This is a Project Manual and contract document set for wastewater treatment plant improvements being undertaken by Harris County Municipal Utility District No. 345 in Harris County, Texas, with engineering services provided by Pape-Dawson. The work consists of replacing Unit No. 2 drain pipe, replacing the Unit No. 2 Clarifier Mechanism, conducting structural patching and repairs to clarifier cracks via epoxy injection, blast and recoating above-ground piping and fittings, and removing and relocating airlift pump piping. The project includes nine construction drawing sheets covering site plans, clarifier details, mechanical demolition and replacement exhibits, and related specifications. Sealed electronic bids are due on October 6, 2026, at 2:00 p.m. local time via the CivCastUSA website, with bid opening conducted electronically and publicly viewable via Microsoft Teams. No pre-bid conference is scheduled. Contractors must achieve substantial completion within 120 calendar days maximum and final completion within 150 calendar days maximum from the Notice to Proceed. The contract will be awarded to the bidder whose proposal is determined to be in the best interests of the project, with the Owner reserving the right to reject any or all bids.
Bid security requirements are 10 percent for bids under $250,000 and 5 percent for bids of $250,000 or more, submitted in the form of a surety bond. Bidders must submit performance bonds, payment bonds, and maintenance bonds equal to 100 percent, 100 percent, and 50 percent of the contract price, respectively. Retainage is held at 10 percent of completed work until 50 percent of the work is completed, after which remaining progress payments may be made in full. The successful bidder must execute the agreement and provide required bonds and insurance certificates within 10 calendar days of receiving the Notice of Award. Economic disincentives of $500 per calendar day apply for each day the work remains uncompleted after the specified time limit. The contract is subject to Texas prevailing wage rate requirements, and bidders are required to verify compliance with various Texas Government Code requirements, including the Interested Party Disclosure Act (TEC Form 1295), anti-boycott provisions, and anti-terrorism representations. Contractor qualifications and proposed subcontractors are subject to Owner approval prior to award.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DOCUMENTS &
SPECIFICATIONS
FOR
WASTEWATER TREATMENT
PLANT IMPROVEMENTS –
PHASE II
TO SERVE
HARRIS COUNTY MUNICIPAL
UTILITY DISTRICT NO. 345
Project No. 14041425-019 Contract No. 01
SEPTEMBER 2026
14041425-019 00001- 1
CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS
FOR THE CONSTRUCTION OF
WASTEWATER TREATMENT PLANT IMPROVEMENTS – PHASE II
TO SERVE
HARRIS COUNTY MUNICIPAL UTILITY DISTRICT NO. 345
LOCATED IN
HARRIS COUNTY, TEXAS
PAPE DAWSON PROJECT NO. 14041425-019
Seals & Certifications
Pape-Dawson
Texas P.E. Board Firm Registration No. 470
JOHN LACY, P.E.
SEPTEMBER, 2026
The Professional Engineer whose signed and dated seal appears above was in responsible charge of preparing the following sections of the Contract Documents, which are fully identified by Section Number and Title in the TABLE OF CONTENTS:
01005, 01045, 01292, 01330, 01340, 01350, 01410, 01415, 01500, 01550, 01560, 01600, 01640, 01660, 01710, 01780, 01782, 01810, 02030, 02050, 02055, 02100, 02501, 02502, 02506, 02735, 09906, 11350, 15012, 15013, 15064, 15140
14041425-019 00001- 1
CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS
FOR THE CONSTRUCTION OF
WASTEWATER TREATMENT PLANT IMPROVEMENTS – PHASE II
TO SERVE
LOCATED IN
HARRIS COUNTY, TEXAS
PAPE DAWSON PROJECT NO. 14041425-019
Seals & Certifications
Texas P.E. Board Firm Registration No. 470 Cristian Aparacio, P.E., ENVE SP September, 2026
The Professional Engineer whose signed and dated seal appears above was in responsible charge of preparing the following sections of the Contract Documents, which are fully identified by Section Number and Title in the TABLE OF CONTENTS:
03133, 03600, 05501
09/08/26
WWTP IMPROVEMENTS PH. II – HARRIS COUNTY MUD 345
TABLE OF CONTENTS
00110 - 1
DIVISION 00 – BIDDING AND CONTRACT REQUIREMENTS
00100 INVITATION TO BIDDERS
00115 LIST OF DRAWING SHEETS
00200 INSTRUCTIONS TO BIDDERS
00200C NOTICE OF AWARD
00410 BID FORM
00520 AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT
00520A CONTRACT PROVISIONS
00610 PERFORMANCE BOND
00615 PAYMENT BOND
00620 MAINTENANCE BOND
00700 STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT
00750 SUPPLEMENTARY CONDITIONS – INSURANCE
00800 SUPPLEMENTARY CONDITIONS – GENERAL
00810 ADDITIONAL CONDITIONS
00820 WAGE RATE RESOLUTION
TEXAS SALES AND USE TAX EXEMPTION CERTIFICATION
DIVISION 01 – GENERAL REQUIREMENTS
01005 SUMMARY OF WORK
01045 COORDINATION WITH OWNER’S OPERATIONS
01292 SCHEDULE OF VALUES
01330 SUBMITTALS
01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
01350 CONSTRUCTION SCHEDULE
01410 TESTING LABORATORY SERVICES
01415 OBSERVATION OF CONSTRUCTION
01500 TEMPORARY FACILITIES AND CONTROLS
01550 BARRICADES AND WARNING DEVICES
01560 TRAFFIC SIGNS
01600 MATERIALS AND EQUIPMENT
01640 MANUFACTURERS’ SERVICES
01660 CLEANING AND ADJUSTING
01710 PROJECT RECORD DOCUMENTS
01780 CONTRACT CLOSEOUT
01782 OPERATIONS AND MAINTENANCE DATA
01810 EQUIPMENT TESTING AND FACILITY STARTUP
TECHNICAL SPECIFICATIONS
DIVISION 02 – SITE WORK
02030 CUTTING AND CONNECTING WORK
02050 DEMOLITION ON WATER/WASTEWATER FACILITY SITES
02055 REMOVING AND REPLACING MISCELLANEOUS EXISTING STRUCTURES
02100 WASTE MATERIAL DISPOSAL
00110 - 2
02501 DUCTILE IRON PIPE AND FITTINGS
02502 STEEL PIPE AND FITTINGS
02506 POLYVINYL CHLORIDE PIPE
02735 BYPASS PUMPING
DIVISION 03 – CONCRETE
03133 CONCRETE REPAIR & STRENGTHENING
03600 STRUCTURAL GROUT
DIVISION 05 – METALS
05501 METAL FABRICATIONS
DIVISION 09 – FINISHES
09906 PROTECTIVE COATING SYSTEMS – WASTEWATER FACILITIES
DIVISION 11 – EQUIPMENT
11350 SECONDARY CLARIFIER - PLOW TYPE, CENTER PIER
DIVISION 15 – MECHANICAL
15012 PIPING AND FITTINGS FOR WASTEWATER TREATMENT PLANTS
15013 VALVES FOR WASTEWATER TREATMENT PLANTS
15064 POLYVINYL CHLORIDE PIPE LESS THAN 4” IN DIAMETER
15140 PIPE HANGERS, SUPPORTS, AND RESTRAINTS
APPENDIX – FORMS SPECIFIED IN THE CONTRACT
CONTRACTOR’S STATEMENT OF QUALIFICATIONS
AFFIDAVIT OF BILLS PAID
TEXAS CONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
TEXAS CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
TEXAS UNCONDITONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
TEXAS UNCONDITONAL WAIVER AND RELEASE ON FINAL PAYMENT
Notes:
A. The General Conditions of this Contract is the Engineers Joint Contract Documents Committee (EJCDC) Document C-700 "Standard General Conditions of the Construction Contract", 2018 Edition, hereinafter referred to as the "General Conditions".
B. If a discrepancy occurs between the Technical Specifications in these Contract Documents and the technical specifications of the jurisdiction where the Work is being performed, the more stringent shall take precedence.
00110 - 3
* END *
\\Pape-Dawson.Com\Hou-Pd\Projects\400\HOU-Standards\Construction\Contracts\2 NON-ABHR\002 TOC.Doc
14041425-019 00100 - 1
SECTION 00100
INVITATION TO BIDDERS
OWNER Harris County Municipal Utility District No. 345 c/o Ms. Kate Henderson Schwartz, Page & Harding 1300 Post Oak Blvd., Ste. 2400 Houston, Texas 77056
ENGINEER Pape-Dawson 2107 CityWest Blvd., 3rd Floor Houston, Texas 77042 Attn: Esteban Gonzalez, P.E.
Telephone: 713-428-2400
PROJECT/WORK Wastewater Treatment Plant Improvements – Phase II to serve Harris
County Municipal Utility District No. 345
BID OPENING TIME Tuesday, October 6, 2026 @ 2:00 p.m.
Sealed electronic bids, addressed to HARRIS COUNTY MUNICIPAL UTILITY DISTRICT NO. 345 will be electronically received on the CivCastUSA Website (www.CivCastUSA.com) until 2:00 p.m. local time, Tuesday, October 6, 2026. Bidders may view the public opening of sealed Bids via Microsoft Teams by calling 210-926-0892 and use the Conference ID: 338 752 64#. The Apparent Low Bidders will be automatically generated and posted for furnishing all plan, labor, material and equipment and performing all work required for the construction of WASTEWATER TREATMENT PLANT IMPROVEMENTS TO SERVE HARRIS COUNTY MUNICIPAL UTILITY DISTRICT NO. 345. A pre-bid conference will not be held. Plans, specifications and bid documents may be viewed and downloaded free of charge (with the option to purchase hard copies) at the CivCastUSA Website. Reproduction charges will apply according to CivCastUSA rates.
The Owner reserves the right to reject any or all PROPOSALS and to waive irregularities in the bidding. In case of ambiguity or lack of clearness in stating the prices in the PROPOSAL, the Owner reserves the right to consider the most advantageous construction thereof or to reject the PROPOSAL.
– END OF SECTION –
http://www.civcastusa.com/
14041425-019 00115 - 1
SECTION 00115
LIST OF DRAWING SHEETS
WASTEWATER TREATMENT PLANT IMPROVEMENTS – PHASE II TO SERVE HARRIS
COUNTY MUD NO. 345
SHEET
DESCRIPTION NO.
