Solicitation_R15PS00691.pdf
PDF 3 MB Posted
- Attached to
- Fish Hatchery Outlet Works Recoating, Pueblo Dam
- Solicitation number
- R15PS00691
About this file
Solicitation No. R15PS00691
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_R15PS00691_Amd_0002.pdf | ||
| Amendment_No._0002.pdf | ||
| Sol_R15PS00691_Amd_0001.pdf | ||
| Amendment_No._0001.pdf | ||
| NOTE_REGARDING_DRAWINGS_-691.pdf | ||
| Sol_R15PS00691.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior Bureau of Reclamation Great Plains Region May 2015
Request For Proposal Solicitation No. R15PS00691
Fish Hatchery Outlet Works Recoating
Pueblo Dam Fryingpan-Arkansas Project, Colorado
U.S. Department of the Interior Bureau of Reclamation Great Plains Region May 2015
This page intentionally left blank i
FISH HATCHERY OUTLET WORKS RECOATING
PUEBLO DAM
FRYINGPAN-ARKANSAS PROJECT
COLORADO
FOREWORD
Jobsite is located at Pueblo Dam approximately 6 miles west of Pueblo, Colorado, in Pueblo County.
Principle features of the work include surface preparation and recoating of piping and valves for fish hatchery outlet works inside of Pueblo Dam.
1. Mobilization and preparatory work.
2. Sediment removal, cleaning, sample collection and analysis for heavy metals in work area locations.
3. Removal of existing coating systems and application of new coating systems.
TELEPHONE INQUIRIES REGARDING THIS SOLICITATION SHOULD BE MADE TO:
Contractual Matters: Gerri Voto-Braun Contracting Officer Billings, Montana Telephone: (406) 247-7809 gvotobraun@usbr.gov
FOR DATE AND PLACE PROPOSALS ARE DUE, SEE “SOLICITATION, OFFER, AND
AWARD," STANDARD FORM 1442, IMMEDIATELY FOLLOWING THE TABLE OF
CONTENTS.
FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION
"RECLAMATION SAFETY AND HEALTH STANDARDS," (2009 EDITION) WHICH IS
APPLICABLE TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT "WBR
1452.223-81 SAFETY AND HEALTH."
PRE-BID SITE VISIT: AN ORGANIZED SITE VISIT HAS BEEN SCHEDULED FOR
MAY 20, 2015 AT 11:00 AM. INTERESTED CONTRACTORS SHALL MAKE
ARRANGEMENTS IN ATTENDING THE SITE VISIT BY CONTACTING MR. JOHN
FOREMAN AT 970-962-4327 OR VIA E-MIAL AT JFOREMAN@USBR.GOV.
ATTENDEES ARE TO PROVIDE AND WEAR SAFETY BOOTS, HARD HATS AND
SAFETY VESTS. PROSPECTIVE CONTRACTORS ARE STRONGLY ENCOURAGED
TO ATTEND THE PRE-BID SITE VISIT TO GAIN A BETTER UNDERSTANDING OF
THE WORK REQUIREMENTS AND SITE CONDITIONS.
SAM: EFFECTIVE JULY 29, 2012, ANY CONTRACTOR INTERESTED IN DOING
BUSINESS WITH THE GOVERNMENT MUST REGISTER IN THE SYSTEM FOR
AWARD MANAGEMENT (SAM) DATABASE PRIOR TO AWARD OF A CONTRACT
OR AGREEMENT. SAM IS A FEDERAL GOVERNMENT OWNED AND OPERATED
FREE WEBSITE THAT CONSOLIDATES THE CENTRAL CONTRACTOR
ii
REGISTRATION (CCR), THE ONLINE REPRESENTATIONS AND CERTIFICATIONS
APPLICATION (ORCA), AND THE EXCLUDED PARTIES LIST SYSTEM (EPLS).
THE VENDOR’S DUNS AND BRADSTREET NUMBER AND BANKING
INFORMATION ARE REQUIRED FOR REGISTRATION. CONTRACTORS MAY
OBTAIN INFORMATION ON REGISTRATION AND ANNUAL CONFIRMATION
REQUIREMENTS VIA THE SAM WEBSITE ACCESSES THROUGH
HTTPS://WWW.SAM.GOV/PORTAL/PUBLIC/SAM/ OR BY THE FEDERAL SERVICE
DESK AT 1-866-606-8220.
