Reference 1 - Three Year Electric Test SOW 2026.pdf

PDF 79 KB Posted

Attached to
J061--3-Year Electrical Test Cincy and Fort Thomas
Solicitation number
36C25026Q0768
Issued by

About this file

This document is a 3-Year Electrical Testing and Maintenance schedule for a multi-building facility complex spanning seven test days scheduled between October and November 2026. The contract encompasses comprehensive electrical testing and maintenance of circuit breakers, transformers, automatic transfer switches (ATS), and motor control centers (MCC) across multiple buildings numbered 1, 2, 3, 8, 13, 14, 15, and PG.

The testing schedule includes seven working days: Day 1 (October 10, 2026) focuses on FTD facility equipment including main switchboards, transformers, and emergency power systems; Day 2 (October 17, 2026) addresses Building 1 unit substations and distribution panels; Day 3 (October 24, 2026) tests Buildings 1 and 14 switchgear and distribution equipment; Day 4 (October 31, 2026) is dedicated to all emergency power systems including emergency switchboards and fire pump ATS; Day 5 (November 7, 2026) covers primary switchgear and fusible primary switches with Duke Energy service disconnection at 8 AM; Day 6 (November 14, 2026) continues emergency power testing across multiple buildings; and Day 7 (November 21, 2026) completes testing for Buildings 2, 3, 8, 13, PG, and high-voltage switch equipment. The facility equipment inventory totals 416 circuit breakers and 68 transformers, accounting for a 10% variance allowance. Testing times range from 8 AM to 8 PM depending on the day, with Duke Energy coordination required for service disconnection and restoration on specific test dates.

View the file

Other files

File Type Posted
36C25026Q0768.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3 Year Electrical Testing and Maintenance Day 1

Test Date: 10-Oct-26 Saturday Building Number

Room Number Time Period Equipment to be tested Breakers Xfmrs ATS MCC

FTD Gen Room 8am - 12pm Main Switchboard "MS" 26 FTD Gen Room 8am - 12pm TRANSFORMER 1 FTD 004C 8am - 12pm MCC MSP 2 1

FTD Boiler Room 12:30pm -

4:00pm Motor Control Center 1 1

FTD Gen Room 12:30pm -

4:00pm MEDP (Emergency Power) 3

FTD Gen Room 12:30pm -

4:00pm EDP-C, EDP-E (6 CB's), EDP-L 6

FTD Gen Room 12:30pm -

4:00pm

ATS-1, ATS-2, ATS-3 3

FTD Gen Room 12:30pm -

4:00pm Generator Main Breaker 1

FTD Gen Room 12:30pm -

4:00pm Reserve (Spare) Breakers 7

46 1 3 2

Breakers Xfmrs ATS MCC

Equipment Listed 378 61 39 15 +10% Variance 38 7 4 2

Total 416 68 43 17

TOTAL FACILITY EQIPMENT

Disconnect Electric Service by Duke Energy- 8 am

Restore Electric Service by Duke Energy- 12 pm

3 Year Electrical Testing and Maintenance Day 2

Test Date: 17-Oct-26 Saturday Building Number

Room Number Time Period Equipment to be tested Breakers Xfmrs ATS MCC

1 B013a 8am - 6pm Unit Substation US-1A (10 CB's) 10 1 1 B16A - DPB (8 CB's) 8

15 B02 - 15MDP (8 CB's) 8 1 B013a - Unit Substation US-1B (11 CB's) 11 1

1 A019 - DPP 2

1 A022A - DPE 8

1 A023 - Unit Substation US-1X, MCC-2 11 1 1

1 C008 - DS-1A, MCC-E 7 1 1

1 C008 - DS-1X 3

1 A0004 - DPF (3FT1 Transformer) (Kitchen) 5 1 1 A023 - Unit Substation US-1P (10 CB's) 10 1 1 - MCCB, MCC-D/G, MCC-C (5th Flr.) 4

1 - MCC-5, MCC-5A 3 2

1 C008 - DS-1P 3

89 6 0 8

3 Year Electrical Testing and Maintenance Day 3

Test Date: 24-Oct-26 Saturday Building Number

Room Number Time Period Equipment to be tested Breakers Xfmrs ATS MCC

1 A023 8am - 5pm US-1C (CB's & Transformer) 10 1 1 A019 - DPA (8 CB's) 8 1 A001D - DPC (8 CB's) 8 1 A10001 - MCP (Penthouse) 1 1 A023 - US-1D (CB's & Transformer) 9 1 1 A032F - DPD (8 CB's) 8 1 C008 - DS-1B (9 CB's), DP2 (1 CB + TRANS), DPF (1) 11 1 A0004 - DP-LF (7 CB's), DP-LF3 (1 CB), BF1 (1 CB), BF2 (1 CB) 10