COVER SHEET 1 OF 9
CONSTRUCTION NOTES 2 OF 9
OVERALL AREA MAP 3 OF 9
PROPOSED SITE PLAN 4 OF 9
CLARIFIER PLAN VIEW 5 OF 9
CLARIFIER SECTION VIEW & DETAILS 6 OF 9
MECHANICAL DEMOLITION & REPLACEMENT EXHIBITS – SHEET 1 OF 3 7 OF 9
MECHANICAL DEMOLITION & REPLACEMENT EXHIBITS – SHEET 2 OF 3 8 OF 9
MECHANICAL DEMOLITION & REPLACEMENT EXHIBITS – SHEET 3 OF 3 9 OF 9
14041425-019 00200 - 1
SECTION 00200
INSTRUCTIONS TO BIDDERS
ARTICLE 1 – DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the Standard General
Conditions of the Construction Contract (General Conditions) and the Supplementary Conditions.
ARTICLE 2 – COPIES OF BIDDING DOCUMENTS
2.01 Bidding Documents may be viewed and downloaded free of charge (with the option to purchase hard copies) at the CivCastUSA Website (www.CivCastUSA.com). Reproduction charges may apply according to CivCastUSA rates.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
3.01 When requested by either the Owner or Engineer, the apparent most qualified, responsible bidder must submit to Owner, within 5 days of notification of award of the Contract, either (i) a fully completed contractor’s statement of qualification or (ii) a written statement that the most recently submitted contractor’s statement of qualification is accurate, which statement of qualification must be considered in the award of the Contract. Failure to accurately complete the contractor’s statement of qualifications or to timely submit the statement of qualifications will, at Owner’s option, disqualify the bidder from consideration in the award of the Contract. The form of the Contractor’s statement of qualifications is available from the Engineer upon request.
Owner may reject, at Owner’s sole discretion, a bidder’s statement of qualifications if the bidder’s statement of qualifications is not on the form provided. Evidence of out-of-state incorporation to conduct business in the state in which the Work is to be performed, along with state contractor license number, as applicable, must also be provided and is a consideration in the award of the Contract.
ARTICLE 4 – EXAMINATION OF BIDDING DOCUMENTS AND SITE
4.01 Provisions concerning subsurface conditions and other physical conditions, Underground
Facilities, and possible changes in the Bidding Documents due to differing or unanticipated conditions appear in Articles 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning any potentially Hazardous Environmental Conditions at the Site and possible
14041425-019 00200 - 2 changes in the Contract Documents due to any such conditions uncovered or revealed at the Site appear in Article 5.06 of the General Conditions.
4.02 Upon request, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid.
Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.
4.03 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, the other related data identified in the Bidding Documents, and any Addenda;
B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work;
D. carefully study all (if available): (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities), and (2) reports and drawings of Hazardous Environmental Conditions at the Site;
E. consider the information known to Bidder; information commonly known to
Contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs;
F. agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and others at the Site that relate to the Work as indicated in the Bidding Documents;
H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and
14041425-019 00200 - 3
I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
4.04 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
ARTICLE 5 – PRE-BID CONFERENCE
5.01 There will be no pre-bid conference for this project.
ARTICLE 6 – SITE AND OTHER AREAS
6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes to existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
ARTICLE 7 – INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to
Engineer in writing online to the www.CivCastUSA.com system or website. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda, through the www.CivCastUSA.com website. Questions will be received up to 72 hours prior to the time and date for opening of Bids. Addenda, if issued, will be provided 48 hours prior to the time and date for opening bids. No explanation or interpretation of the Contract Documents, other than written addenda, is binding. Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.
ARTICLE 8 – BID SECURITY
8.01 A Bid must be accompanied by a Bid security made payable to Owner. The Bid security required is an amount of 10% if the Bidder’s maximum Bid price is less than $250,000. The Bid security required is an amount of 5% if the Bidder’s maximum Bid price is $250,000 or more. The Bid security shall be in the form of a Bid bond issued by a surety meeting the requirements of Articles
6.01 and 6.02 of the General Conditions. CASHIER CHECKS WILL NOT BE ACCEPTED.
14041425-019 00200 - 4
8.02 The Bid security is a guarantee that the successful bidder will enter into the Contract within 9 days and execute the required Bonds on the forms provided and provide the required insurance certificates and Bonds within 5 days after the date Contract Documents are received by the successful bidder. Bid Securities will be returned to all but the 3 most qualified, responsible bidders within 3 days after opening of Bids, and the latter’s Bid Securities will be returned after complete execution of the Contract Documents. If the successful bidder does not enter the Contract after notice of award, then the bidder’s Bid Security will be forfeited and will be retained by Owner. If the award of the Contract to the successful bidder is canceled or not executed for any reason, the Owner may accept the next lowest bid and proceed with the next lowest qualified bidder.
8.03 The Bid security of other Bidders whom Owner believes do not have a reasonable chance of receiving the award will be returned within 7 days after the Bid opening.
ARTICLE 9 – CONTRACT TIMES
9.01 The number of days within which, or the dates by which (Milestones are to be achieved and) the Work is to be completed and ready for final payment are set forth in the Agreement (Section 00520). All bidders submitting a Bid must accept the Contract Times as a requirement to the Contract Documents.