PAYMENT REQUESTS FOR THE ANTICIPATED CONTRACT MUST BE
SUBMITTED ELECTRONICALLY THROUGH THE U.S. DEPARTMENT OF THE
TREASURY’S INTERNET PAYMENT PLATFORM (IPP) SYSTEM. THE IPP
WEBSITE IS HTTPS://WWW.IPP.GOV. THE CONTRACTOR MUST USE THE IPP
WEBSITE TO REGISTER ACCESS AND USE IPP FOR SUBMITTING REQUESTS
FOR PAYMENT. CONTRACTOR ASSISTANCE WITH ENROLLMENT CAN BE
OBTAINED BY CONTACTING THE IPP PRODUCTION HELPDESK VIA E-MAIL
IPPGROUP@BOS.FRB.ORG OR PHONE (866) 973-3131. IF THE CONTRACTOR IS
UNABLE TO COMPLY WITH THE REQUIREMENT TO USE IPP FOR SUBMITTING
INVOICES FOR PAYMENT, THE CONTRACTOR MUST SUBMIT A WAIVER
REQUEST IN WRITING TO THE CONTRACTING OFFICER WITH ITS PROPOSAL
OR BID.
i
TABLE OF CONTENTS
PART 1 – THE SCHEDULE
SECTION A – Solicitation, Offer and Award, Standard Form 1442
SECTION B – Schedule
SECTION C - Descriptions/ Specifications
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety and Health Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 56 10 Protection of Existing Installations 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 60 00 Product Requirements 01 74 00 Cleaning and Waste Management
DIVISION 02 - EXISTING CONDITIONS
02 83 30 Removal and Disposal of Coatings Containing Heavy Metals
DIVISION 09 - FINISHES
09 96 20 Coatings
DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 90 Photographs 51 02 83 Existing Coating Test Results
DIVISION 52 - DRAWINGS
52 00 00 Drawings
SECTION D – Not Used
SECTION E – Inspection and Acceptance Material and Workmanship ............................................................................................................. E-1 Inspection of Construction .............................................................................................................. E-1 Warranty of Construction ................................................................................................................ E-2
SECTION F – Deliveries or Performance Commencement, Prosecution and Completion of Work .................................................................. F-1 Suspension of Work ......................................................................................................................... F-1
SECTION G -- Contract Administration Data Authorities and Delegations ............................................................................................................ G-1 Contractor’s Administration Personnel ........................................................................................... G-1 Electronic Invoicing and Payment Requirements – Internet Payment Platform ............................. G-2 PostAward Conference .................................................................................................................... G-2 ii
SECTION H -- Special Contract Requirements Non-Discrimination Notice to U.S. Department of the Interior Contractors, Subcontractors, and Lessors (Dec1999) .......................................................................................... H-1 Site Security .................................................................................................................................... H-1
PART II – CONTRACT CLAUSES
SECTION I -- Contract Clauses Clauses Incorporated by Reference .................................................................................................. I-1 Restrictions on Endorsements .......................................................................................................... I-3 Release of Claims ............................................................................................................................. I-3 Examination of Records by the Department of the Interior .............................................................. I-3 Liability Insurance ............................................................................................................................ I-3 Order of Precedence – Uniform Contract Format ............................................................................ I-3 Establishing a Minimum Wage for Contractors (Deviation) ............................................................ I-4 Buy American Act – Construction Materials ................................................................................... I-4 Bid Guarantee ................................................................................................................................... I-7 Performance and Payment Bonds ..................................................................................................... I-7 Payments Under Fixed-Price Construction Contracts ...................................................................... I-8 Prompt Payment for Construction Contracts .................................................................................. I-10 Changes .......................................................................................................................................... I-16 Change Order Accounting .............................................................................................................. I-17 Authorized Deviations in Clauses .................................................................................................. I-17 Asbestos-Free Warranty ................................................................................................................. I-17 Safety and Health ........................................................................................................................... I-18 Protesting Federal Employees and the Public from Exposure to Tobacco and Smoke in the Federal Workplace ................................................................................................... I-18 Certification of Representatives for Corporate Sureties ................................................................. I-18 Equipment Ownership and Operating Expense .............................................................................. I-19 Payment for Mobilization and Preparatory Work .......................................................................... I-20 Claims Accounting ......................................................................................................................... I-22 Preservation of Cultural Resources ................................................................................................ I-22 Security Requirements – Alternate III ............................................................................................ I-23 Modification Proposals – Alternate IV ........................................................................................... I-30
