This is a Request for Proposals (RFP) issued by the Village of Mexico, New York, for insulation and soundproofing services related to the Beck's Hotel Redevelopment Project, with Lake Ontario RE HoldCo, LLC as the project owner. The RFP seeks a contractor to provide thermal insulation and sound attenuation improvements for the rehabilitation of a historic hotel constructed in 1851 into a mixed-use facility comprising a first-floor restaurant and banquet space with a full commercial kitchen and second-floor residential apartments. The scope of work includes supply and installation of fire-retardant insulation materials in exterior wall cavities, attic/roof assemblies, and floor assemblies; soundproofing installation in walls between residential units and between residential and commercial spaces; air sealing at penetrations; and coordination with other trades while preserving historic elements. The project is funded through the Restore NY Communities Initiative administered by Empire State Development. Sealed proposals must be submitted electronically via email to Jamie Hawksby, Project Manager, at BecksHotel3302@gmail.com by August 18, 2026 at 12:00 PM. A mandatory walk-through is scheduled for July 28, 2026 from 10:00 AM to 12:00 PM, requiring pre-registration. Written questions must be submitted by August 5, 2026 at 12:00 PM, with responses shared among all prospective proposers.
Proposers must demonstrate relevant experience with rehabilitation, mixed-use, or historic projects through two to three project examples and provide at least two owner or client references. The evaluation criteria include relevant experience and qualifications, understanding of project scope and constraints, staffing and coordination approach, cost proposal, ability to meet MWBE/SDVOB participation goals, project schedule, and references. The project is subject to Minority and Women-Owned Business Enterprise (MWBE) participation goals of 30 percent and Service-Disabled Veteran-Owned Business (SDVOB) participation goals of 6 percent, with proposers required to submit utilization plans and documentation of intent to subcontract to certified firms. The selected contractor must maintain workers' compensation, commercial general liability of $2,000,000 aggregate, business automobile liability of $1,000,000 combined single limit, and professional liability of $1,000,000. The NAICS codes for this project are 238310 and 423330.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP #6 Drawings (Insulation and Soundproofing).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Village of Mexico Lake Ontario RE HoldCo, LLC
Request for Proposals
Becks Hotel Renovation Project Owner: Lake Ontario RE HoldCo, LLC Administering Entity: Village of Mexico
RFP #6 INSULATION AND SOUND PROOFING
Village of Mexico Address:
PO Box 309 3236 Main Street Mexico, NY 13114
Village of Mexico Phone Number:
315-963-7564
Primary Email Contact:
Jamie Hawksby, Project Manager Email : BecksHotel3302@gmail.com
1. Notice to Proposers:
Sealed proposals will be received by the Village of Mexico, electronically via email to Jamie Hawksby, Project Manager, at BecksHotel3302@gmail.com until August 18th, 2026 at Noon, for the following:
Project: Beck’s Hotel Redevelopment – INSULATION AND SOUND PROOFING
RFP # 6
Proposals received after this deadline will not be considered. Proposals may not be submitted via fax. This project is funded through the Restore NY Communci8ites Initiative administered by Empire State Development, with the Village of Mexico as the award recipient and pass through funding to Lake Ontario RE HoldCo, LLC.
Copies of this RFP may be obtained from the Village Clerk’s Office or requested via email at BecksHotel3302@gmail.com
The Village of Mexico reserves the right to reject any or all proposals, waive informalities, and award contracts in whole or in part, consistent with applicable law.
A walk-through date will be scheduled for July 28th, 2026 at 10:00AM-12:00PM Please pre—register by emailing Project Manager Jamie Hawksby at BecksHotel3302@gmail.com
Questions regarding this RFP must be submitted in writing to Project Manager Jamie Hawksby at BecksHotel3302@gmail.com no later than August 5th, 2026 at Noon. Responses will be shared with all prospective proposers.
2. Project Background and Overview The building historically known as John Beck’s Hotel was constructed in 1851 and remains a century-old architectural and social landmark int eh Village of Mexico, New York.
Key features include:
· Full basement with mortared stone foundation walls
· Two-story brick masonry construction
· Historic woodwork and architectural detailing
In 2025, new ownership-initiated plans to redevelop the building into a mixed-use facility including:
· A full-service restaurant and banquet facility on the first floor
· Six (6) apartment/short-stay suites on the second floor
The project's goal is to preserve historic character while meeting modern structural design standards, NYS Building Code requirements, ADA accessibility standards, and life-safety requirements.
3. Project Description
First Floor – Commercial Assembly (A-2 Occupancy)
· Full commercial kitchen, dining, and bar areas
· Separate reception and banquet rooms
· New public restrooms
· Seasonal outdoor dining space
· ADA-compliant public access
· Suspended acoustical ceiling system concealing MEP systems
· Modern lighting integration
Second Floor – Residential (R-2 Occupancy)
· Six apartment/short stay suites designed for modern living
· Code-compliant egress and accessibility
· Rated floor/ceiling separation between occupancies
· Updated mechanical, electrical, and plumbing systems
Selective demolition will be required to modernize the space while preserving historic woodwork and other character-defining elements.
Scope of Work – Insulation and Soundproofing
The selected Insulation Contractor shall furnish all labor, materials, equipment, supervision, and coordination necessary to provide thermal insulation and sound attenuation improvements for the Beck’s Hotel rehabilitation project.