ARTICLE 10 – ECONOMIC DISINCENTIVES
10.01 Provisions for economic disincentives, if any, are set forth in the Agreement.
ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract, if awarded, will be based on materials and equipment specified or described in the
Bidding Documents. Where materials or equipment are specified by a trade or brand name, it is not the intention of the Owner to discriminate against an equal product or another manufacturer, but to set a definite standard of quality or performance, and to establish an equal basis for the evaluation of the completed Bid Form. In preparing his Bid, the Bidder is expected to include the cost of the item so specified. A Bidder wishing to offer substitute items of equipment or materials for those specified is invited to do so by written request to Engineer explaining the substitutions and any cost savings that would result if the substitute item were accepted by the Owner. Each such request shall conform to the requirements of Article 7.05 and
7.06 of the General Conditions. No item of material or equipment will be considered by Engineer as a substitute or “or-equal” unless written request for approval has been submitted by Bidder.
The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. In some cases, approval of substitute or “or equal” items will be set forth in an Addendum issued to all prospective Bidders.
ARTICLE 12 – PREVAILING WAGE RATE SCALE
12.01 Chapter 2258 of the Texas Government Code provides that any political subdivision of the State of Texas shall ascertain the general prevailing wage rate received by the classes of Workers employed on Projects like this Project and shall specify in the call for bids and in the Contract the minimum wage rates which shall be paid for each type of Worker. This statute further provides
14041425-019 00200 - 5 that the CONTRACTOR or subcontractors shall pay a penalty to the OWNER sixty dollars for each Worker employed for each calendar day or part of the day that the Worker is paid less than the wage rates stipulated in the Contract.
12.02 The OWNER is authorized to withhold from the CONTRACTOR the amount of this penalty from any payment due under the Contract.
12.03 The statute also requires that the CONTRACTOR and subcontractors keep an accurate record of the names and occupations of all persons employed by them in the construction of the Project and to show the actual per diem wages paid to each Worker. These records shall be open to the inspection of the OWNER.
12.04 The minimum wage rates that apply to this Contract are specified in the attachment hereto.
CONTRACTOR and subcontractors shall review and ascertain such wage rates and pay at least such minimum rates.
ARTICLE 13 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS
13.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within 5 days after Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, in which case apparent Successful Bidder shall submit an acceptable substitute, Bidder’s price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
13.02 If the apparent Successful Bidder declines to make any such substitution, Owner may award the
Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or entities. Declining to make the requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Article 7.07 of the General Conditions.
ARTICLE 14 – PREPARATION OF BID
14.01 The Bid Form is included with the Bidding Documents.
14.02 All blanks on the electronic Bid Form shall be completed. Section 004100 shall also be completed and uploaded to the www.CivCastUSA.com website. Discrepancies between the unit
14041425-019 00200 - 6 prices in the electronic Bid Form and the unit prices in Section 00410 will be resolved in favor of the unit prices in the electronic Bid Form. A Bid price shall be indicated for each section, Bid item, alternative, adjustment unit price item, and unit price item listed therein. If no amount is to be included, zeroes or the words “No Bid,” “No Change,” or “Not Applicable” shall be entered in the spaces. No segregated bids or assignments will be considered. Unbalanced bids may be rejected. An “unbalanced” Bid means a Bid containing unit prices that are significantly less than cost for some items and significantly more than cost for others. This may be evidenced by submission of unit price Bid items where the cost is significantly higher/lower than the cost of the same Bid items submitted by other Bidders on the same Project.
14.03 A Bid by a CORPORATION shall be executed in the corporate name by the president or a vice-president (or other corporate officer accompanied by evidence of authority to sign). The corporate seal shall be affixed in the space provided and attested by the secretary or assistant secretary of the corporation. The official address of the corporation shall be shown.
14.04 A Bid by a PARTNERSHIP shall be executed in the partnership name and signed by a partner
(whose title must appear under the signature). The official address of the partnership shall be shown.
14.05 A Bid by a LIMITED LIABILITY COMPANY shall be executed in the name of the firm by a member authorized to sign. The official address of the firm shall be shown.
14.06 A Bid by an INDIVIDUAL shall be executed by the individual with the individual’s name and official address.
14.07 A Bid by a JOINT VENTURE shall be executed by each joint venturer. The official address of the joint venture shall be shown.
14.08 All names shall be typed or printed in ink below the signatures.
14.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form. Any bids not showing all Addenda may be rejected.
14.10 Postal and email addresses and telephone number for communications regarding the Bid shall be shown.
14.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state Contractor license number, if any, shall also be shown on the Bid Form.
ARTICLE 15 – BASIS OF BID
15.01 Unit Price
A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the Bid Form.
14041425-019 00200 - 7
B. The total of all estimated prices will be the sum of the products of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with Article 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
15.02 The Bid price shall include such amounts as the Bidder deems proper for overhead and profit on account of cash allowances, if any, named in the Contract Documents as provided in Article 13.02 of the General Conditions.
15.03 The Bid Form may include Supplemental Items that may be required to complete the Work. If minimum unit prices have been established for Supplemental Items shown on the Bid Form, the bidder may not bid a unit price less than the minimum; however, he may increase the unit price.
If maximum unit prices have been established for Supplemental Items shown on the Bid Form, the bidder may not bid a unit price more than the maximum; however, he may decrease the unit price. When Work covered by Supplemental Items is requested by the Owner or Contractor and approved by the Engineer, payment will be based on the quantity actually constructed and the unit prices in the Bid Form. Award of the Contract will be based on the total amount bid, which may include selected Supplemental and Alternate Bid Items (See Article 22.02 below).
ARTICLE 16 – SUBMITTAL OF BID
16.01 Bids shall be completed electronically on the www.CivCastUSA.com website on the Bid Form provided.
16.02 Bids shall be submitted electronically to the www.CivCastUSA.com website no later than the date and time prescribed in the Advertisement or Invitation to Bid.
16.03 An acceptable Bid shall include the completed on-line Bid Form and any other documents that are required to be uploaded to the www.CivCastUSA.com website. The Bid security is a required upload. Other required uploads may include Section 00410 Bid Form, the List of Subcontractors and the List of Substitutions.
16.04 It is each bidder’s responsibility to deliver its Bid and Bid Security as stated in the Instructions to Bidders before the closing time. The fact that a Bid and a Bid Security were dispatched will not be considered. The Bid and Bid Security must be timely delivered to be considered.
ARTICLE 17 – MODIFICATION AND WITHDRAWAL OF BID
17.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids.
17.02 If within 24 hours after Bids are received, any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a http://www.civcastusa.com/
14041425-019 00200 - 8 material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned.
ARTICLE 18 – OPENING OF BIDS
18.01 Bids will be opened electronically on www.CivCastUSA.com at the time indicated in the
Advertisement or Invitation to Bid and read aloud publicly via a Microsoft Teams Meeting. See Section 00100 Invitation to Bid or the Advertisement for the Teams Meeting telephone no. and meeting ID. The “Apparent Low Bidders” will be automatically generated and posted on the www.CivCastUSA.com website for furnishing all plant, labor, material and equipment and performing all work required for the Project.
ARTICLE 19 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE
19.01 All Bids will remain subject to acceptance for the period stated in Section 00410 Bid Form, but
Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 20 – HOUSE BILL 1295.
20.01 Provision of Texas Ethics Commission Form 1295 (“TEC Form 1295”) pursuant to Texas
Government Code § 2252.908 (the “Interested Party Disclosure Act” or the “Act”): Unless bidder is exempt from such requirements pursuant to Texas Government Code Section2252.908(c)(4), the District may not award the contract to a bidder unless the bidder has provided to the District a completed and signed TEC Form 1295 which has been assigned a certificate number by the Texas Ethics Commission (the “TEC”). Pursuant to the rules prescribed by the TEC, the TEC Form 1295 must be completed online through the TEC’s website, assigned a certificate number, printed, signed, and provided to the District. The TEC Form 1295 may accompany the bid or may be submitted separately, but must be provided to the District prior to the award of the contract. For purposes of completing the TEC Form 1295, the entity’s name is Harris County Municipal Utility District No. 345; the 14041425-019; and the description of goods and services is Wastewater Treatment Plant Improvements – Phase II to serve Harris County Municipal Utility District No.
345. Neither the District nor its consultants have the ability to verify the information included in a TEC Form 1295, and neither have an obligation nor undertake responsibility for advising any bidder with respect to the proper completion of the TEC Form 1295.
ARTICLE 21 – CONFLICTS OF INTEREST
21.01 Effective January 1, 2006, Chapter 176 of the Texas Local Government Code (“Chapter 176”) mandates the disclosure of certain items by contractors doing business with or proposing to do business with local government entities, including municipal utility districts, road utility districts, road improvement districts, levee improvement districts, drainage districts, water control and improvement districts, bayou improvement districts, regional water authorities, fresh water supply districts, management districts, tax increment reinvestment zones, development authorities, etc.
21.02 Bidders should review Chapter 176 with their attorney and, if required, Bidder shall provide the TEC completed FORM CIQ with their Bid. The following is a list of the Board of Directors of
14041425-019 00200 - 9
Owner to facilitate Bidder’s compliance with Chapter 176.
Board of Directors Harris County Municipal Utility District No. 345
President Everett M. Dalton Vice President Keith Wright Secretary Arron Pichon Assistant Secretary David Vinzant Director Michael Fitzgerald
ARTICLE 22 – AWARD OF CONTRACT
22.01 Owner reserves the right to reject any or all Bids, including without limitation, non-conforming, non-responsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to not be responsible.
Owner may also reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder.
22.02 The Owner reserves the right to award the project based on any combination of items in the Bid
Form.
22.03 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.
22.04 In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
22.05 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as provided in the Supplementary Conditions.
22.06 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities to perform the Work in accordance with the Contract Documents.
22.07 If the Contract is to be awarded, Owner will award the Contract to the Bidder whose Bid is in the best interests of the Project.
ARTICLE 23 – CONTRACT SECURITY AND INSURANCE
23.01 Article 6 of the General Conditions, and as modified by Section 00750 Supplementary Conditions
- Insurance, sets forth Owner’s requirements as to performance and payment bonds and
14041425-019 00200 - 10 insurance. When the Successful Bidder delivers the executed Agreement to Owner, it shall be accompanied by such bonds and a Certificate of Insurance.
ARTICLE 24 – SIGNING OF AGREEMENT
24.01 When Owner gives a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement with the other Contract Documents which are identified in the Agreement as attached thereto. Within 10 days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within 5 days following the Owner’s Board of Directors’ meeting Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Construction Plans.
