This is a Request for Bids (RFB) issued by the Wayne County Airport Authority (WCAA) for moving walkway removals at Detroit Metropolitan Wayne County Airport. The project involves removing a total of six moving walkways - four at the Big Blue Parking Deck, one at the McNamara Parking Deck, and one at the Evans Terminal International Arrivals. The exposed flooring will be infilled to match existing surrounding floor conditions. The bid is scheduled for release on 8/13/25, with a virtual pre-bid conference on 8/19/25, pre-bid questions due by 8/28/25, and the bid deadline set for 9/10/25 at 2:00 PM. The anticipated contract award is in October 2025, with project completion timelines varying by package: McNamara Parking Deck (60 calendar days), Big Blue Parking Deck (75 calendar days), and Evans Terminal International Arrivals (60 calendar days).

The project requires a Small Business Enterprise (SBE) participation goal of at least 25%, with responses including 30% or more voluntary participation potentially eligible for SBE Equalization Credits. Bidders must provide a bid guarantee of 5% of the total potential bid value. The contract is subject to prevailing wage requirements, and contractors must comply with extensive insurance requirements, including $5,000,000 in Commercial General Liability coverage and $5,000,000 in Automobile Liability. Liquidated damages are specified at $1,300 per day for failure to meet Substantial Completion dates and $500 per day for Final Completion delays. The project is non-federally funded and will be conducted at a fully operational airport that is active 24 hours a day, 365 days a year, with strict security and safety protocols.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR BIDS

FOR

MOVING WALKWAY REMOVALS

SOLICITATION NO. 25-01753

(NON-FEDERALLY FUNDED)

Action Date Time

RFB issued 8/13/25 Pre-Bid (Virtual) Conference

(Recommended/Not Mandatory)

8/19/25 10:00AM

Pre-Bid Question Deadline (purchasing.questions@wcaa.us)

Reference RFB #25-01753 in all emails

8/28/25 2:00PM

Bid Deadline 9/10/25 2:00PM Public Bid Opening* 9/10/25 2:15PM

Board Date** 10/29/25

*As Read Bid Totals will be posted to MITN the next the Business Day.

**Anticipated dates. Subject to change.

Pre-Bid Meeting: TEAMS meeting: To expedite preparing the virtual sign-in list of attendees, for the record and distribution, submit a list of potential virtual participants via email to purchasing.questions@wcaa.us by 08/18/2025. The list should include the participant’s name, company name and phone number.

https://teams.microsoft.com/meetingOptions/?organizerId=10e0f3a8-

66f8-49e9-a6ce-5d75e709385d&tenantId=3dd77ff2-4b51-432b-b1fa-c6b44af89de7&threadId=19_meeting_NTY1ZTRiYzQtYzMxYS00ZWIzL WFlMGYtYzAwNzVjOGQ1MWNi@thread.v2&messageId=0&language= en-US

Bid Submittal Location: https://www.bidnetdirect.com/mitn/wayne-county-airport-authority Registration and Submittal technical assistance: 1-800-835-4603 Monday – Friday, 8:00 am – 7:30 pm (Eastern Time)

Free and paid subscription registration options available

Public Bid Opening: In lieu of an onsite meeting, a virtual (audio-only) Bid Opening will be held, at the date, and time indicated on the cover of this RFB. The telephone access information is as follows:

Phone number: 888.278.0296 Access Code: 2554780# To expedite preparing the virtual sign-in list of attendees, for the record and distribution, submit a list of potential virtual participants via email to purchasing.questions@wcaa.us. The list should include the participant’s name, company name and phone number.

Procurement Contact: CHARMAINE DYSON, SENIOR BUYER Phone: (734) 247-7900, Fax: (734) 955-5648 purchasing.questions@wcaa.us

All questions regarding this RFB must be submitted to the Procurement Contact at the above number and email address. Contact concerning this RFB with any other employee, officer or Board Member of the Airport Authority is not permitted during the solicitation process.

mailto:purchasing.questions@wcaa.us https://teams.microsoft.com/meetingOptions/?organizerId=10e0f3a8-66f8-49e9-a6ce-5d75e709385d&tenantId=3dd77ff2-4b51-432b-b1fa-c6b44af89de7&threadId=19_meeting_NTY1ZTRiYzQtYzMxYS00ZWIzLWFlMGYtYzAwNzVjOGQ1MWNi@thread.v2&messageId=0&language=en-US https://teams.microsoft.com/meetingOptions/?organizerId=10e0f3a8-66f8-49e9-a6ce-5d75e709385d&tenantId=3dd77ff2-4b51-432b-b1fa-c6b44af89de7&threadId=19_meeting_NTY1ZTRiYzQtYzMxYS00ZWIzLWFlMGYtYzAwNzVjOGQ1MWNi@thread.v2&messageId=0&language=en-US https://teams.microsoft.com/meetingOptions/?organizerId=10e0f3a8-66f8-49e9-a6ce-5d75e709385d&tenantId=3dd77ff2-4b51-432b-b1fa-c6b44af89de7&threadId=19_meeting_NTY1ZTRiYzQtYzMxYS00ZWIzLWFlMGYtYzAwNzVjOGQ1MWNi@thread.v2&messageId=0&language=en-US https://teams.microsoft.com/meetingOptions/?organizerId=10e0f3a8-66f8-49e9-a6ce-5d75e709385d&tenantId=3dd77ff2-4b51-432b-b1fa-c6b44af89de7&threadId=19_meeting_NTY1ZTRiYzQtYzMxYS00ZWIzLWFlMGYtYzAwNzVjOGQ1MWNi@thread.v2&messageId=0&language=en-US https://teams.microsoft.com/meetingOptions/?organizerId=10e0f3a8-66f8-49e9-a6ce-5d75e709385d&tenantId=3dd77ff2-4b51-432b-b1fa-c6b44af89de7&threadId=19_meeting_NTY1ZTRiYzQtYzMxYS00ZWIzLWFlMGYtYzAwNzVjOGQ1MWNi@thread.v2&messageId=0&language=en-US https://www.bidnetdirect.com/mitn/wayne-county-airport-authority

WAYNE COUNTY AIRPORT AUTHORITY Page 2 of 23

REQUEST FOR BIDS #25-01753

Rev. 06/13/25

DESCRIPTION: The Wayne County Airport Authority (Airport Authority) is soliciting bids from general contractors, construction managers and other businesses for removal of moving walkways at the Evans Terminal International Arrivals, the McNamara Parking Deck and the Big Blue Parking Deck for the Wayne County Airport Authority at Detroit Metropolitan Airport.

