Project Statement 19086.pdf

PDF 89 KB Posted

Attached to
472/19086. DCS; MI Reformatory - Steam System Repairs / Rplc
Solicitation number
RFP-171-190000003200-1
Issued by
Michigan

About this file

This is a Project Statement from the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design and Construction Division, requesting professional engineering services for steam system repairs/replacement at the Michigan Reformatory in Ionia, MI. The project requires evaluation and recommendations for repairs/replacement of existing steam and condensate piping systems that serve heating, food service, domestic water, and laundry demands through low- and high-pressure service. The project includes a mandatory pre-proposal meeting on September 26, 2019, at 11:00 AM, with proposals due October 10, 2019, at 2:00 PM EST. The schematic design must be completed within 45-60 days from commencement, with subsequent contract phases for Final Design and Construction Administration services potentially following.

The total project funding is authorized at $1.0M, which must cover all project commitments including professional fees, construction, contingency, and abatement. Proposals must be uploaded to SIGMA VSS, with attachments limited to 6mb each. The project requires compliance with all federal, state, and local codes, standards, and regulations, including those administered by EPA, OSHA, DOT, DCH, DEQ, DNR, and MIOSHA. A LEIN check is mandatory for all contractor/vendor representatives attending the pre-bid walk-through meeting.

View the file

Other files

File Type Posted
RFP 19086.pdf PDF
SAMPLE PSC Contract Billable Rate (Rev 1902).pdf PDF
LEIN Request 19086.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0427 (R 4/19)

PROJECT STATEMENT

STATE OF MICHIGAN

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration

Design and Construction Division 3111 West St. Joseph Street

Lansing, Michigan 48909

FILE NUMBER

472/19086.DCS

ACCOUNTING TEMPLATE

472RMIMaintProj

PROPOSAL DUE DATE

Thursday, October 10, 2019, at 2:00 p.m., EST

CLIENT AGENCY

Department of Corrections

PROJECT NAME AND LOCATION

Steam System Repairs/Replacement / Michigan Reformatory PROJECT ADDRESS (if applicable) 1342 W. Main Street, Ionia, MI 48846

CLIENT AGENCY CONTACT

Andrea Stinson / Paul Tefft

TELEPHONE NUMBER

(517) 243-0663 / (616) 527-2500 ext. 2340770

DTMB - DCD PROJECT DIRECTOR

David Sproul

TELEPHONE NUMBER

(517) 284-7917

WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION:

Pre-Proposal Meeting – Thursday, September 26, 2019, beginning at 11:00 AM, at the Michigan Reformatory, Maintenance Building. A tour of the Michigan Reformatory complex will be conducted.

MANDATORY (Check box if Mandatory)

LEIN Check (Department of Corrections ONLY) All contractor / vendor representatives attending Prebid Walk Through Meeting must submit a Vendor / Contractor LEIN Request form). Send the LEIN Request form, filled and signed, by email to Tracy Falor at email address: FalorT@michigan.gov The email “Subject” must include (facility name, project name, date and time of Pre-Bid Walk Through Meeting).

PROJECT DESCRIPTION/SERVICES REQUESTED

The Department of Technology, Management and Budget (DTMB), State Facilities Administration, is requesting professional engineering services to evaluate and recommend the needed repairs/replacement to the existing steam and condensate piping systems within the Michigan Reformatory facility. The current steam system is distributed within the facility through a low- and high-pressure service to meet heating, food service, domestic water, and laundry demands. The professional services will initially commence with an evaluation and development of a condensed Phase 300, Schematic Design, to identify deficiencies, confirm demand loads, and present the recommended scope of work within the construction budget. Subsequent Contract phases for Final Design and Construction Administration services may follow on the completion of the Schematic Design.

Total funding for this project has been authorized at $1.0M. Within this funding allocation all project commitments such as professional fees, construction, contingency and abatement are to be included.

Please NOTE:

• Proposal responses MUST also be uploaded to SIGMA VSS. Please enter the total cost for all phases as bid amount.

• Please remember that individual attachments can be no larger than 6mb.

• If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance. They can be reached by telephone at 888.734.9749 or by email at sigma-procurement-helpdesk@michigan.gov or sigma-vendor@michigan.gov

•• Vendors are reminded to keep our office apprised of SIGMA VSS issues and to include your SIGMA ticket number when communicating with our office. Emailed submissions will need prior DCD approval and will be handled on a case by case basis. Approved emailed submissions MUST be received prior to 2:00 p.m. deadline to be considered.

NIGP CODES

92507, 92567 & 92595

DESIRED SCHEDULE OF WORK

Schematic design completed within 45 to 60 days from the date of commencement.

ACCEPTING RFP QUESTIONS UNTIL: Wednesday, October 2, 2019, at 2:00 p.m., local time mailto:FalorT@michigan.gov mailto:sigma-procurement-helpdesk@michigan.gov mailto:sigma-procurement-helpdesk@michigan.gov mailto:sigma-vendor@michigan.gov

REFERENCE STANDARDS: This project will comply with all codes, standards, regulations, and workers' safety rules that are administered by federal agencies (EPA, OSHA, and DOT), state agencies (DCH, DEQ, DNR, and MIOSHA), and any other local regulations and standards that may apply.

This form is required to be a part of the professional service contract. (Authority: 1984 PA 431) Attachment(s)