Replace Main Kitchen Freezers_100 Bid Drawings.pdf
PDF 12 MB Posted
- Attached to
- Y1AZ--REPLACE MAIN KITCHEN FREEZERS Project 526-21-111 Federal contract opportunity
- Solicitation number
- 36C24223B0046
About this file
This document outlines a federal contract opportunity from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2 to replace main kitchen freezers. The solicitation number is 36C24223B0046 for the Y1AZ--REPLACE MAIN KITCHEN FREEZERS Project 526-21-111. The opportunity type is a solicitation to provide replacement of main kitchen freezers. Relevant details include the federal agency involved, the project name and number, and that the opportunity is for replacement of main kitchen freezers. No other salient information is provided in the document.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24223B0046 0002.docx | DOCX document | |
| 36C24223B0046 0001.docx | DOCX document | |
| REPLACE MAIN KITCHEN FREEZERS_IFB 36C24224B0046_SITE VISIT SIGN IN SHEET_12.20.23.pdf | ||
| Bronx Kitchen Freezers_100Bid Specifications.pdf | ||
| P07_DBA WAGE RATES_REPLACE MAIN KITCHEN FREEZERS - Copy.docx | DOCX document | |
| FAR 52.225-2 BUY AMERICAN CERTIFICATE.docx | DOCX document | |
| 36C24223B0046_2.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TITLE
WEBB AVENUE
SEDGWICK
AVENUE
KI
N
G
SB
R
ID
G E
R O
AD
REPLACE MAIN KITCHEN FREEZERS
TB BF
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
100% CD BID DOCUMENTSCapital Assets Section/
Engineering Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
26 OCTOBER 2022Revisions: Date:
526-21-111
130 W KINGSBRIDGE RD, BRONX, NY 10468
REPLACE MAIN KITCHEN FREEZERS
Approved: Assoc Project Director
Approved: Chief Engineer
Approved: Safety Manager
Approved: NAL
Approved: PCC/Service Director
ARCHITECT/ENGINEER OF RECORDCONSULTANT
MEP Consultant:
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
OWEGO, NY 13827
T:888.696.1198
SAFETY/EGRESS - GROUND FLOOR PLAN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
100% CD BID DOCUMENTSCapital Assets Section/
Engineering Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
26 OCTOBER 2022Revisions: Date:
526-21-111
130 W KINGSBRIDGE RD, BRONX, NY 10468
REPLACE MAIN KITCHEN FREEZERS
Approved: Assoc Project Director
Approved: Chief Engineer
Approved: Safety Manager
Approved: NAL
Approved: PCC/Service Director
ARCHITECT/ENGINEER OF RECORDCONSULTANT
MEP Consultant:
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
PARTITION TYPE - TEMP BARRIER
GROUND FLOOR DEMOLITION PLAN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
100% CD BID DOCUMENTSCapital Assets Section/
Engineering Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
26 OCTOBER 2022Revisions: Date:
526-21-111
130 W KINGSBRIDGE RD, BRONX, NY 10468
REPLACE MAIN KITCHEN FREEZERS
Approved: Assoc Project Director
Approved: Chief Engineer
Approved: Safety Manager
Approved: NAL
Approved: PCC/Service Director
ARCHITECT/ENGINEER OF RECORDCONSULTANT
MEP Consultant:
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
GROUND FLOOR DEMOLITION PLAN
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
100% CD BID DOCUMENTSCapital Assets Section/
Engineering Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
26 OCTOBER 2022Revisions: Date:
526-21-111
130 W KINGSBRIDGE RD, BRONX, NY 10468
REPLACE MAIN KITCHEN FREEZERS
Approved: Assoc Project Director
Approved: Chief Engineer
Approved: Safety Manager
Approved: NAL
Approved: PCC/Service Director
ARCHITECT/ENGINEER OF RECORDCONSULTANT
MEP Consultant:
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
GROUND FLOOR NEW CONSTRUCTION PLAN
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
100% CD BID DOCUMENTSCapital Assets Section/
Engineering Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
26 OCTOBER 2022Revisions: Date:
526-21-111
130 W KINGSBRIDGE RD, BRONX, NY 10468
REPLACE MAIN KITCHEN FREEZERS
Approved: Assoc Project Director
Approved: Chief Engineer
Approved: Safety Manager
Approved: NAL
Approved: PCC/Service Director
ARCHITECT/ENGINEER OF RECORDCONSULTANT
MEP Consultant:
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
OWEGO, NY 13827
CONCRETE PAD ON GRADE DETAIL
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h 6/
/2
:3
9:
P M
100% CD BID DOCUMENTSCapital Assets Section/
Engineering Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
26 OCTOBER 2022Revisions: Date:
526-21-111
130 W KINGSBRIDGE RD, BRONX, NY 10468
REPLACE MAIN KITCHEN FREEZERS
Approved: Assoc Project Director
Approved: Chief Engineer
Approved: Safety Manager
Approved: NAL
Approved: PCC/Service Director
ARCHITECT/ENGINEER OF RECORDCONSULTANT
MEP Consultant:
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
OWEGO, NY 13827
T:888.696.1198
GROUND FLOOR NEW CONSTRUCTION PLAN
FLOOR ASSEMBLY DETAIL AT GE-01A
FLOOR ASSEMBLY DETAIL AT GE-01E, GE-05, GE-06, GE-07, GE-09
FINISH SCHEDULE DOOR ELEVATION AND SECTION SECTION @ GE-01A ONLY
CONTROLS SYMBOLS
T ROOM THERMOSTAT/TRANSMITTER - WALL MOUNT
H7
A
DRAWING SYMBOLS
DRAWING NUMBER WHERE SHOWN
SECTION LETTER
GATE VALVE WITH GLOBE-VALVED
BYPASS
PLUG VALVE
WYE STRAINER WITH VALVED DRAIN AND QUICK-COUPLE
HOSE CONNECTOR
VALVE SYMBOLS
BALL VALVE
GATE VALVE WITH 3/4" HOSE ADAPTER
CHECK VALVE
ANGLE GLOBE VALVE
BUTTERFLY VALVE
MODULATING CONTROL VALVE
TWO POSITION CONTROL VALVE
THREE-WAY MODULATING CONTROL VALVE
AUTOMATIC BALANCING CONTROL VALVE
PRESSURE SAFETY VALVE
GATE VALVE - THREADED/FLANGED
GLOBE VALVE - THREADED/FLANGED
PRESSURE REGULATING VALVE
THREE-WAY TWO POSITION CONTROL VALVE
WYE STRAINER (WITH BALL VALVE & HOSE CONNECTION)
FLEXIBLE CONNECTION
WATER BALANCE DEVICE
MODULATING CONTROL BUTTERFLY VALVE
CIRCUIT SETTER VALVE
QUICK-COUPLE HOSE CONNECTOR
GENERAL PIPING SYMBOLS
ANCHOR
REDUCER OR INCREASER
DIRECTION OF FLOW
SIDE CONNECTION
ECCENTRIC REDUCER
BOTTOM CONNECTION, 45° OR 90°
TOP CONNECTION, 45° OR 90°
DIRECTION OF PIPE PITCH (DOWN)
UNION
RISE OR DROP IN PIPE
CAPPED OUTLET
PRESSURE GAGE
THERMOMETER
FLOW ELEMENT
FLOAT & THERMOSTATIC TRAP SET INCLUDING PIPING
ACCESSORIES SEE DETAIL
INVERTED BUCKET TRAP SET INCLUDING PIPING
ACCESSORIES SEE DETAIL
PIPE UP
PIPE DOWN
REFRIGERANT SIGHT GLASS
TEST PLUG (PRESSURE/TEMPERATURE)
AUTOMATIC AIR VENT
AV
MANUAL AIR VENTMV
THERMOSTATIC TRAP SET INCLUDING PIPING ACCESSORIES
SEE DETAIL
FE
W WATTS
Wb WET-BULB (TEMPERATURE)
VHA VETERANS HEALTH ADMINISTRATION
UC UNIT COOLER
UL UNDERWRITERS LABORATORY
Db DRY-BULB TEMPERATURE
DEG DEGREE
DIA DIAMETER
DPS DIFFERENTIAL PRESSURE SENSOR
CFM CUBIC FEET PER MINUTE
BFP BACKFLOW PREVENTER
BTU BRITISH THERMAL UNIT
BTUH BRITISH THERMAL UNIT PER HOUR
A/E ARCHITECT / ENGINEER
AAV AUTOMATIC AIR VENT
ACC AIR COOLED CONDENSER
ACCU AIR-COOLED CONDENSING UNIT
AFF ABOVE FINISHED FLOOR
AHU AIR-HANDLING UNIT
AMP AMPERGE
APD AIR PRESSURE DROP
ASME AMERICAN SOCIETY OF
MECHANICAL ENGINEERS
C CENTIGRADE (CELCIUS)
EA EXHAUST AIR
EAT ENTERING AIR TEMPERATURE
ECC ENGINEERING CONTROL CENTER
EF EXHAUST FAN
ENT ENTERING
ESP EXTERNAL STATIC PRESSURE
EWT ENTERING WATER TEMPERATURE
EX EXISTING
F FAHRENHEIT
FD FLOOR DRAIN
GA GAUGE
GAL GALLONS
GPM GALLONS PER MINUTE
HP HORSEPOWER
HZ HERTZ
FT FEET
NA NOT APPLICABLE
NTS NOT TO SCALE
MAX MAXIMUM
MCA MINIMUM BRANCH CIRCUIT AMPACITY
MIN MINIMUM
LAT LEAVING AIR TEMPERATURE
LBS/HR POUNDS PER HOUR
LWT LEAVING WATER TEMPERATURE
I/O INPUT/OUTPUT
IN INCHES
IN WC INCH WATER COLUMN
IN WG INCH WATER GAUGE
TAB TESTING, ADJUSTING, BALANCE
TD TEMPERATURE DIFFERENCE
SQ FT SQUARE FOOT (FEET)
SS STAINLESS STEEL
RL REFRIGERANT LIQUID LINE
RLA RUN LOAD AMPERE
RPM REVOLUTIONS PER MINUTE
RS REFRIGERANT SUCTION
PD PRESSURE DROP
PSI POUNDS PER SQUARE INCH
PSIA POUNDS PER SQUARE
INCH
– ABSOLUTE
PSIG POUNDS PER SQUARE INCH– GAGE
ABBREVIATIONS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CD BID DOCUMENTSCapital Assets
U.S. Department
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
MEP Consultant:
REPLACE MAIN KITCHEN FREEZERS
130 W KINGSBRIDGE RD, BRONX, NY 10468
526-21-111
26 OCTOBER 2022 JWE MPL
Approved:
Project Director
Assoc Project Director
Section/ Engineering
Service Approved:
Approved:
Chief Engineer
Safety Manager
Approved:
Approved:
NAL
PCC/Service Director
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
OWEGO, NY 13827
T:888.696.1198 of Veterans Affairs
CONCEPT / PRELIMINARIES SUBMITTAL 18 MAR 22
35% SCHEMATIC DESIGN SUBMITTAL 2 MAY 22
65% DESIGN DEVELOPMENT SUBMITTAL 8 JUL 22
95% CONSTRUCTION DOCUMENTS SUBMITTAL 22 AUG 22
100% CONSTRUCTION DOCUMENTS SUBMITTAL 26 SEP 22
100% CD BID DOCUMENTS SUBMITTAL 26 OCT 22
G sh or tc ut
-ta rg et s-by -id
\1 Am
4f gx
Kh 1N aH Sg
M M
-W y-
Q cI
T2 U
9e tIJ z\ W at so n En gi ne er in g\ 1-
W at so n
En gi ne er in g, P C
\2
1\ Th in kf or m
\T H
-2
R ep la ce
M ai n Ki tc he n Fr ee ze rs B ro nx
V
AM
C \W at so n D ra w in gs
\R ev it\ W at so n R ev it
Pr oj ec t.r vt
/2 5/
:1
3:
P M
M-001
MECHANICAL NOTES, SYMBOLS,
AND ABBREVIATIONS
GENERAL MECHANICAL NOTES:
1. THE GENERAL MECHANICAL NOTES ON THIS SHEET APPLY TO ALL THE MECHANICAL DRAWINGS.
2. IT IS THE MECHANICAL CONTRACTOR'S RESPONSIBILITY TO FIELD VERIFY ALL ASPECTS OF THE DESIGN, TO INCLUDE THE WORK OF SUB-TRADES, PRIOR TO SUBMITTING A BID.
3. THE MECHANICAL DRAWINGS SHALL BE FOLLOWED AS CLOSELY AS POSSIBLE, ALTHOUGH NO ATTEMPT WAS MADE TO SHOW EVERY OFFSET, FITTING, BEAM, PIPE SUPPORT, CLEARANCE, ETC. IT IS THE MECHANICAL CONTRACTOR’S RESPONSIBILITY TO SURVEY ALL WORK AREAS AND SUBMIT FINAL, DETAILED COORDINATED SHOP DRAWINGS FOR REVIEW BY THE DESIGNER OF RECORD TO ENSURE THAT THE DESIGN INTENT WILL BE MET AND THAT ALL TRADES ARE PROPERLY COORDINATED. CHANGES REQUIRED TO FIT EQUIPMENT, PIPING, AND DUCTWORK SHALL BE PROVIDED AT NO ADDITIONAL COST TO THE OWNER. ANY
MAJOR DISCREPANCIES SHALL BE CLARIFIED PRIOR TO SUBMITTAL OF BID.
4. BECAUSE OF THE SMALL SCALE OF THE DRAWINGS, IT IS NOT POSSIBLE TO INDICATE ALL OFFSETS, TRANSITIONS, FITTINGS, CLEARANCES, POSSIBLES CLASHES, AND ACCESSORIES THAT MAY BE REQUIRED.
COORDINATE ALL THE WORK OF ALL THE TRADES TO ENSURE ALL DUCTS, PIPES, CONDUITS, ETC. DO NOT CONFLICT AND CLEAR STRUCTURAL AND ARCHITECTURAL MEMBERS. THE MECHANICAL CONTRACTOR IS RESPONSIBLE FOR DEVELOPING COORDINATED SHOP DRAWINGS FOR REVIEW PRIOR TO STARTING INSTALLATION.
5. MECHANICAL CONTRACTOR SHALL VISIT THE SITE AND BE FULLY COGNIZANT OF ALL CONDITIONS PRIOR TO SUBMITTING BID. REPORT ANY DISCREPANCIES TO THE ENGINEER PRIOR TO SUBMITTAL OF BID.
6. IF A JOB REQUIRES TYING INTO ANY EXISTING MECHANICAL SYSTEM, THE MECHANICAL CONTRACTOR SHALL CONDUCT NECESSARY PRE TEST, ADJUST, AND BALANCING (TAB) ACTIVITIES TO VERIFY BASELINE SOURCE CAPACITY FROM THE FACILITY, UNLESS THE OWNER CAN PROVIDE SUFFICIENT FACILITY MECHANICAL TREND LOGS TO ESTABLISH THAT SUFFICIENT SOURCE CAPACITY EXISTS. UPON DETERMINING INSUFFICIENT SOURCE CAPACITY, THE MECHANICAL CONTRACTOR SHALL IMMEDIATELY REPORT FINDINGS TO THE OWNER AND ENGINEER FOR RECORD FOR ADDITIONAL GUIDANCE BEFORE PROCEEDING.
7. THE WORK INCLUDES ALL ITEMS OF THE MECHANICAL SPECIFICATIONS THAT ARE EITHER WRITTEN ON THE DRAWINGS OR SEPARATELY IN A SPECIFICATIONS BOOK.
8. WHERE THERE IS A CONFLICT ON THE PLANS, SPECIFICATIONS, NOTES, GENERAL NOTES, REFERENCES, PUBLICATIONS, CODES, ETC. WITH RESPECT TO CONSTRUCTION, MATERIALS, PRODUCTS, METHODS, WORKMANSHIP, PROCEDURE, EXECUTION, ETC. THE MOST STRINGENT SHALL BE UTILIZED OR INSTALLED. THE MOST STRINGENT SHALL BE DEFINED AS THE SPECIFICATION OR REQUIREMENT THAT ALLOWS ALL SPECIFICATIONS OR REQUIREMENTS THAT ARE IN CONFLICT TO BE SATISFIED. NO RELIEF OR EXTRA PAYMENT SHALL BE MADE TO THE CONTRACTOR BECAUSE OF THIS INTERPRETATION.
9. MECHANICAL CONTRACTOR SHALL NOT BEGIN FABRICATION, CUT ANY MEMBERS, OR BEGIN INSTALLATION UNTIL THE SUBMITTALS AND COORDINATED SHOP DRAWINGS HAVE BEEN APPROVED. ANY WORK CONSTRUCTED OR INSTALLED PRIOR TO THE APPROVAL OF SUBMITTALS AND COORDINATED SHOP DRAWINGS SHALL BE AT THE MECHANICAL CONTRACTOR'S RISK AND SHALL BE REMOVED AND REINSTALLED OR RECONSTRUCTED AT THE MECHANICAL CONTRACTOR'S EXPENSE AT THE REQUEST OF THE OWNER'S REPRESENTATIVE TO THE COMPLETE SATISFACTION OF THE OWNER'S REPRESENTATIVE.
10. ALL WORK SHALL BE DONE WITH COMPLETE COMPLIANCE WITH THE PUBLISHED EDITIONS OF THE APPLICABLE CODES AND STANDARDS WHETHER STATUTORY OR NOT. ALL WORK SHALL BE INSTALLED TO COMPLY WITH THE INTERNATIONAL BUILDING MECHANICAL CODE, UNDERWRITER'S LABORATORY, INC., AMERICAN NATIONAL STANDARD INSTITUTE, INC. IF ANY PART OF THE INSTALLATION DOES NOT MEET CODE, NOTIFY THE OWNER'S REPRESENTATIVE PRIOR TO BEGINNING THE INSTALLATION. IF ANY PART OF THE PROJECT CANNOT BE INSTALLED TO CONFORM WITH THE PLANS AND/OR SPECIFICATIONS, NOTIFY THE
OWNER'S REPRESENTATIVE PRIOR TO BEGINNING THE INSTALLATION.
11. UNLESS STATED OTHERWISE, ALL EXISTING MATERIAL AND EQUIPMENT SHALL REMAIN THE PROPERTY OF THE PROJECT OWNER.
12. THE MECHANICAL CONTRACTOR SHALL DEVELOP AND PRESENT A CONSTRUCTION PLAN AND WORK SCHEDULE WITH ALL PHASING, STAGING, AND SEQUENCING OF WORK FOR APPROVAL PRIOR TO THE COMMENCEMENT AND BEGINNING IMPLEMENTATION OF HIS WORK. THE MECHANICAL CONTRACTOR SHALL DETERMINE PRIOR TO SUBMITTING HIS WORK SCHEDULE, THE SPECIFIC TIME AVAILABILITY OF ALL AREAS
AND SPACES AND DETERMINE WHAT WORK MUST BE DONE DURING "OFF HOURS".
13. WITH THE EXCEPTION OF SIGNIFICANT NOISE GENERATING ACTIVITIES SUCH AS CORE DRILLING, ETC., WORK OUTSIDE OF THE OCCUPIED SPACES, SUCH AS ON THE ROOF, ETC., MAY BE PERFORMED DURING
NORMAL WORKING HOURS.
14. UNLESS SPECIFICALLY NOTED AS EXISTING, ALL ITEMS, EQUIPMENT, AND WORK SHOWN IS NEW AND SHALL BE FURNISHED AND INSTALLED BY THE MECHANICAL CONTRACTOR.
