Open, Inspect, Report and Overhaul of Console, Ship Control
Solicitation number
70Z08025QAF088
Issued by

About this file

This document is an Overhaul Description for a Ship Control Console used on WMEC 210 Class vessels, issued by the US Coast Guard Surface Forces Logistics Center. The solicitation seeks a contractor to perform a comprehensive overhaul of a specific console (NSN: 2030-01-612-7381, Part Number: 60576) manufactured by Allied Systems Company, Inc. The overhaul requirements mandate restoring the console to its original design and technical specifications using genuine Original Equipment Manufacturer (OEM) parts, with all replacement parts being new and of equal or better quality.

Key details include a cost estimate not to exceed $38,422.89, with quotes due by April 10, 2025 at 10:00 am EDT. The contractor must submit a detailed preliminary inspection estimate to the Coast Guard Contracting Officer, including stock numbers, serial numbers, part numbers, new part prices, labor rates, and labor hours. The overhaul will include standard production tests and inspections, with a certification placed in the box with each unit. The console will be individually packed in a wooden box, preserved against deterioration for two years, and comes with a standard manufacturer's warranty. Quotes should be emailed to Donna.M.Scandaliato@uscg.mil, with recommended sources including Allied Systems Company in Sherwood, Oregon.

View the file

Other files

File Type Posted
52.212-3 May 2024.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OVERHAUL DESCRIPTION

FOR OFFICIAL USE ONLY

ITEM NAME CONSOLE,SHIP CONTROL

STOCK NUMBER 2030-01-612-7381

PART NUMBER 60576

USED ON 210 WMEC

Items as received by the contractor must be complete and of the proper cited part number. Discrepancies shall be reported to the Coast Guard Contracting Officer.

OVERHAUL REQUIREMENTS:

This description covers the requirements for contractor inspection, estimate, and overhaul of the following cited SHIP CONTROL CONSOLE.

NSN: 2030-01-612-7381

Item Name: Console, Ship Control Part Number: 60576

Application: WMEC 210 Class Allied D5700CT Davit Assembly. Original Equipment Manufacturer: Allied Systems Company, Inc.

The contractor shall immediately notify the Coast Guard Contracting Officer if the make and/or model delivered for overhaul does not conform to the Ship Control Console cited above.

Requirements: The contractor shall provide all labor and materials to perform overhaul services on the Control Console as follows:

PRELIMINARY INSPECTION REOUIREMENTS:

Preliminary disassembly and inspection of the Control Console shall be conducted in accordance with Original Equipment Manufacturer (OEM) recommended procedures to determine the total estimated cost for repair including material, labor, testing, preservation, packing and marking costs.

A detailed estimate shall be submitted to the Coast Guard Contracting Officer (CG KO) for review and approval prior to the start of any repair or order of material. The estimate shall include: stock numbers, serial numbers, part numbers, new parts required with prices, labor rate, labor hours required, and a total estimate for all required services. The contractor shall also provide the replacement cost of a new Control Console for comparison to the overhaul cost. The CG KO shall determine the disposition of any Control Console delivered for inspection that is found to be not suitable for repair for whatever reason.

Upon acceptance of the estimate and authorization to proceed by the CG KO, the Control Console shall be overhauled in accordance with OEM recommended procedures and as follows:

OVERHAUL REQUIREMENTS:

Each Control Console shall be overhauled to a condition, which shall restore the operating and performance characteristics to the "ORIGINAL" design and technical specifications. Overhaul shall be performed in accordance with the original equipment manufacturer (OEM) specifications and standards. All repair parts shall be genuine OEM manufactured parts. All replacement parts used in the overhaul shall be new OEM parts or parts of equal or better quality. Reclaimed or recycled parts are not acceptable and shall not be used.

OUALITY ASSURANCE:

Following completion of overhaul, the contactor shall perform standard production tests and inspections to assure maximum design performance. The Contractor shall provide certifications of successful standard production tests and inspections. One certification shall be placed in the box with each unit and a copy for each unit shall be forwarded to the Coast Guard Contracting Officer.

Example of Marking Layout:

NATIONAL STOCK NUMBER: 2030-01-612-7381

ITEM NAME: Console, Ship Control

PART NUMBER: 60576

SERIAL NUMBER: as applicable GOVERNMENT ORDER NUMBER: as applicable DATE OF REPAIR: as applicable Coast Guard SFLC Material, Condition Code ?A".

