Questions and Answers.docx

DOCX document 22 KB Posted

Attached to
J012--Questions and Answers and Site Visit
Solicitation number
36C26120Q0556
Issued by

About this file

This document contains questions and answers regarding fire sprinkler testing and maintenance requirements for multiple facilities within the Veterans Affairs Northern California Health Care System. The facilities utilize wet sprinkler systems exclusively. Inspections are due on various buildings, with the last documented five-year tests occurring in November 2015 and March 2018. Fire alarm panels by manufacturers such as Notifier, Simplex, and Honeywell control the alarm systems. Inspections are required annually but may occur at any time to maintain intervals. Three and five-year inspections will be due based on the provided inspection dates. The VA is seeking a full-service contract and will not allow self-performance of weekly tasks. The current contract number was not provided. Wet sprinkler systems have 20 risers at the Sacramento Medical Center and McClellan campus and 12 risers at the Martinez campus.

View the file

Other files

File Type Posted
Site Visit Information.docx DOCX document
Mather Campus 2017.pdf PDF
Martinez Campus 2019.pdf PDF
36C26120Q0556_3.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fire Sprinkler Testing and Maintenance for VA Northern California Health Care System (VANCHCS) 36C26120Q0556 Questions and Answers

Question 1: Are any of the sprinklers dry systems? If so, how many?

Answer 1: No. All fire sprinkler systems are known to be wet-sprinkler systems.

Question 2: The oldest building is 78 years old, has the 10, 20, and 50 year sprinkler head testing been kept up to date? If not, how many heads need to be caught up?

Answer 2: Last documented 5-year test for SVD Buildings: 647, 649, 650, 652, 700, 701, 702, 728. November 11, 2015.

Last documented 5-year test for EBD Buildings: Bldg. 19 March 6, 2018; Bldg. 20 January 3, 2019.

The facility focus has been Joint Commission inspected buildings. Little attention has been applied to other buildings within our area of responsibility. The intent is to ensure all buildings are inspected/certified per NFPA 25.

Question 3: Who are the manufacturers of the installed fire alarm panels (Siemens, Notifier, Simplex, EST) and who is the incumbent on the fire alarm inspection contract?

Answer 3: Fairfield Outpatient Clinic (Travis Air Force Base): 103 Bodin Circle, Travis AFB CA, 94535

Make/ Model
Building Number
Floor of Main & Auxiliary Panels
Simplex 4100
FF OPC
1st Floor

Mare Island Outpatient Clinic: 201 Walnut Avenue, Vallejo CA, 94592

Make/ Model
Building Number
Floor of Main & Auxiliary Panels
Cerberus Pyrotronics MXL-IQ
201
1st and 2nd Floors

Martinez Community Based Outpatient Clinic (CBOC): 150 Muir Road, Martinez CA, 94553

Make/ Model
Building Number
Floor of Main & Auxiliary Panels
Notifier NFS2-640
1
1st Floor
Notifier NFS2-640
12
1st Floor
Notifier NFS2-640
13
Tied into Building 12
Notifier NFS2-640
14
Tied into Building 12
Notifier NFS2-640
19
1st and 2nd Floors
Notifier NFS2-640
20
1st Floor
Notifier NFS2-640
21
1st, 2nd, 3rd, and 4th Floors
Notifier NFS2-640
22
1st and 2nd Floors (slave panel)
Notifier NFS2-640
23
1st and 2nd Floors (slave panel)
Notifier FSP-851
24
Stand-alone
Building Under Construction
25
1st and 2nd Floors (Under Construction)
Notifier NFS2-640
26
1st and 2nd Floors
Tied into AB7
AB6
1st Floor
Notifier NFS2-640
AB7
1st Floor
Notifier NFS2-640
R1
1st Floor
Tied into R1
R2
1st Floor
Notifier NFS2-640
R4
1st Floor

Oakland Outpatient Clinic: 2221 Martin Luther King Jr. Way, Oakland CA, 94612

Make/ Model
Building Number
Floor of Main & Auxiliary Panels
Honeywell Silent Knight 6700
2221
1st, 2nd, and 3rd Floors

Sacramento Medical Center (Mather): 10535 Hospital way Mather, CA. 95655 Secutron Panels at Mather:

Model
Building Number
Floor or Building on the Main Panel
MR 2100
631
630
MR 2100
645
Stand-alone
MR 2100
646
Stand-alone
MR 2100
647
649, T-8
MR 2900
650
1st, 2nd, 3rd Floors and T-9
MR 2100
651
Stand-alone
MR 2200
652
Warehouse Stand-alone
MR 2200
700
1st, 2nd, 3rd, 4th, 5th Floors and ED
MR 2100
703
701, 702
MR 2200
707
803, 805, 806, 807
MR 2200
720
722, 722A, 802
MR 2900
728
727
MR 2200
730
731
MR 2100
801
798, 799, 800, 801A, 801B

EST Panels at Mather:

Model
Building Number
Floor or Building on the Main Panel
4X-CAB5DR
726
Stand-alone

McClellan Outpatient Clinic: 5342 Dudley Blvd McClellan, CA. 95652 Secutron Panels at MCC:

Model
Building Number
Floor or Building on the Main Panel
MR 2100
88
Dental
MR 2100
949
1st, 2nd, 3rd Floors

Silent Knight Panels at MCC:

Model
Building Number
Floor or Building on the Main Panel
NA
209
Stand-alone for all Floors

Notifier (By Honeywell):

Model
Building Number
Floor or Building on the Main Panel
DR-C4
29
Maintenance and LMS
DR-C4
98
Stand-alone

Question 4: What is the month of the annual inspection for sprinkler and fire alarm?

Answer 4: There is no set month for inspections as long as the inspection interval is maintained. We have service contracts pending for Fire Alarm services and whether the contractor will follow the fiscal year calendar or standard year calendar is yet to be determined.

Question 5: What future years are the 3 and 5 year inspections due? To calculate this cost, bidders need to know the number of riser per location.

Answer 5: Please use information from Question #2 to determine when inspections are due. Bidders can assume that each major building has its own fire riser location.

Question 6: Will the VA consider self-performing the weekly work (pump runs) as this may cut 50% off the price?

Answer 6: No. The intent is to have a full-service contract for our facility.

Question 7: What is the current contract number?

Answer 7: What is the current contract number?

Question 8: I was looking at the inventory spreadsheet and did not see the amount of sprinkler risers listed. To perform the 5 year internal inspections we would need the amount of wet and dry systems.

Answer 8: All sprinkler systems are wet. The number of risers for SMC/MCC is 20. The number of risers for MTZ is 12.