PART III – DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION J – DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
Attachment No. 1 General Decision CO150012, dated March 27, 2015 Attachment No. 2 Standard Form 24, Bid Bond Attachment No. 3 Past Performance Questionnaire (Evaluation Factor 4)
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K -- Representations, Certifications and Other Statements of Offerors Annual Representations and Certifications ..................................................................................... K-1 Incorporation by Reference of Representations an d Certifications ................................................ K-3 Prohibition of Contracting with Inverted Domestic Corporations – Representations ..................... K-4
SECTION L -- Instructions, Conditions and Notices to Bidders Authorized Workers Notice to Potential Bureau of Reclamation Contractors ................................ L-1 Use and Disclosure of Proposal Information ................................................................................... L-2 System for Award Management ...................................................................................................... L-3 Commercial and Government Entity Code Reporting ..................................................................... L-4 Commercial and Government Entity Code Maintenance ................................................................ L-5 iii
Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR art 101-29 .......................................................................... L-6 Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition
Streamlining and Standardization Information System (ASSIST) .................................................. L-6 Submission of Offers in the English Language ............................................................................... L-6
Submission of Offers in U.S. Currency ........................................................................................... L-6 Instructions to Offerors – Competitive Acquisition ........................................................................ L-7 Type of Contract ............................................................................................................................ L-10 Contract Wage Rate Requirements - Secondary Site of Work ...................................................... L-10 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction ........................................................................................................ L-10 Notice of Buy American Act Requirement – Construction Materials ........................................... L-11 Service of Protest – Department of the Interior (Deviation) ......................................................... L-12 Site Visit (Construction)- Alternate I ........................................................................................... L-12 Preparation of Proposals ................................................................................................................ L-12 Authorized Deviations in Provisions ............................................................................................. L-13 Notice of Intent to Acquire Metric Products and Services ............................................................ L-13 Source Evaluation and Selection Procedures ................................................................................ L-14 General Proposal Instructions........................................................................................................ L-16 Technical Proposal Instructions .................................................................................................... L-15 Pricing Proposal Instructions ......................................................................................................... L-18 Notice of Proposed Partnering ....................................................................................................... L-19 Instruction for Mobilization and Preparatory Work Schedule Line Item ...................................... L-20
SECTION M – Evaluation Factors for Award Evaluation Factors for Award – Quality Predominance ................................................................. M-1 Notice of World Trade Organization Government Procurement Agreement Evaluations ............. M-3 iv
This Page Intentionally Left Blank
PART I – THE SCHEDULE
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040148670
Bureau of Reclamation
Great Plains Region
Regional Office PO Box 36900
R60
Billings MT 59107
Bureau of Reclamation
Attn: Gerri Voto-Braun 2021 4th Avenue North Billings, MT 59102
Gerri Voto-Braun 406-247-7809
1x 05/06/2015
R15PS00691
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Fish Hatchery Outlet Works Recoating, Pueblo Dam, Fryingpan-Arkansas Project, Colorado
The estimated price range for this project is $100,000 to $250,000
The project is issued for full and open competitiion
The North American Industrial Classification Code is 238320
The size standard is $15.0 Million
Taxpayer Identification Number: ____________________________
Data Universal Numbering System: ___________________________
Commercial and Government Entity Code: _____________________
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 150 calendar days and complete it within ________________ ________________ calendar days after receiving
Paragraph F.1
06/08/2015
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Gerri Voto-Braun
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
R15PS00691
00010 Fish Hatchery Outlet Works Recoating, Pueblo Dam 1 AU $______________
Price Schedule CLINS 1 through 3 (See the following continuation page)
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Fish Hatchery Outlet Works Recoating
Price Schedule
B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES
FISH HATCHERY OUTLET WORKS RECOATING
Fryingpan–Arkansas Project, Colorado
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(d) Definitions:
(1) CLIN – Contract Line Item Number.
