R17PS00264__Amendmnet_001.pdf

PDF 116 KB Posted

Attached to
Pole Hill Powerplant Penstock Expansion Joint Pack
Solicitation number
R17PS00264
Issued by

About this file

Pole Hill Powerplant Expansion Joint Replacement: Changes to Section 01 14 20, Penstock Operations.

View the file

Other files

File Type Posted
Amendment_002_R17PS00264.pdf PDF
IFB_-Solitation_R17PS00264.pdf PDF
PSN_POLE_HILL_POWERPLANT_PENSTOCK.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

R17PS00264

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Billings MT 59101

R60

2021 4th Avenue North

GP-5000

Great Plains Regional Office Bureau of Reclamation

04/25/2017001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/14/2017

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Paris Everson

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Pole Hill Powerplant Penstock, Expansion Joint Packing Replacement, Colorado-Big Thompson Project, Colorado

See Page 2 for changes incorporated in this amendment.

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment 001 Solicitation No. R17PS00264

DESCRIPTION OF CHANGES:

Section 01 14 20 has changed, therefore remove Section 01 14 20, Penstock Operations in its entirety. Insert Revised Section 01 14 20, Penstock Operations in its entirety.

END

Colorado-Big Thompson Project Pole Hill Powerplant Penstock Expansion Joint Packing Replacement Specifications No. 60-C0670

Penstock Operations Revised 01 14 20 - 1

SECTION 01 14 20

PENSTOCK OPERATIONS

PART 1 GENERAL

1.01 COST

A. Include cost in prices offered in the Price Schedule for other items of work.

1.02 REFERENCES

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards http://www.usbr.gov/ssle/safety/RSHS/rshs.html

1.03 PENSTOCK OPERATIONS

A. Government will unwater the penstock to accommodate Contractor requested and approved interruption of service only during the annual maintenance period. All work on the penstock shall be between August 1, 2017 and September 8, 2017. The Contractor shall be allowed two weeks prior to the annual maintenance period start date to mobilize.

B. Prior to any work being performed on the outside or inside of the penstock, the Contractor and the COR shall perform lockout/tagout procedures in accordance with Section 15 of the RSHS references in this Section.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

http://www.usbr.gov/ssle/safety/RSHS/rshs.html

Colorado-Big Thompson Project Pole Hill Powerplant Penstock Expansion Joint Packing Replacement Specifications No. 60-C0670

Penstock Operations Revised 01 14 20 - 2

This page intentionally left blank.