ARTICLE 25 – SALES AND USE TAXES
25.01 Provisions concerning state sales and use taxes are set forth in the Supplementary Conditions.
ARTICLE 26 – RETAINAGE
26.01 Provisions concerning retainage are set forth in the Agreement.
ARTICLE 27 – WORKERS’ COMPENSATION INSURANCE COVERAGE
27.01 Provisions concerning workers’ compensation insurance coverage are set forth in Section 00750
Supplementary Conditions - Insurance.
- END OF SECTION –
NOTICE OF AWARD
TO: _________________
Attn: ______________
PD JOB NO. 14041425-019
PROJECT DESCRIPTION: WASTEWATER TREATMENT PLANT IMPROVEMENTS – PHASE II TO SERVE
The OWNER has considered the BID submitted by your firm for the above described work in response to the INVITATION TO BIDDERS.
You are hereby notified that your BID has been accepted for a total bid price of _____________________________________________DOLLARS AND xx/100 ($xxx,xxx.xx) for the submitted base bid of $xxx,xxx.xx, and $xx,xxx.xx for Supplemental Items (when authorized by Engineer) S1 thru S9.
You are required by the INSTRUCTION TO BIDDERS to execute the AGREEMENT and furnish the required BONDS AND CERTIFICATES OF INSURANCE within ten (10) calendar days from the date of this Notice to you.
You are required to return an acknowledged copy of this NOTICE OF AWARD to the OWNER.
Dated this ________ day of _______________, 20__ .
By:
Esteban Gonzalez, P.E.
Project Manager
TBPE Firm Registration No. 470
ACCEPTANCE OF NOTICE
Receipt of the above NOTICE OF AWARD is hereby acknowledged on this _______ day of
________________, 20 .
Name (Printed or Typed)
Signature
Title K:\Projects\414\25\19 HCMUD 345 WWTP Improvements II\01 Design Phase (390)\Project Manual\Front ends\200c Notice of Award new logo.docx
FOR:
DATE:
SUBMITTED BY:
Bidding Firm's Full Name
Address
City, State Zip
Phone Number
Addendum No. ______ Dated _____________ Addendum No. ______ Dated _____________
Addendum No. ______ Dated _____________ Addendum No. ______ Dated _____________
Addendum No. ______ Dated _____________ Addendum No. ______ Dated _____________
Addendum No. ______ Dated _____________ Addendum No. ______ Dated _____________
Harris County Municipal Utility District No. 345 (Owner) c/o Pape-Dawson ATTN: Esteban Gonzalez, P.E.
2107 CityWest Blvd, 3rd Flr Houston, Texas 77042
SECTION 00410
BID FORM
WASTEWATER TREATMENT PLANT IMPROVEMENTS - PHASE II TO SERVE HARRIS
COUNTY MUNICIPAL UTILITY DISTRCT NO. 345
Having received and carefully examined the Bidding Documents, the other related data identified in the Bidding Documents, the Project Site, and the Addenda listed in the following table, I, the Undersigned submit this Bid Form.
41425-019 00410 - 1
(1)
(2)
(3)
(4)
(5)
(6)
I acknowledge that:
(1)
(2) (3) (4)
(5)
(6)
(7)
Furthermore, I certify that:
(1)
(2)
(3) (4) (5) to accept all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security;
For the performance of the Work, the enclosed amounts are bid. The unit prices and extended totals on the following pages are written in figures with the unit prices prevailing in the event of any discrepancies. In submitting this Bid Form, I agree:
no other individuals or entities have been solicited or induced to refrain from bidding or to submit a false Bid;
that this Bid will be open to acceptance and is irrevocable for 60 calendar days from the Bid closing date.
that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted;
to enter into and execute the Agreement within 9 calendar days of receipt of Notice of Award or acceptance of this Bid and to furnish the required bonds and a certificate of insurance within 5 calendar days of receipt of Notice of Award or acceptance of this Bid;
to accomplish the Work in accordance with the Contract Documents by furnishing all materials, equipment, and labor for proper construction and completion of the Work; and to the Contract Times as specified in the Agreement.
the estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price bid items will be based on actual quantities, determined as provided in the Contract Documents;
that the Owner reserves the right to award any combination of the items in the Bid Form;
the Owner reserves the right to reject any and all Bids;
the Owner reserves the right to reject any or all proposals and to waive irregularities in the bidding. In case of ambiguity or lack of clearness in stating the prices in the proposal, the Owner reserves the right to consider the most advantageous construction thereof or to reject the proposal;
the total Contract Price may be increased or decreased or the total Contract Time reduced or extended to compensate for changes in the Work as ordered by the Owner; and this Bid is genuine, and the only person or parties associated with or having an interest in this Bid as principals are those named herein;
The Undersigned hereby declares that he has visited the site and has carefully examined the Site Conditions, Drawings, Specifications, Contract Documents, and Bidding Documents related to the work covered by his Bid.
In instance where there is a discrepancy between the computer generated online CivCast Bid Form and this 00410 Bid Form document, this 00410 Bid Form document will take precedence over the computer generated online CivCast Bid Form.
this Bid is made without collusion involving any other person, group, partnership, or the amounts given in this Bid have been carefully checked and are submitted as correct and the Contractor's Statement of Qualifications has been completed true and accurate and is included with this Bid.