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
1 WBR
1452.232
-81
Mobilization and Preparatory Work
For the lump sum of $
2 02 83 30 Removal and Disposal of Coatings Containing Heavy Metals
For the lump sum of $
3 09 96 20 Fish Hatchery Outlet Works Recoating
For the lump sum of $
TOTAL FOR PRICE SCHEDULE $_________________
END OF SUPPLIES OR SERVICES AND PRICES
Price Schedule
B - 2
This page intentionally left blank.
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located at Pueblo Dam approximately 6 miles west of Pueblo, Colorado, in Pueblo County.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Surface preparation and recoating of piping and valves for fish hatchery outlet works inside of Pueblo Dam.
1. Mobilization and preparatory work.
2. Sediment removal, cleaning, sample collection and analysis for heavy metals in work area locations.
3. Removal of existing coating systems and application of new coating systems.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.
1.04 DEFINITIONS
A. When the specifications use a word or term defined in the Federal Acquisition Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 52:
1. CO: Contracting Officer.
2. COR: Contracting Officer’s Representative.
Summary of Work
01 11 00 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, storage areas, and fuel and oil storage areas.
2) Parking areas.
3) Utilities including air, power, and water lines; fire hydrants; and compressor station.
4) First-aid and medical facilities.
5) Areas for processing, storing, and disposing of waste materials from construction operations.
6) Temporary fences.
b. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near the jobsite.
c. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.
1.03 PROJECT CONDITIONS
A. The Fish Hatchery Outlet chamber is located in Buttress 8 of Pueblo Dam. Access to the chamber is as follows:
Use of Site 01 14 10 - 2
1. Enter the dam through the door on Buttress 7, descend approximately 6 steps to the gallery level at elevation 4755. Buttress 8 is located approximately 100 ft to the north. Access to the outlet works valve chamber is gained by ascending a spiral staircase one level to elevation 4767. There is an access shaft for equipment located on the north end of the chamber.
B. Government land may be used for required construction facilities.
C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of the COR.
D. Do not interfere with work of other contractors or the Government.
E. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as approved by the COR.
F. When private land is used for construction facilities, or other construction purposes, make necessary arrangements with landowner for use of private land.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 RESTORATION
A. Restore Contractor use areas to pre-construction condition.
Submittals
01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236-21 - Specifications and Drawings for Construction.
1.03 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement units: US Customary Units.
C. Drawings:
1. Minimum identification in title block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
c. Date.
2. Provide space next to title block for review stamps.
3. Size: D size (22 inches by 34 inches).
4. Draw to scale with neat lettering using drafting equipment or computer drafting equipment.
5. Final drawings:
a. AUTOCAD® format (.dwg), Version 2007, on CD-ROM.
01 33 00 - 2
b. Original D size (22 inches by 34 inches) plots.
c. Show as-built changes, including revision dates, made during installation.
D. Product Data:
1. Mark manufacturer’s data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer’s name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will be clear and legible after photocopying. Do not use highlighter.
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
F. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Adobe® Acrobat PDF (.pdf) format on CD-ROM.
1) Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
d. As-built drawings, photographs, and test records or reports if required by the specifications.
1.04 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor’s approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in "Submittals Required" column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
01 33 00 - 3
C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.
1. Electronic submittals:
a. In Portable Document Format (PDF).
b. Include RSN transmittal letter.
c. Do not include Personally Identifiable Information (PII) in electronic submittals.
2. Submit electronic submittals via email or CD/DVD based on size:
a. The Government can receive e-mails up to 10 MB. Receipt of e-mails exceeding 10 MB (extra-large) may be possible. E-mailing of extra-large electronic submittals may occur only after size limit for transmittal of extra-large e-mail has been verified.
b. Address e-mail of electronic submittals less than extra large size to:
1) sha-GPR-CONSTSVCS@usbr.gov
c. Include electronic submittals that are too large to e-mail with paper copy of submittal. These electronic submittals shall be on CD or DVD.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
E. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned for resubmittal.
1.05 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 21 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.
01 33 00 - 4
a. The time extension will be to the extent that excess review time caused delay to the contract completion date.
b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.
2. No time extension will be allowed if the Contractor fails to make complete approval submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a "suspension order" as the term is used in that clause.
C. Submittal response:
1. Response letter will indicate whether submittal is approved, approved subject to identified changes, or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of the CO after drawings, documentation, and technical data have been approved.