(The Contract resulting from this solicitation is subject to Airport Authority Prevailing Wages Requirements.)

It is the Bidder’s responsibility obtain and view all solicitation documents and addenda issued by the Wayne County Airport Authority (Airport Authority) for this RFB.

This RFB, all attachments (except Attachment I), and addenda are available via the Michigan Intergovernmental Trade Network (MITN) website. All bids must also be uploaded and submitted to MITN. Free and paid subscription registration options are available.

This RFB may be viewed or obtained as follows:

1. To download a copy of this RFB, all attachments (except Attachments I), and all addenda, access the

RFB directly from the MITN website at: https://www.bidnetdirect.com/mitn/wayne-county-airport-authority,

2. The document may also be accessed at the Wayne County Airport Authority website at:

https://www.metroairport.com/business/doing-business-wcaa/business-opportunities/solicitations

3. To obtain by purchase only Attachments I - Construction Documents, send an email request to Detroit@Eng-Repro.com. Reference RFB# 25-01753 in the subject line and provide your company contact info.

Engineering Reproduction, Inc. will respond to the email request with a security form (found in Attachment I) to be completed by the potential Plan Holder for return to Engineering Reproduction, Inc. When the completed form has been received, Engineering Reproduction, Inc. will give the Requestor all the information related to the job, including Cost and availability. No partial sets will be issued.

Engineering Reproduction, Inc. is located at:

13550 Conant Ave.

Detroit, MI 48212 Detroit@eng-repro.com Telephone: 313.366.3390 Fax: 313.366.3393

Paper and electronic files are available for purchase. The Contractor must purchase the paper files, which are the official documents of record for this RFB, and the electronic files. The following is a list of the attachments that are available for purchase. The estimated cost for all is approximately $50.00 excluding shipping.

The Bidder is responsible for the cost of printing/reproduction and shipping. The Bidder may contact Engineering Reproduction, Inc. for an exact amount and shipping options and costs.

Att. Date Attachment Description No. of Pages / Drawings / Size

I-1 6/6/25 Construction Drawings - Big Blue Deck 26

I-2 6/6/25 Construction Drawings - Evans Terminal FIS 21

I-3 6/6/25 Construction Drawings - McNamara Deck 26

I-4 6/6/25 Technical Specifications - Volume 1 172

I-5 6/6/25 Technical Specifications - Volume 2 296 https://www.bidnetdirect.com/mitn/wayne-county-airport-authority https://www.metroairport.com/business/doing-business-wcaa/business-opportunities/solicitations

WAYNE COUNTY AIRPORT AUTHORITY Page 3 of 23

TABLE OF CONTENTS

SECTION 1 – GLOSSARY OF TERMS

SECTION 2 – INSTRUCTIONS AND SPECIAL REQUIREMENTS

SECTION 3 – MINIMUM QUALIFICATIONS

SECTION 4 – PROJECT OVERVIEW

SCOPE OF WORK AND SPECIFICATIONS

SECTION 5 – KEY TERMS AND CONDITIONS

SECTION 6 – INSURANCE REQUIREMENTS

SECTION 8 - SUBMITTAL DOCUMENTS CHECKLIST (not required)

SECTION 9 – REQUIRED FORMS AND CONTRACT DOCUMENTS

REQUIRED FORMS:

ATTACHMENT A – BID FORM

ATTACHMENT B – SUBCONTRACTOR FORM

ATTACHMENT C – BUSINESS INFORMATION QUESTIONNAIRE

ATTACHMENT D – VERIFICATION OF MINIMUM QUALIFICATION FORMS

ATTACHMENT E – PRICE FORM

ATTACHMENT F – PROJECT DOCUMENTS DECLARATION FORM

ATTACHMENT G – DOCUMENT SECURITY AGREEMENT FOR SENSITIVE SECURITY

INFORMATION

CONTRACT DOCUMENTS:

ATTACHMENT H – FORM OF AGREEMENT AND GENERAL TERMS AND CONDITIONS

ATTACHMENT I – CONSTRUCTION DOCUMENTS

ATTACHMENT J - MISCELLANEOUS CONSTRUCTION REQUIREMENTS AND FORMS

ATTACHMENT K – WCAA PREVAILING WAGE INSTRUCTIONS, GENERAL DECISION & SAMPLE

CERTIFIED PAYROLL TEMPLATE

ATTACHMENT S – SBE PROGRAM OVERVIEW

WAYNE COUNTY AIRPORT AUTHORITY Page 4 of 23

SECTION 1 – GLOSSARY OF TERMS

To the extent in this solicitation document the following are defined as:

1) Airports: Detroit Metropolitan Wayne County Airport and Willow Run Airport.

2) Air Trade Area (ATA): Michigan counties of Genesee, Lapeer, Lenawee, Livingston, Macomb, Monroe, Oakland, St. Clair, Washtenaw, and Wayne.

3) Bid Guarantee: sum of money or a bond provided by a Bidder to the Airport Authority with a Bid to guarantee that the Bidder will not withdraw the Bid for a specified period of time, and will enter into a contract with the Airport Authority within the time specified in the Bid, based upon the substantive terms and conditions contained in the RFB or Form of Agreement included in the RFB.

