Rework_and_Repair_ES7034.pdf
PDF 290 KB Posted
- Attached to
- KC-135 & C-17 Fire Cartridges Federal contract opportunity
- Solicitation number
- FA8213-23-R-5004
About this file
This federal contract solicitation seeks fire cartridges for the KC-135 and C-17 aircraft. It includes multiple line items for first article test plans, first article samples, first article inspections, and production quantities. Delivery locations involve multiple foreign military sales cases supporting Central and South American partners. The solicitation incorporates exhibit B for first article test requirements. Evaluation will include testing fire cartridges which are ballistic devices made predominantly of steel and aluminum with a 4.6 grain explosive charge that is electrically initiated. The Department of the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base is the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CDRLs for FAT FD2020-22-50040 - 22-50041 Oct 2022 Corrected.pdf | ||
| CADPAD Item Marking Instruction - Ver 1.5 - 20190501.pdf | ||
| REPSHIP.pdf | ||
| SPI Combined.pdf | ||
| ADC SOW Jan 2018.pdf | ||
| Air Spec_FD2020-22-50040 and 50041.pdf | ||
| CDRLS FD2020-22-50040 AND 50041 Oct 22 Corrected.pdf | ||
| QALI KC-135 Fire Cart MJ92 MJ15.pdf | ||
| SOW - February 2022.pdf | ||
| Item Descriptions_FD2020-22-50040 and 50041.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.
(End of clause)