1.06 TRANSMITTAL
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. Contracting Officer: Bureau of Reclamation, Attention GP-5000, PO Box 36900, Billings MT 59107-6900. Physical address: 2021 4th Avenue North, Billings MT 59101.
2. Contracting Officer’s Representative: Bureau of Reclamation, Attention GP- 2600, PO Box 36900, Billings, MT 59107-6900. Physical address: 2021 4th Avenue North, Billings MT 59101.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
01 33 00 - 5
Table 01 33 00A - List of Submittals
*CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative.
RSN
Clause or Section
Title
Submittals Required
Due Date or Delivery Time
Respon-sible Code
Sets to be sent: *
CO COR
1 Performance and Payment Bonds – Construction 52.228-15
Performance and Payment Bonds
Within 10 calendar days after award
CO 1 0
2 Insurance-work on a Government Installation 52.228-05
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
Before commencing onsite work
CO
3 Liability Insurance 1452.228-70
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
CO 1 0
4 Equal Opportunity 52.222-26
Information required by Executive Order
112246 (SF-100)
Within 30 days following award
CO 1 0
5 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10
Certification that executive compensation and subcontract awards were reported
Within 10 days of each report being submitted
CO 1 0
6 Site Security
GP-7
Employee Information
Initially at least 21 days before beginning onsite work; at least 21 days before additional employees arrive on-site
COR 0 1
7 Site Security
GP-7
Vehicle Information At least 21 days before beginning on-site work
COR 0 1
8 Service Contract Reporting Requirements 52.204-14
Certification that annual report was filed
By October 31st of each year of contract performance
COR 1 0
10 Labor Standards Data 52.222-11
1) List of subcontractors
2) Statement and acknowledgement Form (SF-1413) for each subcontract
Within 14 days after award of contract
COR 1
01 33 00 - 6
Table 01 33 00A - List of Submittals *CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative.
RSN
Clause or Section
Title
Submittals Required
Due Date or Delivery Time
Respon-sible Code
Sets to be sent: *
CO COR
11 Payrolls and Basic Records 52.222-08
Copies of all payrolls
Weekly for each week of contract performance
COR 1 1
10 Schedules for Construction Contracts 52.236-15
Practicable Schedule Within 5 days after work commences on the contract or another period of time as determined by CO
COR 1 paper 1 paper + 1 electronic
11 Schedules for Construction Contracts 52.236-15
Updated Schedule showing actual progress
Monthly or as directed by the
COR 1 paper 1 paper + 1 electronic
12 Release of Claims 1452.204-70
Release of Claims (DI-137) against the Government
After completion of the work and prior to final payment
CO 1 0
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
At least 28 days before use of Government land
COR 0 1 paper + 1 electronic
01 35 10-1 Material Safety Data Sheets
Complete LHM and
SDS
At least 14 days before jobsite delivery of hazardous material
COR 0 1 paper + 1 electronic
01 35 10-2 Material Safety Data Sheets
Updated LHM and
SDS
At least 14 days before jobsite delivery of hazardous material not previously listed
COR 0 1 paper + 1 electronic
01 35 20-1 Safety and Health
Safety Program Submitted and reply of adequacy received before commencing onsite work.
See Section 3 of RSHS
COR 0 1 paper + 1 electronic
01 35 20-2 Safety and Health
Monthly accident summary report
The first day of each month COR 0 1 paper + 1 electronic
01 35 20-3 Safety and Health
Respirator user documentation
At least 14 days before starting onsite work
COR 0 2 paper
01 35 20-4 Safety and Health
Other training certificates
At least 14 days before starting onsite work
COR 0 2 paper
01 35 30-1 Contractor’s Onsite Safety and Health Personnel
Qualifications At least 20 days before beginning onsite work
COR 0 2 paper
01 35 30-2 Contractor’s Onsite Safety and Health Personnel
CIH inspection reports
At least once each week COR 0 1 paper + 1 electronic
01 35 30-3 Contractor’s Onsite Safety and Health Personnel
Safety inspection reports
Submit to COR within 7 days of inspection
COR 0 1 paper + 1 electronic
01 33 00 - 7
Table 01 33 00A - List of Submittals *CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative.