4) Bidder: Business that submits a Bid in response to an RFB issued by the Airport Authority.

5) Board: the governing body of the Airport Authority.

6) Broker: a firm does not itself perform, manage or supervise the work of its contract or subcontract in a manner consistent with the normal business practices for contractors or subcontractors in its line of business.

7) Business: an individual, firm, vendor, association, corporation, limited liability company, partnership, joint venture, sole proprietorship, or other legal entity.

8) Certified Small Business Enterprise (SBE): Business certified by the Wayne Country Airport Authority as being headquartered within the ATA, and not exceeding the Small Business Administration (SBA) Size Standards.

9) Contractor: the successful awarded Bidder of a solicitation, who is legally bound to the contract.

10) Currency: All monetary references in this document are in U.S. Dollar.

11) Detroit Metropolitan Wayne County Airport or DTW: Detroit Metro Airport

12) Experience: For the purposes of this solicitation, Experience shall equal a standard Michigan construction season, which ranges from April to November.

13) Form of Agreement or FOA: the contract document for the solicitation.

14) Freedom of Information Act (FOIA): regulates and sets requirements for the disclosure of public records and defines when, how, and what information may be obtained from the Airport Authority by an interested party.

15) Holiday: the legal holidays observed by the Airport Authority. (New Year’s Day, Martin Luther King Jr. Birthday, Friday before Easter, Memorial Day, Juneteenth, Independence Day, Labor Day, Thanksgiving Day, Day after Thanksgiving, Christmas Eve, Christmas Day, New Year’s Eve)

16) Insurance: all projects require insurance naming the Wayne County Airport Authority and the Charter County of Wayne as additional insured.

17) Joint Venture: A partnership or other legal cooperative agreement between two or more persons or entities.

18) LEED: Leadership in Energy and Environmental Design

19) Managed: For the purpose of this solicitation, Managed shall be defined as being in full responsible charge of, and administering all facets of, a project.

20) Metro Airport or DTW: Detroit Metropolitan Wayne County Airport.

21) Nonresponsible Bid: a Bid submitted in reply to an RFB issued by the Airport Authority, where the

Bidder does not meet all required minimum qualifications or SBE goal requirements, if required, or is not in compliance with the Airport Authority’s requirements concerning ethics, debarment and/or arrearage.

WAYNE COUNTY AIRPORT AUTHORITY Page 5 of 23

22) Nonresponsive Bid: a Bid submitted in reply to an RFB issued by the Airport Authority, which does not conform to all material requirements of the RFB.

23) Notice of Award: written notification from the Airport Authority to the successful Bidder that they have been awarded the contract.

24) Notice to Proceed: written authorization from the Airport Authority to the successful Bidder to proceed with the work defined in the contract.

25) Partnership: an agreement under which two or more persons agree to carry on a business, sharing in the profit or losses, but each liable for losses to the extent of his or her personal assets.

26) Prevailing Wage: Local minimum wage and fringe benefit rates established by the U.S. Department of Labor to be paid to onsite laborers and mechanics on construction projects.

27) Procurement and Contracting Ordinance (Purchasing Ordinance): the common name of the Wayne County Airport Authority Procurement and Contracting Ordinance, which is the policy governing procurement and contracting at the Wayne County Airport Authority.

28) Public-use Airport: an airport that is open to the public which is either 1) publicly owned, or 2) privately owned but designated by the Federal Aviation Administration (FAA) as a reliever, or 3) is privately owned but having scheduled service and at least 2,500 annual enplanements

29) Reciprocity: an expedited application process available to firms headquartered within the Air Trade Area that are already certified as a small business with the Small Business Administration or maintains small business certification with any Public Agency located in the Air Trade Area (at the discretion of the Procurement Administrator).

30) Responsible Bidder: a Bidder who is qualified in all respects to fully perform the required services or to provide the required goods, and who possesses the integrity, experience and reliability necessary for good faith performance. A responsible Bidder meets the minimum qualification requirements and conforms to the Airport Authority’s requirements concerning ethics, debarment, arrearage, and where applicable, SBE participation goal.

31) Responsive Bid: a bid timely submitted by a Bidder in reply to, and in conformity with all material requirements of a Request for Bids issued by the Airport Authority.

32) Similar Government or Private facility: is defined as a facility that has high security of a critical infrastructure, for example, stadiums, court houses, jails, nuclear plants, college campuses, or corporate campuses.

33) Small Business Enterprise (SBE) Program - Program created by Wayne County Airport Authority to increase opportunities for qualified small businesses to participate on Airport Authority contracts that are not federally funded.

34) Subcontractor: Any person or business entity employed to perform part of a contractual obligation under the control of the principal contractor. Any supplier, distributor, or firm that furnishes supplies or services to a prime contractor or another subcontractor.

35) Substantially Complete: a construction project having achieved the “Substantial Completion” date, which is defined in Section 7.1.2 of the Typical Construction Services Agreement General Terms and Conditions, which is included in Attachment B of this RFB.

36) Team Member: an entity identified in the Bidder’s response to this RFB that will be assigned to the project outlined in this RFB if the Bidder is awarded the contract for construction. A Team Member may be the Bidder’s business (as identified on the Business Information Questionnaire included in the RFB), or a Subcontractor, or if the Bidder is a partnership or joint venture, an entity that is part of the partnership or joint venture.

37) Willow Run or YIP: Willow Run Airport

WAYNE COUNTY AIRPORT AUTHORITY Page 6 of 23

SECTION 2 – INSTRUCTIONS AND SPECIAL REQUIREMENTS

1) SOLICITATION INFORMATION AND QUESTIONS: Bidders are advised to review this document in its entirety and to rely only upon the contents of this RFB and accompanying documents and any written clarifications or addenda issued by the Airport Authority. THE AIRPORT AUTHORITY IS NOT RESPONSIBLE FOR ANY VERBAL INSTRUCTIONS. If a Bidder finds a discrepancy, error, or omission in the RFB or any accompanying documents thereto, the Bidder shall promptly notify the Procurement Contact noted on the Cover Page of this RFB, so that written clarification may be sent to all prospective Bidders. All questions must be submitted in writing by the pre-bid question deadline.

