CUI
Request for Information (RFI) For Dense Plasma Focus (DPF) Facility Modernization for Tritium Gas Handling
1.0 Purpose
This Request for Information (RFI) is to obtain information for the purpose of market research which may inform future requirement and contract efforts for facility architectural and engineering modernizations to support the use of Tritium gas. Tritium gas will be employed in support of a Dense Plasma Focus (DPF) machine.
2.0 Introduction
The U.S. Army Contracting Command – Orlando (ACC-Orlando) in support of the U.S. Army Program Executive Office for Simulation, Training and Instrumentation (PEO STRI), Project Manager for Cyber, Test & Training (PM CT2) Instrumentation Management Office (IMO), and the U.S. Army White Sands Missile Range Survivability, Vulnerability and Assessment Directorate (WSMR SVAD) is performing research to gather information and feedback from interested Architectural and Engineering (A&E) firms which have demonstrated knowledge in space planning, design, and construction oversight in facilities that utilize and operate Tritium Gas to assist the Government with construction level plans (architectural, civil, mechanical, electrical, plumbing, fire protection, and telecommunication) and specifications for the modernization of an existing facility at WSMR that will house the Dense Plasma Focus machine utilizing Tritium gas.
Program Description and Background: PM CT2 IMO has a requirement to develop, procure, integrate, and field major and minor test instrumentation systems in support of developmental and operational military systems testing conducted at Major Range and Test Facility Base sites. The DPF is a Central Test and Evaluation Investment Program (CTEIP) effort to provide Pulsed Neutron Effect (PNE) capabilities. The DPF is currently in the CTEIP Phase I. During Phase I the DPF team has identified the need to use Tritium gas to enable the DPF machine to achieve the required performance criteria.
Information Sought: Provide sample projects your company has completed in the past that incorporated Architectural & Engineering Design Solutions related with Tritium Gas type projects. Has your Company performed this type of effort or similar type effort in the past? If so, provide contact number and name for reference and a brief description of your direct support of the effort.
Provide an estimated top level ROM of the anticipated A&E design costs associated with Architectural & Engineering modernizations required to produce construction level plans and specifications with the following key milestones (same deliverables as noted below):
· Conceptual Design
· Preliminary Design Drawings
· 60% Construction Documents
· 100% Construction Documents
Provide an estimated schedule of the design effort required to produce the following key deliverables:
· Conceptual Design and ROM Cost Estimate of Construction
· Preliminary Design Drawings and Updated ROM Cost Estimate of Construction
· 60% Construction Drawings
· 100% Construction Drawings and Specifications and 100% Cost Estimate of Construction
Applicable NAICS Codes: 541310, 541330
Refer to attached pictures below showing existing site and building conditions. Existing building is estimated at 2,800 square feet. It is the intent to completely demolish all existing Mechanical/Electrical/Plumbing and Architectural doors infrastructure, and add an estimated 2,000 square feet of support spaces to this existing facility in addition to site improvements for parking, deliveries, maintenance, and disposal.
Acquisition Strategy: The Government is exploring a range of acquisition strategies and plans to utilize the information gained from responses to this RFI to help further shape the acquisition strategy. The contract type for this effort has not yet been determined.
Response Requested: Persons/firms contemplating submission of a response should carefully examine this RFI and are encouraged to contact the technical Point of Contact (POC) to ascertain the extent of interest in an approach or for clarification(s). Interested parties in any or all of these areas should provide information on their knowledge of and experience in the design, development, implementation and documentation of Tritium facility design.
Sources having the capabilities to meet all of the RFI topic requirements are invited to respond to this notice no later than close of business on October 27, 2021 at 12:00 PM Eastern Standard Time (EST). If your submittal contains company proprietary information it should be marked accordingly. If your submission contains unclassified but sensitive information it should be properly labeled, handled, and transmitted in accordance with the National Industrial Security Program Operating Manual (NISPOM). Classified responses are not desired and will not be reviewed. Submissions to this RFI will not be returned. Any information submitted in response to this RFI Notice is strictly voluntary. This notice is for information planning purposes and the Government will not pay or otherwise reimburse respondents for information submitted.
Electronic responses are required and shall be submitted to: Felecia Charles; felecia.c.charles.civ@mail.mil and PEO STRI Lead Systems Engineer/APM, Erick Serrano, PE, erick.s.serrano.civ@mail.mil. All emails should include in the subject line A&E for DPF and the submitting organization’s name. All documentation shall become the property of the Government.
Disclaimer: This notice does not constitute an invitation for bids or a request for proposal and is not a commitment by the U.S. Government to procure subject products or services nor will the Government reimburse any parties for costs associated with this request. The Government will use the information received to forge its acquisition strategy. Additionally, all submissions become Government property and will not be returned. No basis for a claim against the Government shall arise as a result from a response to this RFI.
The information provided in this notice is subject to change and is not binding to the Government. The Government does not intend to award a contract on the basis of this notice.
Feedback and/or evaluation information will not be provided to any firm regarding their individual capability statements.
RESPONSE INSTRUCTIONS:
Responses shall include documentation of technical expertise and capability in sufficient detail for the Government to determine that your company possesses the necessary functional area expertise and experience to compete for this acquisition.
It is imperative that business concerns responding to this announcement articulate their capabilities clearly and adequately; if not capable of performing individual tasks or aspects of the tasks described, provide a description of the specific aspects of the proposed requirement that would prevent or limit your capability to perform.
1. Only email submissions will be accepted.
2. Use MSOffice compatible (.xlsx, .docx or .pptx) or Adobe Acrobat 9 Pro (.pdf) formats.
3. Classified material will not be accepted.
4. Material samples will not be accepted.
5. The cover sheet shall include the following company information: name, address, URL, POC name and email address, Commercial Government Entity (CAGE) code number, Data Universal Numbering System (DUNS) Number, business type and size, and a statement if your firm is or is not foreign owned, foreign controlled, or has foreign influence.
CONFIDENTIALITY:
No proprietary, classified, confidential, or sensitive information should be included in your response. The Government reserves the right to use any non-proprietary
Controlled By: PM CT2 IMO CUI Category: CUI//SP-CONTRACTS Limited Dissemination Control: FEDCON POC: Erick Serrano, (407) 384-5128