PWS for 9700 Area Rock Crushing Services .pdf
PDF 244 KB Posted
- Attached to
- Concrete Crushing
- Solicitation number
- F4ATA76211A002
About this file
This is a Statement of Work (SOW) for concrete crushing services at Tyndall Air Force Base in Florida, issued by the Air Force Civil Engineer Center dated June 4, 2026.
The contractor shall crush approximately 4,000 cubic yards of concrete and rock material generated from previous blast and pavement evaluation research at the AFCEC/CXA 9700 Area R&D Site. The contractor must furnish, deliver, set up, and operate an industrial crusher capable of producing 3/4" minus recycled concrete aggregate. All crushed concrete shall remain on-site at the 9700 Area for reuse, while non-concrete materials, including reinforcing bars, must be hauled off-site for appropriate disposal. The contractor is responsible for reducing material size if necessary to fit the crushing machine and for moving and loading all concrete materials. The contractor must provide all personnel, equipment, tools, supervision, on-site laboratory capabilities for quality control, and access to restroom facilities. Work must commence no later than 30 days after contract award and be completed within 60 days, with all deliverables received within 90 days of award. The Government will provide the specific site location, access coordination, and necessary site information.
Safety and environmental requirements include full compliance with OSHA regulations, prohibition of live explosive blasting and open burning, coordination of welding permits with the installation fire department, and adherence to Base Environmental requirements including an air general permit (to be prepared and costed by the contractor), maintenance of air quality not exceeding 20% opacity, and identification of fuel types, stormwater management practices, HAZMAT usage, and waste generation in the proposal. Security requirements mandate Local Files Checks for personnel, DBIDS contractor identification cards, AF Form 75 visitor/vehicle passes, and current employee listings with security clearance information. All contractor personnel must comply with the installation's Anti-Terrorism/Force Protection Program.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT
OF
WORK
CONCRETE CRUSHING
9700 AREA
AIR FORCE CIVIL ENGINEER CENTER
TYNDALL AFB, FLORIDA
DATE: 4 JUN 26
TABLE OF CONTENTS
Section Number and Title Page Number
1.0 Description of Services 3
2.0 Deliverables 4
3.0 GOVERNMENT RESPONSIBILITY 4
4.0 Safety and Environmental Requirements 4
5.0 General Information 4
PERFORMANCE WORK STATEMENT
AFCEC/CXA 9700 AREA CONCRETE/ROCK CRUSHING
1. DESCRIPTION OF SERVICES
1.1. The contractor shall crush material (concrete/rock), approximately 4000 cubic yards, at
Tyndall AFB, FL. The materials will be crushed onsite at the AFCEC/CXA, 9700 Area, R&D Site, Tyndall AFB, FL 32403. The referenced concrete and rock material was generated from on-going and previous blast and pavements evaluation research sites.
1.2. SCOPE
1.2.1. The contractor shall:
1.2.1.1. Crush and clean concrete rubble material stockpiled at the 9700 Area and various other locations around TAFB within the contract period to 3/4” minus recycled concrete base materials:
1.2.1.2. Leave crushed concrete on-site at 9700 Area for reuse.
1.2.1.3. Haul all non-concrete materials off-site for appropriate disposal.
1.2.2. The Contractor shall furnish, deliver, set-up, and operate an industrial crusher at the AFCEC/CXA, 9700 Area, Tyndall AFB, FL. The Contractor shall fully operate and provide all personnel, equipment, tools, supervision, and other items necessary for the operation of the crusher.
1.2.3. The crusher must be capable of producing aggregate from stockpiled concrete as a result of infrastructure demolition. The contractor shall separate and dispose of all non-concrete items (i.e., reinforcing bars).
1.2.4. The Contractor shall be responsible to reduce in size the existing provided concrete material if required to fit into their crushing machine. Contractor shall be responsible to move and load all concrete materials into their machinery for crushing operations.
1.2.5. The Contractor shall:
1.2.5.1. Ensure all set-up and installation is properly completed and the plant is operational; meeting all applicable functional specifications.
1.2.5.2. Provide the manpower necessary to operate and maintain the equipment.
1.2.5.3. Provide on-site laboratory capabilities to provide adequate quality control to meet the specified graduation requirements.