No contact with other Airport Authority employees, officers or Board members regarding this document is permitted.

2) PRE-BID MEETING: A pre-bid meeting concerning this RFB may be held. If so, the date, time and location are indicated on the Cover Page of this RFB. Airport Authority staff will be available at this meeting to answer questions about this RFB. Attendance at the meeting is strongly encouraged for the entities that will be submitting a Bid that will be signatory on a contract with the Airport Authority for the work contained in this RFB, as well as subcontractors participating on the Bidders teams.

RSVP REQUIRED TO:purchasing.questions@wcaa.us by 8/18/25. Include your name, company name, email address, and phone number.

3) RFB MODIFICATIONS/ADDENDA: Clarifications or modifications may be made to this solicitation at the discretion of the Airport Authority. Any and all Addenda issued by the Airport Authority will be posted as noted on the Cover Page of this RFB. It is the responsibility of the Bidder to obtain from MITN any issued Addenda and to acknowledge the Addenda on the Bid Form. If any changes are made to this solicitation document by any party other than the Airport Authority, the original document in the Airport Authority’s files takes precedence.

4) BID DEADLINE / LATE SUBMISSIONS: The bid is due not later than the date and time listed on the Cover Page of this RFB. The MITN system does not accept late Bids and will cut you off at the exact deadline date and time, so allow yourself plenty of time when submitting your Bid. The deadline date may in some instances change during the solicitation issuance period. If any deadline date for submission changes, such change will be issued in a published Addendum to this solicitation prior to the deadline date indicated on the Cover Page of this solicitation.

5) SMALL BUSINESS ENTERPRISE (SBE) PARTICIPATION: The Airport Authority encourages participation from small businesses headquartered in the ATA on all non-federally funded contracts. SBE participation of at least twenty-five percent (25%) has been set as a minimum qualification on this solicitation and is required as a matter of responsiveness. The SBE participation can be met by a combination of any SBE prime contractor, subcontractors and/or suppliers. WCAA SBE Certification status must be active as of the bid/quote deadline. The contract resulting from the vendor’s solicitation response will incorporate the proposed SBE participation listed on the Verification of Min Quals form (Attachment D) as a firm commitment, regardless of the minimum qualification listed above. Upon contract award, the contractor must use any such forms as are required and made available by the Airport Authority to demonstrate that the Contractor has met the SBE Commitment. Contractor will be required to submit monthly Contractor/Subcontractor participation reports as required by WCAA. Responses including voluntary participation of 30% or more may be eligible to receive SBE Equalization Credits during the evaluation process. Details about the Airport Authority’s SBE Program may be found in Attachment S. For more information regarding the SBE program, please contact the Business Development Unit at business.development@wcaa.us or (734) 955-5785. All other questions related to this particular solicitation must be sent to Purchasing.Questions@wcaa.us mailto:Purchasing.Questions@wcaa.us

WAYNE COUNTY AIRPORT AUTHORITY Page 7 of 23

6) ELECTRONIC BID SUBMISSION: Failure to submit a timely bid including: 1) a signature binding the offer; 2) a completed Price Form, and 3) Bid Guarantee, if required, may result in your bid being deemed nonresponsive.

a) The Bidder is also to submit the following required information:

i) Electronic copy of the complete Bid must be uploaded and submitted via the MITN website at https://www.bidnetdirect.com/mitn/wayne-county-airport-authority. The electronic file(s) submitted will be considered the original Bid.

ii) BID GUARANTEE: The Bidder is required to submit a refundable Bid Guarantee (an AIA 310 Bond from a surety licensed to conduct business in the State of Michigan or cashier’s check) in the amount of 5% of the Bidder’s total potential value of the Base Bid, should be made payable to the Wayne County Airport Authority. The Bidder should submit photocopy of the Bid Guarantee, Bond, or cashier’s check with the Bid in the electronic response to this RFB. This photocopy must be of sufficient resolution to show a valid stamp and seal. The original should be postmarked by the Bid deadline date and sent to:

The bidder is responsible for submitting the original Bid Guarantee, postmarked by the Bid deadline, to the Airport Authority. The original should be sent to:

Wayne County Airport Authority Michael Berry Administration Building

Detroit Metropolitan Wayne County Airport 11050 Rogell Drive, Building #602

Detroit, Michigan 48242 Attn: Procurement Department (RFB #25-01753)

(Tracking number may be requested.) Failure to submit the properly postmarked Bid Guarantee, Bond, or cashier’s check in the specified form will result in the Bid being deemed Nonresponsive and the Bid rejected without any further evaluation.

Detroit, Michigan 48242 is the mailing address of Detroit Metropolitan Wayne County Airport. The Detroit Metropolitan Airport is physically located within the boundaries of the City of Romulus, Michigan (Tracking number may be requested.) Failure to submit the properly postmarked Bid Guarantee, Bond, or cashier’s check in the specified form may result in the Bid being deemed Nonresponsive and the Bid rejected without any further evaluation.

Note: Return of Bid Guarantee: Bid Guarantees will be returned to Bidders immediately after the Airport Authority has deemed that a Bidder is either Nonresponsive or Nonresponsible. Bid Guarantees for all remaining Bidders will be held until a contract is fully executed; or upon the request by the Bidder, but only after the “firm offer period” has expired.

iii) Verification of Minimum Qualifications Form (or provide the required information to show the Bidder meets each of the Minimum Qualifications as listed in this solicitation document).

iv) Submit an executed Project Documents Declaration Form

v) Submit an executed Document Security Agreement for Sensitive Security Information

vi) Business Information Questionnaire

(1) Certification concerning Iran: The Bidder certified that its business neither (a) engages in investment activities in the energy sector of Iran, including the provision of oil or liquefied natural gas tankers or products used to construct or maintain pipelines used to transport oil or liquefied natural gas for the energy sector of Iran, nor (b) extends credit to another person or entity, if that person or entity will use the credit to engage in investment activities in the energy sector of Iran.

