Project Requirements Document.pdf

PDF 235 KB Posted

Attached to
Architectural-Engineering Services to Design Generator Federal contract opportunity
Solicitation number
12505B21R0017
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Midwest Area

About this file

This Project Requirements Document and related Request for Qualifications outline requirements for architectural-engineering services to design a new emergency generator and provide optional construction administration services. Key details include:

  • The scope of work involves pre-design, design, bid, and construction administration phases to install a new generator, upgrade existing generators, and modify support systems at the National Centers for Animal Health in Ames, Iowa.

  • The design phase contract is for 238 calendar days, with optional periods to provide bid and construction administration services.

  • Evaluation criteria prioritize professional qualifications, specialized experience designing generators and agricultural research facilities, local knowledge, past performance, and in-house resources.

  • Interested firms must submit Standard Form 330 responses by August 26, 2021. A pre-bid site visit is scheduled for August 11-12, 2021 with registration required by August 10.

  • The estimated construction cost is $2,500,000 with the base bid scope not to exceed $2,250,000. The contract will be a firm fixed price awarded by the USDA Agricultural Research Service.

View the file

Other files for this federal contract opportunity

Other files attached to Architectural-Engineering Services to Design Generator, newest first.
File Type Posted
RFIs.pdf PDF
USDA Construction Permit - Modeling Report - (5-19-21).pdf PDF
SF-30 Amendment 01.pdf PDF
Site Visit Sign In Sheets.pdf PDF
SF-330.pdf PDF
Existing Drawings.pdf PDF
Design A-E Checklist.pdf PDF
242.1m-ARS Design Standards.pdf PDF
Statement of Work.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT REQUIREMENTS DOCUMENT

PRD Page 1of 11

Table of Contents

Section/Title Page

1.0 INTRODUCTION

2.0 CONTRACT PROJECT

3.0 SCOPE OF A-E SERVICES

3.1 Predesign Phase A-E Services

3.2 Design Phase A-E Services

3.3 Bid Phase A-E Services

3.4 Construction Phase A-E Services

3.5 Special Services - Design Review and Value Engineering

3.6 Hazardous Materials and Hazardous Substances Abatement Services:

4.0 RELEVANT DOCUMENTS

5.0 PROJECT SPECIFIC REQUIREMENTS

5.1 Project Summary

5.2 Commissioning

5.3 TELECOMMUNICATIONS

5.4 Physical Security - NA

5.5 Commissioning Plan

5.6 Energy Efficiency - NA

5.7 Facilities for the Handicapped - NA

5.8 Permits

5.9 Site and Landscape Design: - NA

5.10 Erosion and Sediment Control - NA

5.11 Storm Water Management - NA

5.12 Manufacturer Product Names

6.0 PROJECT BUDGET LIMITATION

7.0 PROJECT SUBMITTAL SCHEDULE

8.0 PROJECT CONTACT PERSONS

PRD Page 2of 11

1.0 INTRODUCTION

This Project Requirements document specifies specific Architectural – Engineering (A-E) services to be provided under this order. It provides a schedule for the contract deliverables, relates project budget information, outlines unique project needs, and establishes the distribution list for the submissions.

Refer to the Statement of Work (SOW) for detailed information on A-E’s responsibilities and standard requirements for document submissions

2.0 CONTRACT PROJECT

Project Number: NCAH–FEU #20032

Project Title: Design and Construction Administration Services for New Generator

Project Location: USDA – National Centers for Animal Health 1920 Dayton Ave Ames, IA 50010

3.0 SCOPE OF A-E SERVICES

The specific A-E services to be provided under this task order are summarized below. The A-E shall perform the following tasks marked by an “X” in accordance with the schedules and requirements stipulated herein and the Statement of Work.

3.1 Predesign Phase A-E Services

[ ] Environmental Assessment (EA) [ ] Physical Security Risk Assessment (PSRA) [ ] Investigative Report/Studies [ ] Design Charette [X] Program of Requirements (POR) Development [ ] Boundary Survey [ ] Topographical Survey Services [ ] Geotechnical Engineering Services

3.2 Design Phase A-E Services

[ ] Special Consultant Services [ ] Fire Safety Consultant [ ] Industrial Ventilation Consultant [ ] Laboratory Consultant [ ] Telecommunications Consultant [ ] Physical Security Consultant

[ ] Other: Environmental Consultant___________________

PRD Page 3of 11

[ ] Coordination with Construction Manager at Risk firm [ ] Participation in Value Engineering Session (conducted by DR) [ ] Special Presentation of the project to the research program staff and other interest groups.

[X] Design Progress Meetings:

[X] At Project site or [ ] at Alternate site (Teleconference) [ ] Rendered Perspective [X] Design Submissions (i.e., plans, specifications, cost estimates, analyses and calculations, etc.)