14 204 / 205 - 14ESWB (4 CB's), 14OSPDP1 (1 CB), 14OSDP1 (8 CB's), 14TEM, 14TOS1, ATS LR, ATS EM, ATS OS1, ATS OS2

13 2 4

77 4 4 1

3 Year Electrical Testing and Maintenance ALL EMERGENCY POWER Day 4

Test Date: 31-Oct-26 Saturday Building Number

Room Number Time Period Equipment to be tested Breakers Xfmrs ATS MCC

1 B013 8am - 2pm Emergency Switchboard "ESB" 8 1 1 B013 8am-10am ATS 4 "1E4" P1 and P2 1 1 B013 10am -12pm ATS 5 "1E5" P3 and P4 1 1 B013 12pm - 2pm ATS 6 "1E6" S5 and S6 1 1 SB06 8am-11am ATS 8 "1E8" Fire Pump 1 1 B013 8am - 2pm Parallel Switch Gear Breakers 7

15 B015 11am-2pm Bldg 15 Fire Pump ATS 1 15 1 5 0

3 Year Electrical Testing and Maintenance Day 5

Test Date: 7-Nov-26 Saturday Building Number

Room Number Time Period Equipment to be tested Breakers Xfmrs ATS MCC

Disconnect Electric Service by Duke Energy- 8 am

1 B013a 8am - 4pm Primary Switchgear, Preferred and Alternate(Air Breakers and Metering)

1 B013a - US-1A & US-1B Fusable Primary Switch 4 1 A023 - Primary Switchgear, "PS1" (6 - Fusable Primary Switches) 6 1 B013a - Main Capacitor Bank

14 205 - US-14 Fusable Primary Switch US-14 Transformer 1 1 14 204 / 205 - 14 MDP (9 CB's), 14 DP1 (7 CB's) 16

35 1 0 0

3 Year Electrical Testing and Maintenance ALL EMERGENCY POWER Day 6

Test Date: 14-Nov-26 Saturday Building Number

Room Number Time Period Equipment to be tested Breakers Xfmrs ATS MCC

15 B02 8am - 8pm

15 ATS-1, 15 ATS-2, 15 ATS-3, 16 ATS FISHER HOUSE, ATS

Disconnect CB's (4), Elevator transformer, Panel WH (1 CB), Panel

15E1 (1 CB)

6 1 4

1 B013a - ATS 3 "1E3" Medical Air 6 1 1 B013a - ATS 7 "1E7" IRM 5 1 1 A023 - GDE (6 CB's + TRANS) 6 1 1 A023 - ATS-27 LSDP (3 CB's + Trans) 3 1 1 A023 - ATS-28 CDP (8 CB's) 8 1 1 A023 - ATS-29 Liebert and Disconnect CB 1 1 1 C003A - ESWB (11 CB's), ESWB-20 (3 CB's), ESWB-40 A&B (6 CB's) 20 15

1 C003A - ATS-9, ATS-10, ATS-11, ATS-12, ATS-21, ATS-26 6

1 C008 - ATS-30, ATS-1 2

1 A023 - ATS-24 1

1 A001 - EDPEQ 4 2

3RD

FLR.MECH

- EDPEQ3, 30kva Trans, MCC EEQM3 2 1 1

4th Flr.

Mech

- MCC-E/F 2 1

2 5 - EDP (2) (ATS-18, ATS-19 (ECDP1, Trans), ATS-20 (EQDP1, TRANS), ATS-15 (ECDP2, Trans), (LSDP1 Trans))

8 4 4

69 26 22 2

3 Year Electrical Testing and Maintenance Day 7

Test Date: 21-Nov-26 Saturday Building Number

Room Number Time Period Equipment to be tested Breakers Xfmrs ATS MCC

3 13 8am - 6pm Unit Substation US-3 & Dist. Panelboard 5 1 0 8 - Transformers & Gen Breaker, ATS's 2 3 0 1

13 - All normal power equipment 12 8 3 1 2 - Unit Substation US-2, DP1, DP2, MDP 21 7

PG -

MDP (5 CB's), 2-ATS's, GPEM (1 MCB), Elevator transformers (2), Gen Breaker & Transformer

7 3 2

- PPSU - High Voltage Switch for Bldg. 2/3/8/13/PG 47 22 5 2

Reference 1 - Equipment List - Day 1.pdf
Reference 1 - Equipment List - Day 2.pdf
Reference 1 - Equipment List - Day 3.pdf
Reference 1 - Equipment List - Day 4.pdf
Reference 1 - Equipment List - Day 5.pdf
Reference 1 - Equipment List - Day 6.pdf
Reference 1 - Equipment List - Day 7.pdf

File details come from the government source that posted it. Updated .