This document is an unsealed solicitation from the Commonwealth of Virginia Department of Conservation and Recreation for concrete work at Powhatan State Park. The purpose is to establish a contract with a qualified vendor to provide concrete work at Shelters 1 & 2 within the park. The scope of work includes removing existing timbers, excavating, installing a stone base, reinforcing wire, pouring 4-inch thick concrete with a light broom finish, and grading the disturbed area. The sidewalk at Shelter 1 is approximately 5'5" wide and 84' long, while the sidewalk at Shelter 2 is approximately 5'5" wide and 150' long. Site visits are optional but highly recommended prior to the bid due date of May 13, 2024. The contract will be awarded to the lowest responsive and responsible bidder, with preference given to DSBSD-certified micro and small businesses if their bids are determined fair and reasonable. The awarded contractor must be properly licensed in Virginia and comply with all OSHA safety regulations.

The solicitation requires an all-inclusive firm price bid. Bids will be evaluated on a grand total basis, and the Commonwealth reserves the right to reject any and all bids. The awarded contractor will be subject to the Commonwealth's eVA e-procurement requirements, including payment of vendor transaction fees. Other key terms include a one-year warranty, prohibition on subletting work, and requirements for protecting persons and property during the project.

View the file

Other files

File Type Posted
Attachment A_Vendor Data Sheet.docx DOCX document
ATTACHMENT B_pricing list.docx DOCX document
Required Terms and Conditions.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF CONSERVATION AND RECREATION

600 East Main Street, Richmond, VA 23219 QQ 64594 Unsealed Solicitation Concrete Sidewalks and Powhatan State Park

BIDS DUE NO LATER THAN 2:00PM ON MONDAY, MAY 13, 2024

Issue Date: April 27, 2024 Commodity Codes: 91430, 91437, 91382 Location where work will be performed: 4616 Powhatan State Park Road, Powhatan, VA 23139 All Inquiries for Information Should Be Directed To: Cristina Garcia, Procurement Officer at cristina.garcia@dcr.virginia.gov. All questions must be in writing and received via email by 4:00pm EST on Thursday, May 9, 2024. Questions will be answered via email or an addendum posted in eVA. It is the contractor’s responsibility to check eVA for any addenda which may change the Scope of Work.

I. PURPOSE: The purpose of this Quick Quote is to establish a contract with a qualified vendor to provide concrete work at Shelters 1 & 2 within Powhatan State Park located at 4616 Powhatan State Park Road, Powhatan, VA 23139.

NOTE: Site Visits are optional, but highly recommended. They may be scheduled by calling Amelia Hulth at 804-212-5675. All site visits must be completed by Thursday, May 9, 2024 to allow for questions to be answered and a subsequent addendum, if needed to be posted prior to the closing of this solicitation. All contractors wishing to view this project must sign in at the park office.

II. SCOPE OF WORK and SPECIFICATIONS: The contractor shall furnish all materials, labor, tools, equipment, supplies, incidentals and supervision to prepare the area and install a concrete sidewalk surrounding two picnic shelters on the property.

A. Scope of Work One—Worksite, Shelter #1 sidewalk is approximately 5’5” Wide and 84’ Long.

· Remove existing timbers and excavate ground.

· Install 4-6” of compacted #57 stone base, along with reinforcement wire.

· Troweled control joints shall be placed every 5.’

· Pour 300 PSI concrete a minimum of 4” thick.

· Light broom finish

· Remove all form work and backfill sidewalk.

· Grade disturbed area.

B. Scope of Work Two---Worksite, Shelter #2 sidewalk is approximately 5’5” Wide and 150’ Long.

· Remove existing timbers and excavate ground.

· Install 4-6” of compacted #57 stone base, along with reinforcement wire.

· Troweled control joints shall be placed every 5’.

· Pour 30 PSI concrete a minimum of 4” thick.

· Light broom finish.