All insulation and soundproofing materials provided under this scope shall be fire-retardant and suitable for use in a mixed-use, multi‑story building.
Included in Base Bid A. Thermal Insulation
· Supply and installation of fire-retardant insulation materials in:
· Exterior wall cavities where accessible
· Attic and/or roof assemblies (if applicable)
· Floor assemblies over unconditioned spaces, including basement areas
· Insulation materials shall meet or exceed NYS Energy Code requirements
· Air sealing at penetrations and transitions associated with insulation work
· Coordination with framing, drywall, mechanical, and electrical trades
· Preferred fire-rated mineral wool (rock wool) where possible. Fire-retardant fiberglass batts or approved equal materials may be used subject to approval.
B. Soundproofing / Acoustic Control
· Installation of fire‑retardant sound attenuation insulation in:
· Walls between residential units
· Walls and/or ceilings separating residential units from the first floor restaurant and banquet spaces
· Floor/ceiling assemblies between occupied spaces, where accessible
· Acceptable materials include fire‑rated mineral wool, fire-retardant fiberglass batts, or approved equal
· Installation methods shall minimize sound transmission and flanking paths
· Preferred fire-rated mineral wool (rock wool) where possible. Fire-retardant fiberglass batts or approved equal materials may be used subject to approval.
C. Fire Retardant Material Requirements
· All insulation and soundproofing materials shall:
· Be fire-retardant or fire-resistant
· Comply with applicable NYS Building Code fire and life safety requirements
· Be installed in accordance with manufacturer recommendations and code requirements
· Product data sheets shall be submitted upon request to verify fire-retardant properties D. General Requirements
· Field verification of existing conditions
· Protection of existing finishes and historic elements
· Proper handling and disposal of waste materials
· Final inspection and punch list completion
Historic Building Considerations
· Insulation methods shall be compatible with historic masonry and wood framing
· Materials shall not trap moisture or damage historic construction
· Work shall minimize disturbance to existing historic materials
Exclusions The following are excluded unless specifically noted in the bid:
· Structural modifications
· Specialty sound isolation systems (resilient channel, isolation clips, floating floors)
· Drywall replacement or finish painting beyond minor patching Any work not specifically excluded shall be deemed included in the Base Bid.
All plans showing RFP # 6 INSULATION AND SOUND PROOFING will be labeled with Prefix A-200, A-201, S-200, S-201
The selected contractor will provide all labor, supervision, coordination, and services necessary to complete the work associated with their discipline, including but not limited to:
· Review of project drawings and specifications
· Coordination with Owner and project team
· Compliance with applicable NYS and local codes
· Field coordination with other trades
· Site safety and protection of historic elements
· Participation in inspections and close‑out activities
Permitting and Regulatory Compliance
· NYS Building Code compliance
· Sealed drawings and calculations
· Coordination with code officials
· Support during permit review
Construction Phase Services
· Respond to RFIs
· Review drawings
· Review submittals related to scope of work components
· Periodic site visits
· Filed observation reports
· Construction administration support
Historic Considerations
· Preservation-sensitive structural solutions
· Reinforcement strategies minimizing impact to historic materials
· Documentation of existing structural conditions
· Solutions balancing modernization and historic integrity
4. NAICS Code NAICS Code: 238310, 423330
5. MWBE/SDVOB Participation
This project is subject to Contractor and Supplier Diversity requirements administered by Empire State Development.
Participation Goals:
· MWBE – 30%
· SDVOB – 6%
Proposers must:
· Provide proof of certification if applicable
· Submit MWBE/SDVOB utilization plan
· Include documentation of intent to subcontract to certified firms MWBE/SDVOB participation will be included in proposal evaluation scoring.
6. Proposal Requirements
· Firm Information
· Company name, address, and contact
· NYS licensing (if applicable)
· Relevant Experience
· 2–3 similar projects (rehab, mixed‑use, or historic preferred)
· Approach
· Understanding of the project
· Staffing plan and on‑site presence
· Cost Proposal
· Fee or price structure
· Assumptions and exclusions clearly stated
· References
· At least two (2) owner or client references
7. Proposal Submission Instructions
Submit proposals in PDF format via email to:
Jamie Hawksby, Project Manager Email: beckshotel3302@gmail.com Subject Line: RFP – Beck’s Hotel – [RFP # and Type] – [Firm Name]
Submission Deadline: AUGUST 18TH, 2026 12:00PM Late submissions will not be considered.
8. Evaluation Criteria (weighted) Award will be made to the most qualified, responsive, and reasonable proposer whose proposal best serves the interests of the Village of Mexico and project stakeholders.
Proposals will be evaluated based on:
· Relevant experience and qualifications
· Understanding of project scope and constraints
· Staffing and coordination approach
· Cost proposal
· Ability to meet MWBE / SDVOB participation goals
· Project schedule
· References
The Village of Mexico reserves the right to reject any or all proposals and to select the proposal that best serves the project and public interest.
9. Insurance and Indemnification
The selected firm small maintain, at minimum:
· Workers’ Compensation and NYS Disability Insurance
· Commercial General Liability - $2,000,000 aggregate
· Business Automobile Liability - $1,000,000 combined single limit
· Professional Liability (Errors and Omissions) - $1,000,000
The selected firm shall indemnify, defend, and hold harmless the Village of Mexico, its officers, employees, and agents from claims arising from the performance of services under this contract.