RSN
Clause or Section
Title
Submittals Required
Due Date or Delivery Time
Respon-sible Code
Sets to be sent: *
CO COR
01 56 10-1 Protection of Existing Installations
Plan for protecting existing installations
At least 28 days before starting onsite work
COR 0 1 paper + 1 electronic
01 57 30-1 Water Pollution Prevention
Spill Prevention, Control and Countermeasure (SPCC) Plan
At least 28 days before starting onsite work
COR 0 1 paper + 1 electronic
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of waste disposal
COR 0 1 paper + 1 electronic
01 74 00-2 Cleaning and Waste Management
Hazardous Wastes Manifest
Within 7 days of hazardous waste disposal
COR 0 1 paper + 1 electronic
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 28 days before beginning environmental assessment
COR 0 1 paper + 1 electronic
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Within 14 days of completion of work
COR 0 1 paper + 1 electronic
02 83 30-1 Removal and Disposal of Coatings Containing Heavy Metals
Documentation At least 28 days before beginning onsite work
COR 0 1 paper + 1 electronic
02 83 30-2 Removal and Disposal of Coatings Containing Heavy Metals
Plans At least 28 days before beginning onsite work
COR 0 1 paper + 1 electronic
02 83 30-3 Removal and Disposal of Coatings Containing Heavy Metals
Heavy Metal Exposure Certifications and Test Results
At least 28 days before beginning onsite work
COR 0 1 paper + 1 electronic
02 83 30-4 Removal and Disposal of Coatings Containing Heavy Metals
Preconstruction Test Results
At least 28 days before beginning onsite work
COR 0 1 paper + 1 electronic
02 83 30-5 Removal and Disposal of Coatings Containing Heavy Metals
Working level test results
Within 14 days after completion of testing
COR 0 1 paper + 1 electronic
01 33 00 - 8
Table 01 33 00A - List of Submittals *CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative.
RSN
Clause or Section
Title
Submittals Required
Due Date or Delivery Time
Respon-sible Code
Sets to be sent: *
CO COR
02 83 30-6 Removal and Disposal of Coatings Containing Heavy Metals
Post-construction test results
Within 14 days after completion of testing
COR 0 1 paper + 1 electronic
02 83 30-7 Removal and Disposal of Coatings Containing Heavy Metals
Certificate of disposal
Within 14 days after disposal COR 0 1 paper + 1 electronic
09 96 20-1 Coatings Approval Data At least 28 days before application
COR 0 1 paper + 1 electronic
09 96 20-2 Coatings Final Approval Data At least 28 days before application
COR 0 1 paper + 1 electronic
09 96 20-3 Coatings Certifications At least 28 days before application
COR 0 1 paper + 1 electronic
09 96 20-4 Coatings Documentation At least 28 days before application
COR 0 1 paper + 1 electronic
09 96 20-5 Coatings Contractor Quality Testing Data
Within 7 days after testing COR 0 1 paper + 1 electronic
Safety Data Sheets
01 35 10 - 1
SECTION 01 35 10
SAFETY DATA SHEETS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 DEFINITIONS
A. LHM: List of Hazardous Materials.
B. SDS: Safety Data Sheet.
1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous Material Identifications and Material Safety Data - Alternate 1.
1.03 APPLICATION
A. For the purposes of this contract, the definition of “materials delivered under this contract” in the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes materials delivered to the Government and all materials expected to be used during contract performance at the jobsite.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 10-1, Complete LHM and SDS.
C. RSN 01 35 10-2, Updated LHM and SDS:
1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.
1.05 DELIVERY
A. Do not deliver hazardous materials to jobsite which are not included on the original or previously updated LHM and SDS before receipt of updated LHM and SDS by the COR.
PART 2 PRODUCTS
Safety Data Sheets
01 35 10 - 2
PART 3 EXECUTION
Safety and Health
01 35 20 - 1
SECTION 01 35 20
SAFETY AND HEALTH
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include the cost of complying with this section in the prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS-2009 Reclamation Safety and Health Standards
a. Available on the Internet at:
http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
2. FIST 1-1 (2012) Hazardous Energy Control Program
a. Available on the Internet at:
www.usbr.gov/power/data/fist_pub.html
B. Occupational Safety and Health Administration (OSHA)
1. 29 CFR Part 1910 Occupational Safety and Health Standards
2. 29 CFR Part 1926 Safety and Health Regulations for Construction
3. Available on the Internet at www.osha.gov.
C. American Conference of Governmental Industrial Hygienists (ACGIH), Threshold Limit Values (TLVs)
1. Available at www.acgih.org
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 20-1, Safety Program:
1. Submit a comprehensive, job-specific safety and health program in accordance with Section 01 33 00 – Submittals and in accordance with the requirements of Section 3.3 of the Reclamation Safety and Health Standards (RSHS) and these specifications.