· Remove all form work and backfill sidewalk.

· Grade disturbed area.

All measurements are estimates only. It is the contractor’s responsibility to verify prior to entering a bid in this program.

C. General Requirements:

Contractor must coordinate work dates with the park representative. The work shall be scheduled within seven (7) days after receipt of award (ARO) and completed within thirty (30) days. Amelia Hulth (804)212-5675 is the Park Representative for this project.

1. All services shall be performed, unless mutually agreed-upon by the Contractor and the Park Representative during normal business hours between the hours of 8:00am and 5:00pm Monday through Friday except for State and Federal Holidays. Crews will not be allowed to stay in cabins while completing the work.

2. Requests to work Saturdays and Sundays shall be approved by the park contact prior to start date.

3. Work must be scheduled within seven (7) days of purchase order award through eVA and completed within thirty (30) days After Receipt Of (ARO) award.

4. Contractor will place temporary fencing and reasonable and necessary traffic control and protective devices around the construction sites.

5. Contractor shall take precautions not to track debris, dirt and mud from the site onto adjacent roadways and sidewalks.

6. Contractor shall provide necessary and prudent barricades, signs, fencing, warning lights, trench safety and all other safety measures to protect the staff, public and contractor employees.

7. Concrete trucks shall not be washed out on park property unless Park Manager approves a suitable location within the park boundaries.

8. All work shall comply with ACI standards.

9. All running slopes and walking surfaces shall not be steeper than 1:20 and all cross slopes of walking surfaces shall not be steeper than 1:48.

10. At both locations, concrete shall match elevation of existing sidewalks and shelters.

11. Vendors should ask questions or seek additional information regarding this bid from the contracting officer. A contractor that asks questions of park staff without a corresponding email to the contracting officer shall have its bid deemed non-responsive if not based on the current scope of work presented. All questions shall be presented to the contracting officer no later than 4:00PM EST on Thursday, May 9, 2024 to allow adequate time to create an addendum if one is found to be necessary.

D. Contractor Requirements

1. Contractor is responsible for maintaining all necessary insurance and licenses as required and provide documentation before work can begin. All contractor personnel shall be fully qualified and trained.

2. Contractor shall be legally qualified and licensed by the Virginia Department of Professional and Occupational Regulation, Board for Contractors, to perform all work included in the scope of the contract.

3. Contractor shall maintain the proper class of DPOR license for the entire project.

4. Contractor registration is required in accordance with Section 54.1-1103 of the Code of Virginia.

5. The Contractor shall ensure that all OSHA safety regulations are followed throughout the course of the project. The area shall be clearly marked with “work in progress signs” and/or caution tape. Proper signage usage when working in a public right-of-way or where the safety of the public must be maintained.

6. The Contractor shall maintain a clean work site continuously throughout the duration of the project.

7. The Contractor shall be responsible for removal and disposal of all debris as a result of this project. The Contractor shall be responsible for removing all discarded or unused material, trash and debris off the park’s premises.

8. It is the Contractor’s responsibility to verify any information, measurements and obtain any clarifications prior to submitting the bid response. The Department of Conservation and Recreation (DCR) is not liable for any errors or misinterpretations made by the Contractor in response to this solicitation.

9. No portion of this work shall be sublet to subcontractors without first securing written consent of DCR.

III. GENERAL TERMS AND CONDITIONS: See Attachment C entitled “Required Terms and Conditions”

IV. BID INSTRUCTIONS:

A. ELECTRONIC BID Submissions ONLY will be accepted for this solicitation. See Electronic Bid instructions attachment or contact eVA Customer Care at 1-866-289-7367 or eVACustomerCare@DGS.Virginia.gov for assistance prior to the closing date and time.

The awarded vendor shall provide a valid Certificate of Insurance (COI) prior to work beginning on any state owned or controlled property. Vendors that fail to provide a COI that meets the Commonwealth’s requirements as outlined in the Agency Procurement and Surplus Property Manual (APSPM) and Vendor’s Manual will not be allowed to commence work.