WAYNE COUNTY AIRPORT AUTHORITY Page 8 of 23

vii) Subcontractor Form

(1) The Bidder must include information about each subcontractor that will be utilized in the contract. Subcontractors cannot be added or replaced after submittal of the bid without the prior written approval of the Airport Authority.

viii) Bidder must be in Good Standing with the State in which their business is domiciled. The Bidder must certify on its Business Information Questionnaire that it is in Good Standing or not required to obtain such a certificate or otherwise register with that state. If the Bidder is domiciled outside of Michigan, the Bidder will also be required to be in Good Standing with the State of Michigan or certify on its Business Information Questionnaire that it is not required to obtain such standing or otherwise register with the State of Michigan. How to obtain information regarding obtaining a Certificate of Good Standing from the State of Michigan may be found at https://cofs.lara.state.mi.us/corpweb/HelpPages/OrderSystemInfo.aspx.

b) Bids must be submitted via the MITN portal: https://www.mitn.info

c) Submission of a bid establishes a conclusive presumption that the Bidder is thoroughly familiar with the Request for Bids (RFB), and that the Bidder understands and agrees to abide by each and all of the stipulations and requirements contained therein.

d) All documentation submitted with the bid will become the property of the Airport Authority.

e) All costs incurred in the preparation and presentation of the bid is the Bidder’s sole responsibility; no pre-bid costs will be reimbursed to any Bidder.

f) Bids must be held firm for a minimum of 120 days from the Bid Deadline date of the RFB.

g) The Airport Authority has the right to request samples from Responsive and Responsible Bidder.

The requested samples must be provided within two (2) business days of the request by the Airport Authority, or the bid will be considered nonresponsive.

7) BROKER: The Airport Authority will not accept any Proposals from a broker. Any Proposer that is determined to be a broker will be deemed nonresponsive.

8) EXCEPTIONS: Bidder shall clearly identify any proposed deviations from the language in the Request for Bids (including its Terms and Conditions). Each exception must be clearly defined and referenced to the proper paragraph in this RFB or its Terms and Conditions. The exception shall include, at a minimum, the Bidder's proposed substitute language and opinion as to why the suggested substitution will provide equivalent or better service and performance. If no exceptions are noted in the Bidder's Bid, the Airport Authority will assume complete conformance with this specification and the successful Bidder will be required to perform accordingly. Bids not meeting all requirements may be rejected.

Bids taking exception to material terms and conditions (i.e., indemnification, subrogation, insurance, ownership of documents, governmental requirements) will not be considered. The Airport Authority reserves the right to accept or to allow the Bidder to withdraw any or all exceptions.

9) WITHDRAWAL: Bids may be withdrawn or revised via the MITN portal up to the deadline date and time. No Bid may be withdrawn after the deadline for submission.

10) REJECTION OF BIDS: Bids will be rejected for the following reasons:

a) Bidder’s failure to submit all required information of RFB.

b) Bidder’s failure to meet minimum qualifications of RFB.

c) Bidder is in arrears or in default to the Airport Authority on any contract, debt, or other obligation.

d) Bidder is debarred by the Airport Authority or federal government (for federally funded contracts) from consideration for a contract award.

https://cofs.lara.state.mi.us/corpweb/HelpPages/OrderSystemInfo.aspx https://www.mitn.info/

WAYNE COUNTY AIRPORT AUTHORITY Page 9 of 23

e) Bidder has committed a violation of the Airport Authority’s Ethics Ordinance which resulted in a termination of a contract or other material sanction within the two (2) years immediately preceding the date of issuance of this document.

f) Bidder has a contract or other relationship with a client that is determined by the Airport Authority to be a legal or business conflict that is unwaivable or that the Airport Authority, at its sole discretion, is unwilling to waive.

g) In the event a Bidder, including its subsidiaries, affiliated companies and franchises, submits more than one (1) bid, the Airport Authority, at its sole option, will have the right to determine which bid will be considered, or reject all such multiple bids.

11) CANCELLATION OF RFB The Airport Authority reserves the right to cancel this solicitation, in whole or in part, as well as reject any or all bids, or to accept or reject any bid in part, and to waive any minor informality or irregularity in bids received if it is determined by the Chief Executive Officer (CEO) or his designee that the best interest of the Airport Authority will be served by so doing. If the solicitation is cancelled or all bids are rejected by the Airport Authority, a notice will be posted on MITN.

12) PROCUREMENT POLICY: Procurement for the Airport Authority will be handled in a manner providing fair opportunity to all businesses. This will be accomplished without abrogation or sacrifice of quality and as determined to be in the best interest of the Airport Authority. The Chief Executive Officer has the vested authority to execute a contract, subject to Board approval where required.

13) BID SIGNATURES: Bids must be signed by an authorized official of the Bidder. Each signature represents binding commitment upon the Bidder to provide the goods and/or services offered to the Airport Authority if the Bidder is determined to be the lowest Responsive and Responsible Bidder.

Properly authenticated electronic signatures are acceptable and shall be treated the same as if the signee had put pen to paper

14) CONTRACT AWARD AND CONTRACT EXECUTION: The Airport Authority reserves the right to award by item, group of items, or total proposed items and to award more than one contract at its sole discretion, to the lowest Responsive and Responsible Bidder, or Bidders.

i) All contract award recommendations must be approved by either the Airport Authority’s CEO or Board.

ii) The Bidder(s) to whom the award is being recommended will be notified and provided the Airport Authority’s contract for execution at the earliest possible date. If for any reason, the awarded Bidder(s) does not execute a contract within the time specified by the Airport Authority, then the Airport Authority may recommend award to the next lowest Responsive and Responsible Bidder.