2. The Safety Program will not be accepted for review by the COR unless it addresses, in order, lettered and numbered per Appendix B of the RSHS, a http://www.osha.gov/ http://www.acgih.org/
01 35 20 - 2 comprehensive narrative for each applicable item in the outline and program elements contained in these specifications.
3. Generic company safety programs are not acceptable. The Safety Program must be site specific for this contract.
4. The Contractor’s Safety Program must be submitted and accepted by Reclamation prior to commencing onsite work, including mobilization.
5. The Safety Program Statement of Responsibility must state that “the contractor is responsible for ensuring that all work will be in compliance with Reclamation Safety and Health Standards and these specifications.”
6. The Safety and Health Program shall include but not be limited to the following program elements:
a. Emergency Action Plan
1) Detail coordination plan for outside emergency services including response time and a site visit where a rescue requires special capabilities or equipment.
2) This plan shall address detailed emergency contacts and procedures to be used during an onsite emergency.
b. Hazardous Energy Control (lockout/tagout)
1) Include the contractor’s written Hazardous Energy Control Program (HECP).
2) Comply with facility HECP procedures and coordinate activities with Reclamation staff.
c. Electrical Safety
1) Include safe work procedures at the site, electrically qualified persons, grounding techniques, use of mobile generators, construction lighting, power tool safety, and use of personal protective equipment.
d. Hot Work and Fire Prevention
1) Include a plan to address hazards associated with hot work.
2) Include list of workplace fire hazards, potential ignition sources, safe work procedures, engineering controls and equipment to be used to prevent fires during the hot work process.
e. Job Hazard Analysis
1) Provide a list of proposed JHA’s in the Safety Program for each anticipated work task.
2) A detailed JHA shall be completed onsite prior to starting each work task. Work will not begin on the phase of the work
01 35 20 - 3 until a JHA is acceptable to the Onsite Government Representative.
3) Activities involving hazardous materials shall have the appropriate Material Safety Data Sheet(s) attached to the JHA.
f. Respiratory Protection
1) Identify respirator users, tasks and operations with recognized respiratory hazards. Revised for coating work.
g. Hearing Conservation
1) Include a task- and site-specific hearing conservation plan.
2) Identify the type of hearing protection and verify that workers are in a Hearing Conservation Program.
h. Personal Protective Equipment (PPE)
1) Include a detailed plan for each task that specifies which personal protective equipment shall be used for all construction activities.
2) The employer must ensure that the PPE is verified by the manufacturer for the intended use and protection.
3) Provide appropriate PPE at no cost to the employees
i. Hazard Communication
1) Include a written Hazard Communication plan. .
2) The safety and health practices, procedures, and protective equipment used for new and existing products shall be based upon the health hazards identified in the MSDS.
j. Fall Protection and Prevention
1) Detail safe work procedures, training and engineering controls for work in elevated areas where employees are exposed to a fall.
2) The Contractor shall use engineered fall protection systems, fall restraint, and/or fall arrest systems for work in elevated areas. Warning line and safety monitoring systems are not permitted.
k. Scaffolding Safety and Design
1) Include a scaffolding plan indicating what type of scaffolding will be used at the site and provide drawings, design specifications, manufacturer information, fall protection procedures and falling object protection.
01 35 20 - 4
2) Prepared or reviewed and signed by a qualified Professional Engineer (P.E.) except when manufactured systems and standard designs are used.
C. RSN 01 35 20-2, Monthly accident summary report:
1. Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of RSHS.
2. Submit on the first day of every month.
D. RSN 01 35 20-3 Respirator User Documentation
1. Submit documentation of medical qualifications less than 12 months old for all respirator users at the site.
2. Submit results of fit tests less than 12 months old for all users of tight fitting negative pressure respirators at the site.