41425-019 00410 - 2
Bidder: Witness:
Title:
Address:
Phone:
E-Mail:
Bonds on Behalf of Corporate Surety:
[Corporate Seal]
Performance, Payment and Maintenance Bonds will be issued by (Name of Corporate Surety):
Name and Address of Local Agency for Corporate Surety:
Phone Number:
Name of Person(s) Executing
E-Mail:
Name of Insurance Agency:
Phone Number:
41425-019 00410 - 3
BASE BID ITEMS:
Wastewater Treatment Plant Base Bid Items Subtotal $
Supplementary Items Total $
CONTRACT TIME:
WASTEWATER TREATMENT PLANT IMPROVEMENTS - PHASE II TO SERVE HARRIS COUNTY
MUNICIPAL UTILITY DISTRCT NO. 345
14041425-019
BID SUMMARY
Wastewater Treatment Plant Improvements - Phase II to serve Harris County Municipal Utility District No. 345 Grand Total
If this Bid is accepted, we will achieve substantial completion in _______ calendar days (120 days maximum) from the Notice to Proceed. We will achieve final completion in _______ calendar days (150 days maximum) from the Notice to Proceed.
41425-019 00410 - 4
1.
This Bid is based on the following named equipment being supplied for the construction of the Project, and no substitution to this list shall be allowed after the Bid opening. FAILURE TO COMPLETE THE LIST OR
NAMING MORE THAN ONE MANUFACTURER FOR EACH ITEM SHALL BE SUFFICIENT CAUSE TO DISQUALIFY
BIDDER.
WASTEWATER TREATMENT PLANT IMPROVEMENTS - PHASE II TO SERVE HARRIS COUNTY
MUNICIPAL UTILITY DISTRCT NO. 345
14041425-019
EQUIPMENT MANUFACTURERS
Clarifier Equipment: ________________________________________________________________
41425-019 00410 - 5
1.
2.
Coatings: __________________________________________________________
WASTEWATER TREATMENT PLANT IMPROVEMENTS - PHASE II TO SERVE HARRIS COUNTY
MUNICIPAL UTILITY DISTRCT NO. 345
14041425-019
SUBCONTRACTORS
This Bid is based on the following named Subcontractors being used for the construction of the Project, and no substitution to this list shall be allowed after the Bid opening. FAILURE TO COMPLETE THE LIST OR
NAMING MORE THAN ONE SUBCONTRACTOR FOR EACH ITEM SHALL BE SUFFICIENT CAUSE TO
DISQUALIFY BIDDER.
Concrete Crack Repair: __________________________________________________________
41425-019 00410 - 6
Item No. Item Description Unit Approx.
Quantity
Unit Price Total Amount
Mobilization - Including but not limited to all permits, mobilization, clean up and de-mobilization onto and from the site. (This price bid for Mobilization shall not exceed 1% of the total amount bid.)
Payment for this item is subject to retainage as specified elsewhere in the project manual.
Lump Sum
Performance and Payment Bonds for 100 Percent (100%) of the Contract Amount.
This item includes all coordination and efforts of securing all required documents.
Lump Sum
Preparation of Existing Clarifier, Including But Not Limited To, Cleaning Of The Interior Of Structure, Removal And Proper Disposal Of Grit For Proposed Work, In Accordance With Construction Plans And Specifications, Complete In Place
Lump Sum
Remove And Replace Clarifier Components, Including But Not Limited To, Clarifier Drive Cage, Inlet Well, Center Pier, Scum Trough, Skimmer Arm, Scum Pipe And Supports, Baffle, Rake/Collector Arms With Flights And Squeegees, Weir Trough And Plates, Clips, Fasteners, Supports, New Sprayer Header With Adjustable Direction And Flat Spray Nozzles, Mechanical/Structural Equipment, Materials, Furnishing, Installation, Protective Coatings, Proper Disposal Of Replaced Equipment, Removing And Reinstalling Equipment/Appurtenances As Needed For Installation Of Proposed Work, And Testing Of All Piping And Related Appurtenances Required For A Complete And Operational System, In Accordance With Construction Plans And Specifications, Complete In Place
Lump Sum
Wastewater Treatment Plant Base Bid Items
Wastewater Treatment Plant Improvements - Phase II to serve Harris County MUD No. 345
41425-019 00410 - 7
Quantity
Unit Price Total Amount
Wastewater Treatment Plant Improvements - Phase II to serve Harris County MUD No. 345
Remove And Replace Unit No. 2 Drain Piping, Fittings, And Valves, Including But Not Limited To Proper Disposal Of Removed Material, Materials, Furnishing, Installation, Protective Coatings, And Testing Of Piping Required For A Complete And Operational System, In Accordance With Construction Plans And Specifications, Complete In Place
Lump Sum
Surface Preparation And Recoating Of Above Ground Piping, Valves, And Fittings, Including But Not Limited To, Unit No. 2 Digester Piping, RAS Piping, Airlift Pump Piping, In Accordance With Construction Plans And Specifications, Complete In Place
Lump Sum
Remove And Replace Unit No. 2 8" Diameter Butterfly Air Isolation Valve, Including But Not Limited To, Fittings, Joints, Appurtenances And Testing Of Piping Required For A Complete And Operational System, In Accordance With Construction Plans And Specifications, Complete In Place
Each 2
Remove And Replace Unit No. 2 6" Diameter Butterfly Air Isolation Valve, Including But Not Limited To, Fittings, Joints, Appurtenances And Testing Of Piping Required For A Complete And Operational System, In Accordance With Construction Plans And Specifications, Complete In Place
