon Buyer except when specifically issued and confirmed in writing by an authorized member of Buyer’s Procurement organization. Offeror’s acceptance of, or reliance upon any direction to proceed or other instruction by Buyer’s technical personnel, or other representatives not specifically authorized to issue formal purchase order commitments, shall be at Offeror’s own risk and shall not constitute a binding purchase commitment upon Buyer.
Acknowledgement of Amendments. Receipt of an amendment to a solicitation must be acknowledged in writing.
Proposal Contact. Any questions regarding any portion of this RFP must be coordinated through the Buyer’s Procurement organization, identified as Buyer’s Contact in the Introduction. No written or verbal correspondence will be permitted with any other member of the ORNL team without coordination through the Buyer’s Procurement organization. Failure to comply with this requirement may result in the Offeror’s disqualification from consideration for award. The Buyer is open to proposal clarification questions/discussions in regard to this RFP via the email address or telephone number provided in the Introduction.
Omissions. It shall be clearly understood that, notwithstanding the detailed requirements contained herein, it is the Offeror’s responsibility to identify and quote any aspect or area which may have been omitted in this RFP, and which will nevertheless be necessary to meet the general requirements of the defined effort.
Proposal Acceptance. Buyer reserves the right to (a) consider proposals or modifications to proposals received after the due date should such action be determined to be in the best interest of Buyer or its customer, and/or (b) make award without written or oral discussion.
Affordability. This effort is in support of the U.S. Government, who has a vital mission and constrained resources, and it is incumbent upon industry to provide our customer with high quality and affordable solutions. ORNL considers this challenge to be a major discriminator in our ability to win and retain business based upon proven performance and demonstrated value to our customers. ORNL has developed a number of initiatives to drive value for our customer and we expect our partners in our supply chain to do the same.
It is requested as part of your proposal in response to this RFP that you articulate and demonstrate specifics in your offer that are affordable and meet or exceed all technical and schedule requirements. Your response to these criteria will be an element of the ORNL proposal evaluation and award decision process.
Order of Precedence. Any inconsistencies between sections of this RFP shall be resolved in accordance with the following descending order of precedence: (1) This RFP; (2) UT-B Prime Flow Downs; (3) ORNL Terms and Conditions; (4) Special Provisions listed within this RFP; (5) Statement of Work/Technical Specifications.
Payment. Payment shall be made by electronic funds transfer. The form for enrolling is available at http://web.ornl/adm/contracts/eft.shtml.
http://web.ornl/adm/contracts/eft.shtml
BSD-CS-2282
August 9, 2023
Signing Authority. The Offerors proposal shall be signed by an official authorized to contractually commit the Offeror; the names, positions, email address, and phone numbers of persons authorized to negotiate this proposal or persons to be contacted for clarification or questions.
Proposal Validity. Statement that identifies proposal validity. Unless otherwise stated in the Offeror’s proposal, the Offeror’s proposal shall be valid for 120 calendar days.
FOB and Shipping Terms. Offeror’s proposal shall be based and include all costs to deliver all items FOB Destination or other shipping terms that clearly demonstrate Offeror’s intentions of delivery to Buyer’s address at no cost to the Buyer. Crane shall not be driven to site.
Offeror Business Information. Complete business address of the Offeror, the corporate name to be used on any resultant contract, and the remittance address if different from that above. Identify “parent company” or “sponsoring corporation” name, also provide such identity as appropriate.
5. COMPETITION
This RFP is being issued on a competitive basis. The Buyer intends to make one award.
Response Due Date. Your response to this request is due on or before 3:00pm on 03/28/2025. All proposal documents shall be sent to the attention of Johnny Hill via email at hilljl@ornl.gov.
Questions. Questions concerning this RFP must be submitted in writing, via email, to the ORNL Procurement Officer listed in section 2 of this RFP by 3:00pm on 03/25/2025. Information given to one prospective offeror will be furnished to all prospective offerors if lack of the information would be prejudicial to them.
Withdrawal of Offers. Offers may be withdrawn by written notice received at any time before award.