15. DURING THE EXECUTION OF THIS CONTRACT, THE SITE AND BUILDINGS WILL BE OCCUPIED AND IN USE. WORK DONE UNDER THIS CONTRACT SHALL BE PERFORMED WITHOUT INCONVENIENCE TO THE OWNER INSOFAR AS POSSIBLE. ALL WORK SHALL BE COORDINATED WITH THE OWNER'S REPRESENTATIVE AND IS SUBJECT TO THEIR CONTINUOUS APPROVAL.
16. THE MECHANICAL CONTRACTOR IS COMPLETELY RESPONSIBLE FOR ALL CHARACTERISTICS OF THE EQUIPMENT THAT HE INTENDS TO INSTALL AND MUST FOLLOW MANUFACTURER RECOMMENDATIONS FOR PROPER INSTALLATION. IF THERE ARE ANY DIFFERENCES IN THE EQUIPMENT SHOWN ON THE DESIGN DRAWINGS AND THE EQUIPMENT TO BE INSTALLED, THE MECHANICAL CONTRACTOR SHALL MAKE ALL CHANGES AND ADJUSTMENTS TO ACCOMMODATE THE PROPOSED EQUIPMENT AT NO ADDITIONAL COST TO THE OWNER. THIS APPLIES TO ALL SUPPORT SERVICES AND FACILITIES NECESSARY TO PROPERLY INSTALL THE EQUIPMENT TO FUNCTION ADEQUATELY AS PART OF THE SYSTEMS FOR WHICH THEY WERE DESIGNED AND SELECTED. THESE CHARACTERISTICS INCLUDE SUCH THINGS AS WEIGHT, CLEARANCE, DIMENSIONS, ELECTRICAL, MECHANICAL, PLUMBING, AND UTILITY SERVICES, ETC. ACCOMMODATING SERVICES INCLUDE SUCH THINGS AS DIMENSIONS, LOCATIONS, AND SIZES OF SUPPORTING MEMBERS, PIPE, CONNECTION SIZES, ELECTRICAL SERVICE SIZE AND PROTECTION, ELECTRICAL CONNECTION LOCATION, UTILITY AND PLUMBING CONNECTION SIZES AND LOCATIONS, ETC. ALL REQUIRED CHANGES TO THE CONTRACT DRAWINGS AND SPECIFICATIONS SHALL BE DESIGNED AND STAMPED BY REGISTERED ENGINEERS IN THE APPROPRIATE DISCIPLINE EMPLOYED BY THE MECHANICAL CONTRACTOR AND SHALL BE INCLUDED AS PART OF THE EQUIPMENT SUBMITTALS. ALL CHANGES SHALL BE SUBJECT TO THE APPROVAL OF THE PROJECT A/E AND THE OWNER'S REPRESENTATIVE.
17. BEFORE ANY DEMOLITION OR CONSTRUCTION WORK IS BEGUN, THE MECHANICAL CONTRACTOR AND THE OWNER'S REPRESENTATIVE SHALL SURVEY THE EXISTING BUILDING AREA TO BE MODIFIED AND/OR REPLACED TO ACCURATELY DOCUMENT EXISTING CONDITIONS. THIS SURVEY WILL BE USED BY THE OWNER'S REPRESENTATIVE AT JOB COMPLETION TO DETERMINE WHICH BUILDING/SITE COMPONENTS MUST BE
REPLACED WITH NEW.
18. UNLESS STATED OTHERWISE, REQUEST APPROVAL FROM THE OWNER'S REPRESENTATIVE SEVEN DAYS IN ADVANCE FOR THE SHUTDOWN OF ANY EXISTING SYSTEM.
19. UNLESS STATED OTHERWISE, FINAL ADVANCE NOTICE OF 48 HOURS SHALL BE GIVEN TO THE OWNER'S REPRESENTATIVE PRIOR TO THE PROPOSED SHUTDOWN OF ANY SYSTEM.
20. THE CLOSING AND OPENING OF VALVES SHALL BE WITNESSED BY THE OWNER'S REPRESENTATIVE; NOTIFY LOCAL AUTHORITIES AS REQUIRED.
21. PROVIDE ADEQUATE FIRE PROTECTION IN THE ENTIRE CONSTRUCTION AREA FOR THE DURATION OF THE CONSTRUCTION PERIOD. COORDINATE WITH INSTALLING FIRE PROTECTION CONTRACTOR.
22. THE ENTIRE EXISTING FIRE PROTECTION SYSTEM SHALL BE RESTORED TO FULL OPERATION AT THE END OF EACH WORKING DAY. ALL EXISTING FIRE ALARMS AND FIRE EXITS AND ANY OTHER ASPECT OF THE EXISTING FIRE ALARM SYSTEM SHALL REMAIN IN FULL OPERATION. THE COST OF RESPONSE TO ANY FALSE ALARM AS CHARGED BY ANY LOCAL FIRE DEPARTMENT SHALL BE PAID BY THE MECHANICAL
CONTRACTOR.
23. MECHANICAL CONTRACTOR SHALL NOT PENETRATE OR CUT ANY STRUCTURAL MEMBERS NOT SPECIFICALLY SHOWN ON THE DRAWINGS (E.G., JOISTS, BEAMS, ETC.). IF STRUCTURAL MEMBERS CONFLICT WITH ROUTING, CONTACT THE OWNER'S REPRESENTATIVE FOR DIRECTION BEFORE PROCEEDING. EXERCISE CAUTION IN CUTTING CONCRETE FLOORS AND WALLS TO AVOID EXISTING UTILITIES WHICH MAY BE LOCATED
IN AND UNDER CONCRETE SURFACES.
24. THE MECHANICAL CONTRACTOR SHALL PROVIDE NEW OPENINGS IN WALLS, FLOOR, AND ROOF, AND PATCH EXISTING OPENINGS IN CONJUNCTION WITH THE DEMOLITION AND INSTALLATION OF THE NEW BUILDING
COMPONENTS. ALL NECESSARY FRAMING, COUNTER-FLASHING, ETC. SHALL BE INCLUDED.
25. FOR ALL FLOOR, WALL, AND ROOF PENETRATION, VERIFY THE LOCATION OF THE EXISTING STRUCTURAL MEMBERS PRIOR TO DRILLING AND CUTTING, RELOCATE OPENINGS AS REQUIRED AND OFFSET DUCTS, PIPES, CONDUIT, ETC.
26. ALL EXISTING DUCTWORK, PIPING, CONDUIT, AND MECHANICAL EQUIPMENT NOT TO BE REUSED OR REMAIN IN SERVICE SHALL BE REMOVED FROM THE FACILITY. THE OWNER'S REPRESENTATIVE HAS THE OPTION TO RECLAIM ANY DEMOLISHED MATERIALS OR EQUIPMENT, IN WHICH CASE IT SHALL BE DELIVERED TO THE LOCATION DESIGNATED BY THE OWNER'S REPRESENTATIVE.
27. FOR EACH PHASE AND BEFORE INTERRUPTING EACH EXISTING UTILITY, DETERMINE, IN ADVANCE, IF ANY DOWNSTREAM SERVICE BEYOND THE CONSTRUCTION AREA OF THE PHASE, WILL BE INTERRUPTED AND PROVIDE A TEMPORARY SERVICE BYPASSING THE CONSTRUCTION AREA. DETERMINE ALL SUCH TEMPORARY SERVICES PRIOR TO SUBMITTING BID. THERE WILL BE NO FUTURE CONSIDERATION TO THE MECHANICAL CONTRACTOR FOR ANY TEMPORARY SERVICES REQUIRED. PREPARE A DETAILED SHOP DRAWING SHOWING ALL OF THE EXISTING UTILITIES IN THEIR RELOCATED LOCATION AND ALL THE NEW HVAC SYSTEMS.
28. THE FLOOR AREAS BELOW OVERHEAD WORK, WHERE WELDING "HOT WORK" IS TO BE PERFORMED, SHALL BE CLEARED TO A MINIMUM DISTANCE OF 36 FEET BEYOND THE POINT DIRECTLY BELOW THE OVERHEAD "HOT WORK". ALL FLAMMABLE MATERIALS SHALL BE CLEARED TO A DISTANCE 50 FEET BEYOND THE POINT DIRECTLY BELOW THE OVERHEAD "HOT WORK".
29. EXISTING DUCTWORK, DOMESTIC COLD WATER PIPING, DOMESTIC HOT WATER PIPING, CHILLED AND HEATING HOT WATER PIPING, WASTE, VENT, FIRE SPRINKLER LINES, FIRE ALARM EQUIPMENT, ELECTRICAL CONDUIT, TELEPHONE CONDUIT, COMMUNICATION CONDUIT, PNEUMATIC TUBING, ETC., MAY HAVE TO BE RELOCATED TO FACILITATE THE INSTALLATION OF THE NEW WORK. THE CONTRACTOR SHALL DETERMINE ALL EXISTING SERVICES THAT REQUIRE RELOCATION PRIOR TO SUBMITTING HIS BID AND INCLUDE ALL COSTS IN THE BID. THERE WILL BE NO EXTRA COMPENSATION TO THE CONTRACTOR FOR THIS WORK.
30. THE CONTRACTOR IS HEREBY NOTIFIED THAT SOME WORK MAY BE REQUIRED OUTSIDE OF THE AREAS SHOWN ON THESE DRAWINGS. THIS COULD INCLUDE ELECTRICAL WORK, REFRIGERANT LINE ROUTING, CONTROL MODIFICATIONS OR CONNECTIONS AT REMOTE LOCATIONS, CONTROL PANELS, CPU'S, ETC.
31. THE CONTRACTOR SHALL PAY FOR ALL DAMAGE, INCLUDING WATER DAMAGE, TO PROPERTY AND EQUIPMENT CAUSED BY HIS WORK THROUGHOUT THE CONSTRUCTION AND WARRANTEE PERIOD.