A final Notice of Award, and if required, a Notice to Proceed, will be issued after completion of a fully executed contract.

iii) If a Bidder requires an agreement beyond any agreement (e.g. Terms and Conditions) required by the Airport Authority, or required as a part of this solicitation by the Airport Authority, the Airport Authority reserves the right to reject execution of any additional agreements required by the Bidder. In instances where the Airport Authority rejects execution of additional agreements that are required by the Bidder, the Airport Authority reserves the right to deem the bid as Nonresponsive, and to recommend award to the next most Responsive and Responsible Bidder.

15) NO RFB RESPONSE: Bidders who receive this RFB but do not submit a Bid are asked to submit a notice stating the reason(s) for not responding.

16) FREEDOM OF INFORMATION ACT (“FOIA”) REQUIREMENTS: Bids are subject to public disclosure after the Bid Deadline in accordance with state law. For additional information, contact the Airport Authority’s FOIA Coordinator at FOIA@wcaa.us.

17) PROTESTS: A protest must be filed in writing and within the timeframes outlined in Section 9 of the Airport Authority Procurement and Contracting Ordinance. A copy of the Procurement Ordinance is available from Procurement Department at the Airport Authority, and accessed at mailto:FOIA@wcaa.us

WAYNE COUNTY AIRPORT AUTHORITY Page 10 of 23 https://www.metroairport.com/business/about-wcaa/important-documents

18) SECURITY BADGES: Security badges are required. Information regarding the requirements, process and fees for obtaining a badge is available via: https://www.metroairport.com/business/dtw-airport-id-badges .

19) PROOF OF INSURANCE REQUIREMENTS: The successful Bidder must submit proof that they meet all Airport Authority insurance requirements prior to receiving an executed contract and purchase order.

20) BASIS FOR CONTRACT AWARD: The determination of the lowest responsive and responsible Bid shall be based upon the total combined base bid (Package 1, 2, and 3) amount including SBE equalization credits. RFB responses without a complete Price Form and all required forms and information in the Bid Package will be deemed non-responsive for that Bid Package. Selections of work to be awarded will be based on the availability of funding.

21) AIRPORT AUTHORITY ETHICS ORDINANCE: To report an ethics violation or for more information, go to www.wcaa.ethicspoint.com or call 1-888-447-8643. To view or download the WCAA Ethics Ordinance, access the following link:

https://secure.ethicspoint.com/domain/media/en/gui/35303/ethics.pdf

22) TITLE VI: The Wayne County Airport Authority, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (42 U.S.C. §§ 2000d to 2000d-4) and the Regulations, hereby notifies all bidders that it will affirmatively ensure that any contract entered into pursuant to this advertisement, all businesses will be afforded full and fair opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.

https://www.metroairport.com/business/about-wcaa/important-documents https://www.metroairport.com/business/dtw-airport-id-badges https://www.metroairport.com/business/dtw-airport-id-badges http://www.wcaa.ethicspoint.com/ https://secure.ethicspoint.com/domain/media/en/gui/35303/ethics.pdf

WAYNE COUNTY AIRPORT AUTHORITY Page 11 of 23

SECTION 3 – MINIMUM QUALIFICATIONS

1) MINIMUM QUALIFICATIONS: Bidders (specifically, the Business that will be contractually bound under the contract with the Airport Authority) will be deemed nonresponsible and rejected without any further evaluation if they as a Business, do not meet the following qualifications:

Refer to Attachment D – Verification of Minimum Qualifications Form If you have received this document electronically, Attachment D – Verification of Minimum Qualifications Forms is a separate document.

WAYNE COUNTY AIRPORT AUTHORITY Page 12 of 23

SECTION 4 – PROJECT OVERVIEW

1) Through this Request for Bids (RFB), the Wayne County Airport Authority (Airport Authority) hereby invites businesses that meet the qualifications set forth herein to submit Bids for construction services to perform the removal of moving walkways at the Evans Terminal International Arrivals, the McNamara Parking Deck and the Big Blue Parking Deck for the Wayne County Airport Authority at Detroit Metropolitan Airport.

There are a total of six (6) moving walkways to be removed; four (4) moving walkways at the Big Blue Parking Deck, and one (1) at the McNamara Parking Deck and Evans Terminal International Arrivals.

The exposed flooring will be infilled to match the existing conditions of the surrounding floor at each location.

This RFB includes Construction Documents (Attachment I1, I2 and I3) and Technical Specifications (Attachment I4 and I5) that identify technical requirements of the project. The successful Bidder will comply with each set of documents for the work.

2) GENERAL INFORMATION: In August 2002, the Public Airport Authority Act, MCL 259.108-259.125 (“Act 90”) transferred full operational jurisdiction of the Detroit Metropolitan Wayne County Airport and the Willow Run Airport from the Charter County of Wayne to the Wayne County Airport Authority (Airport Authority). The Airport Authority became responsible for the management and operation of the Detroit Metropolitan Wayne County (DTW) and Willow Run (YIP) Airports, including the power to plan, promote, extend, maintain, acquire, purchase, construct, improve, repair, enlarge and operate both airports.

The Detroit Metropolitan Wayne County Airport is one of the largest domestic and international airports in the United States and has a major role in the future of southeast Michigan and the national airport system. The Willow Run Airport serves as a reliever airport, primarily serving cargo and general aviation activity.

Moving walkways have been installed at various locations throughout McNamara Terminal, Evans Terminal, McNamara Parking Deck, and Big Blue Parking Deck in an effort to improve customer satisfaction. However, due to varying factors, moving walkways at several areas within the referenced locations are either required to be removed, or are otherwise no longer desired to be in operation by the Airport Authority.