Each 2
Remove And Replace Unit No. 2 4" Diameter Butterfly Air Isolation Valve, Including But Not Limited To, Fittings, Joints, Appurtenances And Testing Of Piping Required For A Complete And Operational System, In Accordance With Construction Plans And Specifications, Complete In Place
Each 3
41425-019 00410 - 8
Quantity
Unit Price Total Amount
Wastewater Treatment Plant Improvements - Phase II to serve Harris County MUD No. 345
Remove And Relocate Unit No. 2 Airlift Pump & Piping, Including But Not Limited To, Piping, Valves, Fittings, Air Lines, Supports, Relocating Air Drops, Additional Piping, Fittings (Including Surface Preparation & Coating), And Supports For Relocation, And All Appurtenances And Testing Of Piping Required For A Complete And Operational System, In Accordance With Construction Plans And Specifications, Complete In Place
Lump Sum
Traffic Control As Needed For Equipment Delivery, Includes All Traffic Control Devices Required, Preparation And Implementation Of Traffic Controls Plan, In Accordance With Construction Plans And Specifications
Lump Sum
S-1 Additional Pipe Fittings Ton 2
(1) $2,200.00 $
S-2 Additional Piping Linear Foot
(1) $50.00 $
S-3
Contractor Measurement Of Existing WWTP Unit No. 2 Structural Issues (Cracking, Spalling, And Damaged Joints) With Documentation Of Location, Length, And Type To Engineer For Field Confirmation, Complete In Place
Lump Sum
(1) $16,500.00
S-4 Crack Repair - Clean, Route, And Seal By Epoxy Injection (Hairline)
Linear Foot
(1) $100.00 $
S-5 Crack Repair - Clean And Epoxy Injection (1/64" to 1/16")
Linear Foot
(1) $125.00 $
S-6 Crack Repair - Clean And Epoxy Injection or Gravity (1/8" and Larger)
Linear Foot
(1) $145.00 $
Supplementary Items Wastewater Treatment Plant Base Bid Items Subtotal $
END OF BID FORM
Supplementary Items Total $ Wastewater Treatment Plant Improvements - Phase II to serve Harris County Municipal Utility District No. 345 Grand Total $
(1) This unit price is intended to be a minimum only. Bidder may not decrease this unit price, however, Bidder may increase this unit price. If applicable, cross out the minimum unit price and write the increased unit price in the space above the minimum price.
41425-019 00410 - 9
14041425-019 00520 - 1
AGREEMENT
BETWEEN OWNER AND CONTRACTOR
THIS AGREEMENT, dated the _______ day of _____________________, ______, is by and between HARRIS COUNTY MUNICIPAL UTILITY DISTRICT NO. 345 (hereinafter called Owner) and CONTRACTOR (hereinafter called Contractor).
Owner and Contractor, in consideration of the mutual covenants set forth herein, agree as follows:
ARTICLE 1 - WORK
1.01 Contractor shall commence and complete the Work according to the Construction Plans and Technical Specifications prepared by Pape-Dawson Engineers for the Initial Contract Price of ($ ). The Work is generally described as follows:
A. Under this Contract, Contractor shall furnish all materials, appliances, tools, equipment, transportation, services, and all labor and superintendence necessary for the construction of the Work as described in the Project Manual and as shown on the Plans.
The completed installation shall not lack any part that can be reasonably implied as necessary to its proper functioning or any subsidiary item that is customarily furnished, and Contractor shall deliver the installation to Owner in operating condition.
B. Work, in general, under this Contract consists of furnishing, installing, and constructing all structures, equipment, and materials, including appurtenances, as indicated on the Plans.
C. Contractor is employed by Owner as an independent contractor to perform the Work.
Contractor represents and warrants that, to the extent required by “Law” (as defined in Paragraph 7.11 of the General Conditions) in connection with the performance of the Work, Contractor is duly licensed to perform the Work under the Laws of the State in which the Project is located (“Texas”) and that Contractor’s license number, if applicable, is set forth on the signature page of this Subcontract.
ARTICLE 2 - PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:
WASTEWATER TREATMENT PLANT IMPROVEMENTS – PHASE II TO SERVE HARRIS COUNTY
MUNICIPAL UTILITY DISTRICT NO. 345, IN HARRIS COUNTY, TEXAS – P-D JOB NO.
14041425-019
ARTICLE 3 - ENGINEER
14041425-019 00520 - 2
3.01 The Project has been designed by PAPE-DAWSON (hereinafter called Engineer), who is to act as Owner’s representative, assume all duties and responsibilities, and have the rights and authority assigned to Engineer in connection with the completion of the Work in accordance with the Contract Documents.
ARTICLE 4 - CONTRACT TIMES
4.01 Time is of Material Importance
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of material importance to the Owner.
4.02 Days to Achieve Project Completion
A. The Work shall be substantially completed within _____calendar after the date when the
Contract Times commence to run as provided in Article 4.01 of the General Conditions.
4.0…