Please include with your bid the following items to be considered a complete bid package:

•Vendor Data Sheet (Attachment A)
•Pricing Schedule (Attachment B)
•Copy of applicable license/certification(s)

Questions related to how to complete the required attachments should be directed to the Contracting Officer via email at cristina.garcia@dcr.virginia.gov, no later than five (5) days prior to the close of bidding to ensure that answers can be returned.

It is the responsibility of the bidder to assure that his/her bid is submitted electronically prior to the time set for receipt of bids. Bids received after the time designated for receipt of bids will not be considered.

V. SPECIAL TERMS AND CONDITIONS:

A. AUDIT: The contractor shall retain all books, records, and other documents relative to this contract for five (5) years after final payment, or until audited by the Commonwealth of Virginia, whichever is sooner. The agency, its authorized agents, and/or state auditors shall have full access to and the right to examine any of said materials during said period.

B. AWARD: The Commonwealth will make the award on a grand total basis to the lowest responsive and responsible bidder that is a DSBSD certified micro business if such a bid is received, provided that the bid is less than $10,000 and the agency in its sole discretion determines that the bid price is fair and reasonable. Otherwise, award of the contract shall be made to the lowest responsive and responsible bidder that is a DSBSD-certified small business if such a bid is received, provided that the bid is not more than $100,000 and the agency in its sole discretion determines that the bid price is fair and reasonable. If, in the agency’s opinion, the criteria in the previous two sentences are not present, then award shall be made to the lowest responsive and responsible bidder of any size, provided the agency in its sole discretion determines that the price is fair and reasonable. If applicable, unit prices, extensions and grand total must be shown. In case of arithmetic errors, the unit price will govern. If cash discount for prompt payment is offered, it must be clearly shown in the space provided. Discounts for prompt payment will not be considered in making awards. The State reserves the right to reject any and all bids in whole or in part, to waive any informality, and to delete items prior to making an award to the lowest responsive and responsible bidder. The Department of Conservation and Recreation reserves the right to conduct any test it may deem advisable and to make all evaluations. The Commonwealth also reserves the right to reject any or all bids, in whole or in part, to waive informalities and to delete items prior to making the award, whenever it is deemed in the sole opinion of the procuring public body to be in its best interest.

C. eVA ORDERS AND CONTRACTS: The solicitation/contract will result in one purchase order with the applicable eVA transaction fee assessed for each order.

D. BID ACCEPTANCE PERIOD: Any bid in response to this solicitation shall be valid for (60) days. At the end of the (60) days the bid may be withdrawn at the written request of the bidder. If the bid is not withdrawn at that time it remains in effect until an award is made or the solicitation is canceled.

E. BID PRICING: Bid shall be in the form of a firm all-inclusive price for the complete job.

F. CONTRACTOR REGISTRATION: If a contract for construction, removal, repair or improvement of a building or other real property is for $120,000 or more, or if the total value of all such contracts undertaken by bidder/offeror within any 12-month period is $750,000 or more, the bidder/offeror is required under Title 54.1-1100, Code of Virginia (1950), as amended, to be licensed by the State Board of Contractors a “CLASS A CONTRACTOR.” If such a contract is for $10,000 or more but less than $120,000, or if the total value of all such contracts undertaken by bidder/offeror within any 12-month period is $150,000 or more, but less than $750,000 or more, the bidder is required to be licensed as a “CLASS B CONTRACTOR.” If such a contract is over $1,000 but less than $10,000, or if the contractor does less than $150,000 in business in a 12-month period, the bidder is required to be licensed as a “CLASS C CONTRACTOR.” The board shall require a master tradesmen license as a condition of licensure for electrical, plumbing and heating, ventilation and air conditioning contractors. The bidder/offeror shall place on the outside of the envelope containing the bid/proposal and shall place in the bid/proposal over his signature whichever of the following notations is appropriate, inserting his contractor license number:

Licensed Class A Virginia Contractor No. _______________Specialty _______________ Licensed Class B Virginia Contractor No. _______________Specialty _______________ Licensed Class C Virginia Contractor No. _______________Specialty _______________

If the bidder/offeror shall fail to provide this information on his bid/proposal or on the envelope containing the bid/proposal and shall fail to promptly provide said contractor license number to the Commonwealth in writing when requested to do so before or after the opening of bids/proposals, he shall be deemed to be in violation of § 54.11115 of the Code of Virginia (1950), as amended, and his bid/proposal will not be considered.

If a bidder/offeror shall fail to obtain the required license prior to submission of his bid/proposal, the bid/proposal shall not be considered.

G. DELIVERY AND STORAGE: It shall be the responsibility of the contractor to make all arrangements for delivery, unloading, receiving and storing materials in the building during installation. The owner will not assume any responsibility for receiving these shipments. Contractor shall check with the owner and make necessary arrangements for security and storage space in the building during installation.

H. EXTRA CHARGES NOT ALLOWED: The bid price shall be for complete and shall include all applicable mobilization and labor charges; extra charges will not be allowed.

I. eVA ORDERS AND CONTRACTS: The solicitation/contract will result in one (1) purchase order with the applicable eVA transaction fee assessed for each order.

J. FINAL INSPECTION: At the conclusion of the work, the contractor shall demonstrate to the authorized owner’s representative that the work is fully operational and in compliance with contract specifications and codes. Any deficiencies shall be promptly and permanently corrected by the contractor at the contractor’s sole expense prior to final acceptance of the work.

K. INSPECTION OF JOB SITE: My signature on this solicitation constitutes certification that I have inspected the job site and am aware of the conditions under which the work must be accomplished. Claims, as a result of failure to inspect the job site, will not be considered by the Commonwealth.

L. eVA BUSINESS-TO-GOVERNMENT VENDOR REGISTRATION, CONTRACTS, AND ORDERS: The eVA Internet electronic procurement solution, web site portal www.eVA.virginia.gov, streamlines and automates government purchasing activities in the Commonwealth. The eVA portal is the gateway for vendors to conduct business with state agencies and public bodies. All vendors desiring to provide goods and/or services to the Commonwealth shall participate in the eVA Internet e-procurement solution by completing the free eVA Vendor Registration. All bidders must register in eVA and pay the Vendor Transaction Fees specified below; failure to register will result in the bid/proposal being rejected.

Vendor transaction fees are determined by the date the original purchase order is issued and the current fees are as follows:

1. For orders issued July 1, 2014, and after, the Vendor Transaction Fee is:

0. DSBSD-certified Small Businesses: 1%, capped at $500 per order.

0. Businesses that are not DSBSD-certified Small Businesses: 1%, capped at $1,500 per order.

1. Refer to Special Term and Condition “eVA Orders and Contracts” to identify the number of purchase orders that will be issued because of this solicitation/contract with the eVA transaction fee specified above assessed for each order.

For orders issued prior to July 1, 2014, the vendor transaction fees can be found at www.eVA.virginia.gov.

The specified vendor transaction fee will be invoiced, by the Commonwealth of Virginia Department of General Services, typically within 60 days of the order issue date. Any adjustments (increases/decreases) will be handled through purchase order changes.

M. E-VERIFY PROGRAM: Pursuant to Code of Virginia, §2.2-4308.2., any employer with more than an average of 50 employees for the previous 12 months entering into a contract in excess of $50,000 with any agency of the Commonwealth to perform work or provide services pursuant to such contract shall register and participate in the E-Verify program to verify information and work authorization of its newly hired employees performing work pursuant to such public contract. Any such employer who fails to comply with these provisions shall be debarred from contracting with any agency of the Commonwealth for a period up to one year. Such debarment shall cease upon the employer’s registration and participation in the E-Verify program. If requested, the employer shall present a copy of their Maintain Company page from E-Verify to prove that they are enrolled in E-Verify.