SCOPE OF WORK AND SPECIFICATIONS

1) SCOPE OF WORK: The successful Bidder (Contractor) will be required to comply with all requirements and provisions of the Project as described and detailed in this RFB (including its attachments), and to complete the Scope of Work upon the receipt of a Notice to Proceed(s) from the Airport Authority. This RFB is broken into 3 different packages, the Wayne County Airport Authority will be awarding this in one overall contract. The Contractor must provide any and all labor, materials, equipment, tools, supervision, permit costs, coordination, mobilization, demobilization, delivery charges, insurance, bonds, taxes, costs and other services necessary or required to complete the Work in accordance with the Agreement. An overview summary of the items included in the Scope of Work is as follows:

a) Locate all existing utilities within the project limits to ensure that those indicated to remain will be avoided and not disturbed.

b) Obtain all Required Permits: The Airport Authority may obtain approvals of the permit applications from the jurisdictional agencies. The successful Bidder will be responsible for obtaining all permits and paying for all associated construction permit fees, application fees, inspection fees, bonds, and insurances. The following is a list of the required permits:

i) Electrical Permit – City of Romulus.

ii) General Building Permit – City of Romulus

iii) Any other applicable permits required by federal, state and local laws and regulations.

WAYNE COUNTY AIRPORT AUTHORITY Page 13 of 23

c) Written Site Security Program: The Contractor will be required to comply with all security requirements. Refer to the Attachment I – Construction Documents, including Specification SP-20

– Airport Security Requirements for additional requirements. Prior to initiating any construction activity on the site, the Contractor must submit a Written Site Security Program as described in Article 9 of the General Terms and Conditions (Attachment F), for review and approval by the Airport Authority. The Contractor shall not park any vehicle, nor store any construction materials within six

(6) feet of the Airport Operations Area (AOA) perimeter fence;

d) Safety Program: The Contractor will be required to comply with all safety requirements. Refer to the Attachment I – Construction Documents, including Specification SP-10 – Airport Safety Requirements for additional requirements. Prior to beginning construction, the Contractor will be required to develop and submit its written Safety Program to the Airport Authority for review and approval;

e) Manage the Work as required including:

i) Satisfy documentation requirements as required in the Attachment J, including but not limited to the monthly submittal of detailed progress reports and progress schedule updates to the satisfaction of the Engineer and Airport Authority Project Manager.

ii) Manage the Work, the Contractor’s staff, and all subcontractors to the satisfaction of the Engineer and Airport Authority Project Manager;

f) Disposal of all materials/fluids in accordance with all applicable laws at licensed facilities; and

g) All other tasks assigned by the Airport Authority related to the Moving Walkway Removals project.

2) The removal of moving walkways within the McNamara Parking Deck, Big Blue Parking Deck and Evans Terminal International Arrivals at Detroit Metropolitan Airport, which includes but is not limited to: demolition, electrical, mechanical, structural, and flooring;

a) Reconnection of all loads to new equipment;

b) Final acceptance of each site shall be contingent upon successful completion of testing as described in the design documents;

c) Provide all temporary utilities, site offices and site management necessary to perform the work as described;

d) Protection of adjacent structures and facilities;

e) The Contractor is responsible for ensuring all roads and airfield space are always kept free of dust and debris at all times;

f) Construction Staking and Layout of new work and as required; Provide traffic control devices and sequence work in accordance with the Progress Clause, the Special Provision for Maintaining Traffic and as shown on the Plans;

g) The Contractor will be required to complete the work in accordance with the durations and Substantial Completion dates listed in Section 5.4 – Project Milestones.

3) COORDINATION OF WORK: The Contractor(s) will be required to coordinate their work with the Airport Authority, Airport Security, Utility companies, and/or Wayne County Inspectors in the scheduling and performance of each phase as outlined for this project. Additionally, the Contractor is required to coordinate all work with other construction or maintenance activities in the immediate vicinity of this project including.

The Contractor will be required to coordinate its work with the Airport Authority Project Management representatives, Airport Security, Utility companies, and/or Wayne County Inspectors in the scheduling and performance of each phase as outlined for this project. Additionally, the Contractor is required to

WAYNE COUNTY AIRPORT AUTHORITY Page 14 of 23 coordinate all work with other construction or maintenance activities in the immediate vicinity of this project.

4) CONSTRUCTION REQUIREMENTS AND PROCEDURES: This Project is located within a fully operational airport that is active 24-hours a day, 365 days a year. Work shall be performed consistent with approvals provided by the Airport Authority.

a) Access to Site, Staging, Temporary Trailers, Contractor Parking, temporary facilities:

i) No claims for additional fees or extension to contract duration will be considered on the grounds of site restrictions imposed by any security requirements associated with this Project. The Contractor will not be permitted access to the airfield or other restricted areas without proper approval from the Airport Authority.

ii) All on-site staging and temporary storage of equipment and tools must be contained within an Airport Authority approved site. All deliveries to the Project site shall be accomplished using public access roads.

iii) All materials and tools that are required to be delivered to the Project site shall be stored and secured within a designated staging area at all times. No tools or materials shall be left unsecured or unattended in public areas. No containers (tool boxes, storage containers, debris containers, etc.) shall be left unsecured or unattended in public areas.

iv) Locations for staging, Contractor’s and Engineer’s temporary construction trailer, and additional Contractor parking will be assigned on the Airport property at the Pre-Construction Meeting, if required. If a temporary construction trailer is desired, the Contractor shall be required to obtain a permit for the trailer from the Airport Authority and City of Romulus. The Contractor shall not park any vehicle, nor store any construction materials within six (6) feet of the Airport Operations Area (AOA) perimeter fence.

v) Concrete crushing operations will not be permitted on Airport property. The contractor will be required to legally dispose of all removed concrete off-site. All costs associated with disposal are the full responsibility of the Contractor.

vi) The Contractor shall be required to provide and install all temporary measures required to maintain safety and security for the construction of the Project.