Proposal Package. A complete proposal package consists of the following elements:
Technical Proposal Official Quote Exceptions/Non-Compliance Conditions of Proposal / Assumptions Supplementary Requirements
TECHNICAL PROPOSAL REQUIREMENTS:
The Technical Proposal shall not exceed 15 pages.
The technical proposal needs to be specific, detailed, and complete to demonstrate clearly and fully that the Offeror has a thorough understanding of the Buyer’s requirements listed in Attachment C_ Specifications 120 US Ton All-Terrain Crane. The technical proposal must enable the technical evaluators to make a thorough analysis and arrive at a sound determination as to whether or not the proposal meets the Buyer’s requirements. The proposal shall include descriptions sufficient to
BSD-CS-2282
August 9, 2023 describe the Offeror’s technical approach. The technical proposal must be sufficient to show how the Offeror proposes to comply with the Buyer’s requirements, and it must include a full explanation of the methods proposed. The Offeror shall include a glossary of acronyms and special terminology.
Schedule. Provide a schedule for delivery of items specified in the Attachment C_ Specifications 120 US Ton All-Terrain Crane. Delivery schedules shall be indicated for phases or segments, as applicable, as well as for the overall program. Schedules shall be shown in terms of calendar months from the date of authorization to proceed or, where applicable, from the date of a stated event, as for example, receipt of a required approval by the Buyer. Unless the request for proposal indicates that the stipulated schedules are mandatory, they shall be treated as desired or recommended schedules. In this event, proposals based upon the offeror's best alternative schedule, involving no overtime, extra shift or other premium, will be accepted for consideration.
Official Quote:
All proposals shall be submitted in U.S. Dollars (USD). The Offeror shall submit one price to include all required materials and warranty.
This proposal may be subject to a government price audit.
Equipment. Include a breakdown of each item with pertinent pricing.
EXCEPTIONS/NON-COMPLIANCE:
Exception(s) to or non-compliance with any portion of this RFP shall be clearly identified in a separate Exceptions/Non-Compliance section referencing the specific document, page, paragraph, and item.
Exceptions identified in the Offeror’s Technical Proposal need not be restated in this section. You are requested to explain the reason(s) for the non-compliance and identify any alternate solutions to achieve compliance. Any exceptions that are taken to the provisions of this RFP will be considered in evaluating the Offeror’s proposal and may result in your offer being deemed non-responsive. The absence of a proposal section entitled “Exceptions/Non-Compliance” or a statement indicating “no exceptions are taken” implies complete and unequivocal acceptance of all requirements, terms, and conditions.
CONDITIONS OF PROPOSAL/ASSUMPTIONS:
The Offeror shall identify any conditions and/or assumptions of its proposal in a separate Conditions of Proposal/Assumptions section. The Offeror shall include a list of any Buyer/Government equipment and/or information needed as a condition of performance. Offeror shall include its assertion of Limited or Restricted Rights in Data and/or Software.
SUPPLEMENTARY REQUIREMENTS:
Representations and Certifications – Abbreviated. If your proposal exceeds $10,000, Offeror must complete and return a copy of the Representations and Certifications – Abbreviated (BSD-CS-2260) form, a copy of which can be found here: https://contracts.ornl.gov/special-articles-and-forms/.
Small Business Subcontracting Plan. If your offer, including options, is $700,000 or more and the Offeror is a large business, the Offeror shall submit a Small Business Subcontracting Plan that fully meets the
BSD-CS-2282
August 9, 2023 requirements of FAR 52.219-9 or complete the ORNL Small Business Subcontracting Plan Form (BSD-CS- 2129). A copy of this form can be found here: https://contracts.ornl.gov/special-articles-and-forms/. Annual small business reporting will be required via the Electronic Subcontracting Reporting System (http://www.esrs.gov).
Certified Cost and Pricing Data. Offerors are not required to submit certified cost or pricing data with their offer; however, such data may be requested by the Buyer prior to award.
Foreign End Products. The Offeror shall list as foreign end products those end products that are manufactured outside of the United States that do not qualify as domestic end products. List all foreign end products proposed and their country of origin.
Patent Rights. If the Special Provisions section of this RFP includes either the "Exhibit IB, Patent Rights – Acquisition by the Government" or the "Exhibit 1C, Patent Rights - Retention by the Seller (Short Form)" clause, and you have requested an advance waiver of patent rights, Offeror shall submit a copy of the form (attachments are not necessary) that you submitted to the DOE Patent Counsel. (See the form entitled "Exhibit 2B - Petition for Advance Waiver of Patent Rights" found here: https://contracts.ornl.gov/exhibits/.)
6. BASIS OF AWARD
Basis of Award – Lowest Price Technically Acceptable (LPTA). An award resulting from this solicitation will be made to the responsible Offeror submitting the lowest-priced offer that meets all specified requirements. Offers will be evaluated for technical acceptability under each of the factors listed below. An offer that is evaluated as unacceptable under any factor will not be considered for award. In your proposal, please clearly document how your offer meets or exceeds the below listed acceptability factors. Note and explain any deviation from the specifications. Make specific written response to items that cannot be met as specified in the specifications.
Technical Acceptability Factors:
1. Provide the requested item per Specification (Attachment C_ Specifications 120 US Ton All-Terrain
Crane) or equivalent per FAR 52.211-6.
7. SPECIAL PROVISIONS
Operating/Maintenance Manual (JUL 2014) Documents shall be submitted that contain the operational procedures, instructions, maintenance, spare parts list, and handling precautions.
Packing and Shipping (JUL 2014) The Seller is responsible for all packing and shipping provisions to ensure that the system arrives at the Company’s site in an undamaged, working condition. The Seller shall inform the Company of shipping plans two weeks before actual shipment.
http://www.esrs.gov/ https://contracts.ornl.gov/exhibits/ https://www.acquisition.gov/far/52.211-6#:%7E:text=(a)%20If%20an%20item%20in,are%20specified%20in%20the%20solicitation.&text=(4)%20Clearly%20describe%20any%20modifications,product%20referenced%20in%20the%20solicitation.
BSD-CS-2282
August 9, 2023
Imports to ORNL (11/2022) Critical Communication
(a) The Seller shall specify on the bill of lading or air waybill (e.g., "Notify Party", "Broker Select", "Handling Information" fields) that the Company's customs broker be notified to arrange U.S. Customs clearance. This directive should identify the broker as:
V. Alexander & Company 110 Tyson Blvd., Suite 202, Alcoa, TN 37701 Attn: Import Department Contact: Amalia Joyce, ajoyce@valexander.com Phone: 865-970-7461, Fax: 865-970-7490 knoxvilleimportdocs@valexander.com
(b) The location for U.S. Customs clearance to occur shall be specified as:
U.S. Port 2016 - Knoxville, Tennessee
(c) Importer Security Filing (ISF) regulations require transmission of the 10+2 data elements 24 hours prior to the Mother vessel sailing date. A Seller using ocean transport must provide V. Alexander with the completed ISF Form, Commercial Invoice(s), and Packing list(s) via email at least 72 week-day hours prior to loading onboard the Mother vessel.
Instructions to submit ISF data:
1. Email the below items to ISF@valexander.com at minimum 72 hours prior to the Mother Vessel estimated sailing date (ETD).
**Please only include one ISF form per email**
• Completed ISF Form or ISF Details
• Commercial invoice(s)
• Packing list(s)
2. Email Subject Line should include:
• Estimated Sailing Date (ETD) of the Mother Vessel
• Importer of Record Name
• ISF revisions, ISF amendments, or ISF questions should be emailed only to isfoperationsknoxville@valexander.com
(d) The shipment shall be consigned to the following:
UT-Battelle, LLC Oak Ridge National Laboratory (ORNL)
BSD-CS-2282
August 9, 2023 for the U.S. Department of Energy 1 Bethel Valley Road Oak Ridge, Tennessee 37831 Contact:
Goods Recipient/Invoice Approver): Tony Luttrell Jr.