N. FEDERALLY IMPOSED TARIFFS: In the event that the President of the United States, the United States Congress, Customs and Border Protection, or any other federal entity authorized by law, imposes an import duty or tariff (a “tariff”), on an imported good that results in an increase in contractor’s costs to a level that renders performance under the Agreement impracticable, the Commonwealth may agree to an increase to the purchase price for the affected good. No increase in purchase price may exceed 25% of the additional tariff imposed on the goods imported or purchased by the contractor that are provided to the Commonwealth under this Agreement.

Prior to the Commonwealth agreeing to a price increase pursuant to this Section, the contractor must provide to the Commonwealth, the following documentation, all of which must be satisfactory to the Commonwealth:

- evidence demonstrating: (i) the unit price paid by contractor as of the date of award for the good or raw material used to furnish the goods to the Commonwealth under this Agreement, (ii) the applicability of the tariff to the specific good or raw material, and (iii) contractor’s payment of the increased import duty or tariff (either directly or through an increase to the cost paid for the good or raw material). The evidence submitted shall be sufficient in detail and content to allow the Commonwealth to verify that the tariff is the cause of the price change.

- a certification signed by contractor that it has made all reasonable efforts to obtain the good or the raw materials comprising the good procured by the Commonwealth at a lower cost from a different source located outside of the country against which the tariff has been imposed.

- a certification signed by contractor that the documentation, statements, and any other evidence it submits in support of its request for a price increase under this Section are true and correct, and that the contractor would otherwise be unable to perform under this Agreement without such price increase.

- as requested by the Commonwealth, written instructions authorizing the Commonwealth to request additional documentation from individuals or entities that provide the good or the raw materials to verify the information submitted by contractor.

If the Commonwealth agrees to a price increase pursuant to this Section, the parties further agree to add the following terms to this Agreement:

- During the Term and for five (5) years after the termination of this Agreement, contractor shall retain, and the Commonwealth and its authorized representatives shall have the right to audit, examine, and make copies of, all of contractors books, accounts, and other records related to this Agreement and contractor’s costs for providing goods to the Commonwealth, including, but not limited to those kept by the contractor’s agents, assigns, successors, and subcontractors.

- Notwithstanding anything to the contrary in this Agreement, the Commonwealth shall have the right to terminate this Agreement for the Commonwealth’s convenience upon 15 days’ written notice to contractor.

In the event the import duty or tariff is repealed or reduced prior to termination of this Agreement, the increase in the Commonwealth’s contract price shall be reduced by the same amount and adjusted accordingly.

- Any material misrepresentation of fact by contractor relating in any way to the Commonwealth’s payment of additional sums due to tariffs shall be fraud against the taxpayers of the Commonwealth and subject contractor to treble damages pursuant to the Virginia Fraud Against Taxpayers Act.

O. GUARANTEE OF WORK:

1. Except as otherwise specified, all work shall be guaranteed by the contractor against defects resulting from the use of inferior materials, equipment, or workmanship for one (1) year from the date of final acceptance of the entire project by the owner in writing. Equipment and facilities, which have seasonal limitations on their operation, shall be guaranteed for one (1) full year from the date of seasonally appropriate tests and acceptance, in writing, by the owner.