1.2.5.4. Provide access to on-site restroom facilities for contractor use during operating hours
1.2.6. The contractor shall:
1.2.6.1. Commence work no later than thirty (30) days after contract awarded.
1.2.6.2. Complete all on-site work within sixty (60) days after commencement of work. This includes equipment set up, crushing operations, and equipment tear down
2. DELIVERABLES
2.1. All items must be received within ninety (90) days from contract award.
2.2. All items will be stockpiled in the same location as the material to be crushed at the 9700
Area, TAFB.
3. GOVERNMENT RESPONSIBILITY The Government will:
3.1. The work site is located in a controlled military installation. As such, access must be coordinated with relevant site personnel.
3.2. Provide the specific location (site) for the crusher plant and produced aggregate.
3.3. Any specific site information deemed necessary to complete the plant installation.
4. SAFETY REQUIREMENTS
4.1. All work shall be accomplished in accordance with OSHA regulations which can be reviewed and/or obtained from the U.S. Department of Labor Occupational Safety &
Health Administrations website at Internet address http://www.osha.gov/.
4.2. Live explosive blasting is strictly prohibited.
4.3. Open burning is strictly prohibited.
4.4. Contractor shall coordinate welding permit with the installation fire department prior to commencement of any welding, razing, or cutting operations.
4.5 Base Environmental (325 CES) Requirements
4.5.1 Reporting Requirements
a. In proposal, list Type(s) of Fuel and estimated quantity to be used.
b. In proposal, list Storm water best management practices to be used for this project.
c. In proposal, list any HAZMAT to be used and estimated quantities. If no
HAZMAT, negative reply requested in proposal.
d. In proposal, list types of waste to be generated (oil, lubricants, etc…)
4.5.2 Other Notes
a. An air general permit will be required to be prepared by the contractor. Costs for this item to be included in proposal.
http://www.osha.gov/
b. Air quality at work site can’t exceed 20% opacity.
c. Provide proposed water source and location for dust control in proposal
5. GENERAL INFORMATION
5.1. SECURITY
5.1.1. SUITABILITY INVESTIGATIONS. Personnel working in a
government facility for less than 6 months or working anywhere on Tyndall
AFB property are required to have a Local Files Check. The Unit Security
Manager will coordinate the Background Affidavit (with Pass & ID) and DBIDS
Application– allow 3-5 day process time. A favorable local files check is required to be granted base access.
All contracts prohibit hiring of illegal aliens for base duties and corrective/punitive actions can be taken when violations occur (AFI 63-113, ACC Sup).
5.1.2. PASS AND IDENTIFICATION ITEMS. The contractor shall ensure the following pass and identification items required for contract performance are obtained for employees and non-government owned vehicles:
a. DBIDS, Defense Biometrics Identification System - Contractor Identification Card.
Process a DBIDS Application to obtain a DBIDS contractor ID card (If no network access is required). A DBIDS contractor ID card is required for performance on the installation in a contractor capacity, regardless of alternate base access forms of identification (ex: retired military ID).
b. AF Form 75, Visitor/Vehicle Pass (AFI 31-204): The Service Provider shall adhere to local security policy when appling for short/long term visitors’ passes. Any contractor requesting a pass for more than 3 days will complete a Local Files Check with 325 SFS/Pass & ID.
5.1.3. LISTING OF EMPLOYEES. The contractor shall maintain a current listing of employees. The list shall include employee's name, social security number and level of security clearance or base access (to include if escort privileges are authorized), on company letterhead. The list shall be validated and signed by the company and provided to the COR and Unit Security Manager, and CO upon request, prior to the contract start date. Updated listings shall be provided when an employee's status or information changes.
5.2. ANTI-TERRORISM/FORCE PROTECTION AND TRAINING. Contractor personnel, including subcontractors, must comply with and participate in the installation
AT/FP Program, specifically including the conduct of Random Antiterrorism Measures
(RAM). Anti-Terrorism Training. The AF will provide appropriate Level 1 anti-terrorism training to contractor employees as required for mission requirements. This training shall be requested through the contracting officer or COR. (ATO provided).