[ ] 15 Percent Submittal [ ] 35 Percent Submittal [X] 50 Percent Submittal [ ] Progress Submittal(s) between 50 Percent and 95 Percent [X] 95 Percent Submittal [X] 100 Percent Submittal [X] Final Turnover

3.3 Bid Phase A-E Services

[X] Solicitation Review [ ] Duplicating, Collating, and Binding Services (Number of Sets __________) [ ] Solicitation Release [X] Pre-Bid Conference [X] Solicitation Amendments [X] Bid Evaluation

3.4 Construction Phase A-E Services

[X] Construction Inspection Services [X] Monitoring and Inspection of Construction

[ ] Daily [ ] Weekly [ ] Biweekly [X] Monthly, [ ] Other:______________________ [ ] Resident Construction Inspector

Schedule:_____________________ [X] Reports of Construction Progress

[ ] Daily [X] Weekly [ ] Biweekly [ ] Monthly [ ] Other: ________________

[ ] Building Commissioning [ ] Payroll Review

PRD Page 4of 11

[X] Record Drawings and Specifications [X] Operation and Maintenance Manuals

[X] Construction Management Services

[X] Preconstruction Conference [X] Construction Contractor Submittals Review [X] Construction Contract Changes and Clarifications [X] Construction Progress Payment and Payroll Review

3.5 Special Services - Design Review and Value Engineering

[ ] Design Review Services [ ] Value Engineering Services

3.6 Hazardous Materials and Hazardous Substances Abatement Services:

[ ] Abatement Services - Identification, Assessment, and Corrective Action Design Phase [ ] Asbestos containing materials [ ] Lead Paint and lead containing materials [ ] Mercury [ ] Polychlorinated Biphenyls (PCBs) [ ] Biological materials [ ] Radiological materials [ ] Abatement Services - Bidding Phase (refer to PR section 3.3 above) [ ] Abatement Services - Construction Phase (refer to PR section 3.4 above)

4.0 RELEVANT DOCUMENTS

The A-E shall use all documents marked by an “X” in preparing the required contract documents. (Note: These documents will be provided separately by the EPM.)

[X] Existing Record Drawings located: _________________________ [ ] Master Plan, dated _____, completed by ____________________ [ ] Feasibility Study, dated _____, completed by _________________ [ ] Investigative Report, dated _____, completed by ______________ [ ] Program of Requirements, dated _____, completed by _________ [X] Design A-E Checklist [ ] Design Review A-E Checklist [X] Statement of Work, Architectural-Engineering Services [ ] Closeout Procedures, Facility Contracts Branch memo of July 1998 [ ] Design Charette Requirements, SAVE Proceeding 1995, John B. Sankey [ ] A-E Commissioning Requirements, July 2003 [ ] Sample POR [ ] Sample Environmental Assessment (EA) [ ] Sample Physical Security Risk Assessment (PSRA) [ ] Pre-performance Checklist s (Greenhouse, Lab HVAC, and Emergency Generator)

PRD Page 5of 11

[ ] Sample Format for Construction Contract Schedule [ ] Sample Report of Construction [ ] ARS Guidance on Commissioning [ ] Sample, Contractor Submitted CPM for Performance Testing, TAB, and

Commissioning [ ] Telecommunications:

[ ] Telecommunications Distribution Design Guidance (under revision) [ ] Sample Data Cabling SOW

[ ] Physical Security [ ] Sample, Security Design Components Narrative [ ] Protecting Ventilation Systems

[ ] Energy Efficiency [ ] Energy Initiatives Guidance (attached)

5.0 PROJECT SPECIFIC REQUIREMENTS

5.1 Project Summary

Background: The National Centers for Animal Health (NCAH) continues to increase its electrical consumption. The emergency generator capacity will need to be expanded to keep up with campus’s peak electrical growth. The existing Building 153 – Generator / Switchgear building was designed to house six generators. Currently, five of the planned six generators are installed.

Additionally, the existing generators’ remote radiators #1, #2, #4, and #5 have had issues with ice accumulation on the radiator coil and fans. This has led to the generators tripping off.

Project Summary:

- Emissionions permitting strategy (to be completed with the POR) o Fill out the initial MD forms o Aleart USDA if further emissions documentaion / emission modeling efforts are required.

- Provide biddable drawings and specifications for installation of the sixth generator. This generator shall be installed in the third bay and will be named generator #3. Specific task include, but are not limited to:

o Connect new generator to existing switch gear o Increase the KW capacity of the existing generators #1, #2, #4 and #5 by an additional 147KW through software upgrades.

o Provide modifications, to the remote radiators #1, #2, #4, and #5 to prevent ice accumulation on the radiator coils and fans.

o Modify Power Management Control System (PMCS) to incorporate the

PRD Page 6of 11 addition of the new generator.

o Modify Johnson Controls building automation system to incorporate the required controls for the addition of the new generator.

o Install instake air gooseneck and dampers.

o Install generator bay exhaust fan and louvers.

o Install generator exhaust stack.

o Install remote radiator, with weather hood.

o All required electrical connections.

o All required piping connections.

o Perform retesting and commissioning of the new generator and all systems altered / impacted during the installation.

