This document contains responses to requests for information (RFIs) related to a solicitation for replacing main kitchen freezers at a Department of Veterans Affairs medical center. The solicitation seeks bids to remove two existing walk-in freezers and furnish and install two new walk-in freezers from Bally Refrigeration. The project will be conducted in two phases, requiring temporary coolers and freezers as well as a temporary frozen trailer. Structural steel framing for exterior condensing units is a delegated design, and quarry tile will match the existing. Off-hour work will be needed, and self-leveling underlayment is required. Responses provide contact information for the existing controls contractor and preferred security vendor. The bid due date was extended to January 22, 2024 at 2:00 PM EST.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24223B0046 0001.docx | DOCX document | |
| REPLACE MAIN KITCHEN FREEZERS_IFB 36C24224B0046_SITE VISIT SIGN IN SHEET_12.20.23.pdf | ||
| Replace Main Kitchen Freezers_100 Bid Drawings.pdf | ||
| Bronx Kitchen Freezers_100Bid Specifications.pdf | ||
| P07_DBA WAGE RATES_REPLACE MAIN KITCHEN FREEZERS - Copy.docx | DOCX document | |
| FAR 52.225-2 BUY AMERICAN CERTIFICATE.docx | DOCX document | |
| 36C24223B0046_2.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) A 1/12/2024 526-21-111 36C242 Department of Veterans Affairs Network Contracting Office 2 James J. Peters VA Medical Center 130 West Kingsbridge Road Bronx NY 10468-3904 36C242 Department of Veterans Affairs James J. Peters VA Medical Center Network Contracting Office 2 130 West Kingsbridge Road Bronx NY 10468-3904 To all Offerors/Bidders
36C24223B0046 12-13-2023
X X X
MONDAY - 01/22/2024 @2PM EST
X This Amendment A0002 is for IFB Solicitation 36C24223B0046 to Replace Main Kitchen Freezers at the James J. Peters DVA Medical Center, Bronx, NY 10468.
The sole purpose of this amendment is to provide the following information to bidders:
1. Provide a compiled list of RFI's and VA/AE responses. (See continuation pages of this SF30)
2. R evised Bid due date: The bid due date is extended to Monday 1/22/2024@2PM EST.
3. Confirm that ALL amendments must be acknowledged with submitted bids at time of bid opening.
4. Confirm that emailed bids will NOT be accepted. The bid opening is "In Person" and will be held at the James J.
Peters Bronx VA Medical Center located at 130 W. Kingsbridge Road, Bronx, NY 10468, Engineering Service Room GC-106
Patricia Cordero
CONTRACTING OFFICER
ThinkForm Design Architect LLC 38 EAST BROAD STREET, SUITE 3
HOPEWELL, NJ 08525
P: 855.821.0274 F: 609.644.4397 ThinkFormArchitects.com
January 9, 2024 Rev Re: Project # 526-21-111- VAMC Bronx, Main Kitchen Freezer Replacement
Below is a compiled list of all RFI’s submitted for this solicitation with VA/AE responses to RFI’s 1-19. Contractors must bid accordingly.
1) Please confirm if the new walk-in coolers and freezers are to be furnished and installed by the contractor.
VA/AE Response: Yes, new walk-in coolers and freezers are to be furnished and installed by the contractor.
2) Please confirm the basis of design for the new walk-in coolers and freezers is Bally.
VA/AE Response: Yes, Bally is the Basis of Design for the new walk-in coolers and freezers. (See Specifications Section 09 06 00, Part 2.3)
3) There is a spec section for Structural Steel Framing, but no drawings. Please provide structural drawings identifying all the Division 5 work.
VA/AE Response: The structural steel framing for the exterior condensing units is listed as a delegated design submittal per spec section 05 12 00 (see paragraphs 1.4.G and 2.1). See general mechanical note M on drawing sheet M-101 for additional information and guidance.
Contractor shall retain the services of a qualified professional engineer for the design and detailing of the steel dunnage.
4) Drawing A101 detail 3 states quarry tile to match existing. Please specify the manufacturer and type of existing quarry tile so that contractor can procure the correct material price. Also provide specs for the quarry tile work.
VA/AE Response: Quarry tile basis of design is American Olean, Quarry Regular, Canyon Red Square (0Q01), tile dimensions, and finish to match existing.
5) As this project work is in the kitchen area, please specify the work hours.
VA/AE Response: Off-hour work will be required for ALL demolition activities for each phase, for all construction barrier and anti-room work which will be required for all phases, and for any work that will need to be done outside of the construction site, and in the Kitchen Area for Infection Control measures (eg: work above ceiling tiles in kitchen area, relocating electrical conduit, or any work that is considered dust producing) Also, refer to Specifications, Section 01 00 00, Part 1.6, and note L at dwg. AD100.
6) Finish schedule has base bid and deduct alternate. Is the work in deduct alternate to be disregarded? As there is no bid form with separate bid alternates. If agency wants deduct alternate then please provide a detailed bid form with various alternates listed.
VA/AE Response: The VA has chosen to move forward with a Base Bid with NO alternates for this project. Contractors must bid accordingly and pay attention to Base Bid work and all requirements. Please disregard Bid Alternates 1-4 listed in General Requirements 01 00 00 Section 1.3
7) There is a spec section 07 13 00 for sheet waterproofing. Please identify this work on construction drawings.
VA/AE Response: Sheet waterproofing with be installed at concrete pads on grade, see notes at Dwg.1/A100 – ,,…compacted sub base with 10mil plastic poly sheet …’’
8) There is a spec section 09 05 16 for Subsurface Preparation for Floor Finishes. Please advise if agency wants contractor to consider this self-leveling underlayment work at the new flooring work. Contractor cannot determine on his own if its required or not.
VA/AE Response: Refer to floor assembly details 3 &4 /A101, which indicate the requirement for self-leveling substrate.
9) Drawing A100 states to provide ( 4 ) temporary rollable coolers in phase 1, but phase 2 states to provide ( 2 ) coolers and ( 2 ) freezers. So please confirm which is correct and specify the correct count of temporary rollable coolers and freezers for both phases.
VA/AE Response: Solicitation/Design Documents specify the following numbers: Phase I: 4 temporary coolers. Phase II: 6 temporary coolers (4 coolers installed in Phase I +2 additional coolers installed in Phase II) + 2 temporary freezers.
The VA has confirmed this information as well.
10) Please provide a detailed scaled elevation drawing for the signage work.
VA/AE Response: See attached existing signage pictures below. New signage at new door should resemble old signage as a replacement in kind.
11) Drawing A100 states to provide Temporary Frozen Trailer for phase 2. Please provide all the details like manufacturer, model, size, capacity, etc and how long it has to be rented by contractor. Also please confirm agency will provide free electric power to run this trailer.
VA/AE Response: Refer to keyed notes #8 and #9 on drawing E-101 for basis of design trailer and the requirements for the electrical contractor. The contractor will be required to provide any temporary source of power for the temporary trailers as per note below, and/or as directed by the project COR. Power for the temporary freezer trailers as well as rental period will be required for the entire duration of the project and is the responsibility of the contractor. Contractors must bid accordingly.
Additional VA Response to RFI 11: Solicitation drawing E-101 note below:
12) Drawing A100 states Condensers to be installed atop 24” depth steel dunnage. Please provide details of structural steel members/drawing to build the dunnage. Will these structural steel members have to be hot-dipped galvanized?
AE Response: Refer to response to RFI #3 above. Structural steel members shall be hot-dipped galvanized in accordance with specification section 05 12 00 paragraph 2.5.A.
13) Please provide the contact information of the current DDC controls contractor.
VA Response: The existing DDC contractor is ITC.
Daniel DeStefano Project Manager ITC Services 117-19 14rd College Point NY 11356 917-567-9917 718-939-8801
14) New concrete pads are to be constructed at the rear of the building; please advise that construction vehicles will be allowed to reach close to the location of new pads.
VA Response: Installation of the concrete pads are a responsibility of the bidding contractor’s means and methods for construction; there are various ways that the concrete can be transported to the site, including pump, hose, wheelbarrow, etc from the adjacent loading dock area. It is possible that a concrete truck can be parked at the closest corner of the loading dock area if space is available.
15) Does the VA have a preferred security vendor under contract at the hospital? If so, could you provide contact information as relates to the camera installation per the contract drawings?
VA Response:
Ralph Ovale Vantage Burglar Alarm Corp.
Complete Security Management 5440 Little Neck Parkway. Little Neck, NY 11362 Suite 3 Cell 516-779-0624 | Office 718-423-2555 | Fax 718-423-3709 Email: RalphOvale@VantageAlarmCorp.com
16) Due to the limited access to an access point to remove any material from the basement, is the contractor allowed to leave a hoist in place at the access hatch shown to us on the walkthrough?
VA response: Contractor must secure all access to the construction site including the sub-basement. A hoist will be allowed as long as the site is left secured when work is not being done. A secure chain link construction fence around outside work must be installed in order to ensure safety and security of work site.
17) Is the contractor permitted to install a ramp at the back side of the building to install the concrete and equipment due to elevation differences?
VA Response: See response to above RFI 14. Installation of the concrete pads are a responsibility of the bidding contractor’s means and methods for construction. Contractors will not have access from the street (Sedgwick Avenue).
18) During the sidewalk we reviewed some areas where we could exhaust the negative air exhaust duct but did not confirm if we have enough above the ceiling to install the temp ductwork to the window. Will ductwork below the ceiling be permitted if access is limited?
VA Response: Negative pressure ductwork below the ceiling is NOT allowed anywhere “inside” the kitchen area. Contractors must re-route ductwork for negative pressure as necessary.
19) RFI-5 What is the new bid date and time?
VA response: The bid date is extended and the bid opening date will now be 1/22/2024@2PM EST.
Attachments: Below photos showing existing signage provided by AE
END OF RFI RESPONSES