32. ALL CEILING DEMOLITION WORK SHALL BE DONE AFTER NORMAL WORKING HOURS. THE INSTALLATION OF THE NEW CEILING SHALL BE DONE AFTER NORMAL WORKING HOURS. THE WORK AREA SHALL BE
CLEANED BEFORE THE START OF EACH WORKING DAY.
33. REMOVE T-BARS AND 2X4 CEILING PANELS AS REQUIRED FOR THE DEMOLITION AND THE INSTALLATION OF THE NEW WORK. REINSTALL EXISTING OR REPLACE WITH NEW AS REQUIRED TO THE SATISFACTION OF THE OWNER'S REPRESENTATIVE. FOR ANY HARD CEILING AREA, CUT AND DEMOLISH ENOUGH OF THE HARD CEILING TO DO THE WORK REQUIRED. REBUILD AND PATCH THE DEMOLISHED. FINISH AND PAINT TO
MATCH EXISTING TO THE SATISFACTION OF THE OWNER'S REPRESENTATIVE.
34. ANY DEVICE THAT REQUIRES ACCESS FOR ADJUSTMENT OR ROUTINE MAINTENENANCE, SUCH AS BUT NOT LIMITED TO VALVES, VOLUME DAMPERS, CONTROL DEVICES, VAVS, ETC. SHALL BE INSTALLED IN AN
ACCESSIBLE LOCATION.
35. PATCH AND PAINT TO MATCH EXISTING, ALL SURFACES DAMAGED BY THE DEMOLITION AND ALL OPENINGS NOT TO BE REUSED.
36. REPAIR DAMAGE TO CEILING, WALLS, ETC. TO THE SATISFACTION OF THE OWNER'S REPRESENTATIVE.
37. WHEN A DETAIL OR NOTE IS IDENTIFIED AS TYPICAL, THE MECHANICAL CONTRACTOR IS TO APPLY THE DETAIL OR NOTE TO EVERY SIMILAR CONDITION, WHETHER OR NOT THE REFERENCED DETAIL OR NOTE IS
REPEATED OR REFERENCED.
38. WHERE NO CONSTRUCTION DETAIL IS INDICATED, SUCH WORK SHALL BE SIMILAR TO COMPARABLE WORK DETAILED OR NOTED ELSEWHERE OR TO MATCH EXISTING CONDITIONS, SUBJECT TO THE APPROVAL OF
THE OWNER'S REPRESENTATIVE.
39. ALL HOLES, VOIDS, AND DAMAGED OR UNEVEN SURFACES WHICH ARE CAUSED BY THE MECHANICAL CONTRACTOR'S WORK AND WHICH REMAIN EXPOSED IN THE WALL, FLOOR, CEILING, OR OTHER SURFACES SHALL BE PATCHED, REPAIRED, AND BROUGHT FLUSH WITH THE ADJACENT CONSTRUCTION. SUCH SURFACES, NOT CONCEALED BY THE NEW CONSTRUCTION, SHALL MATCH IN EVERY RESPECT THE EXISTING NON-DAMAGED CONSTRUCTION. REMOVE EXISTING UTILITIES BACK BEHIND EXISTING SURFACES AND CAP SO AS NOT TO INTERFERE WITH NEW PATCHES.
40. WHEREVER NEW WALL, FLOOR, OR CEILING FINISHES ARE INDICATED, THE MECHANICAL CONTRACTOR SHALL BRING EXISTING MECHANICAL COMPONENTS FLUSH WITH THE NEW FINISHED SURFACES IF
APPROPRIATE.
41. THE DEMOLITION SHALL INCLUDE ALL ASSOCIATED ANCHORAGES, HANGERS, SUPPORTS, BRACES, FASTENERS, MASTIC, MORTAR, LATH, AND RELATED ITEMS. THE EXISTING SUBSTRATE, INCLUDING CONCRETE, MASONRY, METAL FRAMING AND FURRING SHALL BE REPAIRED WHERE DAMAGE BY THE CONTRACTOR'S WORK.
42. PROVIDE ALL VALVES, INSTRUMENTS, FITTINGS, ETC. AS SHOWN ON THE PIPING DIAGRAMS, SCHEMATICS, ETC. IT IS NOT POSSIBLE TO SHOW ALL VALVES, INSTRUMENTS, ETC. ON THE PLANS, HOWEVER, SELECTED VALVES HAVE BEEN SHOWN FOR REFERENCE. ALL VALVES SHALL BE ACCESSIBLE FROM THE FLOOR OR FROM FIXED PLATFORMS.
43. ALL NEW FIRE ALARM DEVICES INSTALLED IN HVAC EQUIPMENT SUCH AS SMOKE DETECTORS, SMOKE DAMPERS, FIRE/SMOKE DAMPERS, ETC. SHALL BE CONNECTED TO THE MAIN FIRE ALARM PANEL.
44. ALL EQUIPMENT AND MATERIALS SUBJECT TO THE WEATHER THAT ARE NOT FACTORY PAINTED SHALL BE FIELD PAINTED AND WEATHER PROOFED WITH PRIMER, AND TWO COATS OF EXTERIOR PAINT. MATCH THE COLOR OF THE EXISTING BUILDING EXTERIOR. THE COLOR AND QUANTITY OF THE PAINT IS SUBJECT TO THE APPROVAL OF THE OWNER'S REPRESENTATIVE. SUBMITTAL REQUIRED.
45. ANY ANTICIPATED HAZARDOUS MATERIALS (HAZMAT) ARE INDICATED ON THE DRAWINGS, HOWEVER, IT IS IMPOSSIBLE TO PREDICT WHERE EXACTLY ALL HAZMAT MAY BE ENCOUNTERED. IF HAZMAT IS ENCOUNTERED OR SUSPECTED AT ANY POINT DURING CONSTRUCTION, CEASE ALL WORK IMMEDIATELY AND CONTACT THE OWNER’S REPRESENTATIVE FOR GUIDANCE.
46. THE CONTROLS CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR MAKING THE CONTROL SYSTEM COMPLETE AND FULLY OPERABLE. THE CONNECTION TO THE EXISTING CONTROL SYSTEM SHALL BE COMPLETE SUCH THAT ALL NEW MONITORING AND CONTROL POINTS ARE RECOGNIZED BY THE EXISTING CONTROL SYSTEM AND THAT ALL NEW POINTS CAN BE READ, ACTUATED, AND RESET FROM THE EXISTING FRONT END, AND VICE-VERSA. IT IS THE CONTRACTOR’S RESPONSIBILITY TO DETERMINE IF THERE IS ENOUGH SPACE AND/OR COMPATABILITY EXISTS TO USE EXISTING CONTROLLERS OR OTHER ASSOCIATED EXISTING CONTROLS EQUIPMENT. IF COMPATIBILITY AND/OR SPACE DOES NOT EXIST, IT IS THE CONTROLS CONTRACTOR RESPONSIBILITY TO PROVIDE THE REQUIRED CONTROLLERS, BRIDGES, ETC. TO ALLOW FULL INTEGRATION OF REQUIRED POINTS AND TO SATISFY THE SEQUENCE OF OPERATIONS. THE ENGINEER SHALL BE NOTIFIED WHEN EACH PHASE OF THE SYSTEM HAS BEEN COMPLETELY CHECKED OUT, ADJUSTED, CALIBRATED, AND PUT INTO FINAL WORKING CONDITION WITH ALL THE TROUBLESHOOTING COMPLETED. A SUBSEQUENT JOBSITE MEETING WILL BE SCHEDULED WITH TWO WEEKS NOTICE AT WHICH TIME THE CONTROLS CONTRACTOR WILL DEMONSTRATE THE OPERATION OF THE CONTROL SYSTEMS TO ALL CONCERNED. IF ANY ITEMS OF THE CONTROL SEQUENCE CANNOT BE SUCCESSFULLY DEMONSTRATED OR REQUIRE FURTHER TROUBLESHOOTING, A SUBSEQUENT CONTROLS INSPECTION WILL BE REQUIRED AND WILL BE AT THE CONTRACTOR'S EXPENSE. THIS PROVISION SHALL BE A CONDITION OF FINAL ACCEPTANCE. THE CONTRACTOR SHALL BE PREPARED TO DEMONSTRATE ALL ITEMS IN THE SEQUENCE OF OPERATION. SUBSEQUENT CONTROLS DEMONSTRATIONS AND VERIFICATIONS WILL BE REQUIRED AT THE
COMPLETION OF THE PROJECT.
47. UNLESS THE OWNER CHOOSES TO USE THEIR OWN THIRD-PARTY TEST, ADJUST, AND BALANCE AGENCY, THE MECHANICAL CONTRACTOR SHALL UTILIZE A THIRD PARTY TAB AGENCY FOR ALL NECESSARY FINAL TAB AND PROVIDE COORDINATION WITH EQUIPMENT MANUFACTURER FOR TYPICAL STARTUP SERVICES. FULL DOCUMENTATION, TO INCLUDE NECESSARY FACILITY STAFF TRAINING, SHALL BE COMPLETED AND
SUBMITTED TO ALLOW FOR REQUIRED CONTINUED OPERATION AND MAINTENANCE.
