Reach_22a_Specification_Revisions__6-19-15.docx
DOCX document 20 KB Posted
- Attached to
- NGWSP, Reach 22a Federal contract opportunity
- Solicitation number
- R15PS00857
About this file
Specifications Pen and Ink Revisions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Aquifer_Testing_Reach_22A_-_File_Verison_-_03-09-2015.pdf | ||
| Sol_R15PS00857_Amd_000006.pdf | ||
| Contractor_Question_Responses_6-19-15.docx | DOCX document | |
| Sol_R15PS00857_Amd_000005.pdf | ||
| Amendment_004_Detail_specifications.pdf | ||
| Sol_R15PS00857_Amd_000004.pdf | ||
| Amendment_003_(2).pdf | ||
| Sol_R15PS00857_Amd_000003.pdf | ||
| R15PS00857_Solicitation_Amendment_2.docx | DOCX document | |
| Sol_R15PS00857_Amd_000002.pdf | ||
| Sol_R15PS00857_Amd_000001.pdf | ||
| R15PS00857_Solicitation.docx | DOCX document | |
| Sol_R15PS00857.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NGWSP Reach 22a Amendment #006 Section C – Description / Specifications Revisions
01 33 00 Submittals - *pen and ink changes* Table 01 33 00A – List of Submittals – RSN 09 96 20-3) Delete this submittal.
05 50 00 Metal Fabrications - *pen and ink changes*
2.06 Cast Iron Foundry Ring and Cover – A.1) Replace “…class 358.” with “…class 35 B.”
09 96 20 Coatings - *pen and ink changes*
1.03 Submittals – D) Delete this paragraph regarding RSN 09 96 20-3, Certifications.
1.04 Qualifications – C, D, and E) Delete these paragraphs regarding SSPC-QP1, QP2, and QP3 certifications.
3.10 Coating Tabulations – Tabulation No. 05) Add Eaton’s standard coating and colors as an approved coating material manufacturer for the interior and exterior ferrous surfaces of the duplex strainer.
33 05 22 Horizontal Directional Drilling - *pen and ink changes*
1.04 Qualifications – A) Add “…, including key personnel listed under subsection 1.03.B.1...” after “Contractor” to this paragraph.
33 11 10 Pipeline General Requirements - *pen and ink changes*
3.01 General – C.1) Replace this paragraph with the following: “Protect pipe from contamination, damage, and the elements during storage on site by covering it with a tarp as directed by the COR.”
35 21 30 Intake Bulkhead Gate - *pen and ink changes*
3.04 Removal and Storage – C) Replace this paragraph with the following: “Transport to and unload bulkhead gate and accessories at storage site within 50 miles from Cutter Dam, as directed by the COR.”
52 00 00 Drawings - *pen and ink changes* 1695-D-380 River Outlet Works – Modified Gate Structure – Note #3) Replace “…Section 03 62 25…” with “…Section 03 62 20…”