- Support the bid process and provide contruction administration support.

- Provide modifications, to the remote radiators #1, #2, #4, and #5 to prevent ice accumulation on the radiator coils and fans.

5.2 Commissioning

A. Design Commissioning is required for this project. The A-E shall provide all services necessary for performance of commissioning in accordance with the requirements described in section 6. 4 of the SOW and the relevant documents specified in PRD section 4.0 above.

B. Construction Commissioning is required for this project. The A-E shall provide all services necessary to insure commissioning is accomplished in accordance with the requirements described in section 8.2.8 of the SOW and the relevant documents specified in PRD section 4.0 above

5.3 TELECOMMUNICATIONS

The telecommunications infrastructure shall be an engineered structured cabling system design conforming to the BICSI (Building Industry Consulting Service International, Inc.) Telecommunications Standards. ARS Telecommunications Distribution Design Guide (TDDG). The ARS TDDG supersedes section 242.1-

6.13.1. It is the A-E's responsibility to assure that the results of the Telecommunications consultation are sufficient and proper to meet the criteria for the design and construction of the project facility.

5.4 Physical Security - NA

5.5 Commissioning Plan

The A-E will develop the Commissioning Specification to include, PRD Page 7of 11

Commissioning of HVAC systems, and all specialty systems, which are required by ARS Guidance on Commissioning. The Commissioning Specifications shall require the Contractor to submit a CPM for pre-performance testing, TAB, start-up, commissioning, substantial completion, etc. ARS has separated commissioning into design and construction tasks. Refer to SOW section 6.4 for design and 8.1.7 for the construction requirements.

5.6 Energy Efficiency - NA

5.7 Facilities for the Handicapped - NA

5.8 Permits

The A-E is responsible for submitting any required application review packages and coordinating all reviews especially with local planning and zoning agencies, as well as local utilities and citizen groups, for obtaining approvals and permits.

City/ Campus Fire Marshal, planning/zoning officials, building inspectors, and bidding permit representatives, etc. shall be initially involved at the investigative stage.

The A-E is responsible for emission permits reqirued by the Iowa Department of Natural Resources.

5.9 Site and Landscape Design: - NA

5.10 Erosion and Sediment Control - NA

5.11 Storm Water Management - NA

5.12 Manufacturer Product Names

When developing the Specifications, the A-E shall use caution when listing actual company or brand names for products such as laboratory casework, greenhouses, etc. The specifications should be easy enough to interpret, as to avoid any protests by manufacturers over “proposed equal” regarding their product.

6.0 PROJECT BUDGET LIMITATION

6.1 The estimated construction cost of this project is limited to the amount of funds programmed for the work, and shall not exceed $2,500,000 at FY2023. This figure will be bid protected. The base bid scope shall not exceed $ 2,250,000 (90%) Percent of the Estimated Construction Cost (ECC). Additive bid items will be 5 to 10 percent of the ECC with at least one high value additive. The base bid and all additives must not exceed 100 percent of the ECC.

PRD Page 8of 11

6.2 The scope of the base bid shall be developed to provide a complete and operational facility. Additive bid items may be the result of specific instructions from the EPM or may be recommended design additives by the A-E. When additive bid items are used, the A-E shall ensure that such items are clearly indicated on the drawings and in the specifications, cost estimates, bid schedules, and construction performance times. The final cost estimates for the base bid and additive bid items shall not exceed the Estimated Construction Cost

(ECC).

6.3 In developing the Schedule of Items with additive or option line items, the value of the base line item may be 90 to 95 percent of the ECC with at least one additive or option line item valued at 5 percent of the ECC. Due to construction market uncertainty, it is highly desirable to have the sum of all additive or option line items approach 10 percent of the ECC. In all cases, the base line item and all additive or option items must not exceed 100 percent of the ECC. (See SOW section 4.4.4.).

6.4 It is incumbent upon the A-E that the project is designed for construction bids within the programmed amount. See Clause 52.236-22 "Design within Funding Limitations" contained in Section I of the basic contract.

7.0 PROJECT SUBMITTAL SCHEDULE

7.1 The schedule provided herein indicates requirements for each submission and review stage. It is provided for information and direction to the A-E in meeting contract submissions and contract time requirements. Refer to SOW section 4. 4.1. for specific requirements on the submission of construction documents, including electronic format and uploading to the Contracting Opportunities website.

7.2 Within 7 calendar days after the award of the task order, the A-E shall provide the CO a schedule of actual dates in bar chart format for individual submittal and Government review time. The Government requires a minimum of 21 calendar days for review time.