Revisions: Date:
WALK-IN COOLER/FREEZER CALCULATION SUMMARY
GE-01a GE-01E GE-05 GE-06 GE-07 GE-09
Refrigeration Type Refrigerator Freezer Refrigerator Refrigerator Refrigerator Refrigerator
Nominal Width (ft) 11 21 12 12 12 13
Nominal Length (ft) 20 50 21 21 21 21
Nominal Height (ft) 8 8 8 8 8 8
Volume (ft^3) 1768.2 8284.7 1980.0 2000.6 2000.6 2138.4
Surrounding Ambient Temperature (F) 85 85 85 85 85 85
Inside Refrigeration Temperature (F) 32 -10 32 32 32 32
Temperature Reduction dT=Ambient minus Inside Temp (F) 53 95 53 53 53 53
Walls Insulation Type
Walls K Factor-Thermal Conductivity (BTU/hr*SF*degF/in of thickness) 0.12 0.12 0.12 0.12 0.12 0.12
Wall Thickness (in) 4 4 4 4 4 4
Wall Heat Load (BTU/24hrs/SF) 38 68 38 38 38 38
Windows? yes yes yes yes yes yes
Window Area (SF) 1.36 2.72 1.36 1.36 1.36 1.36
Window Heat Load (BTU/24hrs/SF) 1350 2560 1350 1350 1350 1350
Floor Insulation Type Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane
Floor K Factor-Thermal Conductivity (BTU/hr*SF*degF/in of thickness) 0.12 0.12 0.12 0.12 0.12 0.12
Floor Thickness (in) 4 4 4 4 4 4
Floor Heat Load (BTU/24hrs/SF) 38 68 38 38 38 38
Ceiling Insulation Type Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane
Ceiling K Factor-Thermal Conductivity (BTU/hr*SF*degF/in of thickness) 0.12 0.12 0.12 0.12 0.12 0.12
Ceiling Thickness (in) 4 4 4 4 4 4
Ceiling Heat Load (BTU/24hrs/SF) 38 68 38 38 38 38
Walls Transmission Load (BTU/24hrs) 20670.26 83852.26 21621.78 21697.78 21697.78 22205.46
Floor Transmission Load (BTU/24hrs) 8398.79 70419.53 9405.00 9502.97 9502.97 10157.40
Ceiling Transmission Load (BTU/24hrs) 8398.79 70419.53 9405.00 9502.97 9502.97 10157.40
Total Transmission Load (BTU/24hrs) 37,468 224,691 40,432 40,704 40,704 42,520
Average Air Changes Per 24 Hours 13 6 12 12 12 12
Heat Removed in Cooling Air Storage Room Conditions (BTU/cubic ft) 2.09 3.49 2.09 2.09 2.09 2.09
Air Change Load (BTU/24hrs) 48,041 159,024 49,658 50,176 50,176 53,631
Product (Mixed Vegetables, Meat, Dairy, etc) Mixed Vegetables Beef, fresh Mixed Vegetables Beef, fresh Mixed Vegetables Milk, Pasteurized Grade A
Product Latent Heat of Fusion [NOTE IF REFRIGERATOR=0] (BTU/lb) 0 100 0 0 0 0
Specific Heat Above Freezing (BTU/lb/F) 0.90 0.76 0.90 0.84 0.90 0.93
Specific Heat Below Freezing [NOTE IF REFRIGERATOR=0] (BTU/lb/F) 0 0.41 0 0 0 0
Heat of Respiration [NOTE IF FREEZER=0] (BTU/LB/24hrs) 2 0.00 2 0 2 0
Product Load Per Day (lbs/day) 7,000 4,500 7,000 7,000 7,000 7,000
Entering Product Temp (F) 35 35 35 35 100 35
Product Freezing Temp (F) 30 29 30 29 30 31
Product Heat Load (BTU/24hrs) 45,500 543,263 45,500 35,280 455,000 26,040
Motor Horsepower (hp) 0.5 0.5 0.5 0.5 0.5 0.5
Lighting Load (Watt) 221.0 1,035.6 247.5 250.1 250.1 267.3
Equipment Heat Load (BTU/24hrs) 55,624 122,418 57,795 58,006 58,006 59,419
Design Factor of Safety 10% 10% 10% 10% 10% 10%
Hours of Operation 18 18 18 18 18 18
Total Cooling Load Requirement (BTU/hr) 11,405 64,130 11,818 11,255 36,904 11,098
Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane Foamed in Place Urethane
10/25/2022
UP
CON
C. S
TEP
S
NO.
PNE
UMA
TIC
MES
SEN
GER
STA
IR
NO.
STA
IR
SYS
TEM
EQ
UIPM
ENT
RM
SILV
ER
MAC
HINE
RM
REC
OVE
RY
RM
10111213141516171819
9.510.2 19.6
A
B
A2
A7
B3
PHASE 1 DEMOLITION
PHASE 2 DEMOLITION
GENERAL MECHANICAL DEMOLITON NOTES
A. CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND CONDITIONS PRIOR TO BEGINNING WORK.
B. ALL AREAS OF THE BUILDING AFFECTED BY MECHANICAL DEMOLITION WORK SHALL BE PATCHED AND REPAIRED TO MATCH ADJACENT FINAL FINISHES AND REQUIRED FIRE RATING. THE REPAIR WORK SHALL BE DONE TO THE
OWNER'S SATISFACTION.
C. DEMOLITION WORK SHALL INCLUDE REMOVAL OF EXISTING BUILDING CONSTRUCTION TO EXTENT REQUIRED TO
PERFORM NEW CONSTRUCTION ACTIVITIES INDICATED.
D. REMOVE ALL EXISTING MECHANICAL SYSTEM COMPONENTS, MATERIALS, APPARATUS, AND APPLIANCES WITHIN THE DESIGNATED PROJECT AREA, UNLESS OTHERWISE NOTED. COORDINATE WITH ARCHITECTURAL, MECHANICAL, ELECTRICAL, AND FIRE PROTECTION CONTRACT DOCUMENTS FOR ADDITIONAL SCOPE OF WORK FOR SYSTEMS TO BE REMOVED OR RETAINED TO EXTENT REQUIRED TO PERFORM NEW CONSTRUCTION ACTIVITIES INDICATED.
E. DEMOLITION PROCEDURES SHALL PROVIDE FOR SAFE CONDUCT OF THE WORK, PROTECTION OF PERSONNEL, CAREFUL REMOVAL AND OTHER DISPOSITION OF MATERIALS SPECIFIED TO BE SALVAGED. PROTECTION OF PROPERTY TO REMAIN UNDISTURBED, COORDINATION WITH OTHER WORK IN PROGRESS, AND TIMELY
DISCONNECTION OF UTILITY SERVICES.
F. EXISTING WORK SHALL BE CUT, DRILLED, ALTERED, REMOVED, OR TEMPORARILY REMOVED AND REPLACED FOR PERFORMANCE OF WORK UNDER THE CONTRACT. WORK REPLACED SHALL MATCH SIMILAR EXISTING WORK.
STRUCTURAL MEMBERS OF CONCRETE OR STRUCTURAL STEEL SHALL NOT BE CUT OR ALTERED, EXCEPT AS SHOWN, WITHOUT AUTHORIZATION OF THE ENGINEER. WORK REMAINING IN PLACE DAMAGED OR DEFACED DURING THIS CONTRACT SHALL BE RESTORED TO THE CONDITION AT TIME OF AWARD OF CONTRACT. CUT, ALTER, REMOVE, OR TEMPORARILY REMOVE AND REPLACE EXISTING WORK FOR INSTALLATION OF ELECTRICAL
WORK.
G. UNLESS SPECIFIED OTHERWISE, ALL PIPING, WIRING, CONDUIT, AND OTHER DEVICES ASSOCIATED WITH THE EQUIPMENT NOT RE-USED IN THE NEW WORK AREA SHALL BE COMPLETELY DEMOLISHED AND REMOVED FROM THE OWNER'S PROPERTY. THIS INCLUDES ALL CONCRETE PADS, PIPE, VALVES, FITTINGS, INSULATION, AND ALL HANGERS, INCLUDING THE TOP CONNECTION AND ANY FASTENINGS TO BUILDING STRUCTURAL SYSTEMS. ALL OPENINGS SHALL BE SEALED AFTER REMOVAL OF EQUIPMENT, PIPES, DUCTS, AND OTHER PENETRATIONS IN
ROOF, WALLS, FLOORS, IN AN APPROVED MANNER. STRUCTURAL
H. REMOVAL AND DISPOSAL OF ALL EXISTING REFRIGERANT SHALL BE COMPLETED IN ACCORDANCE WITH SECTION 608 OF THE CLEAN AIR ACT (CAA), AND THE ENVIRONMENTAL PROTECTION AGENCY (EPA) REGULATIONS LISTED
IN 40 CFR PART 82, SUBPARTS A AND F.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CD BID DOCUMENTSCapital Assets
U.S. Department
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
MEP Consultant:
REPLACE MAIN KITCHEN FREEZERS
130 W KINGSBRIDGE RD, BRONX, NY 10468
526-21-111
26 OCTOBER 2022 JWE MPL
Approved:
Project Director
Assoc Project Director
Section/ Engineering
Service Approved:
Approved:
Chief Engineer
Safety Manager
Approved:
Approved:
NAL
PCC/Service Director
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
OWEGO, NY 13827
T:888.696.1198 of Veterans Affairs
CONCEPT / PRELIMINARIES SUBMITTAL 18 MAR 22
35% SCHEMATIC DESIGN SUBMITTAL 2 MAY 22
65% DESIGN DEVELOPMENT SUBMITTAL 8 JUL 22
95% CONSTRUCTION DOCUMENTS SUBMITTAL 22 AUG 22
100% CONSTRUCTION DOCUMENTS SUBMITTAL 26 SEP 22
100% CD BID DOCUMENTS SUBMITTAL 26 OCT 22
G sh or tc ut
-ta rg et s-by -id
\1 Am
4f gx
Kh 1N aH Sg
M M
-W y-
Q cI
T2 U
9e tIJ z\ W at so n En gi ne er in g\ 1-
W at so n
En gi ne er in g, P C
\2
1\ Th in kf or m
\T H
-2
R ep la ce
M ai n Ki tc he n Fr ee ze rs B ro nx
V
AM
C \W at so n D ra w in gs
\R ev it\ W at so n R ev it
Pr oj ec t.r vt
/2 5/
:0
0:
P M
MD100
SUB-BASEMENT MECHANICAL
DEMOLITION PLAN
1/8" = 1'-0"1
SUB-BASEMENT MECHANICAL
DEMOLITION PLAN
KEYED DEMOLITION NOTES
EXISTING DUCT MOUNTED EXHAUST FAN TO BE REMOVED.