2. If, within the guarantee period, defects are noticed by the owner which require repairs or changes in connection with the guaranteed work, those repairs or changes being in the opinion of the owner rendered necessary as the result of the use of materials, equipment or workmanship, which are defective, or inferior or not in accordance with the terms of the contract, then the contractor shall, promptly upon receipt of notice from the owner, such notice being given not more than two weeks after the guarantee period expires, and without expense to the owner:

a. Place in satisfactory condition in every particular all of such guaranteed work and correct all defects therein.

b. Make good all damage to the structure, site, equipment, or contents thereof, which is the result of the use of materials, equipment, or workmanship which are inferior, defective, or not in accordance with the terms of the contracts; and

c. Make good any work, materials, equipment, contents of structures, and/or disturbance of the site in fulfilling any such guarantee.

d. In any case, where in fulfilling the requirements of the contract or any guarantee embraced in or required thereby, the contractor disturbs any work guaranteed under contract, he shall restore such work to a condition satisfactory to the owner and guarantee such restored work to the same extent as it was guaranteed under such other contract.

e. If the contractor, after notice, fails to proceed promptly to comply with the terms of the guarantee, the owner may have the defects corrected and the contractor and his surety shall be liable for all expense incurred.

f. All special guarantees applicable to definite parts of the work that may be stipulated in the specifications or other papers forming a part of the contract shall be subject to the term of this section during the first year of the life of such special guarantee.

g. Nothing contained in this section shall be construed to establish a period of limitation with respect to any other obligation which the contractor might have under the contract documents, including liability for defective work under Section 17 of these additional terms and conditions. This paragraph relates only to the specific obligation of the contractor contained in this section to correct the work and does not limit the time within which his obligation to comply with the contract documents may be sought to be enforced, nor of the time within which proceedings may be commenced to establish the contractor’s liability with respect to his other obligations under this contract.

h. In the event the work of the contractor is to be modified by another contractor, either before or after the final inspection, the first contractor shall remain responsible in all respects under the guarantee of work and under any other warranties provided in the contract or by law. However, the contractor shall not be responsible for any defects in material or workmanship introduced by the contractor modifying its work. Both the first contractor and the contractor making the modifications shall each be responsible solely for the work done by each. The contractor modifying the earlier work shall be responsible for any damage to or defect introduced into the work which he is modifying. If any contractor shall claim that another contractor has introduced defects of materials and/or workmanship into the work of the first, it shall be the burden of the contractor making the claim to clearly demonstrate the nature and extent of such introduced defects and the responsibility of the other contractor. Any contractor modifying the work of another shall have the same burden if he asserts defects to have been caused by the contractor whose work he is modifying.

P. PRIME CONTRACTOR RESPONSIBILITIES: The contractor shall be responsible for completely supervising and directing the work under this contract and all subcontractors that he may utilize, using his best skill and attention. Subcontractors who perform work under this contract shall be responsible to the prime contractor. The contractor agrees that he is as fully responsible for the acts and omissions of his subcontractors and of persons employed by them as he is for the acts and omissions of his own employees.

Q. PROTECTION OF PERSONS AND PROPERTY:

a. The contractor expressly undertakes, both directly and through its subcontractor(s), to take every precaution at all times for the protection of persons and property which may come on the building site or be affected by the contractor’s operation in connection with the work.

b. The contractor shall be solely responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the work.

c.The provisions of all rules and regulations governing safety as adopted by the Safety Codes Commission of the Commonwealth of Virginia, issued by the Department of Labor and Industry under Title 40.1 of the Code of Virginia shall apply to all work under this contract.
d.The contractor shall continuously maintain adequate protection of all his work from damage and shall protect the owner’s property from injury or loss arising in connection with this contract. He shall make good any such damage, injury, or loss, except such as may be directly due to errors in the contract documents or caused by agents or employees of the owner. He shall adequately protect adjacent property to prevent any damage to it or loss of use and enjoyment by its owners. He shall provide and maintain all passageways, guard fences, lights, and other facilities for protection required by public authority, local conditions, any of the contract documents or erected for the fulfillment of his obligations for the protection of persons and property.
e.In an emergency affecting the safety or life of persons or of the work, or of the adjoining property, the contractor, without special instruction or authorization from the owner, shall act, at his discretion, to prevent such threatened loss or injury. Also, should he, to prevent threatened loss or injury, be instructed or authorized to act by the owner, he shall so act immediately, without appeal. Any additional compensation or extension of time claimed by the contractor on account of any emergency work shall be determined as provided by paragraph O, of the General Terms and Conditions.