E. RSN 01 35 20-5, Other training certificates
1. First Aid/CPR certifications for onsite foremen and/or safety personnel.
2. Proof of fall protection and prevention training for employees who work in elevated areas.
3. Proof of Lockout/tagout training for all employees who will work in any area protected by lockout/tagout and hazardous energy control procedures.
4. Training certifications and experience for scaffolding competent person.
1.04 SAFETY AND HEALTH
A. Comply with RSHS, local safety programs, and any other referenced safety and health standards. Perform work in accordance with the specific safety program elements and referenced standards.
B. Provide and maintain a work environment and procedures that will:
1. Safeguard the public, Government personnel, and Contractor employees from Contractor operations and activities that are unsanitary, hazardous, or dangerous to health and safety
2. Avoid interruptions of site operations and delays in project completion dates.
3. Control costs in contract performance.
C. For each operation requiring the use of heavy equipment, in addition to the use of backup alarms and high visibility vests, include in the JHA specific steps to ensure the protection of onsite personnel (internal traffic control) from the hazards of being struck by or caught between moving equipment while working around such equipment. Possible methods of controlling said hazards may include radio communications, backup cameras and/or proximity devices, designated observers, etc. Provide all appropriate safety barricades, signs, and warnings.
01 35 20 - 5
D. Provide appropriate safety barricades, signs, and warnings.
E. Erect or label all limited approach and arc flash hazard boundaries for exposed energized equipment. Coordinate these activities with Reclamation electricians.
F. Comply specifically with all requirements contained in RSHS Section 3- Contractor Requirements.
G. Investigate and report all accidents, incidents and near misses in accordance with RSHS Section 3.7.
H. When the Contractor fails or refuses to promptly correct a compliance directive, the Contracting Officer may issue an order to stop all or any part of the work.
1. When satisfactory corrective action is taken, an order to resume work will be issued.
2. The Contractor shall not be entitled to extension of time or to claim for damage or to additional compensation by reason of ether the directive or the stop order.
3. Failure of the Contracting Officer to order discontinuance of any or all of the Contractor’s operations shall not relieve the Contractor of the responsibility for the safety of personnel and property.
I. Disputes regarding safety and health issues will be settled in accordance with RSHS Section 3.
J. The Contractor shall be responsible for providing medical and emergency assistance in a timely manner that is consistent with recognized emergency protocols.
1. In instances where local emergency responders are not readily available, the responsibility to provide emergency services shall default back to the Contractor.
K. The Contractor shall be responsible for insuring that Subcontractors comply with the requirements set forth in this specification, written programs, the regulatory standards and the industry standards incorporated by reference in the RSHS and OSHA standards.
L. Where there is conflict between the standards, the more stringent or restrictive shall be utilized.
M. The Contractor shall fully participate in the Contractor Safety Program Review meeting, according to RSHS Section 3.4.1. The Contractor Safety Program Review meeting will take place before the start of construction.
1. Include subcontractor management representatives.
2. The Safety Personnel shall be present, in order to discuss in detail the Safety Program and Plans.
N. The minimum work crew at any time on the construction site shall consist of no less than two (2) people.
01 35 20 - 6
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Contractor’s Onsite Safety and Health Personnel
01 35 30 - 1
SECTION 01 35 30
CONTRACTOR’S ONSITE SAFETY AND HEALTH PERSONNEL
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for the other items of work.
1.02 REFERENCES
1. Bureau of Reclamation (USBR)
a. RSHS – 2009 Reclamation Safety and Health Standards.
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 – Submittals
B. RSN 01 35 30-1, Qualifications:
1. Contractor’s Onsite Safety Representative
2. Certified Industrial Hygienist (CIH)
C. RSN 01 35 30-2, CIH Inspection Reports:
1. Detailed monthly summary report for all coatings removal and application activities.
a. Summary of exposure monitoring results and sampling activities and interpretation of the data to confirm that the work is being performed in accordance with the submitted plans.
2. Include noted deficiencies, digital photos, abatement dates and follow-up action.
3. Base inspection report on findings of jobsite walk-through with Government personnel.
4. Submit written report to COR within 7 days of the inspection.
D. RSN 01 35 30-3, Safety Inspection Reports:
1. Prepare detailed monthly safety inspection reports listing noted deficiencies, digital photos, abatement dates and follow-up action for all…