EXISTING EXHAUST DUCT TO BE REMOVED IN ITS ENTIRETY.
EXISTING COOLER CONDENSING UNIT TO BE REMOVED.
EXISTING FREEZER COMPRESSOR TO BE REMOVED.
EXISTING REFRIGERANT PIPING TO BE REMOVED. REFER TO SHEET MD101 FOR CONTINUATION ON
THE GROUND LEVEL.
EXISTING CONDENSATE DRAIN PIPING TO BE REMOVED. REFER TO SHEET MD101 FOR OCNTINUATION
ON THE GROUND LEVEL.
EXISTING EQUIPMENT PAD TO BE DEMOLISHED. EXISTING FLOOR SHALL BE LEVELED AND CLEANED
TO MATCH ADJACENT FLOOR FINISH.
Revisions: Date: 10/25/2022
POT WASHING
F.E.C.
FROZEN FOODS
GE-01E
PRE-FAB VEG. FRIG.
GE-05
PRE-FAB MEAT FRIG.
GE-06
FOOD BANK
GE-07
DAIRY REFRIGERATION
GE-09
INGREDIENT ROOM
GE-08
MEAT & VEGETABLE
GE-01C
NUTRITION STORAGE
GE-10A
SUBSISTENCE STORAGE
GE-10
NONFOOD STORAGE
GE-08A
GE-04
OFFICE PROGRAM DEVELOPMENT OFICE
DELIVERY
STERILE STORAGE
DUMB WAITER
GE-11
CORRIDOR
CG-25
FOOD PROCESSING
GD-40B
HOUSEKEEPING
3A
SOILED DISHES
GE-01
CLEAN DISHES
GE-02
TRAY ASSEMBLY AREA
GE-01
DIETETIC OFFICE
DIET COMMUNICATION
GE-01
REFRIGERATOR
CORRIDOR
CG-26
TELEPHONE
EQUIPMENT
GE-13
STAIR NO. 7
ELECTRICAL
CLOSET
G-E
TRANSFORMER
CLOSET
GD-40B
MANUAL CART WASH
GD-01
UP
UP
POT WASHING
F.E.C.
FROZEN FOODS
GE-01E
PRE-FAB VEG. FRIG.
GE-05
PRE-FAB MEAT FRIG.
GE-06
FOOD BANK
GE-07
DAIRY REFRIGERATION
GE-09
INGREDIENT ROOM
GE-08
MEAT & VEGETABLE
GE-01C
NUTRITION STORAGE
GE-10A
SUBSISTENCE STORAGE
GE-10
NONFOOD STORAGE
GE-08A
GE-04
OFFICE PROGRAM DEVELOPMENT OFICE
DELIVERY
STERILE STORAGE
DUMB WAITER
GE-11
CORRIDOR
CG-25
FOOD PROCESSING
GD-40B
HOUSEKEEPING
3A
SOILED DISHES
GE-01
CLEAN DISHES
GE-02
TRAY ASSEMBLY AREA
GE-01
DIETETIC OFFICE
DIET COMMUNICATION
GE-01
REFRIGERATOR
CORRIDOR
CG-26
TELEPHONE
EQUIPMENT
GE-13
STAIR NO. 7
ELECTRICAL
CLOSET
G-E
TRANSFORMER
CLOSET
GD-40B
MANUAL CART WASH
GD-01
UP
UP
10111213141516171819
9.510.2 19.6
A
B
A2
A7
B3 1 1 1 1
2 2
6 6 6 6
PHASE 1 DEMOLITION
PHASE 2 DEMOLITION
GENERAL MECHANICAL DEMOLITON NOTES
A. CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND CONDITIONS PRIOR TO BEGINNING WORK.
B. ALL AREAS OF THE BUILDING AFFECTED BY MECHANICAL DEMOLITION WORK SHALL BE PATCHED AND REPAIRED TO MATCH ADJACENT FINAL FINISHES AND REQUIRED FIRE RATING. THE REPAIR WORK SHALL BE DONE TO THE
OWNER'S SATISFACTION.
C. DEMOLITION WORK SHALL INCLUDE REMOVAL OF EXISTING BUILDING CONSTRUCTION TO EXTENT REQUIRED TO
PERFORM NEW CONSTRUCTION ACTIVITIES INDICATED.
D. REMOVE ALL EXISTING MECHANICAL SYSTEM COMPONENTS, MATERIALS, APPARATUS, AND APPLIANCES WITHIN THE DESIGNATED PROJECT AREA, UNLESS OTHERWISE NOTED. COORDINATE WITH ARCHITECTURAL, MECHANICAL, ELECTRICAL, AND FIRE PROTECTION CONTRACT DOCUMENTS FOR ADDITIONAL SCOPE OF WORK FOR SYSTEMS TO BE REMOVED OR RETAINED TO EXTENT REQUIRED TO PERFORM NEW CONSTRUCTION ACTIVITIES INDICATED.
E. DEMOLITION PROCEDURES SHALL PROVIDE FOR SAFE CONDUCT OF THE WORK, PROTECTION OF PERSONNEL, CAREFUL REMOVAL AND OTHER DISPOSITION OF MATERIALS SPECIFIED TO BE SALVAGED. PROTECTION OF PROPERTY TO REMAIN UNDISTURBED, COORDINATION WITH OTHER WORK IN PROGRESS, AND TIMELY
DISCONNECTION OF UTILITY SERVICES.
F. EXISTING WORK SHALL BE CUT, DRILLED, ALTERED, REMOVED, OR TEMPORARILY REMOVED AND REPLACED FOR PERFORMANCE OF WORK UNDER THE CONTRACT. WORK REPLACED SHALL MATCH SIMILAR EXISTING WORK.
STRUCTURAL MEMBERS OF CONCRETE OR STRUCTURAL STEEL SHALL NOT BE CUT OR ALTERED, EXCEPT AS SHOWN, WITHOUT AUTHORIZATION OF THE ENGINEER. WORK REMAINING IN PLACE DAMAGED OR DEFACED DURING THIS CONTRACT SHALL BE RESTORED TO THE CONDITION AT TIME OF AWARD OF CONTRACT. CUT, ALTER, REMOVE, OR TEMPORARILY REMOVE AND REPLACE EXISTING WORK FOR INSTALLATION OF ELECTRICAL
WORK.
G. UNLESS SPECIFIED OTHERWISE, ALL PIPING, WIRING, CONDUIT, AND OTHER DEVICES ASSOCIATED WITH THE EQUIPMENT NOT RE-USED IN THE NEW WORK AREA SHALL BE COMPLETELY DEMOLISHED AND REMOVED FROM THE OWNER'S PROPERTY. THIS INCLUDES ALL CONCRETE PADS, PIPE, VALVES, FITTINGS, INSULATION, AND ALL HANGERS, INCLUDING THE TOP CONNECTION AND ANY FASTENINGS TO BUILDING STRUCTURAL SYSTEMS. ALL OPENINGS SHALL BE SEALED AFTER REMOVAL OF EQUIPMENT, PIPES, DUCTS, AND OTHER PENETRATIONS IN
ROOF, WALLS, FLOORS, IN AN APPROVED MANNER. STRUCTURAL
H. REMOVAL AND DISPOSAL OF ALL EXISTING REFRIGERANT SHALL BE COMPLETED IN ACCORDANCE WITH SECTION 608 OF THE CLEAN AIR ACT (CAA), AND THE ENVIRONMENTAL PROTECTION AGENCY (EPA) REGULATIONS LISTED
IN 40 CFR PART 82, SUBPARTS A AND F.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CD BID DOCUMENTSCapital Assets
U.S. Department
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
MEP Consultant:
REPLACE MAIN KITCHEN FREEZERS
130 W KINGSBRIDGE RD, BRONX, NY 10468
526-21-111
26 OCTOBER 2022 JWE MPL
Approved:
Project Director
Assoc Project Director
Section/ Engineering
Service Approved:
Approved:
Chief Engineer
Safety Manager
Approved:
Approved:
NAL
PCC/Service Director
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
OWEGO, NY 13827
T:888.696.1198 of Veterans Affairs
CONCEPT / PRELIMINARIES SUBMITTAL 18 MAR 22
35% SCHEMATIC DESIGN SUBMITTAL 2 MAY 22
65% DESIGN DEVELOPMENT SUBMITTAL 8 JUL 22
95% CONSTRUCTION DOCUMENTS SUBMITTAL 22 AUG 22
100% CONSTRUCTION DOCUMENTS SUBMITTAL 26 SEP 22
100% CD BID DOCUMENTS SUBMITTAL 26 OCT 22
G sh or tc ut
-ta rg et s-by -id
\1 Am
4f gx
Kh 1N aH Sg
M M
-W y-
Q cI
T2 U
9e tIJ z\ W at so n En gi ne er in g\ 1-
W at so n
En gi ne er in g, P C
\2
1\ Th in kf or m
\T H
-2
R ep la ce
M ai n Ki tc he n Fr ee ze rs B ro nx
V
AM
C \W at so n D ra w in gs
\R ev it\ W at so n R ev it
Pr oj ec t.r vt
/2 5/
:0
0:
P M
MD101
GROUND LEVEL MECHANICAL
DEMOLITION PLAN
1/8" = 1'-0"1
GROUND LEVEL MECHANICAL
DEMOLITION PLAN
KEYED DEMOLITION NOTES
EXISTING COOLER EVAPORATOR TO BE REMOVED.
EXISTING FREEZER EVAPORATOR TO BE REMOVED.
EXISTING CONDENSATE DRAIN PIPING TO BE REMOVED.
EXISTING CONDENSATE DRAIN PIPING DOWN TO SUB-BASEMENT LEVEL TO BE REMOVED. REFER TO
SHEET MD100 FOR CONTINUATION.
EXISTING FLOOR DRAIN TO BE REMOVED FOR REPLACEMENT.
EXISTING REFRIGERANT PIPING UP TO GROUND FLOOR INTERSTITIAL LEVEL TO BE REMOVED. REFER
TO SHEET MD102 FOR CONTINUATION.
EXISTING REFRIGERANT PIPING DOWN TO SUB-BASEMENT FLOOR TO BE REMOVED. REFER TO SHEET
MD100 FOR CONTINUATION.
EXISTING REFRIGERANT PIPING RISER TO BE REMOVED. REFER TO SHEET MD100 FOR CONTINUATION
ON THE SUB-BASEMENT LEVEL, AND SHEET MD102 FOR CONTINUATION ON THE GROUND FLOOR
INTERSTITIAL LEVEL.
EXISTING FLOOR DRAIN TO REMAIN.
NO.
STA
IR
NO.
STA
IR
10111213141516171819
9.510.2 19.6
A
B
A2
A7
B3
1 1
1 11
PHASE 2 DEMOLITION
GENERAL MECHANICAL DEMOLITON NOTES
A. CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND CONDITIONS PRIOR TO BEGINNING WORK.
B. ALL AREAS OF THE BUILDING AFFECTED BY MECHANICAL DEMOLITION WORK SHALL BE PATCHED AND REPAIRED TO MATCH ADJACENT FINAL FINISHES AND REQUIRED FIRE RATING. THE REPAIR WORK SHALL BE DONE TO THE
OWNER'S SATISFACTION.
C. DEMOLITION WORK SHALL INCLUDE REMOVAL OF EXISTING BUILDING CONSTRUCTION TO EXTENT REQUIRED TO
PERFORM NEW CONSTRUCTION ACTIVITIES INDICATED.
D. REMOVE ALL EXISTING MECHANICAL SYSTEM COMPONENTS, MATERIALS, APPARATUS, AND APPLIANCES WITHIN THE DESIGNATED PROJECT AREA, UNLESS OTHERWISE NOTED. COORDINATE WITH ARCHITECTURAL, MECHANICAL, ELECTRICAL, AND FIRE PROTECTION CONTRACT DOCUMENTS FOR ADDITIONAL SCOPE OF WORK FOR SYSTEMS TO BE REMOVED OR RETAINED TO EXTENT REQUIRED TO PERFORM NEW CONSTRUCTION ACTIVITIES INDICATED.
E. DEMOLITION PROCEDURES SHALL PROVIDE FOR SAFE CONDUCT OF THE WORK, PROTECTION OF PERSONNEL, CAREFUL REMOVAL AND OTHER DISPOSITION OF MATERIALS SPECIFIED TO BE SALVAGED. PROTECTION OF PROPERTY TO REMAIN UNDISTURBED, COORDINATION WITH OTHER WORK IN PROGRESS, AND TIMELY
DISCONNECTION OF UTILITY SERVICES.
F. EXISTING WORK SHALL BE CUT, DRILLED, ALTERED, REMOVED, OR TEMPORARILY REMOVED AND REPLACED FOR PERFORMANCE OF WORK UNDER THE CONTRACT. WORK REPLACED SHALL MATCH SIMILAR EXISTING WORK.
STRUCTURAL MEMBERS OF CONCRETE OR STRUCTURAL STEEL SHALL NOT BE CUT OR ALTERED, EXCEPT AS SHOWN, WITHOUT AUTHORIZATION OF THE ENGINEER. WORK REMAINING IN PLACE DAMAGED OR DEFACED DURING THIS CONTRACT SHALL BE RESTORED TO THE CONDITION AT TIME OF AWARD OF CONTRACT. CUT, ALTER, REMOVE, OR TEMPORARILY REMOVE AND REPLACE EXISTING WORK FOR INSTALLATION OF ELECTRICAL
WORK.
G. UNLESS SPECIFIED OTHERWISE, ALL PIPING, WIRING, CONDUIT, AND OTHER DEVICES ASSOCIATED WITH THE EQUIPMENT NOT RE-USED IN THE NEW WORK AREA SHALL BE COMPLETELY DEMOLISHED AND REMOVED FROM THE OWNER'S PROPERTY. THIS INCLUDES ALL CONCRETE PADS, PIPE, VALVES, FITTINGS, INSULATION, AND ALL HANGERS, INCLUDING THE TOP CONNECTION AND ANY FASTENINGS TO BUILDING STRUCTURAL SYSTEMS. ALL OPENINGS SHALL BE SEALED AFTER REMOVAL OF EQUIPMENT, PIPES, DUCTS, AND OTHER PENETRATIONS IN
ROOF, WALLS, FLOORS, IN AN APPROVED MANNER. STRUCTURAL
H. REMOVAL AND DISPOSAL OF ALL EXISTING REFRIGERANT SHALL BE COMPLETED IN ACCORDANCE WITH SECTION 608 OF THE CLEAN AIR ACT (CAA), AND THE ENVIRONMENTAL PROTECTION AGENCY (EPA) REGULATIONS LISTED
IN 40 CFR PART 82, SUBPARTS A AND F.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CD BID DOCUMENTSCapital Assets
U.S. Department
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
MEP Consultant:
REPLACE MAIN KITCHEN FREEZERS
130 W KINGSBRIDGE RD, BRONX, NY 10468
526-21-111
26 OCTOBER 2022 JWE MPL
Approved:
Project Director
Assoc Project Director
Section/ Engineering
Service Approved:
Approved:
Chief Engineer
Safety Manager
Approved:
Approved:
NAL
PCC/Service Director
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
OWEGO, NY 13827
T:888.696.1198 of Veterans Affairs
CONCEPT / PRELIMINARIES SUBMITTAL 18 MAR 22
35% SCHEMATIC DESIGN SUBMITTAL 2 MAY 22
65% DESIGN DEVELOPMENT SUBMITTAL 8 JUL 22
95% CONSTRUCTION DOCUMENTS SUBMITTAL 22 AUG 22
100% CONSTRUCTION DOCUMENTS SUBMITTAL 26 SEP 22
100% CD BID DOCUMENTS SUBMITTAL 26 OCT 22
G sh or tc ut
-ta rg et s-by -id
\1 Am
4f gx
Kh 1N aH Sg
M M
-W y-
Q cI
T2 U
9e tIJ z\ W at so n En gi ne er in g\ 1-
W at so n
En gi ne er in g, P C
\2
1\ Th in kf or m
\T H
-2
R ep la ce
M ai n Ki tc he n Fr ee ze rs B ro nx
V
AM
C \W at so n D ra w in gs
\R ev it\ W at so n R ev it
Pr oj ec t.r vt
/2 5/
:0
0:
P M
MD102
GROUND LEVEL INTERSTITIAL
MECHANCIAL DEMOLITION PLAN
1/8" = 1'-0"1
GROUND LEVEL INTERSTITIAL
DEMOLITION PLAN
KEYED DEMOLITION NOTES
EXISTING REFRIGERANT PIPING DOWN TO GROUND FLOOR TO BE REMOVED. REFER TO SHEET MD101
FOR CONTINUATION.
EXISTING REFRIGERANT PIPING RISER DOWN TO SUB-BASEMENT LEVEL TO BE REMOVED. REFER TO
SHEET MD100 AND MD101 FOR CONTINUATION ON THE SUB-BASEMENT AND GROUND FLOOR
LEVELS, RESPECTIVELY.
CON
C. S
TEP
S
NO.
PNE
UMA
TIC
MES
SEN
GER
STA
IR
NO.
STA
IR
SYS
TEM
EQ
UIPM
ENT
RM
SILV
ER
MAC
HINE
RM
REC
OVE
RY
RM
101112131415
9.5
10.2
19.6
A
B
A2
A7
B3
CU-GE-01a
CU-GE-05
CU-GE-06
CU-GE-07
CU-GE-09
CU-GE-01E.1
CU-GE-01E.3 CU-GE-01E.2
1/2"ø RL 1 1/8"ø RS
1/2"ø RL 1 3/8"ø RS
1/2"ø RL 1 1/8"ø RS
1/2"ø RL 1 1/8"ø RS
1 3/8"ø RS 1/2"ø RL
1 3/8"ø RS 1/2"ø RL
1/2"ø RL 1 3/8"ø RS
7/8"ø RS 3/8"ø RL
3/4"ø D
CU-GE-01E.4
1/2"ø RL 1 3/8"ø RS
PHASE 1 NEW WORK
PHASE 2 NEW WORK
M-100
GENERAL MECHANICAL NEW WORK NOTES
A. ALL MECHANICAL WORK SHALL BE DONE IN ACCORDANCE WITH ALL LOCAL AND STATE REGULATIONS FOR THE
STATE OF NEW YORK.
B. CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND CONDITIONS PRIOR TO BEGINNING WORK.
C. CONTRACTOR SHALL COORDINATE EXACT LOCATION OF DUCTWORK AND DIFFUSERS WITH LIGHTS, EQUIPMENT, AND CEILING GRID.
D. DRAWINGS ARE DIAGRAMMATIC AND GENERALLY INDICATIVE OF THE WORK. ALL SYSTEMS SHALL FOLLOW ARRANGEMENT AS MUCH AS POSSIBLE, HOWEVER, ACTUAL FIELD CONDITIONS SHALL DICTATE. PROVIDE NECESSARY MODIFICATIONS TO MEET FIELD CONDITIONS AND AVOID CONFLICT WITH OTHER IF RESOLUTION CANNOT BE REACHED WITHOUT COMPROMISING THE DESIGN, THESE CONFLICTS SHALL BE PRESENTED TO THE ENGINEER FOR RESOLUTION. IN CONFLICT AREAS, COMPLETE ONLY WORK NOT AFFECTED BY THE CONFLICT
PRIOR TO RESOLUTION.