Phone: 865-382-6885
(e) Delivery terms are Incoterms 2020 FOB Dest - Freight Prepaid, via freight line.
Note: Fees, fines, and/or other assessments resulting from failure to follow these critical communication steps will be recouped from the Seller.
Process
(a) Material(s) purchased under this agreement may be exempt from United States import duties. The following provisions are included to ensure no duty is improperly paid.
(b) Not withstanding any other provision of this agreement, delivery terms are (as shown in Item (e) above) Oak Ridge, TN, USA. The Seller shall not include in the purchase price the amount for duty unless such duty is specifically identified as a separate line item in the price. Any amount improperly included by the Seller shall be subject to setoff and/or recoupment.
(c) Except as noted, no later than 72 hours before shipment of any foreign material, the Seller shall provide the following documents to the Company's Import Broker and Company's Transportation Department at the addresses provided below:
(1) bill of lading/airway bill naming UT-Battelle LLC as the consignee (required by day of shipment) [Note:
use express bill of lading for ocean transport]
(2) commercial invoice for items to be delivered to Oak Ridge, TN, USA,
(3) itemized packing list,
(4) name of carrier, and
(5) estimated delivery date.
(d) The commercial invoice shall include, at a minimum:
(1) name and address of the manufacturer
(2) description of the item(s),
(3) quantities of the item(s) described,
(4) value of the item(s) to be delivered in US Dollars,
(5) HTSUS number,
(6) country of origin,
(7) US Customs Entry in Knoxville, TN, USA; Port 2016; McGhee/Tyson Airport (TYS),
(8) Incoterms,
(9) purchase order number (if applicable),
(10) ORNL contact name (goods recipient/invoice approver), and
BSD-CS-2282
August 9, 2023
(11) project name (e.g., SNS, CNMS, ITER, etc. - if applicable).
All documents listed above shall be in English.
(e) No later than the day of shipment of any foreign material, the Seller shall provide written notice to Company's Import Broker confirming the name of the carrier and estimated date of arrival, and if available, the flight number or name of the transporting vessel. Note that additional data must be electronically provided at least 72 hours prior to loading if ocean transport will be utilized.
(f) Notices for the Company's Import Broker shall be sent via e-mail to: V. Alexander and Company, Inc., Attn: Import Department; E-mail: knoxvilleimportdocs@valexander.com mwilson@valexander.com
(g) Notices for the Company's Transportation Department shall be sent via e-mail to: logistics@ornl.gov
(f) All shipping documents and packages shall be clearly marked with the following:
Shipment to ORNL for the United States Department of Energy under Contract No. DE-AC05-00OR22725.
Upon arrival of shipment, NOTIFY V. ALEXANDER AND COMPANY (865) 970-7461 FOR CUSTOMS
CLEARANCE.
Delivery Hours NOTE: Deliveries are accepted Monday through Friday, from 7:00 a.m. to 3:00 p.m. (Local Time). Any shipment offloads that require the use of a crane after 1:00 p.m. must be coordinated specifically with the Company's Receiving Department or may be rejected.
Final Acceptance Final acceptance of equipment will be at Oak Ridge, Tennessee. Inspection and tests deemed necessary to show full compliance with the requirements of this Agreement will be made.
Exhibit 2, Representation of Limited Rights Data and Restricted Computer Software BSD-CS-2005
Exhibit 9 Technical Data BSD-CS-2012
Exhibit 17 Rights to Proposal Data (Technical) BSD-CS-2024
8. PAYMENT TERMS
Payment terms are Net 30 days upon final acceptance of the product/service. All payments will be made in U.S. Dollars (USD). Payment shall be made by electronic funds transfer.
BSD-CS-2282
August 9, 2023
9. CLOSING
If any additional information be required or you have any questions on any part of this RFP please contact the ORNL Procurement Officer for this RFP as stated in section 1 above.
File details come from the government source that posted it. Updated .