R. SUBCONTRACTS: No portion of the work shall be subcontracted without prior written consent of the purchasing agency. In the event that the contractor desires to subcontract some part of the work specified herein, the contractor shall furnish the purchasing agency the names, qualifications and experience of their proposed subcontractors. The contractor shall, however, remain fully liable and responsible for the work to be done by its subcontractor(s) and shall assure compliance with all requirements of the contract.

S. USE OF PREMISES AND REMOVAL OF DEBRIS:

a.The contractor shall:
(1)Perform his contract in such a manner as not to interrupt or interfere with the operation of any existing activity on the premises or with the work of any contractor;
(2)Store his apparatus, materials, supplies, and equipment in such orderly fashion at the site of the work as will not unduly interfere with the progress of his work or the work of any other contractor; and
(3)Place upon the work or any part thereof only such loads as are consistent with the safety of that portion of the work.
b.The contractor expressly undertakes, either directly or through his subcontractor(s), to effect all cutting, filling, or patching of his work required to make the same conform to the drawings and specifications, and, except with the consent of the owner, not to cut or otherwise alter the work of any other contractor. The contractor shall not damage or endanger any portion of the work or premises, including existing improvements, unless called for by the contract.
c.The contractor expressly undertakes, either directly or through his subcontractor(s), to clean up frequently all refuse, rubbish, scrap materials, and debris caused by his operations, to the end that at all times the site of the work shall present a neat, orderly, and workmanlike appearance. No such refuse, rubbish, scrap material, and debris shall be left within the completed work nor buried on the building site but shall be removed from the site and properly disposed of in a licensed landfill or otherwise as required by law.
d.The contractor expressly undertakes, either directly or through his subcontractor(s), before final payment, to remove all surplus material, false work, temporary structures, including foundations thereof, plants of any description and debris of every nature resulting from his operations and to put the site in a neat, orderly condition; to thoroughly clean and leave reasonably dust free all finished surfaces including all equipment, piping, etc., on the interior of all buildings included in the contract; and to thoroughly clean all glass installed under the contract including the removal of all paint and mortar splatters and other defacements. If a contractor fails to clean up at the completion of the work, the owner may do so and charge for costs thereof to the contractor.
e.During and at completion of the work, the contractor shall prevent site soil erosion, the runoff of silt and/or debris carrying water from the site, and the blowing of debris off the site in accordance with the applicable requirements and standards of the Virginia Erosion and Sediment Control Handbook, latest edition, and of the contract documents.
f.The contractor shall not operate or disturb the setting of any valves, switches or electrical equipment on the service lines to the building except by proper previous arrangement with the owner. The contractor shall give ample advance notice of the need for cut offs which will be scheduled at the convenience of the owner.

T. WARRANTY (COMMERCIAL): The contractor agrees that the goods or services furnished under any award resulting from this solicitation shall be covered by the most favorable commercial warranties the contractor gives any customer for such goods or services and that the rights and remedies provided therein are in addition to and do not limit hose available to the Commonwealth by any other clause of this solicitation. A copy of this warranty should be furnished with the bid.

U. WORK SITE DAMAGES: Any damage to existing utilities, equipment or finished surfaces resulting from the performance of this contract shall be repaired to the Commonwealth’s satisfaction at the contractor’s expense.

VI. METHOD OF PAYMENT: The Contractor shall invoice complete after completion of work or shipment of goods approved by Contact. Payment will be made under the Commonwealth of Virginia payment terms and conditions. Net 30.

VII. ATTACHMENTS:

A. Vendor Data Sheet B. Pricing List C. General Terms and Conditions D. Attachment D-Photos image1.png