vii) Contractor parking will be permitted at the staging area, however, other Contractor parking sites on the Airport property may be required and designated by the Airport Authority. Transportation to the construction site and staging area(s) from other locations is the responsibility of the Contractor.

viii) The Contractor will conduct the required work in such a manner so as to cause minimum disruption to Airport Authority operations. No traffic flow alterations, blockages or stoppages will be permitted without review and prior approval by the Airport Authority. The Contractor shall be required to provide and install all temporary measures required and as directed by the Airport Authority to maintain safety and security for the construction described herein.

ix) The Contractor will be responsible to provide toilet facilities for all construction workers.

x) The Contractor will be responsible for providing all power and other utilities including water needed to construct the Project.

b) The Contractor shall schedule all Airport Authority utility verification and disconnection requests through the Planning, Design & Construction Department.

c) Hot Work: Hot work is defined as a process or procedure that could result in a fire if not properly controlled. No welding, flame cutting, or other operations involving the use of flame, arcs, or sparking devices will be allowed without adequate protection, subject to prior approval by the Fire Marshal, and a Hot Work permit from the Airport Fire Division.

WAYNE COUNTY AIRPORT AUTHORITY Page 15 of 23

4) PROJECT MILESTONES: Work is required to be Substantially Completed in the phases and construction durations as required in this RFB and its attachments. Refer to Attachment C - Construction Documents for specific information. General information related to project milestones is as follows:

a) Contract Award - It is anticipated that this contract will be awarded in October 2025 by the Wayne

County Airport Authority Board, based upon confirmation of lowest responsive and responsible Bidder. It should be noted the delay of the issuance of an executed Contract, or Notice to Proceed due to incomplete, untimely, or rejected Contractor’s insurance, bonds, Pre-Construction submittals, schedules, permit approvals, and/or other Contractor required submissions shall not be the basis of a claim for a delay nor for additional mobilization costs.

b) Administrative Notice to Proceed - Following receipt of approved Contractor’s insurance, bonds, and issuance of an executed Contract, it is anticipated that an Administrative Notice to Proceed will be issued to permit the Contractor to obtain, prepare and submit pre-construction schedules, submittals, and to plan for construction. It is anticipated that the Pre-Construction Conference will be scheduled and conducted during this time. The Airport Authority’s review of pre-construction submittals once they are complete and accurate will take up to fourteen (14) calendar days.

e) Notice to Proceed - Upon receipt and approval of all permits, required pre-construction submittals, and following the Pre-Construction Conference, a Limited or full Notice to Proceed with Construction (NTP) will be issued

f) Substantial Completion of Construction - The work issued shall be Substantially Complete within the following durations:

i) Package 1 McNamara Parking Deck – 60 calendar days of the NTP with construction.

ii) Package 2 Big Blue Parking Deck – 75 calendar days of the NTP with construction.

iii) Package 3 Evans Terminal International Arrivals – 60 calendar days of the NTP with construction.

g) Final Completion - Construction work including all restoration, cleanup, completion of punch list and removal of temporary pedestrian traffic control and safety devices shall be no later than 30 calendar days after the Substantial Completion date.

h) Schedule & Work Restrictions – The following limitations on the Work will be required as part of the contract resulting from this RFB. It should be noted the below limitations shall not be the basis of a claim for a delay nor for additional mobilization or labor costs:

i) Refer to the Special Provisions for Maintaining Traffic, and Contractor Safety and Security.

6) ALLOWANCES: Certain allowances will be provided in the contract for this Project. A summary of the allowances is as follows:

a) Allowance No. 1 – Permit and Inspection Fees – Contractor costs for agency off-site third-party permit and inspection fees shall be paid under the Allowance described in this RFB. Actual payment will be based on actual costs (without any mark-up) incurred by the Contractor or Subcontractor(s) upon submittal of original paid receipts from each permitting agency. The Contractor will not be paid for permitting agency fines or fees resulting from, but not limited to, unsatisfactory work, multiple inspections of unsatisfactory work, unsatisfactory work site and staging area, unsatisfactory noise or dust control. Other required fees including, but not limited to insurance and bonds, shall be incidental to the Mobilization pay item in accordance with the Basis of payment in the Attachments I – Construction Documents (Drawings and Specifications).

b) Allowance No. 2 – General Construction – Contractor costs for additional work items added by WCAA as “additional work” will be reimbursed to the Contractor using this allowance as established in the Contact Documents. Costs for “additional work” shall be established on a time and material basis which shall be submitted to the Airport Authority and approved prior to starting any work. Any unapproved work performed by the contractor will be at the Contractor’s own expense.

WAYNE COUNTY AIRPORT AUTHORITY Page 16 of 23

7) LIQUIDATED DAMAGES: If the Contractor fails to achieve Substantial or Final Completion on or before the required dates as specified in the Contract Documents then the Contractor and the Contractor’s surety agree to pay the Airport Authority liquidated damages. Liquidated damages for failure to meet the Substantial Completion date shall be $1,300.00 per day starting on the required date of Substantial Completion until Substantial Completion is achieved. Liquidated damages for failure to meet the Final Completion date shall be $500.00 per day starting on the required date of Final Completion until Final Completion is achieved.

a) Notwithstanding anything to the contrary herein, the assessment of liquidated damages are not the

Airport Authority’s sole and exclusive remedy in the event the Contractor fails to achieve Substantial and/or Final Completion the Work by the Completion Dates.

8) REQUIRED DOCUMENT FORMAT AND SOFTWARE:

a) The Contractor will be required to submit in English all final documents in hard copy and electronic format as requested by the Airport Authority (such as Word, Excel, AutoCAD, GIS, PDF and TIFF).

All as-built survey data shall be in Michigan State Plane Coordinates-South Zone, International Feet.

9) PROPERTY OF THE AIRPORT AUTHORITY: All item(s) (including drafts, photos, work papers, prototype…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .