Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project.pdf
PDF 653 KB Posted
- Solicitation number
- 299-3104108-AR-PQ
- Issued by
- Orange County, California
About this file
This is a Request for Pre-Qualification document issued by the County of Orange, OC Waste & Recycling department for the Prima Zone 4 Phase A Main Gas Line Project. The project involves design, permitting, and construction of a Landfill Gas Collection and Control System (LFGCCS) header installation at Prima Deshecha Landfill, including trenching, installation of new HDPE header piping, associated valves and appurtenances, tie-ins to existing infrastructure, backfilling, testing, and restoration of disturbed areas. The estimated construction cost is $9,120,900. Pre-qualification documents are due electronically by 2:00 pm on Friday, September 18, 2026. A mandatory pre-bid meeting and site visit will be held on September 24, 2026, at 9:00 am at Prima Deshecha Landfill (32250 Avenida La Pata, San Juan Capistrano, CA 92675), with attendance required and sign-in verification mandatory. Failure to attend will result in bid rejection. The contract duration is 210 calendar days with 30 weather days. Bidding for pre-qualified contractors will be advertised in September 2026. Only pre-qualified contractors will be eligible to submit formal bids.
Contractors must possess a valid California Class A General Engineering Contractor License and be registered with the Department of Industrial Relations. Essential qualification requirements include general liability insurance with minimum limits of $3,000,000 per occurrence and aggregate, current workers' compensation insurance, and a notarized statement from a surety insurer confirming bonding capacity of at least $9,120,900. Pre-qualification evaluation is divided into four sections: Essential Requirements for Qualification (Pass/Fail), Licenses and Bonding (minimum 15 points), Organization and Performance (minimum 87 points), and Construction Projects (reference-based evaluation). Contractors must submit six references from public projects completed within the last ten years of similar size and scope, with at least four from different municipalities and none from Orange County. The County reserves the right to conduct reference checks, seek publicly available information, conduct oral interviews, waive procedural defects, negotiate final contract terms, withdraw or cancel the solicitation, and defer award for up to 365 days. Pre-qualification documents are confidential but contractor names applying are public records. An appeal process is available within seven calendar days of disqualification notification, with hearing decisions rendered within three business days.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
County of Orange, OC Waste & Recycling Pre-Qual # 299-3104108-AR-PQ Project: Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project
Page | 1
COUNTY OF ORANGE
PROCUREMENT SERVICES
Pre-Qualification # 299-3104108-AR-PQ
Request for Pre-Qualification of Contractors for
OC Waste & Recycling
Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project
County of Orange, OC Waste & Recycling Pre-Qual # 299-3104108-AR-PQ Project: Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project
Page | 0
TABLE OF CONTENTS
SECTION 1. REQUEST FOR PRE-QUALIFICATIONS OF CONTRACTORS
SECTION 2. PROJECT DESCRIPTION
SECTION 3. PRE-QUALIFICATION INFORMATION
SECTION 4. VENDOR RESPONSES
Request For Qualification (RFQ) #299-3104108-AR-PQ Title: Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project
County of Orange RFQ
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
SECTION 1. REQUEST FOR PRE-QUALIFICATIONS OF CONTRACTORS
1.1 GENERAL REQUIREMENTS
This Pre-Qualification process is to pre-qualify Contractors to be eligible to participate in the bidding process of Prima Zone 4 Phase A Main Gas Line Project, with an estimated construction cost of $9,120,900 which will be advertised for bids to the pre-qualified Contractors on 09/2026.
This Pre-Qualification process will include submittal by the Contractor of completed Pre-Qualification
Documents in Supplier Responses by the prescribed deadline and the County of Orange evaluation of Pre-
Qualification Documents based on the list of scoring questions and scoring ranges. Only pre-qualified
Contractors will be eligible to submit a bid for this project.
The DPA will provide all official communication concerning this Pre-Qualification. With respect to this
Pre-Qualification, any County response other than from the DPA and in writing will be unauthorized and the County shall bear no responsibility for any and all reliance upon the unauthorized communication.
1.2 PRE-QUALIFICATION PROCEDURE
A. Pre-qualification Documents for the Prima Zone 4 Phase A Main Gas Line Project are available to interested Contractors. For a copy of the Pre-Qualification Documents, visit the County’s online bidding system, Pre-Qualification # 299-3104108-AR-PQ.
Contractor questions for clarification or interpretation regarding the Pre-Qualification
Documents for this project shall be directed to: Albert Rodriguez, Deputy Purchasing
Agent (“DPA”), via County’s online bidding system only no later than, Friday, September
11, 2026 at 2:00 pm to allow sufficient time for responses prior to submission deadline. If clarification from Contractor questions of this Pre-Qualification is considered necessary by the
County of Orange, a written addendum shall be issued. Any interpretation of, or correction to this
Pre-Qualification, will be made only by an addendum issued by the DPA. It is the Contractor’s responsibility to ensure Contractor has reviewed any and all addenda to this Pre-Qualification.
The County will not be responsible for any other explanations, corrections to, or interpretations of the documents, including any oral information.
The County does not guarantee that you will receive addenda to this solicitation. Contractors should review County’s online bidding system internet site for notice of addenda. It is the responsibility of Contractors to request all additional information/modifications to this solicitation.
It is mandatory that all Contractors who intend to submit a bid for the project specified above shall fully complete the pre-qualification questionnaire and provide all materials requested herein.
NOTE: For Contractors who intend to submit a bid for the project as part of a joint venture, it is mandatory that fully completed Pre-Qualification Questionnaires are submitted and all materials requested herein are provided for each of the constituent entities that comprise the joint venture.
The County shall not be liable for any expenses incurred by potential Contractors in the preparation or submission of their response. The County shall not, in any event, be liable for any https://procurement.opengov.com/portal/ocgov https://procurement.opengov.com/portal/ocgov http://www.bidsync.com,/ https://procurement.opengov.com/portal/ocgov
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ pre-contractual expenses incurred by Contractor prior to the date of award and execution of the
Contract. Pre-contractual expenses are defined as expenses incurred by the Contractor in: a) preparing documents in response to this Pre-Qualification; b) submitting an Pre-Qualification to the County; c) negotiating with the County on any matter related to the Contractor’s Pre-
Qualification; and d) any other expenses incurred by the Contractor prior to the date of award and execution of the Contract.
B. Submittal Instructions
A. Contractors desiring to respond to this Pre-Qualification shall electronically submit, via
County’s online bidding system only, answers to each question in the Pre-Qualification
Questionnaire section.
B. Email, fax, and paper submittals will not be accepted, no exceptions. Contractors must submit their pre-qualifications and any other pertinent information electronically via
County’s online bidding system only.
C. Please ensure that the company seal is legible (when copying the document, either use the darkest setting, or pencil over so it shows up).
D. Please also attach the certification portion of the Pre-Qualification Document and sign in pen. The County requires an actual signature in pen to be valid.
E. Failure to follow the required format may result in a delay for reviewing and scoring the documents or disqualification.
F. Pre-Qualification Documents are due before 2:00 pm on Friday, September 18, 2026 and shall be submitted electronically.
G. Reference Letters for at least three (3) Contractor references shall be provided for selected completed construction projects that are of similar size and scope to the project that is specified. (See Section Quality of Performance)
H. No action on the Contractor’s part is required for the reference questions except to provide current and accurate project information.
LATE SUBMITTALS WILL NOT BE ACCEPTED FOR ANY REASON.
C. The County will use the Pre-Qualification Documents as the basis to recommend to the County
Board of Supervisors whether Contractors meet the Pre-Qualification criteria. The County may check other relevant sources of information outside of the Pre-Qualification Documents.
D. The Pre-Qualification Process will be based on scoring the Supplier Responses received. The scoring method is described in Supplier Responses.
E. Contractors will be notified of the County’s Pre-Qualification determination. The County may rescind a Contractor’s Pre-Qualification based on subsequently learned information. A Contractor that is pre-qualified may acquire bidding documents for this project after it is publicly advertised for bids and may formally submit a bid by the specified bid opening date as published in the
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ project Notice Inviting Bids. A Contractor that is not pre-qualified is not eligible to submit a bid.
While it is the intent of the Pre-Qualification Documents to assist the County in determining bidder responsibility prior to bid and to aid it in selecting the lowest responsible and responsive bidder, a bidder being pre-qualified will not preclude a post-bid evaluation of whether a bidder has the quality, fitness, capacity, and experience to satisfactorily perform the proposed work and has demonstrated the requisite trustworthiness.
F. Should a Contractor fail to be recommended for the pre-qualified bidders list, an appeal can be made by submitting written notice of an appeal (Notice of Appeal) to the Director of OC Waste &
Recycling within seven (7) calendar days of the date the Contractor was notified of The County of Orange Pre-Qualification Determination. Failure to file a timely Notice of Appeal shall result in the Contractor’s waiver of any and all rights to challenge the Pre-Qualification Determination, whether by administrative process, judicial process or any other legal process or proceeding. If the Contractor gives the required Notice of Appeal and requests a hearing, the hearing shall be conducted within five (5) calendar days after The County of Orange receives the Notice of
Appeal. The Contractor may request, in writing, County of Orange to advise it on the basis for the
Pre-Qualification determination and any supporting evidence that was received from others or adduced as a result of an investigation by The County of Orange.
A Hearing Panel (“Hearing Panel”) shall be established and consist of three (3) panelists from various County of Orange infrastructure departments, with a maximum of one (1) panelist from the procuring department. The hearing shall be an informal process conducted by a non-partial panel that has the authority to hear such appeals. The Contractor will be given the opportunity to present information and reasons in opposition to the determination.
Within three (3) business days after the conclusion of the hearing, the Hearing Panel will render its decision in writing to the Contractor. The decision of the Hearing Panel shall be the County’s final administrative decision and any judicial review thereof shall be instituted no later than the time period referred to Section 1094.6 Code of Civil Procedure.
G. The Pre-Qualification Documents, Questionnaire answers, and financial statements submitted by the Contractors are not public records and are not open to public inspection. All information provided will be kept confidential to the extent permitted by law. However, the contents may be disclosed to third parties for purpose of verification, or investigation of substantial allegations, or in the appeal hearing. State law requires that the names of contractors applying for Pre-
Qualification determination shall be public records subject to disclosure, and “Contractor
Information Form” will be used for that purpose.
H. Pre-Qualification Documents must be signed under penalty of perjury in the manner designated at the end of the form (Certification), by an individual(s) who has the legal authority to bind the
Contractor on whose behalf that person is signing. If any information provided by a Contractor becomes inaccurate, the Contractor must immediately notify County of Orange and provide updated accurate information in writing, under penalty of perjury.
I. Contractor shall exercise reasonable care and diligence to avoid submitting a Pre-Qualification that could result in a conflict of interest if Contractor were to be selected. This obligation shall
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ apply to the Contractor; the Contractor’s employees, agents, and relatives; sub-tier Contractors;
and third parties associated with accomplishing work and services in Contractor’s Pre-
Qualification. In the event Contractor has done work for the County on this project in the past or has reason to believe that a conflict of interest may exist for Contractor in regard to this project, Contractor should consult with its legal counsel prior to responding to this Pre-Qualification. Any
Contractor who is found to have an actual conflict of interest may have its Pre-Qualification rejected on that ground.
1.3 COMMUNICATION
Bidders are not to contact other County personnel with any questions or clarifications concerning this solicitation. All questions regarding this solicitation must be submitted via the Question & Answer section of this solicitation within the County’s eProcurement Portal at:
https://procurement.opengov.com/portal/ocgov. Any County response relevant to this solicitation other than through or approved by County is unauthorized and will be considered invalid.
County's Deputy Procurement Agent, Albert Rodriguez, albert.rodriguez@ocwr.ocgov.com, will provide all official communication concerning this solicitation.
1.4 MANDATORY PRE-BID MEETING AND SITE VISIT NOTIFICATION
A Mandatory Pre-Bid meeting and site visit will be held on September 24, 2026, at 9:00 am. Meeting place will be at Prima Deshecha Landfill (32250 Avenida La Pata, San Juan Capistrano, CA 92675).
Sign-in will be with Procurement. No one will be admitted after 9:10am. Failure of any pre-qualified bidder to attend this mandatory pre-bid meeting and site visit shall constitute a substantial variation from the requirements of the contract and the bid of any bidder not in attendance will be rejected as non-responsive. All potential bidders must sign-in to verify their attendance.
1.5 CHECKLIST OF REQUIRED SUBMITTALS
This checklist is provided for the convenience of the Contractor and is not to be included in the Contractor’s
Pre-Qualification Documents. Items listed here are required for submittal.
A. Contractor Information Form
B. Pre-Qualification Questionnaire:
1. All questions answered with any supplemental pages attached (Section and Question numbers, and signature and date included on each additional page)
2. Signed and dated Certification
C. Notarized statement from an admitted surety insurer (approved by the California Department of
Insurance) and authorized to issue bonds per the specific project requirements in Supplier
Responses. **Please sign in pen and ensure the company seal is legible.**
D. Description of construction experience/expertise of key personnel who will be working on the specified project herein (construction foreman, project superintendent, construction project
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ manager, and/or on-site inspector) and what qualifies them to work on this project in Supplier
Responses.
E. Information for six (6) public projects completed within the last ten (10) years under Contractors’ current California State License, that are of similar size and nature to the one for which
Contractor is herein requesting Pre-Qualification in Supplier Responses. These references should be from different entities and must be verifiable.
NOTE: Electronic Bids cannot be viewed by County until after the solicitation deadline. If you encounter any problems with your registration, system, bid/proposal submission, or other system issues, please contact
OpenGov’s support staff via the live chat option or via email at procurement-support@opengov.com.
1.6 THE COUNTY RESERVES THE RIGHT TO:
1. Request revisions and hold discussions with any Respondent as necessary to serve the best interests of the County.
2. Seek publicly available information about the Respondents.
3. Conduct, or not to conduct, oral interviews and/or presentations with the highest-ranked
Respondent(s) and additional Respondents.
4. Waive, at its discretion, any procedural, non-material defects, irregularity, or informality, which
County deems correctable or otherwise not warranting rejection of the bid that do not result in any unfair competitive advantage. Any waiver will not excuse a respondent from full compliance.
5. Verify and validate any information prior to Contract Award and during the entire term of the
Contract.
6. Negotiate the final Contract with any Respondent(s), including pricing/fee schedule, as necessary to serve the best interests of the County;
7. Withdraw or cancel in part or in its entirety this solicitation at any time without prior notice and furthermore makes no representations that any Contract will be awarded to any Respondent responding to this solicitation;
8. Award its total requirements to one Respondent or to apportion those requirements among two or more Respondents as the County may deem to be in its best interests;
9. Reject any Response if it is conditional, incomplete or deviates significantly from the services requested in this solicitation; and/or
10. Request Best and Final Offer from any Respondent determined to be within the competitive range.
Unless requested by the County, late Best and Final Offers will not be accepted by the County for any reason. In addition, negotiations may or may not be conducted with Respondents.
11. Make multiple awards to Respondent(s) for services requested in this solicitation, at its sole discretion, to serve the best interests of the County.
mailto:procurement-support@opengov.com
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
12. Defer award of this Contract for a period of 365 days after the Bid opening. During this period, Bidders shall guarantee the prices quoted in their Bids. County and the responsive, responsible
Bidder may mutually agree in writing to extend this deferral period.
Therefore, Responses submitted shall contain the Respondent’s most favorable terms and conditions, since the selection and award may be made without discussion with any Respondent.
SECTION 2. PROJECT DESCRIPTION
The project consists of design, permitting, and construction of the Zone 4 Phase A Landfill Gas (LFG)
Collection and Control System (LFGCCS) header installation. Work to include trenching, installation of new HDPE header piping, associated valves and appurtenances, tie-ins to existing LFG infrastructure, backfilling, testing, and restoration of disturbed areas. Contractors should account for site constraints including traffic control, construction sequence, coordination with landfill operations, subcontractor scheduling, and materials procurement. Completed work will provide the owner with improvements to the
LFGCCS, including the fully installed Zone 4 Phase A header and associated connections to the existing
LFG infrastructure, with the requirement that the contractor avoid damage to any existing infrastructure not designated for demolition and removal.
2.1 LICENSES
Class A - General Engineering Contractor License
2.2 CONTRACT TIME
210 Calendar Days with 30 Weather Days
2.3 CALIFORNIA STATE CONTRACTOR'S LICENSING REQUIREMENT
Copies of California State Contractor’s licenses are not required to be submitted with the Pre-Qualification
Documents. All prospective bidders must possess the required licenses at the time of Pre-Qualification
Documents submission.
2.4 DEPARTMENT OF INDUSTRIAL RELATIONS (DIR) REQUIREMENT
Contractors must be registered with the DIR at the time of submittals, in accordance with Labor Code
1725.5
2.5 BIDDER'S SECURITY
Bidder’s Security for the specific project is not required to be submitted at this time. However, at the time bids are submitted by the Pre-Qualified Bidders, each bid must follow the requirements as stated in the
General Instruction and Provisions in the bid documents.
2.6 BONDS, INSURANCE AND EXECUTED CONTRACT
Bonds and Insurance for this specific project are not required to be submitted at this time. However, at the time bids are submitted by the Pre-Qualified Bidders, each bid must follow the requirements as stated in the General Instructions and Provisions in the bid documents.
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
SECTION 3. PRE-QUALIFICATION INFORMATION
3.1 SUMMARY OF SECTIONS AND SCORING METHOD
Section
Section: Essential Requirements for Qualification
Section: Licenses and Bonding
Section: Organization, History, Organizational
Performance, Compliance with Civil Laws, etc.
Section: Construction Projects
NOTE: Not all questions in the questionnaire are “scorable”; some questions simply ask for information about the contractor organization’s structure, officers and history. This document includes all questions and the scoring method.
Scores Needed for Pre-Qualification
To pre-qualify, a contractor would be required to have a passing score within each of the four sections referred to above.
Section: Essential Requirements for Qualification
Questions are scored as “Pass/Fail.”
Section: Licenses and Bonding
A passing score of 15 is required
Section: Organization, History, Organizational Performance, Compliance with Civil Laws, etc.
A passing score of 87 is required
Section: Construction Projects
This section includes reference questions.
County of Orange shall conduct reference questions to the Owner or Project Manager of the completed construction projects provided by Contractor.
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
SECTION 4. VENDOR RESPONSES
Responses must be prepared simply and economically, providing a straightforward, concise description of capabilities to satisfy the requirements of this. Emphasis should be on completeness and clarity of content with sufficient detail to allow for accurate evaluation and comparative analysis.
4.1 CONTRACTOR INFORMATION FORM*
Please download the below documents, complete, and upload.
• Contractor_Information_Form...
*Response required
4.2 UNIQUE ENTITY IDENTIFIER NUMBER (UEI) *
The County requires a valid UEI number with active registration status. Your company may obtain one at no cost at https://sam.gov/entity-registration.
*Response required
4.3 CALIFORNIA SECRETARY OF STATE REGISTRATION - ACTIVE AND IN
GOOD STANDING *
Please upload your active certificate from the California Secretary of State.
CA Sec. of State Verification Link = https://bizfileonline.sos.ca.gov/search/business
*Response required
4.4 D-U-N-S NUMBER*
Please provide your company's DUNS number.
The County requires a valid D-U-N-S number prior to Contract Award. If needed, your company may obtain one at no cost at www.dnb.com. If you are unable to provide/obtain a D-U-N-S number, please indicate so in lieu of the number.
*Response required
4.5 FEDERAL TAXPAYER ID NUMBER:*
*Response required
4.6 CALIFORNIA DEPARTMENT OF JUSTICE, OFFICE OF ATTORNEY
GENERAL ACTIVE REGISTRATION*
For Non-Profit and/or Charitable organizations, please provide your active (registration status is current). All others enter N/A.
• RCT Registration Number
• Renewal/Expiration Date
DOJ Verification Link - https://rct.doj.ca.gov/Verification/Web/Search.aspx?facility=Y
*Response required
4.7 ESSENTIAL REQUIREMENTS FOR QUALIFICATIONS
NOTE:
https://government-project.s3.us-west-2.amazonaws.com/81727/5209ecba-e7d0-4ce5-a602-6bbb95f65ec1_Contractor_Information_Form.pdf https://sam.gov/entity-registration https://bizfileonline.sos.ca.gov/search/business http://www.dnb.com/ https://rct.doj.ca.gov/Verification/Web/Search.aspx?facility=Y
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
• Contractor will be immediately disqualified if the answer to any of Questions .1, .2, .3, or .4 1, is “no.”
o 1 An additional notarized statement from the surety may be requested by Department Name at the time of submission of a bid, if this pre-qualification package is submitted more than 60 days prior to submission of the bid.
• Contractor will be immediately disqualified if the answer to any of Questions .5, .6, .7, .8, or
.9 is “yes.”2 If the answer to question .7 is “yes,” and if debarment would be the sole reason for denial of Pre-Qualification, any Pre-Qualification issued will exclude the debarment period.
o 2 A Contractor disqualified solely because of a “Yes” answer given to question .5, .6, or .8 may appeal the disqualification and provide an explanation of the relevant circumstances during the appeal procedure.
• PREQUALIFICATION PROTEST HEARING: In the event that Contractor is disqualified due to any answers provided in this section, Contractor may appeal this disqualification in writing within seven (7) calendar days, pursuant to the County's Contract Policy Manual, Section 3.5-118, available from County of Orange.
Pass/Fail Questions: 7.1 - 7.9
4.7.1 Contractor possesses a valid and current California Contractor’s license for the project for which it intends to submit a bid. *
☐ Yes
☐ No
*Response required
4.7.2 General Liability Insurance Policy*
Contractor has a general liability insurance policy with a policy limit of at least $3,000,000 per occurrence and $3,000,000 aggregate.
☐ Yes
☐ No
*Response required
4.7.3 Contractor has current workers’ compensation insurance policy as required by the
Labor Code or is legally self-insured pursuant to Labor Code section 3700 et. seq. *
☐ Yes
☐ No
☐ Contractor is exempt from this Requirement, because it has no employees
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
*Response required
4.7.4 Notarized Statement from an admitted surety insurer*
Have you attached a notarized statement from an admitted surety insurer (approved by the California
Department of Insurance) and authorized to issue bonds in the State of California, which states: (a) that your current bonding capacity is at least $9,120,900 , (b) the bonding company name, address, and telephone number? Notarized statement must be dated within six (6) months of the Pre-qualification packet submittal.
Note: Notarized statement must be from the surety company, not an agent or broker.
☐ Yes
☐ No
*Response required
4.7.5 Has your Contractor’s license been revoked at any time in the last five years?*
☐ Yes
☐ No
*Response required
4.7.6 Has a surety firm completed a contract on your behalf, or paid for completion because your firm defaulted or was terminated by the project owner within the last five (5) years?*
☐ Yes
☐ No
*Response required
4.7.7 At the time of submitting this Pre-Qualification form, is your firm ineligible to bid on or be awarded a public works contract, or perform as a contractor on a public works contract, pursuant to either Labor Code section 1777.1 or Labor Code section
1777.7?*
☐ Yes
☐ No
*Response required
4.7.8 At any time during the last five (5) years, has your firm, or any of its owners or officers, been convicted of a crime involving the awarding of a contract of a government construction project, or the bidding or performance of a government contract? *
☐ Yes
☐ No
*Response required
4.7.9 At any time during the past five (5) years, has your firm, or any of its owners or officers been a named party to an active case in a court of law with the County of
Orange, any County of Orange Department or special district, any County of
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
Orange elected official or any current or former member(s) of the Board of
Supervisors?*
☐ Yes
☐ No
*Response required
4.8 LICENSES
Non-Scorable Questions: 3.1 - 3.4, 4.1, 4.3
Points Questions: 3.5, 4.2, 4.4, 4.5
4.8.1 List all California construction license numbers, classifications and expiration dates of the California Contractor licenses held by your organization:* Please download the below documents, complete, and upload.
Non-Scorable Question
• License_Number(s)_and_Class...
*Response required
4.8.2 If any of your organization’s license(s) are held in the name of a corporation or partnership, list below the names of the qualifying individual(s) listed on the
California State Licensing Board (CSLB) records who meet(s) the experience and examination requirements for each license.
Non-Scorable Question
4.8.3 Has your organization changed names or license number in the past five years?* Non-Scorable Question
☐ Yes
☐ No
*Response required
When equals "Yes"
4.8.4 Explain, including the reason for the change.*
*Response required
4.8.5 Has any owner, partner, or (for corporations) officer of your organization operated a construction organization under any other name in the last five years?* Non-Scorable Question
☐ Yes
☐ No
*Response required
When equals "Yes"
4.8.6 Explain, including the reason for the change.*
*Response required https://government-project.s3.us-west-2.amazonaws.com/81727/ff03cc49-388d-4a7f-a127-7c253245bba8_License_Number%28s%29_and_Classification.pdf
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
4.8.7 Has any CSLB license held by your organization or its Responsible Managing
Employee (RME) or Responsible Managing Officer (RMO) been suspended within the last five years?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.8.8 Explain, including the reason for the change.*
*Response required
4.9 BONDING
Non-Scorable Questions: 4.1, 4.3
Points Questions: 4.2, 4.4, 4.5
4.9.1 Bonding capacity: Provide documentation from your surety, on their official letterhead, identifying the following:*
• Name of bonding company/surety.
• Name of surety agent, address and telephone number.
*Response required
4.9.2 Was your organization required to pay a premium of more than one percent for a performance and payment bond on any project(s) on which your organization worked at any time during the last three years?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.9.3 State the percentage that your organization was required to pay and explain the reason.* *Response required
4.9.4 List all other sureties (name and full address) that have written bonds for your organization during the last five years, including the dates during which each wrote the bonds.* *Response required
4.9.5 During the last five years, has your organization ever been denied bond credit by a surety company? *
☐ Yes
☐ No
When equals "Yes"
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
4.9.6 Provide details indicating the date when your organization was denied credit and the name of the company or companies which denied credit.* *Response required
4.9.7 Has there ever been a period of time when your organization had no surety bond in place during a public construction project when one was required?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.9.8 State the period during which you had no surety bond in place and explain the reason.* *Response required
4.10 CURRENT ORGANIZATION AND STRUCTURE OF THE BUSINESS
Non-Scorable Questions: 5.1 - 5.5
4.10.1 For organizations that are Corporations
Please download the below documents, complete, and upload.
• For_organizations_that_are_...
4.10.2 For organizations that are Partnerships
Please download the below documents, complete, and upload.
• For_organizations_that_are_...
4.10.3 For organizations that are Sole Proprietorships
Please download the below documents, complete, and upload.
• For_organizations_that_are_...
4.10.4 For organizations that intend to make a bid as part of a joint venture Please download the below documents, complete, and upload.
• For_organizations_that_inte...
4.10.5 For organizations that are Limited Liability Companies Please download the below documents, complete, and upload.
• For_organizations_that_are_...
4.11 HISTORY OF THE BUSINESS AND ORGANIZATIONAL PERFORMANCE
Non-Scorable Questions: 6.1 - 6.4
Points Questions: 6.5 - 6.7
4.11.1 Has there been any change in ownership of the organization at any time during the last five years?
NOTE: A corporation whose shares are publicly traded is not required to answer this question https://government-project.s3.us-west-2.amazonaws.com/81727/782bf63d-d3dc-4ab3-8c2e-5a8070cef3e5_For_organizations_that_are_Corporations.pdf https://government-project.s3.us-west-2.amazonaws.com/81727/af658778-fcac-444f-b5c8-f88c9a5135e0_For_organizations_that_are_Partnerships.pdf https://government-project.s3.us-west-2.amazonaws.com/81727/c5665ab3-1e6a-4924-973f-cc80062e2517_For_organizations_that_are_Sole_Proprietorships.pdf https://government-project.s3.us-west-2.amazonaws.com/81727/35b0e4e4-0439-4592-a694-84cf207dfc26_For_organizations_that_intend_to_make_a_bid_as_part_of_a_joint_venture.pdf https://government-project.s3.us-west-2.amazonaws.com/81727/f13822b6-8c97-4c47-91f5-97db553cee8a_For_organizations_that_are_Limited_Liability_Companies.pdf
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
☐ Yes
☐ No
When equals "Yes"
4.11.2 Explain
4.11.3 Is the organization a subsidiary, parent, holding company, or affiliate of another construction organization?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.11.4 Explain*
NOTE: Include information about the other organization(s) if one organization owns 50 percent or more of another, or if an owner, partner, or officer of your organization holds a similar position in another organization.
*Response required
4.11.5 Are any corporate officers, partners or owners connected to any other construction organizations?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.11.6 Explain*
NOTE: Include information about the other organizations if an owner, partner, or officer of your organization holds a similar position in another organization.
*Response required
4.11.7 State your organization’s gross revenues for each of the last three years:* Current year: ________________
Previous year:________________
Year prior to previous year:________________
*Response required
4.11.8 How many years has your organization been in business in California as a
Contractor under your present business name and license number?*
☐ 3 years
☐ 4 years
☐ 5 years
☐ 6 years or more
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
4.11.9 Is your organization currently the debtor in a bankruptcy case?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.11.10 Please attach a copy of the bankruptcy petition, showing the case number and the date on which the petition was filed. * *Response required
4.11.11 Was your organization in bankruptcy at any time during the last five years?* (This question refers only to a bankruptcy action that was not described in answer to the previous question)
☐ Yes
☐ No
*Response required
When equals "Yes"
4.11.12 Please attach a copy of the bankruptcy petition, showing the case number and the date on which the petition was filed and a copy of the Bankruptcy Court’s discharge order, or of any other document that ended the case, if no discharge order was issued.* *Response required
4.12 DISPUTES
Points Questions: 7.1 - 7.7
4.12.1 At any time in the last five years has your organization been assessed and paid liquidated damages after completion of a project under a construction contract with either a public or private owner?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.12.2 Explain and Identify all such projects by the owner, the owner’s address, the date of completion of the project, the amount of liquidated damages assessed, and all other information necessary to fully explain the assessment of liquidated damages.* *Response required
4.12.3 In the last five years has your organization, or any organization with which any of your company’s owners, officers or partners was associated, been debarred, disqualified, removed or otherwise prevented from bidding on, or completing, any government agency or public works project for any reason?* NOTE: “Associated with” refers to another construction organization in which an owner, partner or officer of your organization held a similar position, and which is listed in response to SECTION
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
TITLED: CURRENT ORGANIZATION AND STRUCTURE OF THE BUSINESS on the questionnaire.
☐ Yes
☐ No
*Response required
When equals "Yes"
4.12.4 Explain and State whether the organization involved was the organization applying for pre-qualification here, or another organization. Identify the name of the company, the name of the person within your organization who was associated with that company, the year of the event, the owner of the project, the project, and the basis for the action.* *Response required
4.12.5 In the last five years has your organization been denied an award of a public works contract based on a finding by a public agency that your company was not a responsible bidder?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.12.6 Explain and Identify the year of the event, the owner, the project and the basis for the finding by the public agency.* *Response required
4.12.7 In the past five years has any claim against your organization concerning your organization’s work on a construction project been filed in court or arbitration?* NOTE: This question refers only to disputes between your organization and the owner of a project.
You need not include information about disputes between your organization and a supplier or another contractor or sub-contractor. You need not include information about “pass-through” disputes in which the actual dispute is between a sub-contractor and a project owner. Also, you may omit reference to all disputes about amounts less than $50,000.
☐ Yes
☐ No
*Response required
When equals "Yes"
4.12.8 Identify the claim(s) by providing the project name, date of the claim, name of the claimant, a brief description of the nature of the claim, the court in which the case was filed and a brief description of the status of the claim (pending or, if resolved, a brief description of the resolution).*
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
4.12.9 In the past five years has your organization made any claim against a general contractor or project owner concerning work on a project or payment for a contract and filed that claim in court or arbitration?* NOTE: This question refers only to disputes between your organization and the owner of a project.
You need not include information about disputes between your organization and a supplier or another contractor or sub-contractor. You need not include information about “pass-through” disputes in which the actual dispute is between a sub-contractor and a project owner. Also, you may omit reference to all disputes about amounts less than $50,000.
☐ Yes
☐ No
*Response required
When equals "Yes"
4.12.10 Identify the claim by providing the project name, date of the claim, name of the entity (or entities) against whom the claim was filed, a brief description of the nature of the claim, the court in which the case was filed and a brief description of the status of the claim (pending, or if resolved, a brief description of the resolution).* *Response required
4.12.11 At any time during the past five years, has any surety company made any payments on your organization’s behalf as a result of a default, to satisfy any claims made against a performance or payment bond issued on your organization’s behalf, in connection with a construction project, either public or private?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.12.12 Explain the amount of each such claim, the name and telephone number of the claimant, the date of the claim, the grounds for the claim, the present status of the claim, the date of resolution of such claim if resolved, the method by which such was resolved if resolved, the nature of the resolution and the amount, if any, at which the claim was resolved.* *Response required
4.12.13 In the last five years has any insurance carrier, for any form of insurance, refused to renew the insurance policy for your organization?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.12.14 Explain and include the name of the insurance carrier, the form of insurance and the year of the refusal.*
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
4.13 COMPLIANCE WITH CIVIL AND CRIMINAL LAWS
Points Questions: 8.1 - 8.3
4.13.1 Has your organization or any of its owners, officers or partners ever been found liable in a civil suit or found guilty in a criminal action for making any false claim or material misrepresentation to any public agency or entity?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.13.2 Explain who was involved, the name of the public agency, the date of the investigation and the grounds for the finding.* *Response required
4.13.3 Has your organization or any of its owners, officers or partners ever been convicted of a crime involving any federal, state, or local law related to construction?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.13.4 Explain who was involved, the name of the public agency, the date of the conviction, and the grounds for the conviction.* *Response required
4.13.5 Has your organization or any of its owners, officers or partners ever been convicted of a federal or state crime of fraud, theft, or any other act of dishonesty?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.13.6 Identify the person or persons convicted, the court (the county if a state court, the district or location of the federal court), the year and the criminal conduct.* *Response required
4.14 COMPLIANCE WITH OCCUPATIONAL SAFETY AND HEALTH LAWS,
WORKERS’ COMPENSATION AND OTHER LABOR LEGISLATION
Points Questions: 9.1 - 9.7
4.14.1 Has CAL OSHA cited and assessed penalties against your organization for any
“serious,” “willful” or “repeat” violations of its safety or health regulations in the past five years? *
☐ Yes
☐ No
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
*Response required
When equals "Yes"
4.14.2 Attach a document describing each citation, the dates of the citations, the nature of the violation, the project on which the citation(s) was or were issued and the amount of penalty paid, if any. If the citation was appealed to the Occupational Safety and Health Appeals Board and a decision has been issued, state the case number and the date of the decision.
NOTE: If you have filed an appeal of a citation, and the Occupational Safety and Health
Appeals Board has not yet ruled on your appeal, you need not include information about it.
4.14.3 Has the federal Occupational Safety and Health Administration cited and assessed penalties against your organization in the past five years? *
☐ Yes
☐ No
*Response required
When equals "Yes"
4.14.4 Describe each citation
NOTE: If you have filed an appeal of a citation and the Appeals Board has not yet ruled on your appeal, or if there is a court appeal pending, you need not include information about the citation.
4.14.5 Has the EPA or any Air Quality Management District or any Regional Water
Quality Control Board cited and assessed penalties against either your organization or the owner of a project on which your organization was the Contractor, in the past five years?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.14.6 Describe each citation
NOTE: If you have filed an appeal of a citation and the Appeals Board has not yet ruled on your appeal, or if there is a court appeal pending, you need not include information about the citation.
4.14.7 How often do you require documented safety meetings to be held for construction employees and field supervisors during the course of a project?* *Response required
4.14.8 List your organization’s Experience Modification Rate (EMR) (California workers’ compensation insurance) for each of the past three premium years and this premium year:* NOTE: An Experience Modification Rate is issued to your organization annually by your workers’ compensation insurance carrier.
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
Current year rate:
Previous year rate:
Year prior to previous year rate:
*Response required
4.14.9 If your EMR for any of these three years is or was 1.00 or higher, you may, if you wish, attach a letter of explanation on a separate signed page, or pages.
4.14.10 Within the last five years has there ever been a period when your organization had employees but was without workers’ compensation insurance or state-approved self-insurance?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.14.11 Please explain the reason for the absence of workers’ compensation insurance on a separate signed page, or pages.* *Response required
When equals "No"
4.14.12 Please provide a statement by your current workers’ compensation insurance carrier that verifies periods of workers’ compensation insurance coverage for the last five years. * If your organization has been in the construction business for less than five years, provide a statement by your workers’ compensation insurance carrier verifying continuous workers’ compensation insurance coverage for the period that your organization has been in the construction business.
*Response required
4.15 PREVAILING WAGE AND APPRENTICESHIP COMPLIANCE RECORD
Points Questions: 10.1 - 10.5
4.15.1 Has there been more than one occasion during the last five years in which your organization was required to pay, either, back wages or penalties for your own organization’s failure to comply with the state’s prevailing wage laws? * NOTE: This question refers only to your own organization’s violation of prevailing wage laws, not to violations of the prevailing wage laws by a sub-contractor.
☐ Yes
☐ No
*Response required
When equals "Yes"
4.15.2 Attach a separate signed page, or pages, describing the nature of each violation, identifying the name of the project, the date of its completion, the public
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ agency for which it was constructed; the number of employees who were initially underpaid and the amount of back wages and penalties that you were required to pay.* *Response required
4.15.3 During the last five years, has there been more than one occasion in which your own organization has been penalized or required to pay back wages for failure to comply with the federal Davis-Bacon prevailing wage requirements? *
☐ Yes
☐ No
*Response required
When equals "Yes"
4.15.4 Attach a separate signed page, or pages, describing the nature of each violation, identifying the name of the project, the date of its completion, the public agency for which it was constructed, the number of employees who were initially underpaid, the amount of back wages you were required to pay, and the amount of any penalty paid.* *Response required
4.15.5 Provide the name, address and telephone number of the apprenticeship program
(approved by the California Apprenticeship Council) from whom you intend to request the dispatch of apprentices to your company for use on any public works project for which you are awarded a contract by the County. * *Response required
4.15.6 Does your organization operates its own State-approved apprenticeship program?*
☐ Yes
☐ No
*Response required
When equals "Yes"
4.15.7 Your organization operates its own State-approved apprenticeship program.*
(a) Identify the craft or crafts in which your organization provided apprenticeship training in the past year.
(b) State the year in which each such apprenticeship program was approved, and attach evidence of the most recent California Apprenticeship Council approval(s) of your apprenticeship program(s).
(c) State the number of individuals who were employed by your organization as apprentices at any time during the past three years in each apprenticeship and the number of persons who, during the past three years, completed apprenticeships in each craft while employed by your organization.
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
4.15.8 At any time during the last five years, has your organization been found to have violated any provision of California apprenticeship laws or regulations, or the laws pertaining to use of apprentices on public works? * NOTE: You may omit reference to any incident that occurred prior to January 1, 1998, if the violation was by a sub-contractor and your organization, as a general contractor on a project, had no knowledge of the sub-contractor’s violation at the time they occurred.
☐ Yes
☐ No
*Response required
When equals "Yes"
4.15.9 Provide the date(s) of such findings and attach copies of the Department's final decision(s).* *Response required
4.16 RECENT PROJECTS COMPLETED
Non-Scorable Question: 11
(Reference Questions)
4.16.1 Describe construction experience/expertise of key personnel who will be working on the specified project herein (construction foreman, project superintendent, construction project manager, and/or on-site inspector) and what qualifies them to work on this project.* *Response required
4.16.2 Contractor shall provide References for six (6) public projects completed within the last ten (10) years under Contractors’ current California State License, that are of similar size and nature to the one for which Contractor is herein requesting Pre-
Qualification. These references should be from different entities and must be verifiable.* *Response required
4.16.3 Recent Construction Projects Completed*
Contractor shall provide information for completed projects as described in Request For Pre-
Qualifications of Contractors under ‘Checklist of Required Submittals’; the names and references must be current and verifiable. The references provided should be a project for which your company was listed as a prime contractor, not a subcontractor performing work. These must be projects that were not County of
Orange projects and no less than four (4) projects should be from another municipality. These should not be projects from the same entity. Use separate sheets of paper that contain all of the following information:
Project:
Name:
Location:
Owner:
Owner Contact (name, current phone number & e-mail):
Description of Project, Scope of Work Performed:
OC Waste & Recycling - Pre-Qualification for Prima Zone 4 Phase A Main Gas Line Project, 299-3104108-AR-PQ
Total Value of Construction (including change orders):
Date Construction Commenced:
Original Contractual Completion Deadline:
Adjusted Completion Deadline Based on Time Extensions Granted by Owner:
Actual Date of Completion:
General Contractor’s Project Manager (lead contact in office), if applicable:
General Contractor’s Superintendent (lead contact on project site), if applicable:
*Response required
4.17 QUALITY OF PERFORMANCE
The reference questions below will be asked of the Owner or Project Manager (acting on behalf of the
Owner) of at least three recent projects that are of similar size and scope to the project that is specified.
Please provide Reference Letters that include responses to the following questions for all three (3) of the references:
Reference Questions
A. Are there any…