7.3 Any request for time extensions or other deviations from this schedule must be submitted to the

CO in writing. Each request must include specific and detailed reasons in support of the schedule alterations. Only the CO can approve time extensions or other changes to the contract/task order provisions. Approvals for deviations will be at the option of the CO. His/her decision will be final.

7.4 The A-E is advised that the conduct of the work, in a manner that insures compliance with the schedule, is essential to the successful construction completion of this project.

PRD Page 9of 11

Task Stages

Performance Time (Calendar Days) [ ] A-E

[ ] DR

[ ] VE

Government Review Time

Cumulative Total

Pr ed es ig n

[ ] Environmental Assessment Draft -- Final --

[ ] Investigative Report Draft -- -- -- Final -- -- --

[X] Design Charette Final 21 -- 21

[X] POR Draft 21 21 42 Final 21 21 42

[ ] Topographical Survey Final Concurrent with Design Phase [ ] Geotechnical Survey Final Concurrent with Design Phase

De sig n

[ ] Design Submissions [ ] 35% Design Submittal -- -- -- [X] 50% Design Submittal 21 21 42 [X] 95% Design Submittal 21 21 42 [X] 100% Design Submittal 14 21 35 [X] Final Turnover 14 -- 14

Total Calendar Days 238

PRD Page 10of 11

7.5 Project Submittal Schedules:

Copies of all required submittal documents shall be sent directly to the following individuals in the quantity shown. A copy of the A-E’s transmittal letter shall be provided to the CO.

“Electronic” copies in PDF format unless otherwise specified by the Government.

Copies of all required submittal documents shall be sent directly to the following individuals in the quantity shown. A copy of the A-E’s transmittal letter shall be provided to the CO.

Pre- Final Submission

One (1) digital copy (PDF) emailed to Engineering Project Manager, Contracting Officer, and Contracting Officer Representative. Cost Estimate shall be in Excel format

Final Turnover:

Two (2) hard copies, one each, mailed to Administrative Officer and Engineering Project Manager and one (1) digital (provided on USB Flash Drive, PDF, and AutoCAD) copy to Administrative Officer, Project Manager, Contracting Officer, Contracting Officer Representative. Cost Estimate shall be in Excel format.

The Government will generate review comments. Those comments will be submitted to the A-E who will provide responses to all government comments within 10 calendar days of receiving them.

PRD Page 11of 11

8.0 PROJECT CONTACT PERSONS

Name and Address Phone E-Mail Address Contracting Officer

(CO)

Josh Dobereiner

USDA, ARS, AFM, MWAAO

1815 N. University Street Peoria, IL 61604

309-681-6410 josh.dobereiner@usda.gov

Contracting Officer’s Representative

Randy Ferriss

USDA, NCAH

1920 Dayton Ave Ames, Ia 50010

515-520-7088 randy.ferriss@usda.gov

Engineering Project Manager (EPM)

Adam Bunnell

USDA, NCAH

1920 Dayton Ave Ames, Ia 50010

515-337-7769 adam.bunnell@usda.gov

Area Office Engineer

(AOE)

Mindy Leach

USDA, ARS, AFM

1815 N. University Street Peoria, IL 61604

309-681-6410 Mindy.leach@usda.gov

Location Environmental Specialist

Karla Tebben

USDA, NCAH

USDA, NCAH

1920 Dayton Ave Ames, Ia 50010

515-337-7026 karla.k.tebben@aphis.usda.gov

ARS Physical Security Officer (PSO)

Robert Steffes

USDA, NCAH

1920 Dayton Ave Ames, Ia 50010

515-337-6835 robert.a.steffes@aphis.usda.gov

NCAH IT Specialist JC Kruse

USDA, NCAH

1920 Dayton Ave Ames, Ia 50010

515-337-7072 jeremy.c.kruse@usda.gov

Architects and Engineers (designers)

TBD

1.0 INTRODUCTION
2.0 CONTRACT PROJECT
3.0 SCOPE OF A-E SERVICES
3.1 Predesign Phase A-E Services
3.2 Design Phase A-E Services
3.3 Bid Phase A-E Services
3.4 Construction Phase A-E Services
3.5 Special Services - Design Review and Value Engineering
3.6 Hazardous Materials and Hazardous Substances Abatement Services:
4.0 RELEVANT DOCUMENTS
5.0 PROJECT SPECIFIC REQUIREMENTS
5.1 Project Summary
5.2 Commissioning
5.3 TELECOMMUNICATIONS
5.4 Physical Security - NA
5.5 Commissioning Plan
5.6 Energy Efficiency - NA
5.7 Facilities for the Handicapped - NA
5.8 Permits
5.9 Site and Landscape Design: - NA
5.10 Erosion and Sediment Control - NA
5.11 Storm Water Management - NA