E. CONNECTIONS TO EQUIPMENT SHALL CONFORM TO MANUFACTURER'S SPECIFICATIONS.
F. ALL HANGER SYSTEMS FOR PIPING AND EQUIPMENT SHALL BE SECURED TO BUILDING STRUCTURAL SYSTEM.
G. PROVIDE ACCESS PANELS IN CEILINGS WHERE REQUIRED FOR OPERATION AND MAINTENANCE OF ALL FANS, VALVES, DAMPERS, AIR-DEFLECTING DEVICES, AND OTHER MECHANICAL EQUIPMENT.
H. ALL PIPING IN FINISHED ROOMS OR SPACES SHALL BE CONCEALED IN A FURRED CHASE OR ABOVE HARD
CEILING, OR ACOUSTICAL CEILING.
I. FOR WATER PIPING CONNECTIONS TO EQUIPMENT, SEE STANDARD EQUIPMENT DETAILS.
J. WATER PIPE CONNECTIONS TO AIR HEATING AND COOLING COILS SHALL BE MADE TO PROVIDE COUNTER FLOW
BETWEEN WATER AND AIR.
K. ALL PRESSURES LISTED ARE GAGE PRESSURE UNLESS OTHERWISE NOTED.
L. ALL CONTROLS AND MONITORING SHALL BE TIED INTO THE EXISTING BUILDING MANAGEMENT SYSTEM USING BACnet IP PROTOCOL IN ACCORDANCE WITH ASHRAE, ANSI, AND ISO16484-5 STANDARDS. CONTROLS CONTRACTOR SHALL PROVIDE CAT5 WIRING TO AN OPEN PORT IN THE NEAREST TELECOMMUNICATION CLOSET
FOR INTEGRATION.
M. ALL EXTERIOR CONDENSING UNITS SHALL BE INSTALLED ON GALVANIZED STEEL DUNNAGE MOUNTED TO EXTERIOR EQUIPMENT PAD. DUNNAGE SHALL BE INSTALLED TO RAISE THE CONDENSING UNITS TO A MINIMUM HEIGHT OF 24" ABOVE THE EQUIPMENT PAD LEVEL. REFER TO SPECIFICATION SECTION 05 12 00 -
STRUCTURAL STEEL FRAMING FOR ADDITIONAL INFORMATION.
7' - 3 1/4"
3'
8"
NOTES:
1. CONTRACTOR SHALL REMOVE AND REPLACE THE EXISTING
AREAWAY GRATE FOLLOWING THE INSTALLATION OF NEW
REFRIGERANT PIPING.
2. DIMENSIONS PROVIDED ARE APPROXIMATE, VERIFY FINAL
DIMENSIONS IN FIELD FOLLOWING INSTALLATION OF
REFRIGERANT PIPING.
3. REFER TO SPECIFICATION SECTION 05 50 00 - METAL
FABRICATIONS FOR MATERIAL AND INSTALLATION
REQUIREMENTS FOR METAL GRATING AND PERIMETER
SUPPORTS.
PROVIDE 2x2x1/8 ANGLE
IRON AT PERIMETER OF
NEW GRATE FOR SUPPORT
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CD BID DOCUMENTSCapital Assets
U.S. Department
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
MEP Consultant:
REPLACE MAIN KITCHEN FREEZERS
130 W KINGSBRIDGE RD, BRONX, NY 10468
526-21-111
26 OCTOBER 2022 JWE MPL
Approved:
Project Director
Assoc Project Director
Section/ Engineering
Service Approved:
Approved:
Chief Engineer
Safety Manager
Approved:
Approved:
NAL
PCC/Service Director
THINKFORM DESIGN ARCHITECT LLC
38 EAST BROAD STREET
HOPEWELL, NJ 08525
T:855.821.0274 F:609.644.4397
WATSON ENGINEERING
1112 STATE ROUTE 434
OWEGO, NY 13827
T:888.696.1198 of Veterans Affairs
CONCEPT / PRELIMINARIES SUBMITTAL 18 MAR 22
35% SCHEMATIC DESIGN SUBMITTAL 2 MAY 22
65% DESIGN DEVELOPMENT SUBMITTAL 8 JUL 22
95% CONSTRUCTION DOCUMENTS SUBMITTAL 22 AUG 22
100% CONSTRUCTION DOCUMENTS SUBMITTAL 26 SEP 22
100% CD BID DOCUMENTS SUBMITTAL 26 OCT 22
G sh or tc ut
-ta rg et s-by -id
\1 Am
4f gx
Kh 1N aH Sg
M M
-W y-
Q cI
T2 U
9e tIJ z\ W at so n En gi ne er in g\ 1-
W at so n
En gi ne er in g, P C
\2
1\ Th in kf or m
\T H
-2
R ep la ce
M ai n Ki tc he n Fr ee ze rs B ro nx
V
AM
C \W at so n D ra w in gs
\R ev it\ W at so n R ev it
Pr oj ec t.r vt
/2 5/
:5
9:
P M
M-100
SUB-BASEMENT MECHANICAL
NEW WORK PLAN
1/8" = 1'-0"1
SUB-BASEMENT MECHANICAL NEW
WORK PLAN
KEYED NEW WORK NOTES
NEW REFRIGERANT LIQUID AND SUCTION LINES UP TO GROUND FLOOR INTERSTITIAL SPACE, TO BE INSTALLED WITHIN EXISTING PIPE CHASE. REFER TO SHEETS M-101 AND M-102 FOR CONTINUATION.
NEW REFRIGERANT LIQUID AND SUCTION LINES UP TO UC-GE-01a ON GROUND FLOOR. REFER TO
SHEET M-101 FOR CONTINUATION.
NEW CONDENSATE DRAIN UP TO GROUND FLOOR. REFER TO SHEET M-101 FOR CONTINUATION.
PROVIDE THRU WALL PENETRATION FOR REFRIGERANT PIPING.
1/2" = 1'-0"2 EXTERIOR AREAWAY GRATE DETAIL
POT WASHING
F.E.C.
FROZEN FOODS
GE-01E
PRE-FAB VEG. FRIG.
GE-05
PRE-FAB MEAT FRIG.
GE-06
FOOD BANK
GE-07
DAIRY REFRIGERATION
GE-09
INGREDIENT ROOM
GE-08
MEAT & VEGETABLE
GE-01C
NUTRITION STORAGE
GE-10A
SUBSISTENCE STORAGE
GE-10
NONFOOD STORAGE
GE-08A
GE-04
OFFICE PROGRAM DEVELOPMENT OFICE
DELIVERY
STERILE STORAGE
DUMB WAITER
GE-11
CORRIDOR
CG-25
FOOD PROCESSING
GD-40B
HOUSEKEEPING
3A
SOILED DISHES
GE-01
CLEAN DISHES
GE-02
TRAY ASSEMBLY AREA
GE-01
DIETETIC OFFICE
DIET COMMUNICATION
GE-01
REFRIGERATOR
CORRIDOR
CG-26
TELEPHONE
EQUIPMENT
GE-13
STAIR NO. 7
ELECTRICAL
CLOSET
G-E
TRANSFORMER
CLOSET
GD-40B
MANUAL CART WASH
GD-01
UP
UP
POT WASHING
F.E.C.
FROZEN FOODS
GE-01E
PRE-FAB VEG. FRIG.
GE-05
PRE-FAB MEAT FRIG.
GE-06
FOOD BANK
GE-07
DAIRY REFRIGERATION
GE-09
INGREDIENT ROOM
GE-08
MEAT & VEGETABLE
GE-01C
NUTRITION STORAGE
GE-10A
SUBSISTENCE STORAGE
GE-10
NONFOOD STORAGE
GE-08A
GE-04
OFFICE PROGRAM DEVELOPMENT OFICE
DELIVERY
STERILE STORAGE
DUMB WAITER
GE-11
CORRIDOR
CG-25
FOOD PROCESSING
GD-40B
HOUSEKEEPING
3A
SOILED DISHES
GE-01
CLEAN DISHES
GE-02
TRAY ASSEMBLY AREA
GE-01
DIETETIC OFFICE
DIET COMMUNICATION
GE-01
REFRIGERATOR
CORRIDOR
CG-26
TELEPHONE
EQUIPMENT
GE-13
STAIR NO. 7
ELECTRICAL
CLOSET
G-E
TRANSFORMER
CLOSET
GD-40B
MANUAL CART WASH
GD-01
UP
UP
10111213141516171819
9.510.2 19.6
A
B
A2
A7
B3
UC-GE-01E.1 UC-GE-01E.2 UC-GE-01E.3
UC-GE-01a
D
D
D1
1 1
6 6
M-101
UC-GE-01E.4
UC-GE-05 UC-GE-06
D
UC-GE-07
UC-GE-09
1 1
D
PHASE 1 NEW WORK PHASE 2 NEW WORK
GENERAL MECHANICAL NEW WORK NOTES
A. ALL MECHANICAL WORK SHALL BE DONE IN ACCORDANCE WITH ALL LOCAL AND STATE REGULATIONS FOR THE
STATE OF NEW YORK.
B. CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND CONDITIONS PRIOR TO BEGINNING WORK.
C. CONTRACTOR SHALL COORDINATE EXACT LOCATION OF DUCTWORK AND DIFFUSERS WITH LIGHTS, EQUIPMENT, AND CEILING GRID.
D. DRAWINGS ARE DIAGRAMMATIC AND GENERALLY INDICATIVE OF THE WORK. ALL SYSTEMS SHALL FOLLOW ARRANGEMENT AS MUCH AS POSSIBLE, HOWEVER, ACTUAL FIELD CONDITIONS SHALL DICTATE. PROVIDE NECESSARY MODIFICATIONS TO MEET FIELD CONDITIONS AND AVOID CONFLICT WITH OTHER IF RESOLUTION CANNOT BE REACHED WITHOUT COMPROMISING THE DESIGN, THESE CONFLICTS SHALL BE PRESENTED TO THE ENGINEER FOR RESOLUTION.