About this file

Specifications Pen and Ink Revisions

View the file

Other files for this federal contract opportunity

Other files attached to NGWSP, Reach 22a, newest first.
File Type Posted
Aquifer_Testing_Reach_22A_-_File_Verison_-_03-09-2015.pdf PDF
Sol_R15PS00857_Amd_000006.pdf PDF
Contractor_Question_Responses_6-19-15.docx DOCX document
Sol_R15PS00857_Amd_000005.pdf PDF
Amendment_004_Detail_specifications.pdf PDF
Sol_R15PS00857_Amd_000004.pdf PDF
Amendment_003_(2).pdf PDF
Sol_R15PS00857_Amd_000003.pdf PDF
R15PS00857_Solicitation_Amendment_2.docx DOCX document
Sol_R15PS00857_Amd_000002.pdf PDF
Sol_R15PS00857_Amd_000001.pdf PDF
R15PS00857_Solicitation.docx DOCX document
Sol_R15PS00857.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NGWSP Reach 22a Amendment #006 Section C – Description / Specifications Revisions

01 33 00 Submittals - *pen and ink changes* Table 01 33 00A – List of Submittals – RSN 09 96 20-3) Delete this submittal.

05 50 00 Metal Fabrications - *pen and ink changes*

2.06 Cast Iron Foundry Ring and Cover – A.1) Replace “…class 358.” with “…class 35 B.”

09 96 20 Coatings - *pen and ink changes*

1.03 Submittals – D) Delete this paragraph regarding RSN 09 96 20-3, Certifications.

1.04 Qualifications – C, D, and E) Delete these paragraphs regarding SSPC-QP1, QP2, and QP3 certifications.

3.10 Coating Tabulations – Tabulation No. 05) Add Eaton’s standard coating and colors as an approved coating material manufacturer for the interior and exterior ferrous surfaces of the duplex strainer.

33 05 22 Horizontal Directional Drilling - *pen and ink changes*

1.04 Qualifications – A) Add “…, including key personnel listed under subsection 1.03.B.1...” after “Contractor” to this paragraph.

33 11 10 Pipeline General Requirements - *pen and ink changes*

3.01 General – C.1) Replace this paragraph with the following: “Protect pipe from contamination, damage, and the elements during storage on site by covering it with a tarp as directed by the COR.”

35 21 30 Intake Bulkhead Gate - *pen and ink changes*

3.04 Removal and Storage – C) Replace this paragraph with the following: “Transport to and unload bulkhead gate and accessories at storage site within 50 miles from Cutter Dam, as directed by the COR.”

52 00 00 Drawings - *pen and ink changes* 1695-D-380 River Outlet Works – Modified Gate Structure – Note #3) Replace “…Section 03 62 25…” with “…Section 03 62 20…”