REQUEST_FOR_PROPOSAL_ENGINEERING.docx
DOCX document 31 KB Posted
- Attached to
- Engineering Services for Donnie Substation
- Solicitation number
- RFQ#202623
- Issued by
- Miami-Dade County, Florida
About this file
This Request for Proposal (RFP) is issued by the City of Homestead/Homestead Energy Services (HES) for comprehensive engineering and design services for the new Donnie Avocado 138kV Substation located in Homestead, Florida. The project scope encompasses complete engineering activities for a new distribution substation rated at 138 kV/13.2 kV with a net output capacity of 89 MVA, designed in a loop-in/loop-out configuration connected to an existing 138 kV transmission line between HES Lucy and FPL Davis substations. The engineering services include structural and civil engineering (site surveys, geotechnical reports, grading and drainage plans, foundations, and SPCC plans), substation engineering (electrical single-line diagrams, general arrangements, grounding and shielding studies, cable and conduit plans, and procurement support), and protection and control engineering (relay diagrams, schematics, wiring diagrams, and bills of materials). The project will be delivered in five phases: 30% design package, 60% design package, 90% design package, Issued for Construction (IFC) package, and as-built documentation due within 30 days of construction completion. Qualifications are due August 6, 2026, and the procurement is issued under Florida Statute 287.055 (Consultants' Competitive Negotiation Act).
All final reports and calculations must be signed and sealed by a Florida Registered Professional Engineer and include grounding and lightning shielding studies, lighting/illumination studies, AC/DC station load and battery sizing calculations, and substation bus strength calculations. Consultant proposals must demonstrate relevant experience with 138kV substation designs in Florida, identify the project manager and lead discipline engineers with Florida PE licensure, provide a detailed project approach addressing schedule, quality assurance/quality control, and risk management, and submit a proposed timeline from contract award through IFC submittal. The City of Homestead encourages participation from MBE/WBE/DBE businesses and is an Equal Opportunity Employer. No estimated contract value, contract term, or specific evaluation weighting is identified in the source materials.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL (RFP): ENGINEERING SERVICES
PROJECT: DONNIE AVOCADO 138kV SUBSTATION Owner: City of Homestead / Homestead Energy Services (HES)
1. PROJECT OVERVIEW
The City of Homestead Energy Services (HES) is seeking proposals from qualified engineering firms (“Consultant”) to provide comprehensive engineering and design services for the new Donnie Avocado Substation. This project consists of all engineering activities required for a new distribution substation rated at 138 kV / 13.2 kV with a net output capacity of 89 MVA.
The facility will be located in Homestead, Florida. The design must facilitate a loop-in/loop-out configuration from the existing 138 kV transmission line between HES Lucy and FPL Davis substations.
2. GENERAL DESIGN SCOPE
The Consultant shall be responsible for the following primary design elements:
· Transmission Interface: Two (2) 138 kV transmission line feeds, two (2) 138 kV line switches, and one (1) 138 kV disconnect switch configured as two radial lines with a bus tie.
· Power Transformers: Two (2) 138 kV / 13.2 kV, 44.8 MVA power transformers.
· High Voltage Protection: 138 kV circuit switchers with an interrupting rating of 20 kA.
· Medium Voltage Bus: 13.2 kV outdoor double bus rated at 2000A.
· Feeders: Eight (6) load positions served by 13.2 kV, 1200A outdoor circuit breakers.
· Auxiliary Power: Two (2) power and light transformers for substation AC requirements.
3. DETAILED SCOPE BY DISCIPLINE
A. Structural and Civil Engineering
· Surveys & Geotechnical: Site boundary, topographical surveys, and geotechnical reports.
· Site Design: Grading and drainage plans, specifications, and drainage calculations.
· Structures: Design and calculations for bus structures, including load trees for concrete poles.
· Foundations: Detailed design and calculations for all equipment foundations.
· Perimeter: Fence plans and details.
· Environmental: SPCC (Spill Prevention, Control, and Countermeasure) plan11.
B. Substation Engineering (Physical Design)
· Arrangement: Electrical Single Line Diagrams, General Arrangements, and Electrical Sections.
· Grounding & Shielding: Grounding plan/study and Lightning shielding plan/study.
· Conduit & Cable: Conduit plans, cable trench drawings/details, and conduit schedules.
· Station Service: AC and DC station load studies, battery sizing, and station light/power calculations.
· Procurement Support: Development of Long Lead Material Lists and Equipment Specifications.
C. Protection and Control (P&C) Engineering
· One-Lines: Relay one-line and three-line diagrams.
· Schematics: AC and DC elementary (schematic) diagrams.
· Wiring: Interconnection relay panel wiring and remote wiring diagrams for all electrical equipment.
· Hardware: Relay panel arrangements and a comprehensive Bill of Materials (BOM).
4. REQUIRED STUDIES AND CALCULATIONS
Final reports for all studies must be signed and sealed by a Florida Registered Professional Engineer and include:
· Grounding and Lightning Shielding Studies.
· Lighting/Illumination Study.
· AC/DC Station Load and Battery Sizing Calculations.
· Substation Bus Strength Calculations.
5. PROJECT DELIVERABLES AND PHASES
The project shall follow a structured review process with submittals at the following intervals:
1. 30% Design Package: Focus on site layout, single lines, and long-lead equipment specs.
2. 60% Design Package: Detailed physical and structural design, including most studies and elementary diagrams.
3. 90% Design Package: Finalized drawings incorporating all previous comments and vendor-certified data.
4. Issued for Construction (IFC): Final signed and sealed package incorporating all HES comments.
5. As-Built Documentation: Processing of field markups within 30 days of construction completion.
6. PROPOSAL REQUIREMENTS
Consultants responding to this RFP should include:
· Project Approach: Detailed methodology for managing schedule, quality (QA/QC), and risks.
· Relevant Experience: Examples of 138kV substation designs performed in Florida.
· Project Team: Identification of the Project Manager and lead discipline engineers (PE licensure in Florida is required).
· Schedule: A proposed timeline from Award of Contract (ARO) through IFC submittal.