SHELF LIFE CD 0

This description covers the requirements for contractor inspection, estimate, and overhaul of the following cited SHIP CONTROL CONSOLE.

NSN: 2030-01-612-7381

Item Name: Console, Ship Control Part Number: 60576

Application: WMEC 210 Class Allied D5700CT Davit Assembly. Original Equipment Manufacturer: Allied Systems Company, Inc.

The contractor shall immediately notify the Coast Guard Contracting Officer if the make and/or model delivered for overhaul does not conform to the Ship Control Console cited above.

Requirements: The contractor shall provide all labor and materials to perform overhaul services on the Control Console as follows:

PRELIMINARY INSPECTION REOUIREMENTS:

Preliminary disassembly and inspection of the Control Console shall be conducted in accordance with Original Equipment Manufacturer (OEM) recommended procedures to determine the total estimated cost for repair including material, labor, testing, preservation, packing and marking costs.

A detailed estimate shall be submitted to the Coast Guard Contracting Officer (CG KO) for review and approval prior to the start of any repair or order of material. The estimate shall include: stock numbers, serial numbers, part numbers, new parts required with prices, labor rate, labor hours required, and a total estimate for all required services. The contractor shall also provide the replacement cost of a new Control Console for comparison to the overhaul cost. The CG KO shall determine the disposition of any Control Console delivered for inspection that is found to be not suitable for repair for whatever reason.

Upon acceptance of the estimate and authorization to proceed by the CG KO, the Control Console shall be overhauled in accordance with OEM recommended procedures and as follows:

OVERHAUL REQUIREMENTS:

Each Control Console shall be overhauled to a condition, which shall restore the operating and performance characteristics to the "ORIGINAL" design and technical specifications. Overhaul shall be performed in accordance with the original equipment manufacturer (OEM) specifications and standards. All repair parts shall be genuine OEM manufactured parts. All replacement parts used in the overhaul shall be new OEM parts or parts of equal or better quality. Reclaimed or recycled parts are not acceptable and shall not be used.

OUALITY ASSURANCE:

Following completion of overhaul, the contactor shall perform standard production tests and inspections to assure maximum design performance. The Contractor shall provide certifications of successful standard production tests and inspections. One certification shall be placed in the box with each unit and a copy for each unit shall be forwarded to the Coast Guard Contracting Officer.

Example of Marking Layout:

NATIONAL STOCK NUMBER: 2030-01-612-7381

ITEM NAME: Console, Ship Control

PART NUMBER: 60576

SERIAL NUMBER: as applicable GOVERNMENT ORDER NUMBER: as applicable DATE OF REPAIR: as applicable Coast Guard SFLC Material, Condition Code ?A".

WARRANTY:

X A. Standard Manufacturer's Warranty

B. Item being repaired as an "onboard repair" or a "system stock" item and will be put into inventory. NOT FOR IMMEDIATE INSTALLATION.

Contractor must guarantee item against defects that lead to failure for days after installation for a period of up to two (2) years after delivery to Coast Guard.

GOVERNMENT ACCEPTANCE:

Acceptance will be made at destination by a Government representative.

Acceptance will be contingent upon the representative's verification of no damage in transit, correctness and completeness of order and contractor's conformance to preservation/packaging, packing and marking requirements.

OVERHAUL DESCRIPTION

PACKAGING AND MARKING FOR SHIPMENT:

X A. Each unit shall be packed individually in it's own wooden box which shall be capable of providing adequate protection to the item during multiple shipments. Mark each box in legible black print lettering with the following information:

NATIONAL STOCK NUMBER

ITEM NAME

PART NUMBER

GOVERNMENT ORDER NUMBER

2030-01-612-7381

CONSOLE,SHIP CONTROL

60576

PRESERVATION / PACKAGING:

X A. Each unit shall be individually preserved and wrapped for protection against deterioration for a period of two (2) years minimum.

B. See Attachments

B. See Attachments

And the words: "Coast Guard SFLC Material, Condition "A"

RECOMMENDED SOURCES:

ALLIED SYSTEMS COMPANY INC DBA ALLI

21433 SW OREGON ST

SHERWOOD, OR 97140-9769

KELLYWILSON@ALLIEDSYSTEMS.COM

503-825-3426

503-825-3426

WRITTEN BY:

DATE :

CRAIG FAW

13 FEB 25

Cost Estimate for Overhaul NOT TO EXCEED: $38,422.89