DRAFT

Page 1 of 2 12/15/2022

07 November 2022

PERFORMANCE WORK STATEMENT

for Repair Hoist Bldg. 1043 Project # YZEU23-2001

Location: Work is to be performed in Building 1043 at Will Rogers Air National Guard Base, Oklahoma City, Oklahoma.

Value Engineering Statement: Contractors are encouraged to draw on their special 'know-how' and experience to propose changes that cut costs while maintaining or enhancing quality, value, and functional performance. You will be required to provide samples of any material(s) you propose as a better value substitute. Otherwise, the specific materials described in this document will be required.

• Access and General Protection/Security Policy and Procedures. Contractor employees with an area of performance within Will Rogers Air National Guard Base shall comply with the following. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Badging Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

• For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations. Contractors will work with the base engineering shop and Security Forces to obtain badging for the base

• AT Level 1 Training. This standard language is for contractor employees with an area of performance within a Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I Awareness Training is available through JKO (http://jko.jten.mil) or myLearning by completing the Force Protection CBT (Computer Based Training).

Certificates maybe required for proof before badging process is concluded.

DRAFT

Page 2 of 2 12/15/2022

Task List Provide all materials and labor to replace existing 3-Ton hoist in Building 1043. Clean job-site of any work related debris. Dispose of all packing materials and replaced parts off-base.

1. Building 1043 (Room 129 East)

a. Remove and dispose of existing 3-Ton hoist.

i. Existing rail system and power supply to remain.

b. Provide and install new 3-Ton hoist.

i. New hoist shall be 3-ton hoist with motor driven trolley.

ii. New hoist shall have chain and hook assembly as to match capabilities of existing hoist.

iii. New hoist and trolley system is to be connected to existing in-place rail system and power supply.

c. New hoist system shall have an initial operating inspection and test completed.

i. Initial inspection and testing report is to be provided to COR or assigned representative prior final acceptance of work.

2. Existing Hoist Data

a. Type: Monorail

b. Make: BEEBE

c. Model: LE45030M4

d. Serial # 6840-0992H

e. Capacity: 3-Ton

3. Additional Notes:

a. The COR or assigned representative shall determine what equipment (if any) is to be returned to the Government prior to disposal.

b. Contact COR or assigned representative for recycling capability of material/equipment to be disposed of.

c. Contractor is to contact COR or assigned representative for recycling capability of material/equipment to be disposed of prior to disposal.

----------END OF PWS----------